TVM + ARCHITECTS Agenda for Meeting No.

0180
ASIA PACIFIC MEDICAL CENTER AKLAN CONSTRUCTION PROJECT

Date : November 29, 2023


Subject : AGENDA FOR MEETING NO. 0180
Thru : ENGR. DANNY FALLE (TCCI)
ENGR. BELTRAN FABULA (24INCH)
ENGR. ROWEL TAPIL (RMT)
ENGR. RANDY CACAYURIN (SYNCHRONIZE)
ENGR. JOHN RIC D. MORALES (JRDM)
ENGR. MEYNARD GELINDON (CPCI)
MAR FABIAN (FABIAN KITCHEN)
Attendees :

DISCUSSIONS RESPONSIBLE DATE REMARKS


PARTY NEEDED

1.0 APPROVAL OF PREVIOUS


MINUTES All
(Coordination Meeting Minutes No.
0179)

STRUCTURAL WORKS

2.0 PROJECT STATUS as of TCCI


NOVEMBER 2023

3.0 PERIMETER FENCING & ROAD COMPLETED


WORKS UPDATE Subject for Issuance of Partial
Completion

ARCHITECTURAL & INTERIOR FIT OUT WORKS

4.0 PROJECT STATUS as of


NOVEMBER 2023 BALANCES PER FLOOR:

Basement:
*Project Accomplishment
Ground Floor:
( % as of November 29, 2023)
Second Floor:

4.1 UPDATE OF WORKS Third Floor:

Fourth Floor:

Fifth Floor:

Sixth Floor:

TVM+ARCHITECTS
TVM + ARCHITECTS Agenda for Meeting No. 0180
ASIA PACIFIC MEDICAL CENTER AKLAN CONSTRUCTION PROJECT

Seventh Floor:

Roofdeck:

Lower Helipad:

Upper Helipad:

5.0 MANPOWER UPDATE

6.0 SAFETY REPORT

SITE DEVELOPMENT AUXILIARY


BUILDINGS

5.0 PROJECT STATUS as of Powerhouse -


NOVEMBER 2023
Warehouse -
*Project Accomplishment
MRF Building -
( % as November 29, 2023)
Guardhouse -
*Percentage of Delay
Covered Sidewalk –
( % as November 29, 2023)

6.1 UPDATE OF WORKS

PLUMBING WORKS

6.0 PROJECT STATUS as of BALANCES PER FLOOR:


NOVEMBER 2023
Basement:

*Project Accomplishment Ground Floor:

( % as of November 29, 2023) Second Floor:

*Percentage of Delay Third Floor:

( % as November 29, 2023) Fourth Floor:

TVM+ARCHITECTS
TVM + ARCHITECTS Agenda for Meeting No. 0180
ASIA PACIFIC MEDICAL CENTER AKLAN CONSTRUCTION PROJECT

6.2 UPDATE OF WORKS Fifth Floor:

Sixth Floor:

Seventh Floor:

Roofdeck:

Lower Helipad:

Upper Helipad:

FIRE PROTECTION WORKS

7.0 PROJECT STATUS as of BALANCES PER FLOOR:


NOVEMBER 2023
Basement:

*Project Accomplishment Ground Floor:

( % as November 29, 2023) Second Floor:

*Percentage of Delay Third Floor:

( % as of November 29, 2023) Fourth Floor:

7.1 UPDATE OF WORKS Fifth Floor:

Sixth Floor:

Seventh Floor:

Roofdeck:

Lower Helipad:

Upper Helipad:

ELECTRICAL WORKS

8.0 PROJECT STATUS as of


NOVEMBER 2023 BALANCES PER FLOOR:

Basement:
*Project Accomplishment
Ground Floor:
( % as of November 29, 2023)
Second Floor:
*Percentage of Delay
Third Floor:
( % as of November 29, 2023)
Fourth Floor:

8.1 UPDATE OF WORKS Fifth Floor:

TVM+ARCHITECTS
TVM + ARCHITECTS Agenda for Meeting No. 0180
ASIA PACIFIC MEDICAL CENTER AKLAN CONSTRUCTION PROJECT

Sixth Floor:

Seventh Floor:

Roofdeck:

Lower Helipad:

Upper Helipad:

ELECTRONICS & AUXILLARY WORKS

9.0 PROJECT STATUS as of


NOVEMBER 2023 BALANCES PER FLOOR:

*Project Accomplishment Basement:

( % as of November 29, 2023) Ground Floor:

*Percentage of Delay Second Floor:

( % as of November 29, 2023) Third Floor:

9.1 UPDATE OF WORKS Fourth Floor:

Fifth Floor:

Sixth Floor:

Seventh Floor:

Roofdeck:

Lower Helipad:

Upper Helipad:

MECHANICAL WORKS

10.0PROJECT STATUS as of BALANCES PER FLOOR:


NOVEMBER 2023
Basement:

*Project Accomplishment Ground Floor:

( % as of November 29, 2023) Second Floor:

*Percentage of Delay Third Floor:

( % as of November 29, 2023) Fourth Floor:

9.1 UPDATE OF WORKS Fifth Floor:

Sixth Floor:

TVM+ARCHITECTS
TVM + ARCHITECTS Agenda for Meeting No. 0180
ASIA PACIFIC MEDICAL CENTER AKLAN CONSTRUCTION PROJECT

Seventh Floor:

Roofdeck:

Lower Helipad:

Upper Helipad:

EXTERIOR/INTERIOR GLASS WORKS & FAÇADE

11.0PROJECT STATUS as of BALANCES PER FLOOR:


NOVEMBER 2023
Basement:

*Project Accomplishment Ground Floor:

( % as of November 29, 2023) Second Floor:

*Percentage of Delay Third Floor:

( % as of November 29, 2023) Fourth Floor:

9.1 UPDATE OF WORKS Fifth Floor:

Sixth Floor:

Seventh Floor:

Roofdeck:

Lower Helipad:

Upper Helipad:

MEDICAL GAS

12.0PROJECT STATUS as NOVEMBER BALANCES PER FLOOR:


2023
Basement:
*Project Accomplishment
Ground Floor:
( % as of November 29, 2023)
Second Floor:
*Percentage of Delay
Third Floor:
( % as of November 29, 2023)
Fourth Floor:

9.1 UPDATE OF WORKS Fifth Floor:

Sixth Floor:

TVM+ARCHITECTS
TVM + ARCHITECTS Agenda for Meeting No. 0180
ASIA PACIFIC MEDICAL CENTER AKLAN CONSTRUCTION PROJECT

Seventh Floor:

Roofdeck:

Lower Helipad:

Upper Helipad:

VINYL FLOORINGS & HANDRAILS

13.0PROJECT STATUS as of BALANCES PER FLOOR:


NOVEMBER 2023
Basement:

*Project Accomplishment Ground Floor:

( % as of November 29, 2023) Second Floor:

*Percentage of Delay Third Floor:

( % as of November 29, 2023) Fourth Floor:

Fifth Floor:
9.1 UPDATE OF WORKS
Sixth Floor:

Seventh Floor:

Roofdeck:

Lower Helipad:

Upper Helipad:

ELEVATOR & ESCALATOR

14.0PROJECT STATUS as of BALANCES PER FLOOR:


NOVEMBER 2023
Basement:

*Project Accomplishment Ground Floor:

( % as November 29, 2023) Second Floor:

*Percentage of Delay Third Floor:

( % as of November 29, 2023) Fourth Floor:

Fifth Floor:

9.1 UPDATE OF WORKS Sixth Floor:

TVM+ARCHITECTS
TVM + ARCHITECTS Agenda for Meeting No. 0180
ASIA PACIFIC MEDICAL CENTER AKLAN CONSTRUCTION PROJECT

Seventh Floor:

Roofdeck:

Lower Helipad:

Upper Helipad:

KITCHEN & DIETARY

15.0 PROJECT STATUS as of


NOVEMBER 2023

*Project Accomplishment

( % as of November 29, 2023)

*Percentage of Delay

( % as of November 29, 2023)

9.1 UPDATE OF WORKS

BUILDING MANAGEMENT SYSTEM

16.0PROJECT STATUS as of
NOVEMBER 2023

*Project Accomplishment

( % as of November 29, 2023)

*Percentage of Delay

( % as of November 29, 2023)

9.1 UPDATE OF WORKS

TVM+ARCHITECTS
TVM + ARCHITECTS Agenda for Meeting No. 0180
ASIA PACIFIC MEDICAL CENTER AKLAN CONSTRUCTION PROJECT

OTHER MATTERS

DISCUSSIONS:

Thank You!

Engr. Marlon Pilante


Project Manager

Prepared by:
Ar. Earl Stanley Laurente
TVM+Architects
Email:
tvmarchitecs.pilante@gmail.com
tvmarchitects@yahoo.com
ar.earlstanleylaurente@gmail.com

TVM+ARCHITECTS