CONTENTS
1. PURPOSE....................................................................................................................
2. SCOPE.........................................................................................................................
3. REFERENCES.............................................................................................................
4. DEFINITIONS.............................................................................................................
5. RESPONSIBILITIES...................................................................................................
6. INSTRUCTIONS.........................................................................................................
1 PURPOSE
2 SCOPE
3 REFERENCES
Management Documents
4 DEFINITIONS
5 RESPONSIBILITIES
Department Managers are responsible for ensuring that personnel working under their
control are aware of and apply the requirements of this Procedure and resulting
work instructions.
Detailed responsibilities for the various departments involved are given in Section 6.0.
6 INSTRUCTIONS
General
Evaluation of Importance
The problem shall be analysed to determine its root cause or causes, and
consideration shall be given to the following lines of enquiry:
e. Checking audit reports, historical reports and data from past projects
including Client complaints to establish whether the problem has
occurred before, or whether the problem is associated with particular
suppliers or subcontractors.
d. Notifying other Bechtel Group companies so that they may avoid the
problem.
Project Management
Engineering
Engineering shall review requests for concessions and specification waivers from
Construction and from suppliers and subcontractors, for technical acceptability.
Such requests shall be individually evaluated and disposition advised and an
analysis made if a significant number arise from one cause. (Corrective action
may in this case involve either changing a design, specification requirement and
specified work method, or confirming the need for compliance with the original
requirements.)
Procurement
Procurement shall input into project weekly and monthly reports information
concerning significant non-conformities at suppliers and subcontractors.
Construction
Where requests for concessions and specification waivers arise from either
Company or subcontractor manufacture and construction operations, such
requests shall be transmitted to Engineering for assessment.