You are on page 1of 2

Team Member Names: Anthony Morici, Emerson LaForge, Kristi Kola Team Member Names: Anthony Morici, Emerson

Team Member Names: Anthony Morici, Emerson LaForge, Kristi Kola

Date: 01/31/2024 Date: 2.2.2024

We finished wall #1. We built walls #6 and #8. Stub wall #15 and the railing were We finished wall #7 and started wall #3. We cut out the tread and tread support
also completed. We also started walls #7 and #14. and also connected the rail to frame #9. Started editing pictures on Photoshop.

Team Member Names: Anthony Morici, Emerson LaForge, Kristi Kola Team Member Names: Anthony Morici, Emerson LaForge, Kristi Kola

Date: 02.14.2024
Date: 02.08.2024

Started the day finishing wall #3 and #14. We built walls #10, #9, and #2. We also Today was a shortened class so we didn’t have much time, but we completed the
glued together our spiral staircase. Finished cutting out the pictures on canva and steps. We cut the railing pieces and glued them to the stairs along with the rope
started a floor plan in Revit. for the top of the railing.
Date. 02.15.2024
Team Member Names: Anthony Morici, Emerson LaForge, Kristi Kola
02.21.24 Team Member Names: Anthony Morici, Emerson LaForge, Kristi Kola

We started assembling the walls and frames. We put up frames 4,6,7,8 and 9 and walls
Started assembling the framework. Placed frames 9, 8, and 7 and placed walls 2,2, and
1,16, 3, 10, 14, 2, 14, 6, 9, 13, 7, and 8. Attempted to make the Revit model 3D.
16. Laser cut ourselves out of he kssjebbjjh

Team Member Names: Anthony Morici, Emerson LaForge, Kristi Kola Team Member Names: Anthony Morici, Emerson LaForge, Kristi Kola

Date: 02.27.2024
02.29.2429.24

Placed some of the second floor. Built frames 1, 2, and 3. Cut the hole in frame so
We placed walls 11 and 12. Put the stairs in place. Placed frame 5 after that. that the stairs can fit in the correct spot. We pinned wall 16 in place.
Covered some holes and repaired some walls that were weak.