Professional Documents
Culture Documents
Variable Load Factors 9. Plant Factor – is the ratio of the average load to
1. Reserve over peak or reserve capacity over and the equipment rating supplying the load.
above the peak load – is the plant capacity less
the peak load. Average Load
Plant Factor=
Reserved Over Peak Load = Plant Capacity – Peak Load Equipment Rating Supplying the Load
Problems
1. A central station is supplying energy to a community
through two substations. One substation feeds four
distributing circuits; the other, six. The maximum daily
recorded demands are: Power Station – 12000 kW
Substation A 6000 kW Substation B 9000 kW
Feeder 1 1700 kW Feeder 1 620 kW
Feeder 2 1800 kW Feeder 2 1500 kW
Feeder 3 2800 kW Feeder 3 1000 kW
Feeder 4 600 kW Feeder 4 2900 kW
Feeder 5 2200 kW
Feeder 6 3000 kW