标识号 任务 任务名称 工期 开始时间 完成时间 备注 2009年11月

模式 日 一 二
1 Pre-Commissioning&Commissioning 66 days 2020/2/4 2020/5/6
2 Heat tracing pre-commissioning& commissioning test(tank farm) 2020/2/4 更新图纸
3 Pipeline cathodic protection pre-commissioning 2020/2/5 已回复SC,待批准后继续进行
4 Onshore station portable water pump pre-commissioning inspection 2 days 2020/3/17 2020/3/18
5 Onshore station portable water pump commissioning test 1 day 2020/3/18 2020/3/18
6 Onshore station portable water piping system 2 days 2020/3/19 2020/3/23
pre-commissioning inspection
7 Onshore station portable water piping system commissioning t2 days 2020/3/23 2020/3/24
8 Heat tracing pre-commissioning& commissioning test(Jetty)5 days 2020/3/30 2020/4/3
9 Jetty PAGA system pre-commissioning & commissioning test 1 day 2020/2/13 2020/2/13 NCR
10 Jetty CCTV system pre-commissioning & commissioning test 1 day 2020/3/23 2020/3/24 正在内测
11 Jetty network communication system comissioning 1 day 2020/2/17 2020/2/17
12 Jetty firefighting system pump(B) pre-commissioning 2 days 2020/3/24 2020/3/25 消防泵SC回复,安装支墩
inspection(Diesel)
13 Jetty firefighting system pump(B) commissioning test 1 day 2020/4/6 2020/4/7 更换盘根
14 Jetty firefighting system Jockey pump pre-commissioning inspection1 day 2020/2/19 2020/2/19 已完成其中1台,需回复SC后继续
15 Jetty firefighting system jockey pump commissioning test 1 day 2020/2/20 2020/2/20
16 Onshore station & Jetty Fire alarm system comissioning 5 days 2020/3/23 2020/3/27 已沟通安排内测
17 Jetty Temperature infrared detection system commissioning 5 days 2020/3/23 2020/3/27 需安排吊篮
18 Tank farm firefighting water syetem commissioning test 3 days 2020/4/15 2020/4/17 需PCV及稳压泵完成安装改造后进行
19 Jetty firefighting pump(C) commissioning test(Electric) 1 day 2020/3/25 2020/3/26 待供电局同意后内侧,安装支墩
20 Jetty firefighting foam system pre-commissioning inspection 5 days 2020/3/23 2020/3/27 泡沫泵电机对中问题,需底座扩孔改造
21 Jetty firefighting water system pre-commissioning & commissioning 2 days 2020/2/27 2020/2/28 待消防泵完成单体测试后进行,可安排
消防炮单体预验收
22 VRU pre-commissioning inspection 2 days 2020/5/1 2020/5/5 气体分析装置需要更换,需厂家提
供,进汽油前完成
23 Jetty firefighting foam system commissioning test 22 days 2020/3/2 2020/3/31 已完成部分设备预验收,部分需消防泵
完成验收后进行
24 Jetty firefighting control system function test(ABB) 5 days 2020/3/23 2020/3/27 厂家隔离后进场内测,与DCS通讯及柴
25 The communication between the flowmeter and DCS test 3 days 2020/5/1 2020/5/6 进油前流量计厂家进场调试
26 After oil-in commissioning test 2 days 2020/3/5 2020/3/6

任务 外部任务 手动任务 仅完成时间


拆分 外部里程碑 仅工期 期限
项目: N.O.S.F
日期: 2020/3/17 里程碑 非活动任务 手动摘要总成 进度
摘要 非活动里程碑 手动摘要 手动进度
项目摘要 非活动摘要 仅开始时间