Jha - Installation of Tower Crane
Jha - Installation of Tower Crane
Receiving equipment/materials at
the site (the reception and
Traffic Hazard
unloading of the parts must be
performed systematically)
3. GROUND
ASSEMBLE OF Material Falls, Environmental
Using mobile crane
COUNTER JIB AND hazard
SUPPORT BARS
Hand injury and equipment
Bolting, hammering, and screwing
damage
4. ERECTION and
INSTALLATION OF Material Falls, Environmental
Using mobile crane
COUNTER JIB AND hazard
SUPPORT BARS
• Material Falls,
Environmental hazard Falling
objects cause head injuries.
• Electric shocks cause
6. ERECTION and instant death.
INSTALLATION OF Using mobile crane • Death and severe injuries
OPERATOR CABIN due to Wire rope struck the
other worker,
• Fatal injuries due to
Collision with people or objects
when articulating.
Nothing follows
PROJECT, Hann Reserve Project
OWER CRANE
SAFETY CONTROL MEASURES
• Tool Box Talks includes the proper wearing and correct use of the Full Body Safety Harness.
• Pre-training of how to use a double lanyard, and ensuring the 100% tie-off
• Provide Full Body Safety Harness with double lanyards (color coded) for all erectors
• Only a trained/experienced person is allowed to do the task
• All work required supervision
• Restriction (close barricades) of the working area,
• warning signs “DANGER” Crane Lifting
• PPE shall be worn all time
• All materials and tools to be used at heights shall be properly secure and tied off
• Ensure that the electrical supply box is locked and power is turned off.
• An only qualified electrician is approved to do the task
• Ensure all electrical connections are waterproof and heavy insulated
• Tool Box Talks includes the proper wearing and correct use of the Full Body Safety Harness.
• Pre-training of how to use a double lanyard, and ensuring the 100% tie-off
• Provide Full Body Safety Harness with double lanyards (colour coded) for all erectors
• Only a trained/experienced person is allowed to do the task
• All work required supervision
• Restriction (close barricades) of the working area, warning signs “DANGER” Crane Lifting
• PPE shall be worn all time
• All materials and tools to be used at heights shall be properly secure and tied
• All materials that need to bring down should be properly manage (using ropes, tower crane,
mobile crane lifts)
• Good housekeeping
Perform a last minute risk assessment before performing any material handling task.
Make sure to check the path of travel for any obstacles before moving any materials.
Perform a proper warm up and stretch before performing any material handling task.
The PPE required for any material handling tasks are: Safety glasses, appropriate gloves and
appropriate non slip footwear. Additional PPE may be required depending upon environment
conditions.
Nothing follows