Project Name: Wilmont's Pharmacy Drone Project Revision Number: 00

Revision Date: 14/02/2020

Project Earned Value Calculation Period


1 2 3 4 5 6 7 8 9
Weeks in 5 week increments
Activities 1 to 5 6 to 10 11 to 15 16 to 20 21 to 25 26 to 30 31 to 35 36 to 40 41 to 45 Totals
Total Earned Total % Total Earned Total % Total Earned Total % Total Earned Total % Total Earned Total % Total Earned Total % Total Earned Total % Total Earned Total % Total Earned Total %
Value Complete Value Complete Value Complete Value Complete Value Complete Value Complete Value Complete Value Complete Value Complete
1.1 Initiating
1.1.1 Develop Scope and Plan $ 6,120.00 100.00% $ - $ - $ - $ - $ - $ - $ - $ - $ 6,120.00
1.1.2 Engage Stakeholders $ 612.00 10.00% $ 612.00 10.00% $ 612.00 10.00% $ 612.00 10.00% $ 612.00 10.00% $ 612.00 10.00% $ 612.00 10.00% $ 612.00 10.00% $ 1,224.00 20.00% $ 6,120.00
1.1.3 Funding $ 6,220.00 100.00% $ - $ - $ - $ - $ - $ - $ - $ - $ 6,220.00
1.1.4 Preparing List of Difficulties $ 18,360.00 100.00% $ - $ - $ - $ - $ - $ - $ - $ - $ 18,360.00

1.2 Planning
1.2.1 Gathering information regarding Drone $ - $ 5,280.00 100.00% $ - $ - $ - $ - $ - $ - $ - $ 5,280.00
1.2.2 System Design $ - $ 6,900.00 100.00% $ - $ - $ - $ - $ - $ - $ - $ 6,900.00
1.2.3 Cost Estimate $ - $ 3,960.00 100.00% $ - $ - $ - $ - $ - $ - $ - $ 3,960.00
1.2.4 Approvals $ - $ 4,060.00 100.00% $ - $ - $ - $ - $ - $ - $ - $ 4,060.00

1.3 Construction Phase of One Drone


1.3.1 Gathering Team $ - $ - $ 1,600.00 100.00% $ - $ - $ - $ - $ - $ - $ 1,600.00
1.3.2 Educating Manpower $ - $ - $ 2,950.00 100.00% $ - $ - $ - $ - $ - $ - $ 2,950.00
1.3.3 Renting / Gathering Tools and Equipment $ - $ - $ 3,500.00 100.00% $ - $ - $ - $ - $ - $ - $ 3,500.00
1.3.4 Complete Coding $ - $ - $ 5,000.00 100.00% $ - $ - $ - $ - $ - $ - $ 5,000.00
1.3.5 Complete Construction $ - $ - $ - $ 5,200.00 100.00% $ - $ - $ - $ - $ - $ 5,200.00

1.4 Testing of Drone


1.4.1 Flight Test $ - $ - $ - $ - $ 2,250.00 100.00% $ - $ - $ - $ - $ 2,250.00
1.4.2 Integrity Test $ - $ - $ - $ - $ 2,500.00 50.00% $ 2,500.00 50.00% $ - $ - $ - $ 5,000.00
1.4.3 Component Test $ - $ - $ - $ 5,200.00 100.00% $ - $ - $ - $ - $ - $ 5,200.00
1.4.4 Area Covering Test $ - $ - $ - $ - $ 2,500.00 100.00% $ - $ - $ - $ - $ 2,500.00

1.5 Construction Phase of Other Three Drones


1.5.1 Complete Coding $ - $ - $ - $ - $ - $ 13,400.00 100.00% $ - $ - $ - $ 13,400.00
1.5.2 Complete Construction $ - $ - $ - $ - $ - $ - $ 13,600.00 100.00% $ - $ - $ 13,600.00

1.6 Testing of Other Three Drones


1.6.1 Flight Test $ - $ - $ - $ - $ - $ - $ 2,250.00 100.00% $ - $ - $ 2,250.00
1.6.2 Integrity Test $ - $ - $ - $ - $ - $ - $ 3,333.33 66.67% $ 1,666.67 33.33% $ - $ 5,000.00
1.6.3 Component Test $ - $ - $ - $ - $ - $ - $ 5,200.00 100.00% $ - $ - $ 5,200.00
1.6.4 Area Covering Test $ - $ - $ - $ - $ - $ - $ 1,666.67 66.67% $ 833.33 33.33% $ - $ 2,500.00

1.7 Delivery
1.7.1 Packing and Packaging $ - $ - $ - $ - $ - $ - $ - $ 2,160.00 100.00% $ - $ 2,160.00
1.7.2 Documents Regarding Design $ - $ - $ - $ - $ - $ - $ - $ 2,740.00 100.00% $ - $ 2,740.00
1.7.3 User Manual and Application $ - $ - $ - $ - $ - $ - $ - $ 2,740.00 100.00% $ - $ 2,740.00
1.7.4 Certificates $ - $ - $ - $ - $ - $ - $ - $ 1,910.00 100.00% $ - $ 1,910.00

1.8 Training
1.8.1 Handling of Drone Flight $ - $ - $ - $ - $ - $ - $ - $ - $ 16,150.00 100.00% $ 16,150.00
1.8.2 Maintenance / Troubleshooting of Drone $ - $ - $ - $ - $ - $ - $ - $ - $ 16,150.00 100.00% $ 16,150.00

1.9 Warranty and Payment


1.9.1 Time $ - $ - $ - $ - $ - $ - $ - $ - $ 600.00 100.00% $ 600.00
1.9.2 Accessories $ - $ - $ - $ - $ - $ - $ - $ - $ 700.00 100.00% $ 700.00
1.9.3 Payment $ - $ - $ - $ - $ - $ - $ - $ - $ 600.00 100.00% $ 600.00

Total Earned Value $ 31,312.00 $ 20,812.00 $ 13,662.00 $ 11,012.00 $ 7,862.00 $ 16,512.00 $ 26,662.00 $ 12,662.00 $ 35,424.00 $ 175,920.00

Period 1 2 3 4 5 6 7 8 9
Total Cumulative Plan Cost $ 31,618.00 $ 52,736.00 $ 66,520.40 $ 77,654.80 $ 85,639.20 $ 102,273.60 $ 128,813.20 $ 141,352.80 $ 175,920.00
Total Cumulative Actual Cost $ 31,900.00 $ 53,380.00 $ 67,280.00 $ 79,080.00 $ 87,130.00 $ 103,780.00 $ 130,530.00 $ 143,730.00 $ 178,130.00
Total Earned Value $ 31,312.00 2081200.00% $ 13,662.00 $ 11,012.00 $ 7,862.00 $ 16,512.00 $ 26,662.00 $ 12,662.00 $ 35,424.00
Status:
Chart Title
$200,000.00

$180,000.00

$160,000.00

$140,000.00

$120,000.00
Total Cost

$100,000.00

$80,000.00

$60,000.00

$40,000.00

$20,000.00

$-
1 2 3 4 5 6 7 8 9
Period

Total Cumulative Plan Cost Total Cumulative Actual Cost Total Earned Value