OVERALL PLANNING FOR NEW CAR PARK (IDLING PERIOD)

Admin Building

7th AUGUST
-
31st AUGUST - 8th SEPTEMBER 8th SEPTEMBER
New Guard
House Gate D

Area Take from WD Handover to WD Activities


- CCTV pole footing casting
- Fencing works
7th August - Premix rectification
- Road marking
8th September
- Premix rectification
- Road marking
31st August
(Idling Period) - Wearing coarse laying
- Road marking
AREA TO BE TAKEN BEFORE AND DURING IDLING PERIOD

Admin Building

7th AUGUST
-
31st AUGUST - 8th SEPTEMBER 8th SEPTEMBER
New Guard
House
Gate D

Area Take from WD Handover to WD Activities


- CCTV pole footing casting
- Fencing works
7th August - Premix rectification
- Road marking
8th September - Premix rectification
- Road marking
31st August
(Idling Period) - Wearing coarse laying
- Road marking