Construction of Super Health Center - NETWORK
Construction of Super Health Center - NETWORK
EARTHWORKS 800(2) Clearing and Grubbing 803(1)a Structure Excavation (... 804(1)a Embankment from Ex...
Duration 12.5 days Duration 2 days Duration 1 day Duration 4 days
Start 5/1/24 1:00 PM Start 5/1/24 1:00 PM Start 5/3/24 1:00 PM Start 5/6/24 1:00 PM
Finish 5/17/24 5:00 PM Finish 5/3/24 1:00 PM Finish 5/6/24 1:00 PM Finish 5/10/24 1:00 PM
1001(1)a PVC Pipes and Fittin... 1002(3)a PPR-C Pipe, Ø13mm ... 1002(5)a Plumbing Fixtures 1002(16) Floor Drain Plates 1002(27) Plumbing Works (Ot...
Duration 4 days Duration 4.38 days Duration 2 days Duration 0.5 days Duration 4.13 days
Start 8/27/24 2:02 PM Start 9/2/24 2:02 PM Start 9/9/24 8:04 AM Start 9/11/24 8:04 AM Start 9/11/24 1:04 PM
Finish 9/2/24 2:02 PM Finish 9/9/24 8:04 AM Finish 9/11/24 8:04 AM Finish 9/11/24 1:04 PM Finish 9/17/24 2:07 PM
MECHANICAL WORKS
Duration 21 days
Start 8/27/24 2:02 PM
Finish 9/25/24 2:02 PM
1046(2)a1 100mm thick CHB ... 1046(2)a2 150mm thick CHB ...
Duration 15.25 days Duration 14.88 days
Start 8/27/24 2:02 PM Start 9/17/24 4:02 PM
Finish 9/17/24 4:02 PM Finish 10/8/24 3:04 PM
1100(10) Conduits, Boxes and ... 1101(33) Wires and Wiring De... 1102(1) Panelboard w/ Main &...
Duration 8 days Duration 15 days Duration 5 days
Start 10/8/24 3:04 PM Start 10/18/24 3:04 PM Start 11/8/24 3:04 PM
Finish 10/18/24 3:04 PM Finish 11/8/24 3:04 PM Finish 11/15/24 3:04 PM