You are on page 1of 19

 

TO CARRY OUT MODIFICATION PROJECT ON GAS OIL PIPELINE TO INSTALL WIRELESS 
GUIDED WAVE RADAR. LOCATION: 6” STAB AT 4000 SERIES GAS OIL SUCTION HEADER LINE 

Doc No  OBZA‐MOS‐TO‐2017‐001
METHOD OF STATEMENT FOR INSTALLTION WORK  Rev 00 
Date  Nov 21st 2017
 

TABLE OF CONTENTS 
1.  INTRODUCTION ...................................................................................................................... 3 
2.  SCOPE OF WORK ..................................................................................................................... 3 
3.  JOB METHOD STATEMENT ...................................................................................................... 3 
3.1 Preparation Job ......................................................................................................................... 3 
3.2 Removal of Existing 6” Pipe ....................................................................................................... 3 
3.3 Installation of 3” Pipe Console and GWR Instrument ............................................................... 4 
3.4 Completion of Job ..................................................................................................................... 4 
4.  SAFETY PRECAUTION .............................................................................................................. 4 
4.1 PPE ............................................................................................................................................. 4 
4.2 Communication ......................................................................................................................... 4 
4.3 Environment .............................................................................................................................. 5 
4.4 Protection against falling materials/object ............................................................................... 5 
4.5 General safety measures ........................................................................................................... 5 
5.  TOOLS AND EQUIPMENT ........................................................................................................ 5 
6.  ACCESS AND EGRESS ROUTE ................................................................................................... 6 
7.  FALL PROTECTION MEASURES ................................................................................................. 6 
8.  OTHER ESSENTIAL TOOLS ........................................................................................................ 6 
9.  HAZARDOUS SUBSTANCES ...................................................................................................... 7 
10.  SPECIFIC TRAINING REQUIRED ............................................................................................ 7 
11.  SAFE WORKING LOAD ......................................................................................................... 7 
12.  PERSONNEL PROTECTIVE EQUIPMENT (PPE) ....................................................................... 7 
13.  MANPOWER ....................................................................................................................... 7 
14.  SAFETY CONCERN ............................................................................................................... 7 
15.  LIFTING PLAN ...................................................................................................................... 8 
16.  ATTACHMENT ..................................................................................................................... 8 
 
 
 
 
 
Page | 2  
 
 
TO CARRY OUT MODIFICATION PROJECT ON GAS OIL PIPELINE TO INSTALL WIRELESS 
GUIDED WAVE RADAR. LOCATION: 6” STAB AT 4000 SERIES GAS OIL SUCTION HEADER LINE 

Doc No  OBZA‐MOS‐TO‐2017‐001
METHOD OF STATEMENT FOR INSTALLTION WORK  Rev 00 
Date  Nov 21st 2017
 
1. INTRODUCTION 

This  procedure  envisages  the  method  of  statement  for  installation  of  Wireless  Guided  Wave 
Radar Console located at 6” Stab at 4000 Series Gas Oil Suction Header Line.  
 
 
2. SCOPE OF WORK 

Scope of work under this package are as follow:‐ 
 
a. Workshop fabrication work to the pipe console including painting work 
b. Delivery to the site 
c. Pipe dismantling work to the existing 6” pipe – lifting using 20 MT Crane 
d. Blinding/drop valve/drop spool (if required) 
e. Installation of console  
f. Installation of equipment – Wireless Guided Wave Radar 
g. De‐blinding 
h. Housekeeping 

3. JOB METHOD STATEMENT 
 
Detail method of statement and sequence for installation work shall be described below. 
 

3.1 Preparation Job 
 
3.1.1 Submission of Procedure,  HIRADC,  MOS and any others related  documents.  Obtain 
approval prior start the work. 
3.1.2 Manpower  attended  Safety  Induction  conducted  by  Langsat  Terminal  (One) 
(hereinafter called the LTO) 
3.1.3 Mobilize crane to site for lifting work. Ensure crane complete with valid documents 
(JKKP, PMA and etc.).  
3.1.4 Inspection of crane. Ensure crane in good condition and meet standard requirements. 
3.1.5 Mobilize all equipment, tools and fabricated item (pipe console) to job area.  
3.1.6 Inspection to the electric tools and equipment 
3.1.7 Barricade working area (hard barricade or soft barricade). If required put proper 
signage.  
3.1.8 Cover working area with canvas to avoid any oil spillage onto ground. 
3.1.9 For double protection, steel tray will put under pipe before dismantling work.   
 

3.2 Removal of Existing 6” Pipe 
 
3.2.1 Obtain permit to work and gas check prior start the work.  

Page | 3  
 
 
TO CARRY OUT MODIFICATION PROJECT ON GAS OIL PIPELINE TO INSTALL WIRELESS 
GUIDED WAVE RADAR. LOCATION: 6” STAB AT 4000 SERIES GAS OIL SUCTION HEADER LINE 

Doc No  OBZA‐MOS‐TO‐2017‐001
METHOD OF STATEMENT FOR INSTALLTION WORK  Rev 00 
Date  Nov 21st 2017
 
3.2.2 Close all valve connected to the line – refer blind list that provided by LTO 
3.2.3 Install spade/blind flange at specific location as per blind list that provided by LTO 
3.2.4 Set‐up crane at correct position. Remove any obstruction for lifting operation.  
3.2.5 Set‐up lifting gear to the pipe that be removed – 6” pipe. Install tag line. 
3.2.6 Loosen all stud bolt.  
3.2.7 Rig‐up and hold the load  
3.2.8 Remove all stud bolt and lifting the pipe spool. Locate the pipe spool at designated 
area – Refer Section 15 for Lifting Plan 
 

3.3 Installation of 3” Pipe Console and GWR Instrument 
 
3.3.1 Set‐up lifting gear to the pipe consul 
3.3.2 Cleaning flange surface 
3.3.3 Lifting the pipe consul to the position. 
3.3.4 Install gasket and stud bolts 
3.3.5 Lifting GWR Instrument 
3.3.6 Install Gasket and stud bolts 
3.3.7 Flange alignment work 
3.3.8 Bolt  tightening  work  using  manual  torque  wrench.  Refer  Attachment  4  for  torque 
value for bolt tightening work.  
 

3.4 Completion of Job 
 
3.4.1 Site inspection is carried out to ensure conformance of the installation work 
3.4.2 De‐blinding work – remove blind flange/spade and reinstatement work 
3.4.3 Open valve as per initial condition 
3.4.4 Inform to LTO when work completed and closed PTW. 
3.4.5 Housekeeping and demobilization 

4. SAFETY PRECAUTION 
 

4.1 PPE 
 
4.1.1 All workers shall wear proper PPE such as white color safety helmet, safety glass and 
safety shoes at all time. 
4.1.2 Wear suitable hand glove during operation 
 

4.2 Communication 
 
4.2.1 Tool box meeting with all workers prior start the work every morning 
4.2.2 All works at site shall be carried out as per approved Method of Statement. Supervisor 

Page | 4  
 
 
TO CARRY OUT MODIFICATION PROJECT ON GAS OIL PIPELINE TO INSTALL WIRELESS 
GUIDED WAVE RADAR. LOCATION: 6” STAB AT 4000 SERIES GAS OIL SUCTION HEADER LINE 

Doc No  OBZA‐MOS‐TO‐2017‐001
METHOD OF STATEMENT FOR INSTALLTION WORK  Rev 00 
Date  Nov 21st 2017
 
at site need to ensure all works carried out in proper manner.  
4.2.3 During  lifting  operation  communication  between  rigger  and  crane  operator  using 
hand signal.  
 

4.3 Environment 
 
4.3.1 Working in bad weather condition are not allowed. 
 

4.4 Protection against falling materials/object 
 
4.4.1 When  working  at  height  at  the  pipe  rack,  protection  shall  be  made  against  falling 
materials, such as hand tools, cable tray, etc. 
4.4.2 Close or barricade the area during work. 
 

4.5 General safety measures 
 
4.5.1 Report any incident or near‐miss to LgT‐1 HSSEQ personnel. 
4.5.2 Daily safety toolbox to be executed before start any work. 
4.5.3 Risk assessment (HIRADC) shall be reviewed and approved before start any work. 
4.5.4 Daily permit to work (PTW) to be obtained and approved. 

5. TOOLS AND EQUIPMENT 
 
Basic tools and equipment to be used during operation are as follow:‐ 
 
5.1  Spanner Set size 19mm, 22mm, 27mm, 30mm, 32mm, 36mm (Common Ring &  
    Hammer Ring) 
5.2   Manual Torque Wrench c/w socket 
5.3   Lifting Belt 1.0 MT x 3m 
5.4   Shackle 2.75 MT 
5.5   Chain Block 1.0 MT 
5.6   Hammer 
5.7   Nylon Rope  
 
 
 
 
 
 

Page | 5  
 
 
TO CARRY OUT MODIFICATION PROJECT ON GAS OIL PIPELINE TO INSTALL WIRELESS 
GUIDED WAVE RADAR. LOCATION: 6” STAB AT 4000 SERIES GAS OIL SUCTION HEADER LINE 

Doc No  OBZA‐MOS‐TO‐2017‐001
METHOD OF STATEMENT FOR INSTALLTION WORK  Rev 00 
Date  Nov 21st 2017
 
6. ACCESS AND EGRESS ROUTE 
 
Access route for transfer all material and assembly point during emergency shows in Figure 1.0 
below. 
 

 
 
Figure 1.0: Access Route 

7. FALL PROTECTION MEASURES 
 
Not applicable for this type of work 

8. OTHER ESSENTIAL TOOLS 
 
All tools used shall be non‐spark tools. 
 

Page | 6  
 
 
TO CARRY OUT MODIFICATION PROJECT ON GAS OIL PIPELINE TO INSTALL WIRELESS 
GUIDED WAVE RADAR. LOCATION: 6” STAB AT 4000 SERIES GAS OIL SUCTION HEADER LINE 

Doc No  OBZA‐MOS‐TO‐2017‐001
METHOD OF STATEMENT FOR INSTALLTION WORK  Rev 00 
Date  Nov 21st 2017
 
9. HAZARDOUS SUBSTANCES 
 
Not applicable for this type of work 

10. SPECIFIC TRAINING REQUIRED 
 
Crane operator – hold valid JKKP crane operator certificate 

11. SAFE WORKING LOAD 
 
Routine lifting operation only – load below than 1 MT 

12. PERSONNEL PROTECTIVE EQUIPMENT (PPE) 
 

 
 

13. MANPOWER 
 
14.1  Supervisor 
14.2  Fitters 
14.3  Semi‐skilled 

14. SAFETY CONCERN 
 
15.1  Vehicles movement 
15.2  Finger injury 
15.3  Ergonomics – poor body posture 
15.4  Slip, trip and fall 
15.5  Dehydration 
15.6  Strong wind 
15.7  Uncertain weather condition 
15.8  Falling lifting object 

Page | 7  
 
 
TO CARRY OUT MODIFICATION PROJECT ON GAS OIL PIPELINE TO INSTALL WIRELESS 
GUIDED WAVE RADAR. LOCATION: 6” STAB AT 4000 SERIES GAS OIL SUCTION HEADER LINE 

Doc No  OBZA‐MOS‐TO‐2017‐001
METHOD OF STATEMENT FOR INSTALLTION WORK  Rev 00 
Date  Nov 21st 2017
 
15. LIFTING PLAN 
 
Lifting analysis for lifting work are as follow:‐ 
 
Weight of item to lift (approximately)  :  200 kg 
Weight (contingency)  :  1.5 x 200 kg 
  :  300 kg 
Weight of lifting gear (approximately)  :  50 kg 
Weight of crane block (approximately)  :  200 kg 
Total weight  :  550 kg 
Crane Radius  :  20m 
Crane capacity at 20m radius  :  2,200 kg 
Safety factor (2,200 kg / 550 kg)  :  4.0 > 1.0  OK! 
 
*Note:‐ 
1. Crane to be used: Mobile Crane 25 MT 
2. Wire Sling: Web sling 1 MT x 6m 
3. Shackle: 1.25 MT     

16. ATTACHMENT 
 
ATTACHMENT 1: Risk Assessment HIRADC 
ATTACHMENT 2: Lifting Arrangement 
ATTACHMENT 3: Crane Load Chart 
ATTACHMENT 4: Bolt Tightening Torque Value 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Page | 8  
 
 
TO CARRY OUT MODIFICATION PROJECT ON GAS OIL PIPELINE TO INSTALL WIRELESS 
GUIDED WAVE RADAR. LOCATION: 6” STAB AT 4000 SERIES GAS OIL SUCTION HEADER LINE 

Doc No  OBZA‐MOS‐TO‐2017‐001
METHOD OF STATEMENT FOR INSTALLTION WORK  Rev 00 
Date  Nov 21st 2017
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
ATTACHMENT 1: Risk Assessment HIRADC 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Page | 9  
 
 
Assessment No: Obza/HIR/LTO/001 
HAZARD IDENTIFICATION, RISK ASSESSMENT & DETERMINE CONTROL (HIRADC) REGISTER 
Revision No: 00 
Department: Technical/Maintenance  Revision Date: 28th 2017 
Title Of Activity: Installation of GWR Instruments & Console   Assessors: Khaidir, Yunizar, Farid, Ariff, Latiff 
Job Performed by (Designation & Name): Technician & Contractor   Section: LGT1 
Prepared By / Date: Khaidir / 28th 2017  Checked By / Date: Mr Spencer / 30th Nov 2017  Approved By / Date: En Mohd Shahriwan Idris / 30th Nov 2017 
Hazard Identification  Risk Assessment  Determine Risk Control 
    Legal Compliance  Recommendation 
1. Elimination of hazard 
2. Substitution  
Safety &  Applicable OSH Legislations 
Existing Control  Risk  Risk  3. Engineering 
No  Sub‐Activity  Type  Hazard  Health  ECM  L  S (please state specific section/reg. 
Measure  Rating  Categ  4. Administration (min control 
Effect  excl. OSH Act  
requirement  for S>4) 
5. PPE 
Competence lorry driver 
with valid driving 
Injury,  Administration – do not allowed lorry 
Vehicle  license, provide traffic 
property  0.3  3  4  4  II  OSHA Sect 15 & 24  driver without valid driving license to 
accident  controller & short 
damage  enter to plant 
briefing to driver prior 
enter to plant 
Wear safety 
Foot and 
Falling of  shoes & leather 
hand  0.6  2  2  3  I  OSHA Sect 15 & 24  Nil 
handling item  hand gloves, 
injuries 
Mobilization of  competent person 
equipment, tools, 
machinery and material.  Awkward 
Upper body  Adopt proper 
Unload the equipment,  posture during  0.6  2  2  3  I  OSHA Sect 15 & 24  Nil 
pain  working posture 
tools, machinery and  lifting 
1  R 
material by manual 
handling. Transfer the  Personnel 
Hand and  Wear safety 
equipment, tools and  injuries during 
finger  shoes & leather  0.3  2  2  1  I  OSHA Sect 15 & 24  Nil 
machineries using  handling 
injuries  hand gloves 
lorry/pick‐up vehicle.  materials 
Equipment 
Damage to  Demarcation and 
damage due to 
client  barricade work  0.3  3  3  3  I  OSHA Sect 15 & 24  Nil 
in‐proper 
equipment  areas 
handling 
Psychosocial ‐ 
fatigue,  Obtain enough 
Physical 
prolonged  rest, buddy  0.6  2  2  3  I  OSHA Sect 15 & 24  Nil 
injury 
work, heat  system 
stress 

Page 1 of 4 
 
 
Assessment No: Obza/HIR/LTO/001 
HAZARD IDENTIFICATION, RISK ASSESSMENT & DETERMINE CONTROL (HIRADC) REGISTER 
Revision No: 00 
Department: Technical/Maintenance  Revision Date: 22nd 2017 
Title Of Activity: Installation of GWR Instruments & Console   Assessors: Khaidir, Yunizar, Farid, Ariff, Latiff 
Job Performed by (Designation & Name): Technician & Contractor   Section: LGT1 
Prepared By / Date: Khaidir / 22nd 2017  Checked By / Date: Mr Spencer / 30th Nov 2017  Approved By / Date: En Mohd Shahriwan Idris / 30th Nov 2017 
Hazard Identification  Risk Assessment  Determine Risk Control 
    Legal Compliance  Recommendation 
1. Elimination of hazard 
2. Substitution  
Safety &  Applicable OSH Legislations 
Existing Control  Risk  Risk  3. Engineering 
No  Sub‐Activity  Type  Hazard  Health  ECM  L  S (please state specific section/reg. 
Measure  Rating  Categ  4. Administration (min control 
Effect  excl. OSH Act  
requirement  for S>4) 
5. PPE 

Hand caught in  Bruise, 
Pipe Isolation Work  Wear hand glove  0.3  3  3  3  I  OSHA Sect 15 & 24  Nil 
between  hand injury 
‐ Blinding, de‐blinding 
2  and reinstatement  R 
work  Wear safety goggles, 
‐ Bolt Tightening Work  Releasing of  Eyes, face,  tool inspection, approval 
0.6  3  2  4  II  OSHA Sect 15 & 24  Nil 
pressure in pipe  body injury  from client to drop 
valve/pipe 
 

Page 2 of 4 
 
 
Assessment No: Obza/HIR/LTO/001 
HAZARD IDENTIFICATION, RISK ASSESSMENT & DETERMINE CONTROL (HIRADC) REGISTER 
Revision No: 00 
Department: Technical/Maintenance  Revision Date: 22nd 2017 
Title Of Activity: Installation of GWR Instruments & Console   Assessors: Khaidir, Yunizar, Farid, Ariff, Latiff 
Job Performed by (Designation & Name): Technician & Contractor   Section: LGT1 
Prepared By / Date: Khaidir / 22nd 2017  Checked By / Date: Mr Spencer / 30th Nov 2017  Approved By / Date: En Mohd Shahriwan Idris / 30th Nov 2017 
Hazard Identification  Risk Assessment  Determine Risk Control 
    Legal Compliance  Recommendation 
6. Elimination of hazard 
7. Substitution  
Safety &  Applicable OSH Legislations 
Existing Control  Risk  Risk  8. Engineering 
No  Sub‐Activity  Type  Hazard  Health  ECM  L  S (please state specific section/reg. 
Measure  Rating  Categ  9. Administration (min control 
Effect  excl. OSH Act  
requirement  for S>4) 
10. PPE 
Wear safety 
Slips, trips and  shoes & leather 
Injury  0.3  3  2  2  I  OSHA Sect 15 & 24  Nil 
falls  hand gloves, 
competent person 
Competence crane 
operator with valid JKKP 
Injury,  Cert, provide experience  Administration – do not allowed crane 
Falling of 
property  rigger and signal man  0.6  3  3  6  II  OSHA Sect 15 & 24  operator without valid JKKP Cert to 
Lifting item 
damage  c/w cert, eliminate  involve lifting work 
obstruction prior lifting 
work 
Lifting Work using Crane 
Competence crane 
‐ Removal of existing 
operator with valid JKKP 
piping line 
3  R  Injury,  Cert, Crane set‐up at 
‐ Installation of console  Crane topple 
property  solid area & ground,  0.6  3  3  6  II  OSHA Sect 15 & 24  Nil 
‐ Installation of  and overload 
damage  provide experience 
equipment 
rigger and signal man 
c/w cert 
Boom/lifting  Eliminate obstruction 
item crash with  property  prior lifting work, good 
0.6  3  3  6  II  OSHA Sect 15 & 24  Nil 
equipment /  damage  communication ‐ 
structure  operator and signalman 

Rigger at correct 
Workers 
Serious  position, good 
trapped at  0.3  3  2  2  I  OSHA Sect 15 & 24  Nil 
injury  communication ‐ 
pinch point 
operator and signalman 

Page 3 of 4 
 
 

 
Assessment No: Obza/HIR/LTO/001 
HAZARD IDENTIFICATION, RISK ASSESSMENT & DETERMINE CONTROL (HIRADC) REGISTER 
Revision No: 00 
Department: Technical/Maintenance  Revision Date: 22nd 2017 
Title Of Activity: Installation of GWR Instruments & Console   Assessors: Khaidir, Yunizar, Farid, Ariff, Latiff 
Job Performed by (Designation & Name): Technician & Contractor   Section: LGT1 
Prepared By / Date: Khaidir / 22nd 2017  Checked By / Date: Mr Spencer / 30th Nov 2017  Approved By / Date: En Mohd Shahriwan Idris / 30th Nov 2017 
Hazard Identification  Risk Assessment  Determine Risk Control 
    Legal Compliance  Recommendation 
1. Elimination of hazard 
2. Substitution  
Safety &  Applicable OSH Legislations 
Existing Control  Risk  Risk  3. Engineering 
No  Sub‐Activity  Type  Hazard  Health  ECM  L  S (please state specific section/reg. 
Measure  Rating  Categ  4. Administration (min control 
Effect  excl. OSH Act  
requirement  for S>4) 
5. PPE 
Awkward 
posture  Adopt proper 
Back pain  0.3  2  2  1  I  OSHA Sect 15 & 24  Nil 
during  work posture 
housekeeping 
4  Housekeeping  R 
Beware and 
Bruise and 
Slip and trip  safety shoes not  0.3  2  2  1  I  OSHA Sect 15 & 24  Nil 
body injury 
worn out 

Note: 

OSHA ‐ Occupational Safety & Health Act 1994 

Page 4 of 4 
 
 
TO CARRY OUT MODIFICATION PROJECT ON GAS OIL PIPELINE TO INSTALL WIRELESS 
GUIDED WAVE RADAR. LOCATION: 6” STAB AT 4000 SERIES GAS OIL SUCTION HEADER LINE 

Doc No  OBZA‐MOS‐TO‐2017‐001
METHOD OF STATEMENT FOR INSTALLTION WORK  Rev 00 
Date  Nov 21st 2017
 
 
 
 
 
 
 
 
 
 
 
 
 
 
ATTACHMENT 2: Lifting Arrangement 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Page | 10  
 
LIFTING ARRANGEMENT
LIFTING ARRANGEMENT

TOP ELEVATION

obza-dwg-to-2017-001
 
TO CARRY OUT MODIFICATION PROJECT ON GAS OIL PIPELINE TO INSTALL WIRELESS 
GUIDED WAVE RADAR. LOCATION: 6” STAB AT 4000 SERIES GAS OIL SUCTION HEADER LINE 

Doc No  OBZA‐MOS‐TO‐2017‐001
METHOD OF STATEMENT FOR INSTALLTION WORK  Rev 00 
Date  Nov 21st 2017
 
 
 
 
 
 
 
 
 
 
 
 
 
 
ATTACHMENT 3: Crane Load Chart 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Page | 11  
 
 
 
TO CARRY OUT MODIFICATION PROJECT ON GAS OIL PIPELINE TO INSTALL WIRELESS 
GUIDED WAVE RADAR. LOCATION: 6” STAB AT 4000 SERIES GAS OIL SUCTION HEADER LINE 

Doc No  OBZA‐MOS‐TO‐2017‐001
METHOD OF STATEMENT FOR INSTALLTION WORK  Rev 00 
Date  Nov 21st 2017
 
 
 
 
 
 
 
 
 
 
 
 
 
 
ATTACHMENT 4: Bolt Tightening Torque Value 

Page | 12  
 
Title: Document No: Rev: Date:
FLANGE MANAGEMENT PROCEDURE PRO-FM-FSO-BER-000-16 FM/CWS/04 14/2/2017

Generated from license ATW Joint Integrity Software

Table 1. Recommended Torque Value - Class 150#

FLANGE RATING 150#


SPIRAL WOUND / NON-ASBESTOS
Gasket
TORQUE VALUE (Nm) Dry (µ-0.20) TORQUE VALUE (Nm) Moly (µ-0.13) TORQUE VALUE (Nm) PTFE (µ-0.12)

BOLT MATERIAL B7 / L7 /
B7 / L7 / B7 / L7 /
Line Size Bolt Nut Size No. of B8M Remarks B8M Remarks B7M / B8M Remarks
B7M / L7M B7M / L7M
(NPS) Size(Inch) AF Bolt Hole L7M
1/2 1/2 22 4 61 61 42 42 39 39
3/4 1/2 22 4 61 61 42 42 39 39
1 1/2 22 4 71 71 49 49 45 45
1 1/2 1/2 22 4 92 92 62 62 58 58
2 5/8 27 4 180 180 122 122 114 114
3 5/8 27 4 200 200 136 136 127 127
4 5/8 27 8 180 180 122 122 114 114
6 3/4 32 8 351 351 238 238 221 221
8 3/4 32 8 351 351 228 228 221 221
10 7/8 36 12 449 449 304 304 283 283
12 7/8 36 12 506 506 342 342 319 319
14 1 41 12 753 753 509 509 474 474
16 1 41 16 669 669 453 453 422 422
18 1 1/8 46 16 985 985 663 663 618 618
20 1 1/8 46 20 985 985 663 663 618 618
24 1 1/4 50 20 1383 1383 929 929 864 864
28 1 1/4 50 28 1383 1383 929 929 864 864

Page 36