Minutes of Departmental Safety Meeting held on 21st January, 2018 at 8 A.M.

Members’ Attendance:

Present:

P.N. Rao, Gautam Das, N. Sarma, Bikramjit Borah, M.H. Choudhury, S. Acharjee, G.
Borgohain, A. Phukan, M. Ahmed, D.J. Gogoi, Jadu Gogoi, Muhim Borah, Dipankar Baruah,
Bittu Dey, P. Sensuwa, P. Konwar, B. Changmai, G. Dutta, D.C. Das, G. Gogoi, T. Saikia,
A. Rahman, Biju Phukan, Nagendra Singh, Ranjit Gohain, Jiten Baruah

Absent: S. Baruah, K. Saikia, A.K. Das, S. Sarmah, S. N Saikia, S. N Taye, B. Gogoi, S.


Sonowal, M. Saikia, I. Hussain, Madhab Borah, Mn. Borah, R. Chutia, Debajit Gogoi, S.
Gogoi, RK Hazarika, R. Kurmi, T. Deori, P. Lekharu, AC Tamuli, M. Dutta, H. Gogoi, D.
Changmai, Parashmoni Dutta, U.K Borgohain, A. Urang, B. Thakur, N. Tanti, P. Baruah, N.
Bora, K. Gogoi, Dilip Baruah

1.0 The meeting was presided over by Shri P.N. Rao, DGM-Elect. (M)
2.0 Review minutes of last meeting held on 30/11/2017.

3.0 REVIEW OF EARLIER POINTS

Sl. Department/ Subject Action By Status


No. Designation
1 D.J. Gogoi Sr. EE(Fields) Job is in progress.
Earthing values of stay wires A list is being prepared
at LT poles of housing areas for all the stay wires
to be checked.
2 M.Ahmed Sr. EE(Fields) *Checked all cradle
Conditions of LT/HT lines guards and identification
cradles guards should be of necessary
checked for physical repairing/replacement
integrity done

* Job is in progress
* 3 nos. done (CISF,
Teachers’ colony out of 8
nos. identified

3 P.Baruah(M/S In OCS-1, the space below Installation Shifting of scrap items


Power grid few area-light poles to be Manager/Sr. from near poles
Associate) made clear of scrap EE(Fields) completed. Point can be
items/pipes for safety of closed.
maintenance crew

4 Sr. EE(Fields) *DGM-E suggested that


D.J. Gogoi To avoid possible entry of all the panels to be
mouse/rats inside LT/HT checked and identified
panels, necessary
arrangements should be done

“PROACTIVE SAFETY FOR HSE EXCELLENCE”


4.0 NEW POINTS RAISED:

1 Ganesh Gogoi Water well-11 deep tube Sr. EE(Fields)


well working space
constraint
2 Mn. Borah Engine movement during Sr. EE(Rigs) /IM (V-2)
ILM should be done after
dismantling PCR rooftop
AC units. Reason: Roof
flappers of PCR(between
PCR1 and engines)
becomes unsafe for
handling

5.0 ANY OTHER POINTS:


1) Raised by D. Baruah, JE: HT/LT panels cleaning can be done through Vacuum
cleaner

“PROACTIVE SAFETY FOR HSE EXCELLENCE”