You are on page 1of 8

CONSTRUCTION OF SUPE... OTHERGENERALREQUIRE... B.

3 Permits and Clearances


Duration 273.27 days Duration 273 days Duration 15 days
Start 5/1/24 8:00 AM Start 5/1/24 8:00 AM Start 5/1/24 8:00 AM
Finish 5/19/25 10:09 AM Finish 5/16/25 5:00 PM Finish 5/21/24 5:00 PM

B.5 Project Billboard / Signbo...


Duration 0.5 days
Start 5/1/24 8:00 AM
Finish 5/1/24 1:00 PM

B.7(2) Occupational Safety an...


Duration 273 days
Start 5/1/24 8:00 AM
Finish 5/16/25 5:00 PM

EARTHWORKS 800(2) Clearing and Grubbing 803(1)a Structure Excavation (... 804(1)a Embankment from Ex...
Duration 12.5 days Duration 2 days Duration 1 day Duration 4 days
Start 5/1/24 1:00 PM Start 5/1/24 1:00 PM Start 5/3/24 1:00 PM Start 5/6/24 1:00 PM
Finish 5/17/24 5:00 PM Finish 5/3/24 1:00 PM Finish 5/6/24 1:00 PM Finish 5/10/24 1:00 PM

REINFORCED CONCRETE ...


Duration 71.63 days
Start 5/20/24 8:00 AM
Finish 8/27/24 2:02 PM

FINISHINGS & OTHER CIVI...


Duration 181.64 days
Start 8/27/24 2:02 PM
Finish 5/8/25 10:09 AM
ankment from Ex... 804(1)b Embankment from Bo... 804(4) Gravel Bedding
Duration 2.25 days Duration 3.25 days
Start 5/10/24 1:00 PM Start 5/14/24 3:00 PM
Finish 5/14/24 3:00 PM Finish 5/17/24 5:00 PM

900(1)c2 Str. Concrete (F1, Sl... 900(1)c3 Str. Concret


Duration 38.25 days Duration 3.25 days
Start 7/1/24 9:02 AM Start 8/22/24 11:02
Finish 8/22/24 11:02 AM Finish 8/27/24 2:02 P

902(1)a Reinfocing Steel (Def.... 903(2) Formworks and Falsew...


Duration 9.63 days Duration 20.5 days
Start 5/20/24 8:00 AM Start 5/31/24 2:02 PM
Finish 5/31/24 2:02 PM Finish 7/1/24 9:02 AM
00(1)c3 Str. Concrete (FTB, ...
3.25 days
8/22/24 11:02 AM
8/27/24 2:02 PM

1001(1)a PVC Pipes and Fittin... 1002(3)a PPR-C Pipe, Ø13mm ... 1002(5)a Plumbing Fixtures 1002(16) Floor Drain Plates 1002(27) Plumbing Works (Ot...
Duration 4 days Duration 4.38 days Duration 2 days Duration 0.5 days Duration 4.13 days
Start 8/27/24 2:02 PM Start 9/2/24 2:02 PM Start 9/9/24 8:04 AM Start 9/11/24 8:04 AM Start 9/11/24 1:04 PM
Finish 9/2/24 2:02 PM Finish 9/9/24 8:04 AM Finish 9/11/24 8:04 AM Finish 9/11/24 1:04 PM Finish 9/17/24 2:07 PM

1003(1) Carpentry & Joinery (... 1003(17) Carpentry & Joinery...


Duration 49.88 days Duration 3.13 days
Start 11/27/24 9:07 AM Start 2/5/25 8:09 AM
Finish 2/5/25 8:09 AM Finish 2/10/25 9:12 AM

1013(2) Fabricated Metal Roof...


Duration 1 day
Start 11/5/24 11:02 AM
Finish 11/6/24 11:02 AM

1014(1)b2 Prepainted Metal S... 1018(1) Ceramic Tiles and Tri...


Duration 17.5 days Duration 11.25 days
Start 10/10/24 4:02 PM Start 2/5/25 8:09 AM
Finish 11/5/24 11:02 AM Finish 2/20/25 10:09 AM
1007(1)b Aluminum Glass Do... 1008(1)c Aluminum Glass Wi... 1010(2)a Hollow Core Flush D... 1010(2)b Wooden Panel Doors
Duration 2 days Duration 15 days Duration 6 days Duration 9.38 days
Start 2/10/25 9:12 AM Start 2/12/25 9:12 AM Start 3/5/25 9:12 AM Start 3/13/25 9:12 AM
Finish 2/12/25 9:12 AM Finish 3/5/25 9:12 AM Finish 3/13/25 9:12 AM Finish 3/26/25 1:14 PM

1018(3) Granite Tiles


Duration 24.38 days
Start 2/20/25 10:09 AM
Finish 3/26/25 2:12 PM
ELECTRICAL WORKS
Duration 44 days
Start 10/8/24 3:04 PM
Finish 12/9/24 3:04 PM

MECHANICAL WORKS
Duration 21 days
Start 8/27/24 2:02 PM
Finish 9/25/24 2:02 PM

SPECIAL PAY ITEM


Duration 7 days
Start 5/8/25 10:09 AM
Finish 5/19/25 10:09 AM
1027(1) Cement Plaster Finish 1027(3) Decorative Stone 1032(1)a Painting Works (Con...
Duration 35.38 days Duration 2 days Duration 114.13 days
Start 10/8/24 3:04 PM Start 11/27/24 9:07 AM Start 11/29/24 9:07 AM
Finish 11/27/24 9:07 AM Finish 11/29/24 9:07 AM Finish 5/8/25 10:09 AM

1032(1)c Painting Works (Steel)


Duration 35.13 days
Start 10/17/24 11:02 AM
Finish 12/5/24 1:04 PM

1036(1)a Polycarbonate Sheets 1043(2) PVC Doors & Frames


Duration 4.38 days Duration 5 days
Start 10/10/24 4:02 PM Start 11/27/24 9:07 AM
Finish 10/17/24 10:04 AM Finish 12/4/24 9:07 AM

1046(2)a1 100mm thick CHB ... 1046(2)a2 150mm thick CHB ...
Duration 15.25 days Duration 14.88 days
Start 8/27/24 2:02 PM Start 9/17/24 4:02 PM
Finish 9/17/24 4:02 PM Finish 10/8/24 3:04 PM

1047(2)b Structural Steel Tru... 1047(2)c Structural Steel Purl...


Duration 32.25 days Duration 4.5 days
Start 8/27/24 2:02 PM Start 10/10/24 4:02 PM
Finish 10/10/24 4:02 PM Finish 10/17/24 11:02 AM

1100(10) Conduits, Boxes and ... 1101(33) Wires and Wiring De... 1102(1) Panelboard w/ Main &...
Duration 8 days Duration 15 days Duration 5 days
Start 10/8/24 3:04 PM Start 10/18/24 3:04 PM Start 11/8/24 3:04 PM
Finish 10/18/24 3:04 PM Finish 11/8/24 3:04 PM Finish 11/15/24 3:04 PM

1201(9)c Overhead Tank, Poly...


Duration 21 days
Start 8/27/24 2:02 PM
Finish 9/25/24 2:02 PM
1051(6) Metal Railings
Duration 6 days
Start 3/26/25 2:12 PM
Finish 4/3/25 2:12 PM

1103(1) Lighting Fixtures and ...


Duration 16 days
Start 11/15/24 3:04 PM
Finish 12/9/24 3:04 PM

SPL-1 Signage / Logo & Lette...


Duration 7 days
Start 5/8/25 10:09 AM
Finish 5/19/25 10:09 AM

You might also like