Ctrls Mumbai DC

World’s 1st LEED platinum Certified and


Asia’s Largest Rated 4 Data center

DC 5 Cooling Management
by DC4 Chillers
Presentation Date – 21st February 2022

Secure Scalable Carrier Neutral 99.995% Uptime

Report Prepared By- Ramdas Satpute


DC 4 Cooling Management

DC 4 Cooling System are explained as below

1. Chiller – 1800 TR – 2 Nos (Water cooled) working


450 TR – 4 Nos (Air cooled) Standby
2. Water cooled chiller Pumps :-
Condensor Pumps - 5400 GPM – 2 Nos
Primary Pumps - 3420 GPM – 2 Nos
Secondary Pumps - 3420 GPM – 2 Nos
Air Cooled Chillers – Pumps:-
AC assisting pump - 3420 GPM – 1 Nos
AC Primary Pumps - 855 GPM - 4 Nos

3. Thermal Storage Tank – 55 KL - 2 Nos

4. Cooling Tower – 1800 TR -2 Nos


DC 4 Cooling Management

DC 4 Cooling load calculation

Sr No Floor Design Cooling (TR)

1 Lower ground floor 6


2 Ground floor 127
3 1st floor - Server Hall 1 335
4 2nd floor 1646
5 3rd floor 1645

Total Required 3759 TR


DC 5 Cooling Management – (July 2022)
Option 1 - 1800 TR x 2 Water cooled Chiller (1W+1S) , AC Chiller for DC 1

Sr No Floor Design Cooling (TR ) on 100 % Working Load % Req TR

DC 4
1 LG 6 100% 6

2 Gr 127 50% 63.5


3 1st floor - Server Hall 1 380 30% 114
4 2nd floor 1650 30% 495
5 3rd floor 1650 30% 495

Total Required 3813 1173.5


Installed 1800
Balance 626.5

DC5 - 1st floor 1646 38% 625.48


DC 5 Cooling Management – (July 2022)
Option 2 - 1800 TR x 2 Water cooled working + 1800 Air cooled standby

Sr No Floor Design Cooling (TR ) on 100 % Working Load % Req TR

DC 4
1 LG 6 100% 6
2 Gr 127 80% 101.6

3 1st floor - Server Hall 1 380 80% 304


4 2nd floor 1650 80% 1320
5 3rd floor 1650 80% 1320

Total Required 3813 3051.6


Installed 3600
Balance 548.4

DC5 - 1st floor 1650 33% 544.5


DC 5 Cooling Management – (July 2022)

Option 3 - 1800 TR x 3 Water cooled Chiller (2W+1S) -


Third Chiller with all Equipment PO to be released by 1st week of March

Design Cooling (TR ) on 100


Sr No Floor % Working Load % Req TR

DC 4
1 LG 6 100% 6
2 Gr 127 80% 101.6
1st floor - Server Hall
3 1 380 80% 304
4 2nd floor 1650 80% 1320
5 3rd floor 1650 80% 1320

Total Required 3813 3051.6


Installed 3600
Balance 548.4

DC5 - 1st floor 1650 33% 544.5


DC 5 Cooling Management – (July 2022)

Option 4 - 1800 TR x 3 Water cooled Chiller (2W+1S) -


Third Chiller with all Equipment PO to be released by 1st week of March

Sr No Floor Design Cooling (TR ) on 100 % Working Load % Req TR

DC 4
1 LG 6 100% 6
2 Gr 127 70% 88.9
3 1st floor - Server Hall 1 380 70% 266
4 2nd floor 1650 70% 1155
5 3rd floor 1650 70% 1155

Total Required 3813 2670.9


Installed 3600
Balance 929.1

DC5 - 1st floor 1650 56% 924


DC 5 Cooling Management – (July 2022)

Option 5 - 1800 TR x 3 Water cooled Chiller (2W+1S) -


Third Chiller with all Equipment PO to be released by 1st week of March
Design Cooling (TR ) on 100
Sr No Floor % Working Load % Req TR

DC 4
1 LG 6 100% 6
2 Gr 127 60% 76.2
1st floor - Server Hall
3 1 380 60% 228
4 2nd floor 1650 60% 990
5 3rd floor 1650 60% 990

Total Required 3813 2290.2


Installed 3600
Balance 1309.8

DC5 - 1st floor 1650 79% 1303.5


DC 5 Cooling Management – (July 2022)

Option 6 - 1800 TR x 3 Water cooled Chiller (3W) - Air cooled Standby – Excluding 4 th floor.
Third Chiller with all Equipment PO to be released by 1st week of March
Design Cooling (TR ) on
Sr No Floor 100 % Working Load % Req TR

DC 4
1 LG 6 100% 6
2 Gr 127 100% 127
3 1st floor - Server Hall 1 380 100% 380
4 2nd floor 1650 100% 1650
5 3rd floor 1650 100% 1650

Total Required 3813 3813


Installed 5400
Balance 1587

DC5 - 1st floor 1650 96% 1584


DC 5 Budgetary Proposal

1. High Side Works - 23.42 Cr

Sr No Description Qty Unit Rate Amount


High Side

1 DG 4 Nos 15,743,720 69,272,368

2 Transformer with accessories 4 Nos 7,000,000 30,800,000

3 HT Panel & Incoming cable, bus duct 1 Lot 24,000,000 26,400,000

4 LT Panel 1 Lot 49,000,000 53,900,000

5 PDU 1 Lot 8,679,355 9,547,291

6 PDU 1 Lot 8,654,389 9,519,828

7 PAHU 1 Lot 26,315,000 28,946,500

8 UPS 1 Lot 2,885,979 3,174,577

9 Battery 1 Lot 2,376,000 2,613,600

Amount 234,174,163
DC 5 Budgetary Proposal
2. Low Side Works - 7.69 Cr
Sr No Description Qty Unit Rate Amount

1 DG Lifiting shifting 4 Nos 540,000 2,376,000

2 Electrical low side 1 Lot 5,497,050 6,046,755

3 HSD Low side 1 Lot 381,127 419,240

4 Civil Interior 1 Lot 17,674,102 19,441,512

5 HVAC Low Side 1 Lot 9,499,505 10,449,456

6 Raised floor 1 Lot 8,875,899 9,763,489

7 Grills & Gromets 1 Lot 1,558,550 1,714,405

8 IBMS 1 Lot 4,491,000 4,940,100

9 Pre Action 1 Lot 4,500,000 4,950,000

10 CAC 1 Lot 2,554,340 2,809,774

11 DG Exhaust 1 Lot 635,700 699,270

12 DG Exhaust 1 Lot 3,612,000 3,973,200

13 PAHU Low side 1 Lot 2,685,000 2,953,500

14 Dummy Panel 1 Lot 634,786 698,265

15 Lighting arrestor 1 Lot 182,800 201,080

16 UPS Low side 1 Lot 638,682 702,550

17 Signage 1 Lot 360,695 396,765

18 DC Acoustic 1 Lot 3,601,989 3,962,188

19 TST Low side 1 Lot 360,000 396,000

Amount 76,893,548
DC 5 Budgetary Proposal
3. Additional Chiller option & DC 4-DC5 Connectivity – 3.83 Cr
Sr No Description Qty Unit Rate Amount

1 Chiller 1 Nos 16,409,670 18,050,637

2 Cooling tower 1 Nos 2,310,000 2,541,000

3 TST 1 Nos 1,335,000 1,468,500

4 Primary Pump 1 Nos 483,875 532,263

5 Secondary pump 1 Nos 691,050 760,155

6 Condensor pump 1 Nos 825,080 907,588

7 Chiller Low side 1 Lot 2,253,779 2,479,157

8 Chiller & Pump piping 1 Lot 4,860,100 5,346,110

Amount 32,085,409

DC4 to DC 5 Connectivity

1 DC4 to DC 5 HVAC Low side 1 Lot 5,686,490 6,255,139


DC 5 Budgetary Proposal

Sr No Description Qty Unit Rate Amount

1 High Side Works 1 Lot 234,174,163

2 Low Side Works 1 Lot 76,893,548

2 Additional Chiller works 1 Lot 32,085,409

DC4 to DC 5 HVAC
4 Connectivity 1 Lot 5,686,490 6,255,139

5 Total 349,408,259
THANKING YOU

Prepared by –Ramdas Satpute