DAILY WORK REPORT

NAME: BALAJI RADHAKRISHNAN

DATE: 06.03.2018

S.No Work Description Progress Remarks

Unit#1,2,3 and 4 Lv switchgear monitored and Tariff Meter


1 Done
Reading Recorded

Unit#4 Condenser Incomer#A and B faulty voltmeter replaced


2 Done
with new one

Unit#3 Collecting Motor feeder Local and DCS mode function test
3 Done
done

Unit#3 Generator Space Heater feeder Local and DCS mode


4 Done
function test done

5 Unit#1 Classifier#A Operation test under progress Under Progress

Unit#3 Mill Gear Oil Pump#A1,A2,B1,B2,C1 motor IR test and


6 Done MotorA2 J/B side cable connection circuit is wrong then its corrected.
Local mode Start and rotation check done

7 Unit#4 Mill Gear Oil Pump#A1 and A2 local start done Done
wrong then its corrected.