PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 01: General Requirements

Item No. Description Unit Quantity Rate (USD) Amount (USD)

PRELIMINARIES
The General Requirements are applicable to the whole of the works.
All Requirements specified in the contract conditions and technical
specifications.
General Requirements or otherwise indicated in the Contract
Documents, are not necessarily listed in the Bill of Quantities, the cost
of General Requirements shall be deemed to be included in the unit
rates of the BOQ items and will not be paid separately.
The Contractor is deemed to include in his prices, all costs to comply
with the instructions, rules and specifications stipulated or observed by
the Local Government Authorities, insurances, guarantees, testing &
commission, permits, bonds, .. Etc.
The Contractor shall perform all works required in this section.
Including, but not limited to coordination, related works, occupancy
requirements, and all other requirements; as per the specifications.

UNOPS has the right to vary the BoQ item-/+20%

Page 1 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 02: Site Construction

Item No. Description Unit Quantity Rate (USD)

DIVISION 2: SITE CONSTRUCTION


Preambles
* The Bidders are requested to refer the General Notes, Pricing Preambles, Drawings, Specifications,
Conditions of Contract, Special Conditions of Contract, all other relevant documents and to visit the
site prior to pricing of the following items. Implementing Contractor is responsible for the well
being of hospital assets and services in areas of project activities. Meanwhile, the contractor is
bound to keep all other hospital sections in smooth operable mode, all in terms of vehicles traffic,
patients and visitor’s movement, utility services inflow/outflow, safety measures, and sound
pollution.

* The contractor should be aware that the proposed work will be carried out for an existing
functioning building and that the renovation activities should not interrupt other ongoing daily
activities. The Contractor is held responsible on the following: (a) Removing the demolished
material out of the site to an approved dump location within a maximum of three days. (b) the
dismantled material (including but limited to: doors, windows, lighting fixtures, mechanical fixtures,
etc.) is the sole property of the end user (Hospital Administration) and should be dismantled,
moved & stored as per Statement of Method approved by the Engineer. (c) Coordinate his daily
activities and the work schedule throughout the renovation period with the Client and the
Employer’s Representative. (d) Protect and safeguard the existing facilities, mechanical fixtures,
and building finishes, including paint, floor tiles, existing fixtures, doors, windows and structural
elements, etc even if these are our side of construction area but has direct or indirect interference
by the Contractor, his equipment, his staff or his operations. (e) Responsible for the method of
demolitions and any damage or subsequent damage to the existing or adjoining structures. (f) Take
all necessary measures to protect and minimize environmental hazards including pollution, noise,
dust, etc. (g) Noise and dust from the works shall be kept to the minimum possible. To reduce dust
supply of clean water shall be used to dampen the site. (h) Take all necessary precautions to
prevent anything emanating from or associated with the works from being deposited on areas
outside the contractor’s site areas. (i) Aware that the boundary wall which forms part of the wall to
be demolished extension is to be left untouched and in a safe a stable manner following demolition
works.

* The Rate includes the following works: (a) Provision for hindrance due to current situations. (b)
Safety provisions. (c) All the requirement to complete the work in accordance with Engineers'
instructions. (d) All direct, indirect works and expenses required for the completion of the coming
items. (e) All required tests by an approved laboratory for the defected and damaged concrete
element specified by the engineer. (f) All necessary scaffolding, tarpaulins and dust sheets,
protecting existing work from damage by workmen or the weather and removing all temporary
coverings and screens on completion.

* All dismantled materials must be stored in a place related to the contractor until to be reinstalled
(the needed materials) at the new locations according to Engineers' instructions. All above items
must be approved from Engineer to determine the time and location. The price includes repairing
any demolishing works Observing not to delay the normal function of all hospital departments
during the work. Cart away the depressed materials and all required as per engineering
instructions.

* If the owner wishes to take any of the materials/items from the existing site before demolishing,
the Contractor shall hand over the selected material/item to the owner and deliver them to the
approved location.
* Dismantle: includes manage cutting of services feed sources based on statement of method
approved by the Engineer, dismantling with care, storing the dismantled parts in a secured and
adequate storage area. All abiding approved safety plan measures.
* Handing to Client: includes handing to the client or any other party the Client names in writing, in a
tidy manner all of the dismantled parts and devices which are in acceptable condition and are not
intended to be reinstalled.
* Dispose: includes dispose and remove out of Site the damaged and broken out parts and debris, as
per Statement of Method approved by the Engineer that includes, but not limited to, disposal
working hours, movement paths, staff & equipment, separation between project's staff & hospital
users, gender safeguard, protection against pollution.

Carried forward

Item No. Description Unit Quantity Rate (USD)


Brought forward from previous page
* All wall partitions and wall finishes to be carefully demolished , wall plaster to be maintained
* Any demolishing work indicated on the drawings should consider maintenance of any resulting
* damage to adjacent
All existing doors to be existing items
carefully such as not
dismantled limited
and handed , plaster
over to, finishing
Hospital and etc....
Management except
* doors that are indicated on drawings to be kept and to be maintained
All existing external windows to be maintained which include but not limited to window
* accessories, locks, aluminum
All building elements proposed work and
to be glass workor altered (as shown on the drawings) should be
demolished
* checked / verified on site by the contractor
All dimensions shown on the as built drawings prior
aretoindicative
carrying out
onlythe
andworks,
shouldand
beanyusedidentified
only as a
discrepancies
reference / defects
to some of the should
main be reported
elements todemolition.
the relevant consultants.
* Further builder`s work in connection withfor
Structural Slab / Wall penetrations / openings in addition
* to
thethose already
contractor identified
shall submitshould be coordinated
a method statement ofwiththe the MEP Engineers
demolition work and . ensure that structural
* elements are not overloaded and shall be responsible for increasing
the contractor to check and advise for any existing utilities or conduits under the structural supports or will
tiles that adding
be
new supports
removed, and as ismay
itshall be
hisliaise
ownrequired as a result
responsibilty of any
towith
repair anycutting,
damagesremoval,
occur or demolition
to and utilitieswork,
this hospital's andsure
taking
tomanagement
make
* The contractor
in consideration that and
the maximumcoordinate the required authorities
unsupported length (length of the proposed demolished slab or
the continuity of the hospital's operation.
during the execution of Works. However the contractor should submit method statement that
clarify how to elaborate on the adopted operational plan of the hospital to be implemented during
the maintenance works especially that many areas shall receive demolition and dismantling works,
Page 2 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 02: Site Construction

* The contractor to check any damages that maybe occured during dismantling any MEP installation
* that are connected
The contractor shallto the out
submit fullofworkshop
scope rehabilitation zone, and
drawings showing the itexisting
is his own responsibilty
levels and clarify to
therepair
any damages
connection tooccur
the to this utilities
existing conncetions
and to make sure
manholes to thesite
the continuity
engineer offor
theapproval.
hospital's operation.
* Before starting the execution of the roofing layer, the Contractor shall justify the existing slopes for
the water drain and perform water tests to ensure the slopes are as per the Engineer's instruction.
1 SECTION 02220 - Demolition
Carefully dismantling, removing the existing following items,including handling to the client with
1.1 proper sorting and packaging and packing system with tags to all items as client and engineer's
a. instructions
All electrical,and all necessary
mechanical works according
and medical engineer's
fixtures and approvals.
equipment to be carefully dismantled and
b. handed over to Hospital Management for maintenance, storage
All movable furniture shall be removed and handed over to Hospital and Management
possible reusefor
LS 1
c. maintenance, storage
All fixed furniture to beand possible reuse
dismantled and handed over to Hospital Management for maintenance,
storage and possible reuse

Carried forward

Item No. Dismantling Existing Aluminum Partitions: Description Unit Quantity Rate (USD)
Dismantle and remove of the aluminum Brought forward from previous
glass partition includingpagedoors and to be handed to
1.2 service/storage department at the hospital. The rate shall include making good (after
removal/dismantling) existing structure with all necessary related materials and equipment to m2 65
1.3 Dismantle
receive theand
Dismantling new remove
Existing
finish, of Aluminum
Block Partitions:
including windows
all related works such as sanding down and putty works, complete m2 405
Dismantle
Demolition
as shown on and
and remove
removal
drawings, of the
of aluminum
existing
specifications andwindows
walls and without
partitions
as per frames
whatever
Engineer's and
it is to
instructions. be handed
( stone, block,to
etc. ) with
service/storage
their finish above department
(like tiling) at
asthe hospital.
directed Theengineer,
by the rate shallininclude making
order to removegood (after or create
partitions
1.4 removal/dismantling) existing structure
openings (doors and windows), demolition with all necessary
process has to related materials and
be in a appropriate equipment
technical wayto to No. 28
receive the new
avoid causing anyfinish,
damage including
to theall related works
structural suchand
elements as sanding downincludes
walls . Work and putty works, and
providing complete
as shown on drawings, specifications and as per Engineer's instructions.
1.5 Dismantling Existing Doors: No. 68
1.6 Dismantle and
Expanding the remove
existing of theopening
door existing doors and architraves and to be handed to service/storage
department at the hospital. The rate shall No. 10
Expand the existing door opening,work to include
include making
supportgood (after removal/dismantling)
the existing door opening, demolish existing
the
structure with all necessary related
existing wall that includes the door opening,materialsconstruct
and equipment to receive the
a new reinforced new finish,
concrete including
stiffener beam all
related works such as sanding down and putty works, complete as shown on
and columns to create a new opening, support the existing slab above the new door opening with drawings,
steel beam, and fill the gap with a new block, Support before demolition which shall be kept in the

Carried forward

Item No. Description Unit Quantity Rate (USD)


Brought forward from previous page

1.6 Demolishing wall Tile Work: m2 30


Carefully demolish/ Remove wall tiles and cement plastering layers to reach the skeleton (block
wall or concrete), including but not limited to removal of surplus material and moving to an
1.7 Demolishing floor tile
approved dumping Work:
area, making good (after demolition/removal) the existing structure with all m2 500
Carefully
necessarydemolish/ Removeand
related materials floorequipment
tiles and all
tobeneath
receive thelayers,
newincluding but notalllimited
finish including to removal
necessary works
of surplus material and moving to an approved dumping area, making good (after
1.8 Demolishing false ceiling
demolition/removal) Work: structure with all necessary related materials and equipment to
the existing m2 1150
Carefully demolish/
receive the new finishRemove false
including allceilings,
necessaryincluding
works suchbut not limited to
as cleaning theremoval
surfaceof surplus
after material
removing of
and moving to an approved dumping area, making good (after demolition/removal) the existing
2 SECTION 02300 - Earthworks
structure with all necessary related materials and equipment to receive the new finish including all
2.1 necessary
Excavationsworks
fromsuch as cleaning
natural or reducedthelevels
surface after isremoving
(which lower) inofany
ceilings, debris
surface, kindand fungus,
of soil, concrete or
a. asphalt...etc.
Slab on gardeto the required
excavation anddepth
grade and dimensions
beams as shown
as per drawings foron drawings.
service Price to include:
building
support of excavation sides including but not limited to any type of shoring, planking, shuttering, m³ 145
b. for grade beams
scaffolding, or any under
othernew block and
temporary newrequired
works rooms for the maintain the stability of the excavation, m³ 40

3 SECTIONlevel,
Supply, 02720-
andAggregate
apply wellBase Course
compact crushed aggregate base course, 200mm thickness for
3.1 required locations after compaction to 100% modified AASHTO density, CBR ≥ 80%, all as per
drawings, specifications and the Engineer's instructions.
a. 200 mm thick, base course layer for service building slab on grade m3 40
b. 200 mm thick, base course layer for grade beams under new block and new rooms m3 17

Carried to Summary

Page 3 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 02: Site Construction

Amount (USD)

Amount (USD)

Page 4 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 02: Site Construction

Amount (USD)
0
0
0

0
0

Amount (USD)
0

0
0

0
0

Sum Check
0 0.00

Page 5 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 03: Concrete Works

Item No. Description Unit Quantity Rate (USD)

*Note:
The Contractor is responsible to conduct a survey to inspect all existing concrete works (floors,
stairs,ceilings and amps) to be maintaned and report the engineer about the condition per area
with a schedule of work after site assessment to achive the proposed design intent prior
executing.

1 SECTION 03150- Concrete Accessories


1.1 Supply and install compressive filler board (fiber or approved equivalent, 50mm thick, including all
necessary preparation and fixing works as per drawings, specifications and Engineer's instructions.
a. for new rooms m2 25

1.2 Supply and install mastic sealant including backing rod, including all necessary preparation and
fixing works as per drawings, specifications and Engineer's instructions.
a. for new rooms L.M 10

2 SECTION 03300 - Cast In Place Concrete


2.1 Plain concrete grade 20
Supply and apply plain concrete with cubic crushing strength (Fcu) of 20 MPa (20N/mm2) at 28
days, using ordinary Portland cement (ASTM c150 Type -1), including all necessary formwork and
all as per specification, drawings, and approval of the Engineer

a. for slab on grade and footing for service building m3 20


b. for grade beams under new block and new rooms m3 6

2.2 Reinforced concrete grade 25


Supply and install reinforced concrete with cubic crushing strength (Fcu) of 25 MPa (25N/mm2) at
28 days, using ordinary Portland cement (ASTM c150 Type -1), including all necessary
reinforcement steel as per structural drawings,formwork , construction joints, plasticizers and all
required as per drawings, specifications and the Engineer's instructions.

a. for slab on grade of service building m3 30

2.3 Reinforced concrete grade 35


Supply and install reinforced concrete with cubic crushing strength (Fcu) of 35 MPa (35N/mm2) at
28 days, using ordinary Portland cement (ASTM c150 Type -1), including reinforcement steel as per
structural drawings, all necessary formwork , construction joints, plasticizers and all required as per
drawings, specifications and the Engineer's instructions.

for main building


a. for foundations, footings m3 2
b. for grade beams under new block m3 5
c. columns m3 2
d. Slabs m3 2
e. beams m3 1
for service building
f. for foundations, footings m3 12
g. Grade beams m3 10
h. columns m3 10
i. Slabs m3 40
j. beams m3 15

Carried forward

Item No. Description Unit Quantity Rate (USD)


Brought forward from previous page

3 Concrete screed– Concrete Topping


SECTION 03530
3.1 Supply and apply concrete screed minimum 30 mm thick, slope to drain,compressive strength of
20N/mm , including construction joints ,polysulfiedpolymer mastic complete as per drawings,
2
a. For service building
specifications top of roof
and Engineer's instructions. m2 200
Foam concrete
3.2 Supply and apply one layer foam concrete of 50mm min. thick, slope to drain, density (600-
700)kg/m³ with compressive strength of (2.1-3)N/mm², complete as per drawings and
a. For service building top of roof
specifications. m2 200

Page 6 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 03: Concrete Works

3.3 Screed flooring


Supply
for mainand lay fully leveled, trowelled screed flooring topping of grade 30 concrete of minimum
building
a. 50mm thick. with nonmetalic hardener under self leveling epoxy flooring, mix and workmanship m2 235
b. For servicetobuilding
according and roof recommendations
manufacturer's electrical room, and new
and therooms
Engineer's instructions, including m2 200
construction joints where nedded, all as per specifications and drawings and the Engineer's

Carried to Summary

Page 7 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 03: Concrete Works

Amount (USD)

0
0

0
0
0
0
0

0
0
0
0
0

Amount (USD)
0

Page 8 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 03: Concrete Works

0
0

Sum Check
0 0.00

Page 9 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 04: Masonry Works

Item No. Description Unit Quantity Rate (USD)

1 SECTION 04220-Concrete Unit Masonry


Block work shall be set out and built to the respective dimensions, thicknesses and heights required
and the Contractor shall set out courses, openings and the like with approved setting out rods. The
hollow and solid concrete blocks shall be sound and free from cracks, broken edges,
honeycombing, and other defects that would interfere with the proper placing of block or impair
the strength or performance during construction. The average compressive strength of the blocks
shall not be less than 35 kg/cm2 for hollow block and 60 kg/cm2 for solid block. The blocks shall be
of first class, regular in shape, size and color. The drying shrinkage of the blocks when unrestrained,
shall not exceed 0.1%. Also, the water absorption of the blocks shall be not more than 10% by
mass. The blocks shall be laid on a full bed of mortar and bonded with each other by toothing
alternate courses and the joints between the blocks shall be filled with mortar before the next
mortar bed is laid. Whole blocks shall be used except where it is necessary to cut closers. The
blockwork courses shall be kept horizontal and matching perpends shall be in vertical alignment.
The blocks should overlap the block below it by half of its length (half bond). Not more than 100 cm
height of masonry shall be constructed at a time. The blocks shall be kept in a moist condition for
14 days. After curing, the blocks shall be dried before being used for work. Cement mortar for
blockwork and stonework shall be mixed in the proportions of (1:3) (cement: sand).

Rates shall include: (1) Preparation of surfaces of floor slab, columns (steel or RCC) and wall
surfaces for proper bonding and for control joint details as given in drawings. (2) All labor,
scaffolding, safety nets, working platforms, and other necessary requirements to execute the work
to the given standards and to complete the work as per specification. (3) Supplying hollow or solid
cement block from good and approved factory in perfect dimension and build it in good manner.
(4) Laying out the block units, spreading 2.5cm thick mortar under the blocks, also the work
includes: (Lifting, handling, placing, buttering the "ears" of the blocks with mortar, wiping any
excess mortar off, keeping the work level and plumb). (5) Jointing and sealing the gaps between
masonry and other structural members, i.e., Columns, beams, slabs etc., provide openings as
required, finish around the same. (6) Installing reinforced concrete lintels above doors and
windows, lintels should extend beyond the opening at each end by at least 15 cm and Reinforced
concrete bond beams and stiffener columns in walls as detailed in structural drawings. (7) Curing
with water properly for not less than seven days. (8) Movements, Expansion joints. (9) Work must
be true to horizontal lines and perfect plumb. Vertical joints are required to be truly vertical and
align vertically with those of alternate courses. (10) Cement mortars, reinforced concrete infill
(B250) between columns and block walls (10-20 cm wide) with 2ø8mm/40cm horizontally and
2ø10mm vertically according to drawings, pipes encasement, false columns 20x20 cm/4.0m among
the parapet wall with 4ø12mm and bituminous paper between block work and drop beams and all
requirements needed to finish the works according to the drawings, specification and to the
Engineers' instructions. (11) Supplying and installing bituminous paper between block work and
drop beams and testing as well as all requirements needed to finish the works.

1.1 Hollow concrete block walls, 100mm thick.


a For main Building m2 145

1.2 Hollow concrete block walls, 150mm thick.


a For main Building m2 205

1.3 Hollow concrete block walls, 200mm thick.


a For main Building m2 210
b For service building and roof electrical room m 2 150

1.4 Solid Concrete block walls, 200mm thick.


a For service building and roof electrical room m2 40

1.5 Cavity wall, hollow block 200mm thick, acoustical rockwool insulation 50mm thick, hollow block
100mm thick
a For service building and roof electrical room m2 120

Carried forward

Item No. Description Unit Quantity Rate (USD)


Brought forward from previous page

2 SECTION 04450 - Natural Stone Works


2.1 Marble sills and thresholds
Supply and install
for windows first class
sills, door Italian and
thresholds Carrara marbleneeded
wherever or equivelant, light grey color , 30mm thick, for
windows' sills , doors thresholds and wherever needed, bedded in cement and sand mortar 1:3,
a. For main building
pointed using special pre­mix grout, all as per drawings and specifications. Color to be approved by m2 15
b. the Engineer
For service .
building and roof electrical room m2 3

Page 10 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 04: Masonry Works

Carried to Summary

Page 11 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 04: Masonry Works

Amount (USD)

0
0

Amount (USD)
0

0
0

Page 12 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 04: Masonry Works

Sum Check
0 0.00

Page 13 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 05: Metal Works

Item No. Description Unit Quantity Rate (USD)

1 SECTION 5500- Metal Fabrication


1.1 Project Name Sign Board:
Supply and installation of Project Name Board (2.0m x 1.9m sign board and 1.2m from ground) as
per drawing Comprised of 5 reflected Aluminum sheets of (1900 mm wide, 300 mm height and 3
mm thick. With its supports, fittings and concrete footings, and doing all it takes according to the
drawings and Engineers' instructions. The works include:
(1) Unclassified excavation for R. C footings, cut existing pavement using electrical saw, backfilling
or borrow fill with compacting using suitable equipment's, dispose all disposal materials to
approved location.
(2) Cast in situ Reinforced concrete for footings (Cube Fc'=20mpa), conformed to ACI-318M codes
requirements.
(3) Steel anchor channel to be epoxy coated 3 layers, 100 micron each. No. 1
(4) Stainless steel tubes with a diameter of 150 mm and a thickness of 40 mm for columns and
timber.
(5) Sign board shall be bolted to 150 x 75mm timber support.
(6) Support and 1ø14mm bolt with washer and nut to be imbedded in the timber as per drawing.
(7) Disposal and hauling of waste material to the approved location.
(8) All works shall be done according to standards, drawings, and specifications.

1.2 Sandwich Panel


Supply and install composite sandwich panel 50mm thickness for roof electrical room, and
including all necessary related works, complete as shown on drawings, specifications and
as per Engineers' instructions

a. For roof electrical room m2 5

Carried to Summary

Page 14 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 05: Metal Works

Amount (USD)

Sum Check
0 0.00

Page 15 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 06: Wood and Plastic

Item No. Description Unit Quantity Rate (USD)

SECTION 06416: Solid Surfacing Countertops


1 SECTION 06410 - Architectural woodworks
1.1 Supply and fix the following counters, desks, cabinets including all required related works,
accessories, fixing, welding, painting, all as per drawings and specifications
The Contractor shall refer to enlargment drawings for more details. The contractor shall provide
workshop drawing clarifyiny the fixing method, required sub-structure, finishing materials,
dimensions, accessories, hardware, etc. subject to engineer's approval.
Drawings AD-300 to AD-303

a DIRTY UTILITY ROOM COUNTER- 12mm aclyric solid surface countertop with 12X100mm ACRYLIC
SOLID SURFACE BACK-SPLASH, WITH (450X450)mm SINK,MIXER, AND DRAIN CONNECTION NO. 1
L=0.9m,W=0.6m,H=1.0m
b DIRTY UTILITY ROOM wall mounted cabinets TYPE 2 L=0.9m,W=0.3m, H=0.6m -CABINET
BOTTOM,TOP & SIDES: 18mm THICK PLYWOOD PANELS WITH 0.8mm THICK HPL ON BOTH SIDES &
0.8mm THICK PVC EDGING,CABINET BOTTOM,TOP & SIDES: 18mm THICK PLYWOOD ADJUSTABLE NO. 1
SHELVES: 18mm THICK PLYWOOD 0.8mm THICK PVC EDGING,BACK OF CABINET: 3mm THICK MDF
PANELS

c NURSES LOUNGE ROOM COUNTER- 12mm aclyric solid surface countertop with 12X100mm
ACRYLIC SOLID SURFACE BACK-SPLASH WITH (450X450)mm SINK,MIXER, AND DRAIN CONNECTION NO. 1
L=1.5m,W=0.6m,H=1.0m
d NURSES LOUNGE ROOM wall mounted cabinets TYPE 2 L=1.5m,W=0.3m, H=0.6m -CABINET
BOTTOM,TOP & SIDES: 18mm THICK PLYWOOD PANELS WITH 0.8mm THICK HPL ON BOTH SIDES &
0.8mm THICK PVC EDGING,CABINET BOTTOM,TOP & SIDES: 18mm THICK PLYWOOD ADJUSTABLE NO. 1
SHELVES: 18mm THICK PLYWOOD 0.8mm THICK PVC EDGING,BACK OF CABINET: 3mm THICK MDF
PANELS

e STAFF LOUNGE ROOM COUNTER- 12mm aclyric solid surface countertop with 12X100mm ACRYLIC
SOLID SURFACE BACK-SPLASH WITH (450X450)mm SINK,MIXER, AND DRAIN CONNECTION NO. 1
L=1.5m,W=0.6m,H=1.0m
f STAFF LOUNGE ROOM wall mounted cabinets TYPE 2 L=1.5m,W=0.3m, H=0.6m -CABINET
BOTTOM,TOP & SIDES: 18mm THICK PLYWOOD PANELS WITH 0.8mm THICK HPL ON BOTH SIDES &
0.8mm THICK PVC EDGING,CABINET BOTTOM,TOP & SIDES: 18mm THICK PLYWOOD ADJUSTABLE NO. 1
SHELVES: 18mm THICK PLYWOOD 0.8mm THICK PVC EDGING,BACK OF CABINET: 3mm THICK MDF
PANELS

g TREATMENT ROOM COUNTER- 12mm aclyric solid surface countertop with 12X100mm ACRYLIC
SOLID SURFACE BACK-SPLASH, WITH (450X450)mm SINK,MIXER, AND DRAIN CONNECTION NO. 1
L=1.8m,W=0.6m,H=1.0m
h TREATMRNT ROOM wall mounted cabinets TYPE 2 L=1.8m,W=0.3m, H=0.6m -CABINET
BOTTOM,TOP & SIDES: 18mm THICK PLYWOOD PANELS WITH 0.8mm THICK HPL ON BOTH SIDES &
0.8mm THICK PVC EDGING,CABINET BOTTOM,TOP & SIDES: 18mm THICK PLYWOOD ADJUSTABLE NO. 1
SHELVES: 18mm THICK PLYWOOD 0.8mm THICK PVC EDGING,BACK OF CABINET: 3mm THICK MDF
PANELS

i DOCTOR LOUNGE ROOM COUNTER- 12mm aclyric solid surface countertop with 12X100mm NO. 1
j ACRYLIC
DOCTOR SOLID SURFACE
LOUNGE ROOMBACK-SPLASH
wall mountedwith sink L=1.5m,W=0.6m,H=1.0m
cabinets TYPE 2 L=1.5m,W=0.3m, H=0.6m -CABINET NO. 1
BOTTOM,TOP & SIDES: 18mm THICK PLYWOOD PANELS WITH 0.8mm THICK HPL ON BOTH SIDES &
0.8mm THICK PVC EDGING,CABINET BOTTOM,TOP & SIDES: 18mm THICK PLYWOOD ADJUSTABLE
k STERILIZATION
SHELVES: 18mmCOUNTER- 12mm aclyric
THICK PLYWOOD 0.8mmsolid surface
THICK countertop with
PVC EDGING,BACK OF12X100mm ACRYLIC
CABINET: 3mm THICKSOLID
MDF NO. 1
l SURFACE BACK-SPLASH,
STERILIZATION WITHcabinets
wall mounted (450X450)mm
TYPE 2SINK,MIXER, AND DRAIN
L=2.3m,W=0.3m, H=0.6mCONNECTION
-CABINET BOTTOM,TOP &
L=3.2m,W=0.6m,H=1.0m NO. 1
SIDES: 18mm THICK PLYWOOD PANELS WITH 0.8mm THICK HPL ON BOTH SIDES & 0.8mm THICK
PVC EDGING,CABINET BOTTOM,TOP & SIDES: 18mm THICK PLYWOOD ADJUSTABLE SHELVES:
18mm THICK PLYWOOD 0.8mm THICK PVC EDGING,BACK OF CABINET: 3mm THICK MDF PANELS
Carried forward

Item No. Description Unit Quantity Rate (USD)


Brought forward from previous page

m CORRIDOR COUNTER- 12mm aclyric solid surface countertop with 12X100mm ACRYLIC SOLID NO. 1
n SURFACE BACK-SPLASH,
CORRIDOR wall mountedWITH (450X450)mm
cabinets SINK,MIXER, AND
TYPE 2 L=1.8m,W=0.3m, DRAIN-CABINET
H=0.6m CONNECTION
BOTTOM,TOP &
L=1.8m,W=0.6m,H=1.0m NO. 1
SIDES: 18mm THICK PLYWOOD PANELS WITH 0.8mm THICK HPL ON BOTH SIDES & 0.8mm THICK
PVC EDGING,CABINET BOTTOM,TOP & SIDES: 18mm THICK PLYWOOD ADJUSTABLE SHELVES:
o CORRIDOR
18mm THICKCOUNTER-
PLYWOOD12mm0.8mm aclyric
THICKsolid
PVCsurface countertop
EDGING,BACK with 12X100mm
OF CABINET: ACRYLIC
3mm THICK MDFSOLID
PANELS NO. 1
p SURFACE
CORRIDORBACK-SPLASH,
wall mountedWITH (450X450)mm
cabinets SINK,MIXER, AND
TYPE 2 L=1.4m,W=0.3m, DRAIN-CABINET
H=0.6m CONNECTION
BOTTOM,TOP &
L=1.4m,W=0.6m,H=1.0m NO. 1
SIDES: 18mm THICK PLYWOOD PANELS WITH 0.8mm THICK HPL ON BOTH SIDES & 0.8mm THICK
PVC EDGING,CABINET BOTTOM,TOP & SIDES: 18mm THICK PLYWOOD ADJUSTABLE SHELVES:
q SLUICE ROOMPLYWOOD
18mm THICK COUNTER-0.8mm
12mmTHICKaclyricPVC
solid surface countertop
EDGING,BACK with 12X100mm
OF CABINET: 3mm THICKACRYLIC SOLID
MDF PANELS NO. 1
r SURFACE BACK-SPLASH,
SLUICE ROOM WITHcabinets
wall mounted (450X450)mm
TYPE 2 SINK,MIXER, AND DRAIN
L=1.2m,W=0.3m, H=0.6mCONNECTION
-CABINET BOTTOM,TOP &
L=1.2m,W=0.6m,H=1.0m NO. 1
SIDES: 18mm THICK PLYWOOD PANELS WITH 0.8mm THICK HPL ON BOTH SIDES & 0.8mm THICK
PVC EDGING,CABINET BOTTOM,TOP & SIDES: 18mm THICK PLYWOOD ADJUSTABLE SHELVES:
s NURSES DESK-12mm
18mm THICK PLYWOOD aclyric
0.8mmsolidTHICK
surface
PVCcountertop withOF
EDGING,BACK wooden and 3mm
CABINET: metalTHICK
subframe
MDF PANELS NO. 1
t L=1.2m,W=0.6m,H=1.15m
NURSES DESK-12mm aclyric solid surface countertop with wooden and metal subframe NO. 1
u L=1.5m,W=0.6m,H=1.15m
NURSES DESK-12mm aclyric solid surface countertop with wooden and metal subframe NO. 1
v L=1.8m,W=0.6m,H=1.15m
NURSES DESK-12mm aclyric solid surface countertop with wooden and metal subframe NO. 1
w L=2.4m,W=0.6m,H=1.15m
MEDS STORE DESK-12mm aclyric solid surface countertop with wooden and metal subframe NO. 1
L=2.4m,W=0.6m,H=1.15m

Page 16 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 06: Wood and Plastic

Carried to Summary

Page 17 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 06: Wood and Plastic

Amount (USD)

0
0

0
0

Amount (USD)
0

0
0

0
0

0
0

0
0
0
0
0

Page 18 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 06: Wood and Plastic

0
0
0
0
0

Sum Check
0 0.00

Page 19 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 07: Thermal and Moisture Protection

Item No. Description Unit Quantity Rate (USD)

1 SECTION 07130 - Sheet Waterproofing


1.1 Supply and install 4 mm thick torch applied SBS modified bituminous water- proofing membrane,
with Min. 10 cm overlap and 20 cm skirting with tucked into grooves and pointed with mastic,
flashing including bitumen primer one coat.
a. For Main building roof, with fine granule m2 1,400
b. For service building roof m2 200

1.2 Supply and apply 4mm thick torch applied bituminous waterproofing sheet, with Min. 10 cm
overlap on top of hot liquid asphalt layer complete as per drawings and specifications and approval
of the Engineer.
for wet areas
a. For Main building m2 185

1.3 Supply and install two layers of felt insulation including all necessary works, for all sub-structural,
all as per structural drawings, manufacturer'e instructions, the Contractor shall submit a catalouges
and samples for Engineer's approval
a. For service building m2 385
b. for Grade beams under new block and new rooms foundation m 2 145

2 SECTION 07140 - Cold Fluid Applied Waterproofing


2.1 Supply and apply three perpendicular coats cold fluid applied proofing, all as per structural
drawings, specifications and approval of the Engineer.
For foundation and vertical surfaces and wherever required.
a. For service building m2 385
b. for Grade beams under new block m2 145

3 SECTION 07260 - Vapor Retarders


3.1 Supply and install polyethylene sheets 250 micron, all as per drawings and specifications.
a. below slab on grade and grade beams for service building m2 200
b. For service building roof m2 200
c. for Grade beams under new block m2 65

4 SECTION 07840- Elastic Firestop Sealant


4.1 Supply and install A silicon-based firestop sealant as per drawings and specifications for fire zoning
a. areas, Contractors
For Main building shall submit sample and catalouge to be approved by the Engineer. L.m 450

Carried to Summary

Page 20 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 07: Thermal and Moisture Protection

Amount (USD)

0
0

0
0

0
0

0
0
0

Sum Check
0 0.00

Page 21 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 07: Thermal and Moisture Protection

Page 22 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 08: Openings

Item No.

1
1.1

a.

1.2

a.

Page 23 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 08: Openings

1.3

a.

1.4

a.

Page 24 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 08: Openings

Item No.

2
2.1

a.

2.2
a.

Page 25 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 08: Openings

Item No.

3
3.1

a.

4
4.1

a.

4.2

Page 26 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 08: Openings

Description Unit

DIVISION 8 - DOORS & WINDOWS


Notes:
Steel and Wood Doors
The items shall include supply, fabricate, test and installation of doors made out of approved
quality class I treated timber to be finished as per the given specification and drawings. Discarding
materials with defects that impair quality of carpentry construction and that are too small to use in
fabricating carpentry with minimum joints or optimum joint arrangement. The rate should include
frame cover mold, architrave, middle Push plates and bottom kick plates (stainless steel 316 -Norris
1mm the), all accessories and hardware, door handle, hinges 10cm height, door stopper, required
fully tempered clear glass of 8mm thickness, and all other needed fittings according to
specifications, drawings and Engineers' instructions. The work includes sanding sealer, prime coats,
at finishing (paint or laminated). The contractor shall submit shop drawings for the approval of
Engineer, prior to fabrication. The contractor shall refer to all relevant specifications and drawings
prior to pricing and it shall be his responsibility to complete the works to the entire satisfaction of
the Engineer at no additional cost. All samples shall be provided for Engineers' approval prior to
purchase of material. The contractor shall check the measurement of openings physically at the
site before fabricating the doors and windows.

Rates shall include: (1) Supply, fabricate and installation of doors, windows, made out of approved
quality timber Jak or equivalent to be finish as per the respective specification and drawings. (2)
Hoisting, fixing in position and drilling. (3) Cutting and fitting around obstructions, Bedding and
painting. (3) Nails, screws, glue, etc. (4) Flushed doors and frames shall be primed with sanding
seller, two coats of putty. (5) Pressure impregnating, termite protecting, seasoning and planning all
timber and sand papering to receive final finish. (6) Final Finish (7) All necessary ironmongery union
/ Yale or approved equivalent supplied by authorized dealer appointed by the manufacturer and
approved by the Engineer and as per schedules. Samples of ironmongery should be submitted for
approval prior to purchase. (8) Supplying and fixing steel frame and all the necessary installation
and completion of the work duly instructed the engineer. The width of frame taking into account
the thickness of the wall and thickness of the plastering or ceramic on both sides. (9) Fixing brass
fixing screws, lock sets with 3 keys match with master key system. (10) Preservative treatment for
back of door and door frame in contact with masonry or concrete. (11) All external windows and
doors to be fully surrounded and bonded to adjacent structure with EPDM membranes to agreed
details.

SECTION 08110 : Steel Doors and Frames


Supply, installation and finishing fire rated steel door comprising of hot dipped galvanized steel
sheet 1.25mm thk. for door leaf and 2mm thk. for door frame powder coated with hammer finish.
The work includes, providing and installing all required hardware and accessories (4hinges/side,
locks, handles, ... etc.)of high quality, sanding, priming, puttying, three coats finishing, fixing
properly using anti-rust anchors , repairing any damages and finishing properly around the doors,,
and all necessary related works, complete as shown on drawings, specifications and as per
Engineer's instructions

for main building


Steel doors, FR 90 minutes m2

Supply and install flush steel louver doors, including welding, fixing, fittings, accessories, hardware
sets , painting with epoxy primer and epoxy paint finish and all required as per drawings and
specifications, and per the engineer 's approval.
For service building and roof electrical room m2

Page 27 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 08: Openings

Supply and install steel louver windows 3mm steel plate for louvers, including welding, fixing,
fittings, accessories, hardware sets,painting with epoxy primer and epoxy paint finish and all
required as per drawings and specifications.
For service building and roof electrical room m2

Maintenance of Steel Doors:


Maintenance and repair of steel doors. The work and price include replacing all missing and
damaged hardware, supplies, and accessories (frames, fiber 4mm, hinges, kick plates, locks,
handles, hardware, rubber, and etc.), re-fixing and sealing with silicone properly, cleaning and
polishing, painting including all necessary related works, complete as shown on drawings,
specifications an as per Engineers' instructions

for main building No.

Carried forwa

Page 28 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 08: Openings

Description Unit
Brought forward from previous page

SECTION 08210- Wood Doors


Supply and install solid core flush wood doors with high pressure laminated ( fire rated wherever
required), approved finish as per schedules, details, and specifications including powder coated
For main building
steel frames, welding, painting system, fixing, workmanship, accessories, 1mm stainless steel kick
Wood doorsstainless steel push plate, louver, vision panels ( fully tempered 8mm clear
plate, 1mm m2

Maintenance of Wooden Doors


Maintenance and repair of wooden doors with frames. The work and price include providing and
For main building
replacement of all missing and damaged parts, hardware and accessories of high quality, sanding, No.
priming, puttying and polishing, applying 3coats of wooden paint using a special machine. Also, the
price includes providing and installing stainless steel protection plate (kick plate), stainless steel

Page 29 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 08: Openings

Carried forwa

Description Unit
Brought forward from previous page

Aluminum Doors and Windows


All aluminum profile, sections, ironmongeries and accessories of best quality and free from
manufacturing defects
Rates shall include to be
for: (1) completed
Verify that walland fixed inand
surfaces proper manner
openings areand
readyaccording to the
to receive frames and
specifications
are within and manufacturer
tolerances. (2) All instructions.
accessories, Fabrication
wheels, rails, and
hinges, fixing of
handles, all Aluminum
locks, components
brushes, rubber
SECTION
shall beand08120-out
carried Aluminum Doors and Frames All aluminum is to comply with the relevant
EPDM, angles ofbywindows
experienced
musttradesman.
be the original and of high quality. (3) Rubber beadings,
Supply, casement
rollers, installationstays,
and finishing of full
barrel bolts, body
rings, aluminum
casement leaf doors
fasteners and4mm thick Aluminum
any other necessary tocomposite
sheet of approved
for main building color for paneling., of sizes mentioned hereinafter with thickness not less than
1.5 mm. Comprising of 70 mm X 50 mm aluminum tubes, frames 70 mm X 50 mm of high quality
aluminum
and durable,doors,
6mmDouble
doubleglazing
glass layers 12mm total panels thick (if required) or single clear safety m2

SECTION 08520- Aluminum Windows


Supply and install Aluminum sliding/Fixed windows, (special section, thickness not less than 1.8
mm). Thebuilding
for main price includes all accessories (frames, double glass layers 6mm inner pane,12mm air
space, 6mm outer pane , rubber, and etc.), color and reflectiveness, fixing with anti-rust screws,
aluminum window,
sealing with siliconedouble glazing
properly, complete as shown on drawings, specifications an as per Engineers' m2

Maintenance and repair of Aluminum Windows No.


Maintenance and repair of existing aluminum windows. The work and rate nclude replacing all
missing and damaged parts and accessories (frames, panes, glass 6mm, hinges, locks, handles,
rubber, fly screen with frames, and etc), re-fixing and sealing with silicone properly, cleaning and
polishing, complete as shown on drawings, specifications an as per Engineers' instructions Carried to Summ

Page 30 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 08: Openings

Quantity Rate (USD) Amount (USD)

12 0

25 0

Page 31 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 08: Openings

5 0

4 0

Carried forward 0

Page 32 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 08: Openings

Quantity Rate (USD) Amount (USD)


0

260 0

2 0

Page 33 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 08: Openings

Carried forward 0

Quantity Rate (USD) Amount (USD)


0

50 0

30 0

43 0

Carried to Summary 0 0.00

Page 34 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 08: Openings

Page 35 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 09: Finishes

Item No. Description Unit Quantity Rate (USD) Amount (USD)

DIVISION 9 - FINISHING
1 SECTION 09220- Portland Cement Plaster
All works must be according to drawings, specification and Engineers' instructions. Rates shall
include: (1) Supply of all needed materials, including (cement, sand, expanded metal lath,
corners from galvanized steel mesh, galvanized angles for the corners, windows and external
decoration as well as the use of galvanized wire mesh between concrete and block work,
beads and strips at joints of different backgrounds edges) and workmanship (installation of
scaffolding and dismantling, working platforms, safety nets, etc.). (2) Preparation works by
covering all conduits of electricity, water supplies, etc., with a galvanized wire mesh at least
20cm width coated by mortar (1:1) cement: sand and the work includes removal of wires and
nails and cleaning of surfaces to be ready for plastering. (3) Contractor shall take into
consideration that all – direct and indirect works and expenses required for the completion of
the coming items are included in the unit price. (4) Trimming of concrete chippings, removing
the wires and etc. And cleaning of existing surfaces to be ready for plastering. (5) Checking
out all of the preliminary installation in ceilings and walls such as electrical, water supply and
waste water pipes and repairing the damages if any. (6) The work includes closing all opening
in existing walls, as opening around existing (plumbing, electrical) and between existing walls
and slabs by using Galvanized mesh and mortar cement. (7) Curing with water for at least
three days for each coat. (8) Any cracks between the columns should be treated with Sikaflex.
(9) The first layer of the plastering should be in one direction and should be leveled. (10) This
should be done prior to commencement of plastering and after obtaining a written approval
from the Engineer. Contractor is required to protect existing finishing (tiles, stones, walls) by
covering it. Therefore, contractor is responsible for any damage or dirt occurs in the site as a
result of his work. Payment will be according to the engineering measurement quantities.

Supply, laying and finishing internal plastering 15 mm thick for the damaged areas of walls
and ceilings and where it needs. The work includes removing and peeling the damaged and
feeble areas properly using electrical grinder and wire brush, Repair of cracks in walls by
chipping and remove 30mm wide plaster strip along the crack, fix 20Gauge 12x12mm GI wire
mesh (Chicken mesh) on chipped wall using concrete nails, apply 4mm thick repair grout to
cover the mesh, providing all materials of high quality. Also, the work includes rough primer
nail rendering to form a key with (mix 1:1) cement sand, second layer 13mm: Base-Coat
"Rendering" with (1:3) cement: sand and third layer: Finishing Coat with (1:1) cement: sand.
Works include all materials needed to finish the works according to specifications, drawings
and Engineers' instructions, Price include removal of the existing plaster according to
Engineers' instructions.

1.1 New Plastering to internal walls and ceiling


a. for main building m2 975 0
b. For service building and roof electrical room m² 680 0

1.2 Repair plastering for internal walls and ceiling


a. for main building m2 2,250 0

1.3 External cement and sand plastering


Supply and apply new three coats cement and sand plastering for external walls and
wherever required, work to include metal lath, corner mesh, strip mesh, corner bead, metal 0
lathe sheet and plaster stop bead, all as per drawings and specifications.

a. For service building, roof electrical room and new rooms m2 400 0

Carried forward 0

Item No. Description Unit Quantity Rate (USD) Amount (USD)


Brought forward from previous page 0

2 SECTION 09300 - Tiles


All works must be according to drawings, specification and Engineers' instructions. Rates shall
2.1 include: (1) Samples for approval and all the required tests. (2) Cleaning, mechanical polishing
Floor tiles
and pointing using grout. (3) Local marble must be Grade (A) free cracks and clay flaws. (4)
2.1.1 Supply and the
Measuring install jointlessquantities
stockpiled terrazzo tiles under
of tiles andvinyl sheetsthe
obtaining andEngineer
wherever neededprior
approval size to
a. (300x300)mm
For main building , thickness not less than 30mm , with marble chips bedded on and including
cement sand mortar (1:3), including sand fill to any required thickness, cleaning and polishing m 55 0
2

upon completion, complete as per drawings and specifications.


2.1.2 Providing, laying, and finishing porcelain floor tiles of high-grade glaze porcelain floor tiles, the
a. porcelain tiles, (conformed
size (300x300)mm , anti-slip,tothickness
Europeannotspecification or equivalent) by using a mortar cement
less than 9mm
or special adhesive and to be approved by the Engineer, and tiles water absorption rate shall m2 125 0 5
be less than 0.5 according to ASTM C373 and PTCA. The work includes, supplying and laying

Carried forward 0

Item No. Description Unit Quantity Rate (USD) Amount (USD)


Brought forward from previous page 0

2.2 Walls Tiles


Note: All works of plastering under any kind of walls tiles are included within the price of the
2.2.1 tiles items.
Ceramic Wall Tiles:
a. Supply,
for maininstallation,
building and finishing of high-grade glaze Ceramic wall tiles Size (300x300)mm,
thickness not less than 8mm, the tiles material to (conformed European standard or m2 560 0
equivalent and of approved make) in all colors, shades except burgundy, bottle green, black
2.3 of any size as
SKIRTING: approved
Item includesbyallEngineer-in-Charge,
surface preparationinwork
skirting,
suchrisers of stepsand
as cleaning andscrubbing,
dados, over 12
2.3.1 patchinginstallation,
Supply, defective areas, ..etc. asofper
and finishing 80the
mmspecifications. Item also
height, (conformed include supply
to European and or
standard install
of mortar layer
equivalent) andwith
to bethickness
approvedneeded
by the for levelingglaze
Engineer, skirting with required
porcelain skirts toprojection
match theover walls.
selected
a. for as
All mainperbuilding
related specifications. L.m 1,045 0
porcelain tiles. The work includes preparing surfaces , installing tiles accurately on a layer of
b. For service building
cement-based and roof electrical
glue adhesive, grouting room
and finishing joints properly using cement based L.m 115 0

Carried forward 0

Item No. Description Unit Quantity Rate (USD) Amount (USD)


Brought forward from previous page 0

3 SECTION 09500 - Acoustical Suspended Ceilings


3.1 Mineral fiber acoustical false ceiling
a Providing fabricating and fixing of modular grid type false ceiling at all height as directed of
For main building
600 mm x 600 mm x 15 mm thick, mineral fiber acoustical tegular ceiling tiles of approved m2 740 0
texture, design and pattern and of type classic lite RH- 99 laid on prelude XL exposed grid
3.2 system with
Gypsum 9 mm
board widewith
ceiling T section flanges
medical epoxycolor
paintwhite. The tiles should have Humidity
a Supply
For and
main install 12.5 mm thick suspended ceiling gypsum board painted with medical epoxy
building 2
paint, price to include channel, steel anchor, fixing, painting system , accessories and all m 225 0
required as per drawings, specifications and approval of the Engineer.
3.3 Aluminum false ceiling 0
a Supply
For mainand installation of Aluminum false ceiling, tiles size 600 mm X 600 mm x 1mm thick. of
building
high quality approved by the engineer, to be suspended and installed properly by grid of m2 100 0
suspension system. The rate also includes all it takes and needs to get the work completely
finished according to the technical rules, drawings, and as instructed by the engineer.

Page 36 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 09: Finishes

Carried forward 0

Item No. Description Unit Quantity Rate (USD) Amount (USD)


Brought forward from previous page 0

4 SECTION 09650 -Resilient flooring


* Notes:
All resilient flooring sheets shall be anti bacterial type.
The Contractor shall provide the manufacturer's catlouges for the Engineer's Approval,
catalouges
Cleaning of shall include
existing cutting
flooring and
to be insatallation
ready to recievemethods
the newand all required
flooring sheets details
The installer to maintain the zero level during and after installation using Self Leveling.

4.1 vinyl sheets


a. Supply
For mainand install vinyl sheets of 2mm thickness, heavy duty anti slip, smoothed finish with
building
100 mm full cove former skirting, moisture and fire resistant, complete as per drawings and m2 55 0
specifications.
5 SECTION 09900 - Painting
Note:
Unit rates shall include: (1) All the painting materials used should be approved and tested by
5.1 approved
Supply andlocal laboratory
apply and have
internal high acrylicthe final
semi approved
matt paint , from
Price the
shallEngineer. (2) Supplying
include surface of all
preparation
materials,
of scaffolding, workmanship and toolsand
andtwo
whatever
coats ofelse needed. (3) Preparation of
a. forexisting
surface
surface, maintain
mainincluding
building cleaning
cracks, priming,
surfacesand
properly of dust, dirt,
putty, complete as shown on
and stuck, peeling and removing the m2 2,385 0
drawings and as per specifications the engineer's instructions.
b. For service building and roof electrical room m2 510 0

5.2 Emulsion paint


a. Supply
for mainand apply emulsion paint for ceilings, three coats in addition to putty and priming
building
coat, color to be approved by the Engineer and all according to drawings and specifications. m2 350 0
b. For service building and roof electrical room m2 170 0

5.3 External weather paint


a. Supply and building,
For service apply silicon
roofbased fine room
electrical textured
andweather paint, for external walls, and wherever
new rooms
required, apply according to the manufacturer's instruction, work to include cleaning, and all m2 400 0
according to drawings and specification. Contractor to provide sample to be approved by the
Engineer.

Carried forward 0

Item No. Description Unit Quantity Rate (USD) Amount (USD)


Brought forward from previous page 0

6 SECTION 03350- Concrete Finishing


6.1 Medical Epoxy Flooring
a. Supply
for mainand apply
main self leveling medical epoxy for flooring 3mm thickness with one coat primer
building
on top of trowelled screed, the contractor shall prepare the trowelled screed surface to m2 1,250 0
receive the self leveling epoxy and to be sure that the surface is clean and levelled according
6.2 to manufacturer's
Medical Epoxy paintrecommendations and all as per drawings, specifications and Engineer's
a. Supply
for mainand apply medical epoxy paint for walls not less than 500 micron with one coat
building 2
primer, according to manufacturer's recommendations and all as per drawings, specifications m 485 0
and Engineer's instructions.

7 Radiation protection wall m2 75 0


Supply and apply Radiation protection wall consist of :radiation protection cladding (gypsum
boards with sheet lead coating fixed to metal subframe thickness according to equipment
supplier recommendation), including all related material, fixing, fitting works, skilled labor,
and all necessary related works, complete as shown on drawings, specifications and as per

Sum Check
Carried to Summary 0 0.00

Page 37 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 10: Specialties

Item No. Description Unit Quantity Rate (USD)

1 SECTION 10440 - Signage


1.1 Supply and install signage system, comprising of lazer printed text in both Arabic and English
languages on high quality plastic of 3mm thick, complete with all required mounting decvices, all as
specified and indicated.
for main building
1.1.1 Signs fixed on walls and doors
a. SI-03, 150mmx150mm No. 1
b. SI-07, 75mmx150mm No. 60
c. SI-13, 150mmx150mm No. 22

1.1.2 Ceiling mounted signs


a. SI-02 75mmx150mm No. 18
b. SI-05, 150mmx450mm No. 7
c. SI-12, 100mmx800mm No. 5

2 SECTION 10800- Toilet, Bath and Laundry Specialties


2.1 Supply, install, & fix the following toilet accessories of stainless steel Grade 304, satin finish &
mirrors, all according to drawings, specification and Engineer's instructions. Contractor to provide
samples to be approved by the Engineer for quality, finish and size:
for main building
a. Horizontal grab bar, AX01 No. 12
b. Vertical grab bar, AX02 No. 6
c. Sanitary napkin disposal, AX03 No. 16
d. Toilet paper disposal, AX04 No. 16
e. Soap Dispenser, AX05 No. 30
f. Paper towel dispenser, AX06 No. 30
g. Robe hook, AX08 No. 6
h. Waste bin, AX09 No. 46
Mirrors, 6mm thick, on and including 18mm Lamiwood edge with 2mm solid colour pvc, 3mm x
2.2 3mm bevelled edges and P.V.C back bonded safety film, including all necessary fixings, fittings and
accessories, complete as shown on drawing and specifications
for main building
a. Mirror 900mmx600mm, AX07 No. 19

3 SECTION 10190- Cubicle Curtain, Track and Hardware


3.1 Supply and install cubicle curtain, the curtain fabric shall be 100% flame retardant fibers or filament
a. according to BC 5867, Part 1 & 2 (Type C) and DIN 4102, Part 1 (Class B1: Flame retardant). The
for main building
weight of the fabric shall be not less than 200g/m. Fabric shall be of stable dimensions & shrinkage L.m 130
shall not exceed 3% in each dimension when repeatedly washed with Hospital grade detergent as
4 SECTION
Supply and10260
install- Wall andmounted
surface Corner Guard
crash rail of aluminum clips covered by Acrovyn high impact
4.1 acrylic vinyl at 90cm height, size 150 x 35.4mm with continuous Alum retainer with cushion for
added shock absorption, including fixing, fittings , accessories and all required to complete the job
a. forper
as main building
drawings and the manufacturer's recommendations. L.m 265

Carried to Summary

Page 38 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 10: Specialties

Amount (USD)

0
0
0

0
0
0

0
0
0
0
0
0
0
0

Sum Check
0 0.00

Page 39 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 11: Equipment

Item No. Description Unit Quantity Rate (USD) Amount (USD)

1 SECTION 11700 - Medical Equipment

1.1 Bedhead units


Supply and install custom-made horizontal surface-mounted patient’s bedhead unit (BHU), made of
high-quality heat-treated aluminum extrusion, fixed with galvanized steel brackets that should be
fixed during the plastering phase, with a front panel made of 1mm colored aluminum, the unit
colors shall be chosen and approved by the hospital’s management, the upper or lower panels shall
be removable to provide easy access to individual components, complete with all required works
and as per related medical drawings.

Eclampsia
a. Bedhead Units, Horizontal, ER- Treatment/ Observation (M-B-042) No. 3 0
ICU
b. Bedhead Units, Horizontal, ICU (Local Custom-Made) (M-B-030) No. 2 0
Internal medicine
c. Bedhead Units, Horizontal, Inpatient, Procedure (Local Custom-Made) (M-B-021) No. 4 0
Surgery
d. Bedhead Units, Horizontal, PACU (M-B-035) No. 4 0
e. Bedhead Units, Horizontal, Procedure (M-B-055) No. 2 0

Carried to Summary 0

Page 40 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 11: Equipment

Sum Check
0.00

Page 41 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 16: Electrical Works

Item No. Description Unit Quantity Rate (USD)

16.1 Section 16620-Automatic Transfer Switch (ATS)


16.1.1 Supply, install, test and commission automatic transfer switch complete as specified and shown on
the drawing with all devices and accessories.
a ATS-1 "1250A" No. 1
b ATS-2 "1250A" No. 1

16.2 Section 16440-Main Distribution Board


16.2.1 Supply, deliver, install, test and commission main distribution board (MDB) (Form 4B construction)
as specified and shown on the drawings, including main molded case or air circuit breakers,
outgoing molded case circuit breakers (MCCB), busbars, protection devices, electronic metering
and monitoring device for the main feeder. The works include all related civil works for installation.
Contractor should co-ordinate with Electric Power Company in order to connect the main power
cables to the main circuit breaker. The main distribution board shall incorporate a compartment for
3 phase kilowatt hour meter. Note: All electrical equipment must be approved by supervision &
client engineers before being supplied.

a MDB-Hospital No. 1
b EMDB No. 1

16.3 Section 16435 Generators Paralleling (Totalizing) Switchgear


Supply, install and commission Generators Paralleling (Totalizing) Switchgear including main
incoming and motorized outgoing circuit breakers, busbars and all accessories needed.
Generators Paralleling (Totalizing) Sync Switchgear.as shown on the drawing and speciifed on the
a specfications " SYNC-PANEL" No. 1

16.4 Section 16261 - Uninterruptible Power Supply (UPS)


Supply, install test and commission UPS system. The unit rate shall include all sealed lead acid
maintenance free 30 minutes backup batteries and chargers (Rating as shown on the drawings),
inverters, rectifiers and automatic change-over switch, all control and protection devices,
connection terminals and all required inter- assemblies control wiring and cabling, push-buttons
and indicator lamps, metal enclosure and steel plinths, built-in ventilation fans, cables and/or wires
from the respective isolating switch to the unit, termination of the main incoming and outgoing
cables, protection against dust and corrosion, and all other requirements and accessories as shown
on the drawings and as called for in the specifications and in accordance to relevant codes of
practice and highest prevailing engineering standards. The UPS shall be on-line three-phase
input/output high efficiency, rating as shown on the drawings, with built-in static by-pass, in-put
power factor correction, and equipped with RS232 and remote auto shut down and management
software. (All UPSs shall be capable of working in parallel mode when applicable).

a UPS (100 KVA) No. 1

16.5 Section 16440 - Sub-Main Distribution Boards


Supply, install, test and commission sub main distribution boards (SMDB) (Form 2B construction) as
a specified
SMDB-G and shown on the drawings, including main molded case or air circuit breakers, outgoing No.
molded case circuit breakers (MCCB), busbars, protection devices, electronic metering and 1
b ESMDB-G
monitoring device for the main feeder. The works include all related civil works for installation. No. 1
c USMDB-G No. 1

16.6 Section 16443-Motor Control Centers (MCC)


Supply, install, test and commission the following motor control centers (MCC) as specified and
a shown
EMCC-Ron the drawings. MCC shall be form 2B constructions. The MCC should include main
incoming and outgoing circuit breakers, busbars, measuring, metering, all starting devices, No. 1
b EMCC-SITE
protection, and indicating lamps as per specifications and shown on the drawings. No. 1
c MCC-R No. 1

Carried forward

Item No. Description Unit Quantity Rate (USD)


Brought forward from previous page
16.7 Section 16445-Distribution Boards
Supply, install, connect and commission distribution boards including enclosure, main isolator,
a miniature outgoing circuit breakers, contactors, busbars and other needed accessories.
DB.IN No. 1
b EDB.IN No. 1
c DB.SU No. 1
d EDB.SU No. 1
e UDB.SU No. 1
f DB.EC No. 1
g EDB.EC No. 1
h UDB.EC No. 1
i DB.ICU No. 1
j EDB.ICU No. 1
k UDB.ICU No. 1
l DB-SITE No. 1

Page 42 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 16: Electrical Works

16.8 Section 16780-Isolated Power System


16.8.1 Supply, install, connect and commission Isolated Power Supply System panels, including all wires,
a MCBs, MCCB, isolation transformers, all monitoring devices, LIM(Line insulating monitor), Indicator
IPS.OR1
light on IPSS cover, double pole switches, and all needed works as specified and shown on the No. 1
b IPS.OR2
drawings No. 1
c IPS.OR3 No. 1
d IPS.MO1 No. 1
e IPS.MO2 No. 1

16.9 Section 16125 - Earthing Systems


Supply ,Test, connect grounding system for the main electrical room ,MDB where the price shall
include all required materials, cables, earth pits and earth bars in order to meet the desired and
a accepted grounding resistance in the drawings , specifications and engineer's instruction. L.S 1

Supply ,Test, connect grounding system for the Generator and the body of the Generator where
the price shall include all required materials, cables, earth pits and earth bars in order to meet the
b desired and accepted grounding resistance in the drawings , specifications and engineer's L.S 1
instruction.

c Supply ,Test, connect grounding system for all low current systems where the price shall include all L.S 1
required materials,
Supply ,Test, cables,
connect earth
earthing pits
grid and earth
system bars in order
for operation roomtowhere
meet the
the desired andinclude
price shall accepted
all
d groundingmaterials,
resistance in theearth
drawings , specifications and engineer's L.S 5
required cables, pits and earth bars in order to meetconstruction
the desired and accepted
grounding resistance in the drawings , specifications and engineer's construction.

Carried forward

Item No. Description Unit Quantity Rate (USD)


Brought forward from previous page

16.10 Section 16122-Feeding Power Cables


Supply, install, test and commission the following power cables as specified and shown on the
drawings.
(3x6 mm2The cables shall) be installed on cable trays or in UPVC conduits. The works include the
CU/XLPE/PVC
a conduits, Manholes size minimum as shown on the drawings,galvanized cable trays mounted L.M 10
b (2x25mm2 +or
horizontally 1x16mm2
vertically,CU/XLPE/LSOH ) FIRE RATED
cable ladders mounted in electrical shafts , electrical trench and UPVC L.M 135
c (2x35+ 1x16mm2 CU/XLPE/LSOH ) FIRE RATED L.M 165
d (5x6 mm2 CU/XLPE/PVC) L.M 35
e (5x6 mm2 CU/XLPE/LSOH) L.M 315
f (5x6 mm2 CU/XLPE/LSOH) FIRE RATED L.M 200
g (5x10 mm2 CU/XLPE/PVC) L.M 35
h (5x10 mm2 CU/XLPE/LS0H) L.M 90
i (5x16 mm2 CU/XLPE/PVC) L.M 55
j (4x35 mm2 CU/XLPE/PVC + 1x16 mm2 PVC/ECC ) L.M 30
k (4x50 mm2 CU/XLPE/PVC + 1x25 mm2 PVC/ECC ) L.M 30
l (4x35 mm2 CU/XLPE/LSOH + 1x16 mm2 PVC/ECC ) L.M 30
m (4x70 mm2 CU/XLPE/LSOH + 1x35 mm2 PVC/ECC) L.M 30
n (4x95 mm2 CU/XLPE/LSOH + 1x50 mm2 PVC/ECC) FIRE RATED L.M 20
o (4x120 mm2 CU/XLPE/PVC + 1x70 mm2 PVC/ECC) L.M 10
p (4x185 mm2 CU/XLPE/PVC + 1x95 mm2 PVC/ECC) L.M 20
q (4x240 mm2 CU/XLPE/SWA/PVC + 1x120 mm2 PVC/ECC) (inside electrical trench and UPVC L.M 400
conduits
(4x185 mm2), with concrete encasement
CU/XLPE/SWA/PVC at road
) (inside crossing
electrical areasand
trench andUPVC
manholes.
conduits ), with concrete
r L.M 70
encasement
(4x300 mm2atCU/XLPE/SWA/PVC
road crossing areas) and manholes.
(inside electrical trench and UPVC conduits ), with concrete
s L.M 80
encasement
(1S.C. 630)mm2at road crossing areas and
CU/XLPE/AWA/PVC manholes.
CABLES (inside electrical trench and UPVC conduits ), with
t L.M 70
concrete encasement at road crossing areas and manholes.
16.11 Section 16140 - Wiring Devices
16.11.1 Socket Outlets
Supply, install, test and connect the following socket outlets including wires, cables, PVC or
galvanized conduits and all accessories up to distribution board as per drawings and specifications.

Page 43 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 16: Electrical Works

a 13A, 230V single phase, 3-PIN socket outlet with switch. No. 83
b 13A, 230V single phase, 3-PIN socket outlet with switch, weatherproof. No. 1
c 13A, 230V single phase, 3-PIN double socket outlet with switch. No. 62
d 13A, 230V single phase, 3-PIN double socket outlet with switch, weatherproof. No. 6
e 13A, 230V single phase, 3-PIN double socket outlet with switch desk/counter mounted. No. 4
f 30A, 230V single phase, 3-PIN clean, anti-germs, Industrial socket outlet. No. 3
g 13A Fused, switched spur with flex outlet, shuttered No. 4
h Connection unit with flex outlet wall mounted for medical equipment No. 15
i Connection unit with flex outlet ceiling mounted for medical equipment No. 3
j 20A, 230V single phase, 3-PIN fused connection unit with double pole switch for FCU,IU, E.H &CSU No. 29
k 16A, 230V single phase, 3-PIN socket outlet with switch. No. 8

16.11.2 Power Point for Mechanical Equipment


Supply, install, test and connect the following power points for mechanical equipment , including
a wires, cables,
Power PVC
point for or galvanized
Electric conduits
water heater, walland all accessories
mounted upPrice
split unit. to equipment from electrical
includes conduits, panel
20A double
to theswitch.
unit as shown as per drawings and specifications. No. 15
pole

Carried Forward

Item No. Description Unit Quantity Rate (USD)


Brought forward from previous page

16.11.3 Power Point for Medical Equipment's


Supply, install, test and connect the following power points for medical equipment's & BHU's ,
a including
Power pointwires,
for cables,
D-PANEL PVC orfrom
Fed galvanized
Normalconduits and all accessories up to equipment's from
electrical panel to the unit as shown as per drawings and specifications. No. 2
b Power point for D-PANEL Fed from Emergency No. 2
c Power point for IN-PANEL Fed from Normal No. 4
d Power point for IN-PANEL Fed from Emergency No. 4
e Power point for IN2-PANEL Fed from Normal No. 2
f Power point for IN2-PANEL Fed from Emergency No. 2
g Power point for E-PANEL Fed from UPS No. 4
h Power point for E-PANEL Fed from Emergency No. 4
i Power point for IE-PANEL Fed from UPS No. 1
j Power point for IE-PANEL Fed from Emergency No. 1
k Power point for S.C.P. Fed from IPS No. 5
l Power point for PNDT01 Fed from IPS No. 6
m Power point for PNDT02 Fed from IPS No. 6
n Power point for BHU-P Fed from UPS No. 3
o Power point for BHU-P Fed from Emergency No. 3
p Power point for OR-PANEL Fed from IPS No. 2
q Power point for BHU-R Fed from UPS No. 1
r Power point for BHU-R Fed from Emergency No. 1
s Power point for ICU-BOX Fed from UPS No. 2
t Power point for BHU-ICU Fed from UPS No. 4
u Power point for BHU-ICU Fed from Emergency No. 4
v Power point for BHU-ASS Fed from Emergency No. 1
w Power point for BHU-ASS Fed from Normal No. 1

16.11.4 Disconnect Switch Isolator


Supply, install, test and commission the following heavy duty disconnect switch isolators as
a specified
Disconnectand shown
switch on the drawings.
isolator,1 The25A,
phase rating disconnect
IP-65 switch should suit the equipment rating,
single phase for single phase equipment, and 3 phase for 3 phase equipment. The outdoor isolators No. 19
b Disconnect
and switch isolator,1
inside mechanical roomsphase ratingwaterproof
shall have 32A, IP-65 enclosure with IP=65.Isolater upto 25A include No. 2
c Disconnect switch isolator,3 phase rating 25A, IP-65 No. 19
d Disconnect switch isolator,3 phase rating 32A, IP-65 No. 2
e Disconnect switch isolator,3 phase rating 40A, IP-65 No. 1
f Disconnect switch isolator,3 phase rating 125A, IP-65 No. 1

16.11.5 Lighting Points


Internal/External Lighting Points
Supply, install and connect internal/external lighting points including wires, conduits, lighting
a switches, ceiling point.
Internal lighting rose and all needed to complete the job as per specifications ,drawings &
engineer's instructions No. 325
b Internal lighting point ( exit signs & emergency kit ) No. 125
c Exhuast fan point. No. 5

Page 44 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 16: Electrical Works

Carried Forward

Item No. Description Unit Quantity Rate (USD)


Brought forward from previous page

16.12 Section 16510 - Lighting Fixtures


16.12.1 Internal Lighting Fixtures
Supply, install, connect and commission the following internal lighting fixtures as per drawings and
a specifications.
TYPE (L1) No. 106
b TYPE (L2) No. 21
c TYPE (L3) No. 10
d TYPE (L4) No. 5
e TYPE (L5). No. 40
f TYPE (L6). No. 4
g TYPE (L7). No. 18
h TYPE (L8). No. 62
i TYPE (L9). No. 11
j TYPE (L10). No. 15
k TYPE (L13). No. 14
l TYPE (L16). No. 19

16.12.2 Exit Signs & Emergency kit Fixtures


Supply, install, connect and commission the following exit signs & emergency kit fixtures as per
a drawings
TYPE (E1) and specifications.
EMERGENCY KIT. Wires shall be fire rated. No. 95
b TYPE (E2). No. 29
c TYPE (E3). No. 3

16.13 Section 16710- Fire Detection System


Note
Supply,: New Firetest
install, Alarm
andSystem whichaddressable
commission will be connected from
type fire rehabilitation
equipment area to the
in accordance existing
with NFPA area
shall be theand
72/BS5839 same brand
NFPA for proper
70/BS7671 integrity,
inclusive of contractor
all equipmentshalland
invisgate and check
accessories, brandcharger,
batteries, of existing
fire alarm
internal system before
conductors and/or submiting below system
cables, switches, power item.
supply, Automatic telephone dialer, the job
a 4 Loop
shall Fire Alarm
include Control
but not limitedPanel
to installation, termination, commissioning and testing and any job No. 1
b Addressable Photoelectric Smoke detector No. 130
c Addressable Photoelectric Smoke detector above false ceiling No. 53
d Addressable Rate of rise heat detector No. 2
e 24V DC Conventional Indoor Flasher No. 29
f 24V DC Conventional Outdoor Siren/Flasher No. 1
g Addressable Zone Module No. 8
h Addressable Control Module No. 12
i Manual call/ Break Glass point at 1200mm FFL No. 16
j End of line resistor No. 16
k short circuit isolator No. 15
l Fire alarm point, where the job includes but not limited to supply, install, test, terminate, labelling, No. 253
commissioning and shop drawing approval from civil defence department of fire devices fire alarm
and fireman devices system, wiring, G.I conduits, supporting items, civil work as described in this
document. Contractor shall execute fire alarm and fireman devices system in building/hospital

Carried Forward

Item No. Description Unit Quantity Rate (USD)


Brought forward from previous page

16.14 Section 16690 - Structure Cabling System


The item unit rate shall include all PVC and/or galvanized steel conduits/ trunking, telephone
and/or data RJ-45 socket outlet and/or socket outlet RJ-45 for CCTV camera point on wall, ceiling,
or counter mounted as indicated, galvanized steel wall and/or floor mounting box, UTP CAT6 cable
through 25mm PVC conduit with pull boxes from the appropriate patch panel (s) to the served

Page 45 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 16: Electrical Works

Note; Outlets face plate color, material shape and type of finishes shall be as per the Engineer
approval,
Telephoneback boxes
and/or Dataof Outlets
the outlets
shallshall be coordinated
be measured with the
in Number approved type /model of the
(No.).
outlets
Note : intended
New Data to be used
System on this
which will project,
be and must
connected from be included in the
rehabilitation areaprice of the
to the point.area shall
existing
Note; where telephone or data socket outlets installed in a multi-compartments trunks or in floor
be the same brand for proper integrity, contractor shall investegate and check
box; the outlets, conduits and cabling to the nearest distribution floor patch panel shall brand of be
existing
included
Data system before submiting below system item.
in this item, multi-comportments trunks and floor box shall be priced under separate item
Note; The rack size include the patch panels & switches needed for all IP systems
a 1 x RJ45 wall mounted Voice/Data outlet complete with 1x4P UTP CAT6 cables and conduits from No. 35
b outlet
ditto astoabove
relatedbutpatching connectivity.
desk mounted. No. 2
b Single RJ45 for CCTV camera and door control panel ceiling/wall mounted (outlet, cabling and No. 22
c patching
Data/Voice arePoints
includeforinBHU's,
the structure
PNDT's,cable
WAC'ssystem Job).with 1x4P UTP CAT6 cable
& S.C.Ps No. 68
d 1 x RJ45 wall mounted Voice/Data outlet complete with 1x4P SFTP CAT6 cables and conduits from No. 13
e outlet to related
Data/Voice Pointspatching connectivity.
for BHU's, PNDT's, WAC's & S.C.Ps with 1x4P SFTP CAT6 cable No. 42
f 1.0m UTP Cat6 Patch cord No. 175
g 48 port UTP CAT6 patch panel No. 5
h 12 port universal LC SMOF/MMOF connector ( as needed , where the contractor shall investigate No. 2
the existing condition and supply the correct type) fiber patch panel. The works includes pigtails
fusion: New
Note , cassette and tray.
structure cabling systemSystem
which will be connected from rehabilitation area to the
16.15 Section 16690 - Structure Cabling
existing area shall be the same brand for proper integrity, contractor shall investegate and check
brand of existing structure cabling system before submiting below system item.
a IP-PABX: supply, install, terminate , test and commission Hybrid PABX and telephone set . The job No. 1
b shall include
30U free butdata
stand not cabinet
limited to the set with
complete , MDFaccessories
, batteries , internal wiring and all required work to
complete the job according to section 16740-of specifications, drawings and engineer instruction. No. 1
c 12U wall mounted data cabinet complete with accessories No. 3
d 48 port UTP CAT6 switch panel No. 3
e 48 port UTP CAT6 switch panel No. 1
f 24 port UTP CAT6 switch panel No. 1
g 24 port UTP CAT6 POE switch panel No. 1

Carried Forward

Item No. Description Unit Quantity Rate (USD)


Brought forward from previous page

16.16 Section 16737 - Access control System


Supply, install, test and connect the following Access control system network, the price shall
a include wires, conduits,
Master Access boxes, control wires, data switch, UTP CAT6 cables and any interfacing
Control Panel
hardware for integration with other systems as required to make a complete operating system as No. 1
b Key Pad
shown on the drawings No. 14
c Monitored Electrical Lock No. 14
d Door Release Push Button No. 14
e Junction Box No. 14
f 2-Door Control Panel No. 3
g 4-Door Control Panel No. 2
h Software L.S 1

16.17 Section 16729 - IP based CCTV System


Note
Supply,: New CCTV
install, system which
terminate, willcommission
test and be connected from rehabilitation
IP based CCTV system,area to the
the job existing
shall includearea shall
empty
be
PVCthe same brand
conduits, forrope,
pulling proper
pullintegrity, contractor
boxes, fittings, civil shall
worksinvestegate and check
and any required job brand
needed ofto
existing
complete
CCTVsystem
the job needed before submiting
to complete the below system item.
job according to section 16729 and other related sections of
a CCTV SYSTEM drawings
specifications, Network ,NVR
and Engineer's instructions. Note the wiring from cameras , connection to L.S 1
b Fixed in ceiling recessed/Surface mounted dome networkable camera day night varifocal 3.8-13mm No. 15
c , 1/2.7"
Full CMOSDaylight
function, image sensor as specified
3.8-13mm varifocalinnetworkable
Section 16729. cameras complete with outdoor housing IP No. 2
d 66 (NEMA
Archive 4X) , 1/3"
recorder CMOS
server imagetosensor
capable record, 90
3MP sensor
days pixels
(10 FPS for, 150
as specified in Section
high resolution 16729.
cameras). L.S 1
e Contractor to submit
Software Video Management calculations of HDD required. (the HDD price shall included in price)
No. 1
f PC with 1No. (40" LED screen) No. 1

Page 46 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 16: Electrical Works

Carried Forward

Item No. Description Unit Quantity Rate (USD)


Brought forward from previous page

16.18 Section 16735 - Voice Evacuation System


The item unit rate shall include all PVC conduits, fire rated wires from the panels to the served
speaker,
Note galvanized
: New steel trunking,
Voice evacuation systemcomplete with
which will beallconnected
in and outfrom
cables up to the served
rehabilitation speaker
area to the as
per the manufacturer’s
existing area shall recommendations,
be the same brand and allintegrity,
for proper other accessories needed in accordance
and to the
a 6W loudspeaker
relevant codes ofwith tap changer
practice and transformer,
highest Recessed
prevailing incontractor
engineering false shall
ceiling,
standards.
investegate
IP20 check
No. 45
brand of existing Voice evacuation system before submiting below system item.
b End of line resistor No. 8
c Interface to fire alarm system L.S 1
d Digital voice command center (main rack) as specified and shown on the drawings with amplifire. No. 1
16.19 Section 16790 - Nurse Call System
Supply, installation, Testing & Commissioning of following Nurse Call system Components including
connection
Note : New wires,
Nurse cables,
call systemconduits,
whichpower will besource
connectedwhere needed, galvanized
connected trunks, complete
from rehabilitation area to the in all
respects
existing with shall
area all necessary
be the accessories
same brand as proper
for required for completion
integrity, contractor & successful
shall operation
investegate and ofcheck
the
a Over Door
system Light No. 16
brand ofasexisting
per drawings,
Nurse call medical
system specialist requirements,
before submiting below relevant
systemstandard
item. & technical
b Connection to BHU&MED including staff to staff , nurse call & nurse emergency as per drawings No. 15
c and needed connections per medical specialist
intercome inside operation theater No. 5
d staff assist & code blue station No. 3
e Toilet Set Points (Including Toilet Emergency Push Button - bath station, Toilet reset unit with No. 1
f emergency pull button)
Nurse call system main courier controller No. 1
g Annunciator panel No. 3
h Nurse call station No. 3
i Main nurse call station No. 1
j. Toilet Set Points (Including Emergency Ceiling Suspended Pull Cord, Toilet Emergency Push Button - No. 3
bath station, Toilet reset unit with emergency pull button)
16.20 Connection to Main Hospital Existing Systems
Supply, installation, Testing & Commissioning of following Connection to Main Hospital Existing
a Systems
connectionincluding
to mainconnection wires, cables,
hospital transformer andconduits,
main lowpower voltage source
panelwhere needed,
, this will deemedgalvanized
to inculde
trunks,UPVC
complete in all"respects with all necessary accessories as required for completion & L.S 1
b empty
connection conduits
to main 4x100mm
hospital PABX ", from
from location
the new of newto
PABX service
existingbuilding
PABX upto
, existing
including all transformer
, conduits ,
successful
and low operation
voltage panel of, the system
including all asmanholes
per drawings,
, medical
conduits , specialist
civil works , requirements,
pull robes , end relevant
caps ,etc. L.S 1
c civil works , pull robes , end caps ,manholes and all accessories needed
connection to main hospital Fire Alarm Control Panel , from the new FACP to existing FACP , ,etc.
L.S 1
d including
connection allto, cables, conduits
main hospital , civil
Data works, , from
Cabinet pull robes
the new , end caps
data ,manholes
cabinet and alldata
to existing accessories
cabinet ,
needed ,etc. L.S 1
e including
connection allto, cables, conduits
main hospital , cables,
Nurse civil works
Call Control Panel, pull robes
,from the, end
newcaps Nurse ,manholes
call controlandpanel
all to
accessories needed ,etc. L.S 1
f existing Nurse call control panel , including all , cables, conduits , civil
connection to main hospital CCTV rack , from the new CCTV rack to existing CCTV rack , including works , pull robes , end
caps ,manholes and all accessories needed L.S 1
all , cables, conduits , civil works , pull robes,etc.
, end caps ,manholes and all accessories needed ,etc.
Carried to Summary

Page 47 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 16: Electrical Works

Amount (USD)

0
0
0
0
0

0
0
0
0
0

0
0
0

0
0
0
0
0
0
0
0
0
0
0
0
0

Amount (USD)
0

0
0
0
0
0
0
0
0
0
0
0
0

Page 48 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 16: Electrical Works

0
0
0
0
0

0
0

Amount (USD)
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

Page 49 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 16: Electrical Works

0
0
0
0
0
0
0

Amount (USD)
0

0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0

0
0
0

Page 50 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 16: Electrical Works

Amount (USD)
0

0
0
0
0
0
0
0
0
0
0
0
0

0
0
0

0
0
0
0
0
0
0
0
0
0
0
0

Amount (USD)
0

Page 51 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 16: Electrical Works

0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0

Amount (USD)
0

0
0
0
0
0
0
0
0

0
0
0
0
0
0

Page 52 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 16: Electrical Works

Amount (USD)
0

0
0
0
0

0
0
0
0
0
0
0
0
0
0

0
0
0
0
0
0
0
Sum Check
0 0

Page 53 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 15: Mechanical Works

Item No. Description Unit Quantity Rate (USD) Amount (USD)


0
0
Supply. Install, Test and Commission the following items in accordance with the Specifications,
0
Drawings, Preambles and Engineer's approval
0
1 Section (1) - HVAC System 0
Ventilation and Air Conditioning 0
1.1 Section 15810 0
Supply, install, test and commission galvanized sheet steel duct with 22-gauge thickness and G90,
flange method connection for all ducts connections, including all supports and hangers, brackets,
1.1.1 sealant, volume dampers, and all necessary accessories to complete the job in perfect running m2 905 0
order, in accordance with drawings, specifications, and the approval of the engineer.

0
Supply, install, test and commission thermal insulation for duct work of rigid glass fiber, with a
thickness of 24 mm and density of 24 Kg/m3, including aluminium vapor barrier thickness and all
1.1.2 necessary accessories to complete the job in perfect running order, in accordance with drawings, m2 740 0
specifications, and the approval of the engineer.

0
Supply, install, test and commission thermal insulation for duct work of rigid glass fiber, with a
thickness of 40 mm and density of 48 Kg/m3, and 0.7mm thick aluminum steel sheet cladding,
1.1.3 including aluminium vapor barrier thickness and all necessary accessories to complete the job in m2 281 0
perfect running order, in accordance with drawings, specifications, and the approval of the
engineer.

0
1.2 Section 15850 0
Supply, install, test and commission air distribution terminals, made of extruded aluminum
1.2.1 complete with frame, fixing trim, air directional vanes, dampers, the plenum box and insulated 0
flexible ducts etc.… as specified and shown on drawings
1.2.1.1 4-Way Square Ceiling Diffusers (Supply) 0
a SD-1, (150x150)mm No. 2 0
b SD-2, (230x230)mm No. 6 0
c SD-3, (300x300)mm No. 7 0
d SD-4, (380x380)mm No. 2 0
e SD-5, (450x450)mm No. 1 0
0
1.2.1.2 4-Way Square Ceiling Diffusers (Return) 0
a RD-2, (230x230)mm No. 4 0
b RD-3, (300x300)mm No. 7 0
c RD-4, (380x380)mm No. 1 0
d RD-5, (450x450)mm No. 3 0

1.2.1.3 Registers (Supply) 0


a S.R-1, (250x200)mm No. 3 0
b S.R-2, (510x250)mm No. 1 0

1.2.1.4 Registers (Return) 0


a R.R-1, (250x200)mm No. 3 0

1.2.1.5 Exhaust Air Grill 0


a EG-1, (150x150)mm No. 17 0
b EG-2, (200x200)mm No. 3 0
c EG-3, (250x250)mm No. 1 0

1.2.1.5 Return Grill 0


a RG-1, (600x300)mm No. 8 0

1.2.1.5 Door Grill 0


a DG-1, (300x250)mm No. 3 0
0

0
0
0
Carried Forward 0

Item No. Description Unit Quantity Rate (USD) Amount (USD)


Brought forward from previous page 0
1.2.3 Supply, install, test and commission fresh air louver with sand trap connected to fresh air duct, 0
a including all structural
(750x500)mm, Fresh airsupport, fitting,
louver with painting
primary as&per
filter specifications,
sand trap and engineer instruction
No. 1 0

Page 54 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 15: Mechanical Works

b (800x600)mm, Fresh air louver with primary filter & sand trap No. 1 0
c (950x500)mm, Fresh air louver with primary filter & sand trap No. 1 0
d (500x300)mm, Fresh air louver with primary filter & sand trap No. 1 0
e (500x350)mm, Fresh air louver with primary filter & sand trap No. 3 0
f (1000x600)mm, Fresh air louver with primary filter & sand trap No. 1 0

0
1.2.4 Supply, install, test and commission perforated supply diffuser with (HEPA) filter, including all 0
a structural support, fitting, painting as per specifications, and engineer instruction
(1200x600)mm No. 18 0

1.3 Section 15837 0


1.3.1 Supply, install, test and commission ventilation exhaust and fresh fan complete with flexible 0
a connections, wirefan,
EXF-01, Propeller mesh,Aircounter flanges, anti vibration mountings, control panel, supports, back
flow 35 L/s
draft damper, electrical connections (MCC), wiring off-on nearby isolating weather proof switches, No. 7 0
b EXF-02,
as shownCenterfugal
on drawings Inline
andDirect Drive, Air flow 225 L/ s, 100 Pa
as specified. No. 1 0
c EXF-03, Centerfugal Inline Direct Drive, Air flow 140 L/ s, 100 Pa No. 2 0
d EXF-04, Centerfugal Inline Direct Drive, Air flow 265 L/ s, 200 Pa No. 1 0
e EXF-05, Centerfugal Inline Direct Drive, Air flow 710 L/ s, 200 Pa No. 1 0
f EXF-06, Centerfugal Inline Direct Drive, Air flow 225 L/ s, 100 Pa No. 1 0
g EXF-07, Centerfugal Inline Direct Drive, Air flow 195 L/ s, 90 Pa No. 1 0
h EXF-08, Centerfugal Inline Direct Drive, Air flow 180 L/ s, 70 Pa No. 1 0
g EXF-09, Centerfugal Inline Direct Drive, Air flow 60 L/ s, 75 Pa No. 1 0
h EXF-10, Centerfugal Inline Direct Drive, Air flow 105 L/ s, 90 Pa No. 1 0
i EXF-11, Centerfugal Inline Direct Drive, Air flow 290 L/ s, 90 Pa No. 1 0
j EXF-12, Centerfugal Inline Direct Drive, Air flow 195 L/ s, 90 Pa No. 1 0
k FAF-01, Centerfugal Inline Direct Drive, Air flow 285 L/ s, 180 Pa No. 1 0
l FAF-02, Centerfugal Inline Direct Drive, Air flow 300 L/ s, 180 Pa No. 1 0
m FAF-03, Centerfugal Inline Direct Drive, Air flow 355 L/ s, 180 Pa No. 1 0
n EXF-COM, Propeller fan, Air flow 170 L/s No. 1 0
o EXF-CLY, Propeller fan, Air flow 200 L/s No. 1 0

1.4 Section 15741 0


1.4.1 Supply, install, test and commission Air handling unit, direct-expansion (DX) coils, all 0
interconnecting (refrigerant grade) copper pipe work between the AHU and the condensing units,
complete with DX coil, condensate pan, fan, motor, starters, filters, vibration isolator, rooms 0
a AHU-01
thermostat, necessary valves, control panel, insulations and all necessary accessories and No. 1 0
- Calculated Total Cooling Capacity: 10.70 kW.
b AHU-02 No. 1 0
- Calculated Total Cooling Capacity: 11.50 kW.

0
Carried Forward 0

Item No. Description Unit Quantity Rate (USD) Amount (USD)


Brought forward from previous page 0
c AHU-03 No. 1 0
- Calculated Total Cooling Capacity: 11.60 kW.

d AHU-04 No. 1 0
- Calculated Total Cooling Capacity: 12.70 kW.
e AHU-05 No. 1 0
- Calculated Total Cooling Capacity: 37.20 kW.
f AHU-06 No. 1 0
- Calculated Total Cooling Capacity: 28.30 kW.
1.5 Section 15710
1.5.1 Supply, install, test, and commission heat pump condensing unit, full inverter type, R-410a
a refrigerant, including
CU-01, Cooling refrigerant
Load 10.70 kW pipes, supports, electrical connection, condensate pipe, and all
related works, as shown on drawings, specifications and engineer instruction. No. 1 0
b CU-02, Cooling Load 11.50 kW No. 1 0
c CU-03, Cooling Load 11.60 kW No. 1 0
d CU-04, Cooling Load 12.70 kW No. 1 0
e CU-05, Cooling Load 37.20 kW No. 1 0
f CU-06, Cooling Load 28.30 kW No. 1 0

Page 55 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 15: Mechanical Works

0
Carried Forward 0

Item No. Description Unit Quantity Rate (USD) Amount (USD)


Brought forward from previous page 0
1.6 Section 15741
Supply, install, test, commission and maintain VRF system (Heat Pump Invertors), including the
indoor ducted
all control Concealed
wiring andbetween
and cabling wall mounted types
outdoor andand outdoor
indoor units,units with direct-expansion
refrigerant gas line between(DX)an
1.6.1 coils,
indoor allunit
interconnecting
and thealso (refrigerant
condensing grade) copper
unit following pipe requirements
supplier's work betweenshall
the indoor and the
be insulated andoutdoor
vapor
the liquid
units, line shall be insulated and vapor sealed, power connections between the isolator
sealed.and
switch Additionally,
the outdoorin those anti-vibration
cases where thepadcapillary tubes serving an indoor unitbase
are with
installed in
the VRF system
condensing shall be unit,
unit, selected on 37°c ambaint fortemperature
the outdoor unit 23°c
and and concrete
indoor temperature all
atthe
accessories,
cooling mode, control and electric
0°c ambaint connections
temperature as shown
and 22°c indoorontemperature
drawings andatas specified.
heating mode . The
compressors should guarantee a continuous operation even if trouble occurs at an indoor unit.
1.6.1.1 Outdoor Units
a VRF-01, Cooling Capcity 23.40 kW No. 1 0
b VRF-02, Cooling Capcity 18.70 kW No. 1 0
c VRF-03, Cooling Capcity 15.90 kW No. 1 0
1.6.1.2 CEILING SUSPENDED INDOOR
a CSU-01, total cooling 3.4 kW, total heating 1.20 kW No. 10 0
b CSU-02, total cooling 3.60 kW, total heating 1.60 kW No. 5 0
c CSU-03, total cooling 1.60 kW, total heating 0.50 kW No. 5 0
d CSU-04, total cooling 4.00 kW, total heating 1.90 kW No. 1 0
e CSU-05, total cooling 2.90 kW, total heating 1.50 kW No. 1 0
f CSU-06, total cooling 2.20 kW, total heating 0.60 kW No. 1 0
g CSU-07, total cooling 2.1 kW, total heating 0.60 kW No. 1 0
h CSU-08, total cooling 2.30 kW, total heating 0.80 kW No. 1 0
i CSU-09, total cooling 3.90 kW, total heating 0.90 kW No. 1 0
j CSU-10, total cooling 3.60 kW, total heating 0.90 kW No. 1 0
k CSU-11, total cooling 2.10 kW, total heating 0.30 kW No. 1 0
l CSU-12, total cooling 1.40 kW, total heating 0.20 kW No. 1 0
m CSU-13, total cooling 2.30 kW, total heating 0.90 kW No. 1 0
n CSU-14, total cooling 2.2 kW, total heating 0.50 kW No. 1 0
o CSU-15, total cooling 3.3 kW, total heating 0.85 kW No. 1 0
p CSU-16, total cooling 1.60 kW, total heating 0.50 kW No. 1 0
q CCS-01, total cooling 3.30 kW, total heating 1.90 kW No. 1 0
r CCS-02, total cooling 6.00 kW, total heating 3.60 kW No. 1 0

0
1.6.2 Supply, install, test and commission split air-condition unit, full inverter type, R-410, cold and heat
a unit; shall include
ISU-1/OU-1, Total indoor
capacityunit,
7.00outdoor
kW unit, refrigerant pipes, 80mm dia. PVC sleeves for
refrigerant pipes, supports, electrical connection, room thermostat, condensate pipe, electrical No. 2 0
a ISU-2/OU-2,and
connection Totalallcapacity
related 3.50 kWas shown on drawings, specifications and engineer instruction.
works, No. 2 0

1.7 Section 15020


1.7.1 Supply, install, test and commission CPVC condensate water pipe PN16 work complete with traps
a fittings
Diam. 25 and
mmaccessories for drain of fan coil units , as specified and shown on drawings.
Lm 80 0
b Diam. 50 mm Lm 20 0

0
Carried Forward 0

Item No. Description Unit Quantity Rate (USD) Amount (USD)


Brought forward from previous page 0
Section (2) - Plumbing System
2 Domestic Water System

2.1 Section 15020

Page 56 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 15: Mechanical Works

2.1.1 Supply, install, test and commission PPR-CT pipes class 2 (S-3.2) complying with (EN ISO 15874) or
a SDR
Diam.7.4
20complying
mm with DIN 8077, DIN 8078 for cold water supply for pipes runs in ceiling voids,
shafts, Internally exposed and exposed outside, for exposed pipes to the sun, shall be insulated by Lm 230 0
b Diam. 25
closed cellmm
rubber insulation 6 mm thickness insulation and protected by smooth aluminum Lm 120 0
c Diam. 32 mm Lm 45 0
d Diam. 40 mm Lm 65 0
e Diam. 50 mm Lm 20 0
f Diam. 63 mm Lm 15 0
0
2.1.2 Supply, install, test and commission PPR-CT pipes class 2 (S-3.2) complying with (EN ISO 15874) or 0
a SDR
Diam.7.4
20complying
mm with DIN 8077, DIN 8078) for hot water supply/return with insulation for pipes
runs in ceiling voids, shafts, Internally exposed and exposed outside, for exposed pipes to the sun, Lm 190 0
b Diam. 25 mm
shall be insulated by closed cell rubber insulation 6 mm thickness insulation and protected by Lm 80 0
c Diam. 32 mm Lm 10 0
d Diam. 40 mm Lm 15 0
0
2.2 Section 15420 0
2.2.1 Supply, install, test and commission hot water cylinder (10 bar), including fixings, electric heating 0
element, temperature
Ref.EWH-01(50 L) control system, interconnecting pipe works, valves, vents, temperature
a gauges, control panel, wiring, gauges, sensors, bases, drain valves, angle valves, flexible pipe, all No. 14 0
b Ref.EWH-02(300 L)
safety valves, and any other necessary items to complete the job in perfect condition all as No. 1 0
0
2.3 Section 15430
2.3.1 Supply, install, test and commission plumbing fixtures and related mixers, the price shall include all 0
accessories (angle valves, wall washers, gaskets, screws and inserts, angles, supports, wall
MX1 Toilet seat
a connectors, smell preventers, sealant and consumables), flexible pipes for drain, satinless steel No 11 0
b MX2 Hand
flexible Spray
at all counter sinks, execution of related civil works including material, the installation of No 16 0
c MX3 Shower No 6 0
d MX4 Wash Basin and Basin Mixer for toilets No 17 0
e MX5 Wash Basin and Basin Mixer for H.C toilets No 2 0
f MX6 Wash Basin and Basin Mixer for rooms No 10 0
g MX7 Toilet Squat Pan Seat No 5 0
h Scrub (single station) with Mixer for Opertaion room No 5 0

0
Carried forward 0

Item No. Description Unit Quantity Rate (USD) Amount (USD)


Brought forward from previous page 0

3 Drainage System
3.1 Section 15150
Above Ground Drainage
3.1.1 Supply, install, test and commission above ground soil, waste overflow, and venting, solvent weld
UPVC
Diam.50pipe
mmclass 4, for all floors, vent pipe and rain water pipes, complete with fittings, supports,
a brackets, hangers, clips, sleeves, and all necessary accessories to complete the installations as Lm 200 0
b Diam. 80 mm
specified and shown on drawings: Lm 50 0
c Diam. 110 mm Lm 60 0

Below Ground Drainage


3.1.2 Supply, install, test and commission below ground soil, waste overflow, and venting, running inside
the ground
Diam.50 mmfloor & site, solvent weld UPVC pipe class 4, for all floors and vent pipe, complete with
a fittings, back filling and all necessary accessories to complete the installations as specified and Lm 55 0
b Diam. 80
shown onmm
drawings: Lm 140 0
c Diam. 110 mm Lm 60 0
d Diam. 160 mm Lm 230 0

3.2 Section 15155


3.2.1 Supply, install, test and commission Stainless steel floor drains complete with Stainless steel covers
(cover to be
Ref. Floor coordinated
Drain (FD) 80mmwith
dia.tiling), strainers, trap and all necessary accessories in accordance
a with specifications and drawings. No. 53 0
3.3 Section 15155
3.2.1 Supply, install, test and commission Stainless steel shower drains complete with Stainless steel
covers (coverDrain
Ref. Shower to be(SD)
coordinated
80mm dia. with tiling), strainers, trap and all necessary accessories in
a accordance with specifications and drawings. No. 4 0
0
3.2.2 Supply, install, test and commission floor clean out with cover and all necessary accessories all as in 0
drawings
Ref. Cleanand
outspecified.
(FCO) 110mm dia.
a No. 14 0
Supply, install, test and commission Rain Water Outlet with cover and all necessary accessories all
3.2.3 as in drawings and specified.
a Ref. (RWO) 110mm dia. No. 2 0
Supply, install, test and commission vent cap for the vent pipe, stainless steel type, complete with
3.2.4 all necessary accessories all as in drawings and specified.
a Vent cap, 110mm dia. No. 5 0
b Vent cap, 80mm dia. No. 3 0
c Vent cap, 50mm dia. No. 3 0

3.2.5 Supply, install, test and commission sewage manholes. including all necessary civil works,
excavation,
Depth ≤ 1200backfilling, concrete base, reinforcement, plastering of internal and exposed external
mm, (600x600)
a walls, benching with all necessary to hand over in good operating condition also the price including No. 14 0
manhole covers as indicated in drawings and specified. Manholes more than 100cm deep shall be

Page 57 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 15: Mechanical Works

b Depth > 1200 mm, (Dia 900) No. 4 0

3.2.6 Supply, install, test and commission trench drain (T.D) with heavy duty ductile iron grating with
110mm
(LxWxD)outlet connection
1500x250x200 mmwith P-trap. Sizes as shown on drawings
a No. 4 0

Carried forward 0

Item No. Description Unit Quantity Rate (USD) Amount (USD)


Brought forward from previous page 0

4 Section (3) - Fire Fighting System


0
0
4.1 Section 15520 0
4.1.1 Supply, install, test, commission of portable fire extinguisher, include all necessary accessories as 0
specified
Type (CO2)and
6kgshown on drawings
a No. 4 0
b Type (POWDER) 6kg No. 15 0

4.1.2 Supply, install, test and commission fire hose cabinets (Stainless steel Doors) recessed in the wall, 0
complete
HRC-01 with swivel bracket, manual hose nozzle, pipe connection, 30 meters long Ø25mm, hose
a in rubber non kickable type with fire extinguisher ABC powder 6kg and all necessary accessories as No. 6 0
specified and shown on drawings. 0
4.2.3 Supply, install, test and commission black seamless steel pipes schedule 40, as specified including
protection
Dia. 40 mmfor pipes which run under ground and above ground inside the building, Jointing
a between pipes and fittings shall be by grooving, including flexible connections, end caps, hangers, Lm 25 0
brackets and automatic air vents all as specified. Price shall include all civil works as specified and
5 Section (4) - Compressed Air System
0
0
5.1 Section 15480 0
5.1.1 Supply , Install and commission air compressor for LABS & CSSD & LAUNDRY screw type stationary , 0
11-bar with 1ºC
Compressed dew point.
air plant The price
COMP-02 include
with air pre filter,
receiver, Airdischarge
free air receiver, valves, pressure
144 L/min reducing
with Pressure
a valves, test line, and all accessories to complete the work. No. 1 0
Required 9 bar
5.1.2 Seamless black steel pipes schedule 40, to compressed air pipe works, including all fittings, 0
threading,
Ø15mm and all accessories as shown on drawings and as per specification
a Lm 35 0
0
5.2.3 Supply, install, test, commission and maintain pressure reducing valve assembly Complete with
black
Ø15mm steel pipes and all required accessories, as specified and shown on drawings.
a No. 1 0

5.2.4 Supply, install, test, commission and maintain Pressure Gauge with isolating valve, complete with
black
Ø15mm steel pipes and all required accessories, as specified and shown on drawings.
a No. 4 0

Carried forward 0

Item No. Description Unit Quantity Rate (USD) Amount (USD)


Brought forward from previous page 0

6 Section (5) - Medical Gases

Page 58 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 15: Mechanical Works

6.1 Section 15480


6.1.1 Supply, install, test & commission Copper pipe degreased, light gauge, solid drawn, phosphorous
de-oxidized,
Dia. 35mm non-arsenical tube conforming to BS-EN 1057:1996 (formerly BS 2871, Part 1, Table
a 'X'). Suitable for use with BS 864 Part 2 fittings, installed, connected, and tested complete with Lm 110 0
b Dia. 28mmfor HKD type concrete inserts with drop rod and munsen ring brackets, spaced to HTM
allowance Lm 580 0
c Dia. 22 mm Lm 300 0
d Dia. 15 mm Lm 840 0
e Dia. 12 mm Lm 270 0

6.1.2 Supply, install, test and commission Emergency isolation valve complying to HTM 0201 and C11,
housed within aOutlet)
AVSU-GR-01(3 Lockable box with “break glass” safety Feature emergency access, including NIST
a Connection ports, secondary alarm and all required accessories, as specified and shown on No. 1 0
b AVSU-GR-02(3
drawings. Outlet) No. 1 0
c AVSU-GR-03(3 Outlet) No. 1 0
d AVSU-GR-04(4 Outlet) No. 1 0
e AVSU-GR-05(4 Outlet) No. 1 0
f AVSU-GR-06(3 Outlet) No. 1 0
g AVSU-GR-07(3 Outlet) No. 1 0
h AVSU-GR-08(3 Outlet) No. 1 0
i AVSU-GR-09(5 Outlet) No. 1 0
j AVSU-GR-10(5 Outlet) No. 1 0
k AVSU-GR-11(5 Outlet) No. 1 0

6.1.3 Supply, install, test and commission Skid mounted, lateral channel, directly driven, AGS pump
assembly.
AGS Pump-1,complete
capacitywith
130control
L/min, panel
duplexassembly incorporating
type, (1 DUTY, pressure switch for alarm signal
1 STAND-BY)
a connections, drip leg drains for exhaust line one vacuum flow regulation valve and pressure switch. Set 5 0

6.1.4 Supply, install, test and commission Vacuum plant must complying Fully with the requirements of
both
Vacuum C11Plant
& HTM 02-01, three
(VACP-01), number,
triplex, free airoil-Flooded
discharge rotary vane,
490 L/min directly-
with driven vacuum
two vacuum receiver Pumps and
each one
a duplex filter assemblies with electrical control panel and Bacterial filter group duplex. Including Set 1 0
500 liter.
vacuum collector Ø108mm. Suitable for 3 phase 400v, 50 Hz electrical supply.
Supply, install, test and commission Medical air plant Complying fully with HTM 02-01. using three
6.1.5 rotary screw type air compressors, Desiccant dryers andpressure
filter assembly
Compressors operate at a nominal 10 bar, with Control sensedand steel
in the Receiver
receiver. vessel(s).
With by-
supplied
pass and complete with actual
test line, duplex Digital
1-st and dew
2-nd point readout. Air pressure reducing set all, Suitable for
a Compressed
3 phase 400V,air50plant (COMP-01)
Hz electrical free
supply. airstage filter
discharge groups.
1200 L/min with two air receiver each one 1000 Set 1 0
liter.

Carried forward 0

Item No. Description Unit Quantity Rate (USD) Amount (USD)


Brought forward from previous page 0

6.1.6 Supply, install, test and commission Primary, secondary, and Reserve manifolds Complying to C11
and
2x10HTM 0201,
Primary O2suitable
manifoldforheader
use with the
with manifold
control control
panel, paneltype
Cylinders installed
J and extension headers
a complete with tail pipes, cylinders, isolating valve, check valves and all required accessories as No. 1 0
b 2x5 Primary
specified andO2 manifold
shown header with control panel, Cylinders type J
on drawings. No. 1 0
c 2x2 Secondary O2 manifold header with control panel, Cylinders type J No. 1 0

d 2x2 Primary N2O manifold header with control panel, Cylinders type G No. 1 0
e 2x1 Secondary N2O manifold header with control panel, Cylinders type G No. 1 0
f 2x3 Reserve MA4 manifold header with control panel, Cylinders type J No. 1 0
g 2x4 Reserve SA7 manifold header with control panel, Cylinders type J No. 1 0
h O2 cylinder type J for ICU Dep. (Emergency Case) No. 3 0
i CO2 cylinder for Major Operation room Dep. No. 6 0
j Medical Gases Master Alarm Control Panel with repeater indicator alarm panel No. 1 0

6.1.7 Supply, install, test & commission medical gas terminal units installed, connected, and tested
complete
Oxygen (O2)with plastic fascia plate, 150mm stub pipe and all required accessories, for all types of
Outlet
a the bed head unit referring to the medical BOQ, as specified and shown on drawings. No. 56 0
b Vacuum (V) Outlet No. 56 0
c Nitrous Oxide (N2O) Outlet No. 14 0
d Medical Air (MA4) Outlet No. 54 0
e Surgicl Air (SA7) Outlet No. 6 0
f AGSS Outlet No. 14 0
g CO2 Outlet No. 3 0

Page 59 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 15: Mechanical Works

Carried to Summary 0

Page 60 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023 Division 15: Mechanical Works

Sum Check

Page 61 of
PROJECT NAME: Dhamar General Hospital - Dhamar DATE: July /2023

Grand Summary

Bill No. Description Page Amount (USD)

1 Division 01 to 10: Civil and Architectural works

Division 01: General Requirements

Division 02: Site Construction

Division 03: Concrete Works

Division 04: Masonry Works

Division 05: Metal Works

Division 06: Woods and Plastics

Division 07: Thermal and Moisture Protection

Division 08: Openings

Division 09: Finishes

Division 10: Specialties

Division 11: Equipment

2 Division 15: Mechanical Works

3 Division 16: Electrical Works

a. Total of Bills

b. Percent Addition/Reduction (%)

c. Addition/Reduction Amount (USD)= (axb)

d. Total of Bills including (Addition/Reduction) (USD)=(a+c)

e Total Amount (USD), Numbers and Words

Page 62 of