RUPTL Revision Step
RUPTL Revision Step
A.Lapor ke PLN.
B.Submit FS
C Submit study interkoneksi (bisa aja lokasi berada diluar system.intinya masih berada didalam system)
Eventhu in the location already planning for PLTU but still not construct yet and renewal energy more
ready.Corporate Director will accept the renewal energy.
Incase theres potensial and PLN system accomodated.than PLN will held the procurement
-Process Bidding
-Winner granted
-Contract sign
3.Hydro?
Location of Hydro already registered by PLN, already announced to ESDM, KPK, KPPU
Located in NTB Sumbawa dompu.theres plans of PLTU 2x25mw, but theres potential tambang garam
and plasma and biomas, can PLTU location being move?
Answers ;