COMMISSIONING PLAN ‐ OAHU (Tower ‐ 5)

Project: MAYAN YAS ISLAND LIVING, Plot YS3‐4‐6
Date: 06/06/2020

Commissioning Date
Sl. No Equipment Reference Equipment Model Duration Required Manpower Commissioning Activities Remarks
Starting Ending
Team‐2  Temperature readings will be 
Pre Commissioning, Air Balancing, 
Supply Side Day 1 Day 5 5 Days Specialized Technician ‐1 checked after getting the chilled 
Checking Electrical Parameters
1 OAHU‐B5.9‐01 VS‐150‐R‐F/R/EN Helper ‐ 1  water connection
Team‐2 
Pre Commissioning, Air Balancing, 
Exhaust Side Day 6 Day 10 5 Days Specialized Technician ‐1
Checking Electrical Parameters
Helper ‐ 1 
Team‐2  Temperature readings will be 
Pre Commissioning, Air Balancing, 
Supply Side Day 11 Day 15 5 Days Specialized Technicean ‐1 checked after getting the chilled 
Checking Electrical Parameters
2 OAHU‐B5.9‐02 VS‐180‐R‐F/R/EN Helper ‐ 1 water connection
Team‐2 
Pre Commissioning, Air Balancing, 
Exhaust Side Day 16 Day 20 5 Days Specialized Technician ‐1
Checking Electrical Parameters
Helper ‐ 1
Team‐2  Temperature readings will be 
Pre Commissioning, Air Balancing, 
Supply Side Day 21 Day 25 5 Days Specialized Technicean ‐1 checked after getting the chilled 
Checking Electrical Parameters
3 OAHU‐B5.B1‐02 VS‐100‐R‐F/R/EN Helper ‐ 1 water connection
Team‐2 
Pre Commissioning, Air Balancing, 
Exhaust Side Day 26 Day 30 5 Days Specialized Technician ‐1
Checking Electrical Parameters
Helper ‐ 1

Note:
1) T&C can be start only after clearing the below mentioned conditions.
a) All building ceiling, partition doors & windows should be fully installed (If spaces are not architecturally sealed, abnormal pressure 
distributions will unbalance the system and lead to inconsistent results)
b) There should be electric power supply in building (either permanent or temporary).
c) Ducting work should be finished completely.
e) Installtion of Diffusers/Grilles should be completely finished.
2) Main Contractor has to provide required temporary access opening during the time of T&C

3) All the above mentioned dates are valid only if the working of equipment/installation is proper. If any rectification works required, the work duration may change.

Page 1 of 1