You are on page 1of 2

VARIABLE LOADS AND THEIR SIGNIFICANCE 2.

Average Load – is the ratio of the energy


produced (in kW-hr) to the number of hours.
Variable Load Terminology
 Load Curve – refers to the graph used to Average Load=
Energy Produced, kW-hr
represent the relationship between the Number of Hours
demanded load and time sequence. It is the
3. Load Factor – is the ratio of the average load to
graphical representation of electrical
the peak load. The value to obtained is always less
consumption for 24-hr period with amount of
than one.
electricity consumed in kW as ordinates and
hours of the day from 12MN to 12NN to 12 MN Average Load
as abscissas. Load Factor=
Peak Load
 Load Duration Curve - the graphical presentation
of the number of hours in year duration which 4. Power Factor – is the ratio of the actual power to
1000 kW, 2000 kW, 3000 kW and so on, is the apparent power.
demanded.
 System – a group of customers served by a certain Average Load
Load Factor=
transformer, a group of transformers served by Peak Load
the feeder, etc.
5. Demand Factor – is the ratio of the actual
 Monthly Load Curve – is the average daily load
maximum demand to the connected load. The
curves over a one-month that is used in
value to be obtained is always less than one.
establishing rates. Actual Maximum Demand
 Annual Load Curve – is the average of the daily Demand Factor=
Connected Load
load curves over a period of one year that is used
in determining the annual load factor. 6. Diversity Factor – is the ratio of the sum of the
 Load Duration Curve – is obtained from the same individual maximum demands to the maximum
data as the daily load curves for one year or a simultaneous demand. The value to be obtained
period of 8760 hours. is always greater than one.
 Base-load power plants – include steam,
hydroelectric and geothermal power plants. Sum of Individual Demands
Diversity Factor=
 Peak-load power plants – include diesel-electric Maximum Simultaneous Demand
and gas turbine power plants.
7. Plant Capacity Factor – is the ratio of the annual
kW-hrs produce to the product of the kW plant
capacity and the operating hours.

Actual Energy Produced


Capacity Factor=
Maximum Energy Produced on the Same Period

8. Plant Use Factor – is the ratio of the annual kW-


hrs produced to the product of the kW plant
capacity and the operating hours.

Annual Energy Produced, kW-hr


Plant Use Factor=
(Plant Capacity) (Number of Operating Hours)

Variable Load Factors 9. Plant Factor – is the ratio of the average load to
1. Reserve over peak or reserve capacity over and the equipment rating supplying the load.
above the peak load – is the plant capacity less
the peak load. Average Load
Plant Factor=
Reserved Over Peak Load = Plant Capacity – Peak Load Equipment Rating Supplying the Load
Problems
1. A central station is supplying energy to a community
through two substations. One substation feeds four
distributing circuits; the other, six. The maximum daily
recorded demands are: Power Station – 12000 kW
Substation A 6000 kW Substation B 9000 kW
Feeder 1 1700 kW Feeder 1 620 kW
Feeder 2 1800 kW Feeder 2 1500 kW
Feeder 3 2800 kW Feeder 3 1000 kW
Feeder 4 600 kW Feeder 4 2900 kW
Feeder 5 2200 kW
Feeder 6 3000 kW

Calulate the diversity factor between a.)


substations, b.) feeders on substation A, c.)
feeders on substation B.
10. Utilization Factor – is the ratio of the maximum
system demand to the rated system capacity. 2. The annual peak load on a 15000 kW power plant
is 10500 kW. Two substations are supplied by this
Maximum System Demand plant. Annual energy dispatch through substation
Utilization Factor=
System Rated Capacity A is 27500000 kW-hrs with a peak load of 8900
kW, while 16500000 kW-hr are sent through B
11. Operation Factor – is the ratio of duration of with a peak at 6650 kW. Neglect line losses. Find
actual service to the total expected duration. a.) the diversity factor between substations, and
b.) the capacity factor of the power plant.
Duration of Actual Service
Operation Factor=
Total Duration of the Considered Period

12. Annual Capacity Factor – is the ratio of the annual


kW-hr produced to the plant capacity, in kW,
times 8760 hours.

Annual Energy Produced, kW-hrs


Annual Capacity Factor=
(Plant Capacity, in kW)(8760 hrs)

You might also like