DC 5 Cooling Management
by DC4 Chillers
Presentation Date – 21st February 2022
DC 4
1 LG 6 100% 6
DC 4
1 LG 6 100% 6
2 Gr 127 80% 101.6
DC 4
1 LG 6 100% 6
2 Gr 127 80% 101.6
1st floor - Server Hall
3 1 380 80% 304
4 2nd floor 1650 80% 1320
5 3rd floor 1650 80% 1320
DC 4
1 LG 6 100% 6
2 Gr 127 70% 88.9
3 1st floor - Server Hall 1 380 70% 266
4 2nd floor 1650 70% 1155
5 3rd floor 1650 70% 1155
DC 4
1 LG 6 100% 6
2 Gr 127 60% 76.2
1st floor - Server Hall
3 1 380 60% 228
4 2nd floor 1650 60% 990
5 3rd floor 1650 60% 990
Option 6 - 1800 TR x 3 Water cooled Chiller (3W) - Air cooled Standby – Excluding 4 th floor.
Third Chiller with all Equipment PO to be released by 1st week of March
Design Cooling (TR ) on
Sr No Floor 100 % Working Load % Req TR
DC 4
1 LG 6 100% 6
2 Gr 127 100% 127
3 1st floor - Server Hall 1 380 100% 380
4 2nd floor 1650 100% 1650
5 3rd floor 1650 100% 1650
Amount 234,174,163
DC 5 Budgetary Proposal
2. Low Side Works - 7.69 Cr
Sr No Description Qty Unit Rate Amount
Amount 76,893,548
DC 5 Budgetary Proposal
3. Additional Chiller option & DC 4-DC5 Connectivity – 3.83 Cr
Sr No Description Qty Unit Rate Amount
Amount 32,085,409
DC4 to DC 5 Connectivity
DC4 to DC 5 HVAC
4 Connectivity 1 Lot 5,686,490 6,255,139
5 Total 349,408,259