Professional Documents
Culture Documents
Provincial Government
Bagmati Province
Ministry of Physical Infrastructure
Development Hetauda, Nepal
FINAL REPORT
Volume I. Main Report
Submitted by
Sentinel Engineering Consultancy Pvt. Ltd.
Balaju, Kathmandu
May, 2020
i
Sisnughari Muhan Irrigation Project, Nuwakot 2020
Synopsis
The Sisnughari Muhan Irrigation Project has 19 Ha of net command area which lies in the
Tadi Rural Municipality in Nuwakot district. The source has limited water but it is perennial.
A core walls and single stage orifice is proposed as an intake. As per the demand of the user
and site condition, the main and branches are proposed HDPE pipeline. The length of the
main pipeline is 825m and branches is around 1200 m. The canal has the designed discharge
of the canal is 56 lps at the intake. The pipe has designed to accommodate the future water
demand as per the proposed cropping pattern. protection work in the intake also proposed.
Sisnughari Muhan Irrigation Project is a demand driven project. At present, only limited area
of the proposed command area has paddy, wheat and vegetables cultivation is carried out by
present physical infrastructure. With the construction of this project, the proposed command
area is expected to be provided with year round irrigation facility. Consequently, the
agriculture yield will be increased substantially and eventually, the living standard of the
people living within the command area will rise. The total cost of the project has been
estimated to be NRs. 63,11,000 (as per rates of 2076/77) and the internal rate of return is
18.01% and project is recommended for implementation.
ii
Sisnughari Muhan Irrigation Project, Nuwakot 2020
Salient Features
iii
Sisnughari Muhan Irrigation Project, Nuwakot 2020
Acronyms
iv
Sisnughari Muhan Irrigation Project, Nuwakot 2020
Table of Content
List of figure................................................................................................................ viii
List of Table ................................................................................................................ viii
1 Introduction ............................................................................................................ 1
1.1 Background of the project ............................................................................................. 1
1.2 Context of the present Study ........................................................................................ 1
1.3 Objective and Scope of the work .................................................................................. 2
1.4 Approach and Methodology .......................................................................................... 2
1.5 Report structure ............................................................................................................ 3
2 Study area ........................................................................................................................ 4
2.1 Project Area ................................................................................................................... 4
2.1.1 Location and Accessibility ........................................................................................... 4
2.1.2 Climate, Topography and Soil ..................................................................................... 4
2.1.3 Socio-Economic background ....................................................................................... 5
2.1.4 Existing Irrigation Infra-structures .............................................................................. 5
2.1.5 Issues related to infra-structures and Institutions. .................................................... 5
3 Methodology.................................................................................................................... 6
3.1 Inception meeting.......................................................................................................... 6
3.2 Field survey .................................................................................................................... 6
3.3 Hydrological study ......................................................................................................... 6
3.4 Estimation of Flow at Diversion/Intake Site .................................................................. 7
3.4.1 MIP Method ................................................................................................................ 7
3.4.2 Estimation of 80% Reliable Monthly Flow .................................................................. 7
3.4.3 Sharma and Adhikari (2004) ....................................................................................... 7
3.4.4 Mean Monthly Flow Calculation ................................................................................. 8
3.4.5 High Flood Estimation ................................................................................................. 8
4 Socio economic and Agriculture status ......................................................................... 11
4.1 Demographic Characteristics ....................................................................................... 11
4.2 Social Organization and Water User's Association:..................................................... 11
4.3 Economy and Occupation ............................................................................................ 11
4.4 Operational Land Holding and Tenancy Status ........................................................... 12
4.5 Crop water requirement .............................................................................................. 12
4.6 Agricultural Benefit ...................................................................................................... 19
5 Engineering System Design ........................................................................................... 22
5.1 Off take structure ........................................................................................................ 22
5.2 Canal Network ............................................................................................................. 27
v
Sisnughari Muhan Irrigation Project, Nuwakot 2020
vii
Sisnughari Muhan Irrigation Project, Nuwakot 2020
List of figure
List of Table
Table 3.1: Regional Equation Coefficients for Estimation of Monthly Flows ...................... 8
Table 3.3. 50 years flood in Sisnughari Muhan river by different methods .......................... 9
Table 3.4. Flow estimation in in seepage by MIP method..................................................... 9
Table 4.1. Demographic situation of the study area ............................................................ 11
Table 4.2. PET in the study area under present climatic condition ..................................... 15
Table 4.3. Scheme water calculated for future cropping intensity....................................... 16
Table 4.4. Proposed cropping pattern in study area ............................................................. 17
Table 4.5. Climatic data used to calculate the crop water requirement ............................... 18
Table 4.6. Average Yields of Major Crops at rain-fed and irrigated Condition (Mt/ha) ..... 19
Table 4.7. Market price of major items................................................................................ 19
Table 4.8. Net benefit after provide irrigation facilities ...................................................... 20
Table 4.9. Crop budget for proposed crops.......................................................................... 21
Table 5.1. Design of core wall ............................................................................................. 23
Table 7.1. Screening of Major Potential Impact .................................................................. 36
Table 8.1. Abstract of cost of the project ......................................................................... 43
Table 8.2. Economic indicator with sensitivity analysis ..................................................... 45
viii
Sisnughari Muhan Irrigation Project, Nuwakot 2020
1. INTRODUCTION
intake extracting water from this source, the diversion of water does not affect the schemes
downstream.
2
Sisnughari Muhan Irrigation Project, Nuwakot 2020
3
Sisnughari Muhan Irrigation Project, Nuwakot 2020
2 STUDY AREA
area is lies in one side of the main canal. Soil of the command area is suitable and fertile for
the production of food grains and vegetables. The proposed command area is composed of
plain and leveled land and soil depth is sufficient for various type of crop cultivation.
5
Sisnughari Muhan Irrigation Project, Nuwakot 2020
3 METHODOLOGY
7
Sisnughari Muhan Irrigation Project, Nuwakot 2020
Const Coefficient
Transformation
Month A Avg. Elev. Ann. Ppt. A3000 A5000
1 2 3 4 5 6
Jan -16.7 1.36 0.470 0.820 - Ln
Feb -17.2 1.42 0.456 0.814 - Ln
Mar 0.384 - - - 0.091 Sqrt
Apr 0.181 - - - 0.104 Sqrt
Where,
Q2 = 2 year return period flood
Q100 = 100 year return period flood
A3000 = Catchment area under 3000 m
For estimating the floods of different return periods, the relationship used in the WECS and
DHM method can be used.
Qf = exp (Ln (Q2+Sơn)
Where, Qf = Flow for various return Periods
ơn = Ln(Q100/Q2)/2.326
8
Sisnughari Muhan Irrigation Project, Nuwakot 2020
The calculation of the design discharge is shown in the annex 1. The summary of the
maximum discharge obtained from the different method shown in the table 3.2.
January 2.71 15.26 17.00 14.00 January 2.47 4.93 5.00 5.00
February 1.88 10.58 12.00 10.00 February 1.82 3.63 4.00 3.00
March 1.38 7.77 8.00 7.00 March 1.35 2.69 3.00 3.00
April 1.00 5.63 6.00 7.00 April 1.00 1.99 2.00 2.00
May 1.88 10.58 9.00 12.00 May 0.82 1.64 2.00 2.00
June 3.13 17.62 16.00 32.00 June 1.29 2.57 2.00 4.00
July 13.54 76.23 62.00 92.00 July 4.71 9.39 8.00 17.00
August 25.00 140.75 125.00 135.00 August 20.59 41.06 33.00 40.00
September 20.83 117.27 123.00 103.00 September 17.65 35.19 37.00 30.00
October 10.42 58.66 73.00 51.00 October 7.65 15.25 20.00 14.00
November 5.00 28.15 36.00 26.00 November 4.82 9.61 11.00 9.00
December 3.75 21.11 23.00 20.00 December 3.53 7.04 8.00 7.00
9
Sisnughari Muhan Irrigation Project, Nuwakot 2020
Figure 3.2. Mean monthly flow and 80% reliable mean monthly flow in Sisnughari Muhan
by MIP method
The agriculture status, design, cost estimate and economic analysis will be discussed in the
coming chapter separately.
10
Sisnughari Muhan Irrigation Project, Nuwakot 2020
11
Sisnughari Muhan Irrigation Project, Nuwakot 2020
The value of Kc varies mainly on the specific crop type and somehow depends on the soil
evaporation and climate condition. The value of Kc also varies with in the life period of the
plant. There is different value in growing period, maturity period and harvesting period. It
converts the reference evapotranspiration to the crop evapotranspiration. Kc approach is
accepted universally.
Scheme water requirement was calculating by using CROPWAT8.0. For that the first step is
to calculate the ETo. As describe in the equation 4.1, ETo can calculate by the CROPWAT
model. There are different methods to calculate ETo but Penman-Monteith method was used
in this study. After that the effective rainfall was calculated. Effective rainfall (P eff) was
calculated by the USDA soil conservation method where effective rainfall was calculated as
per following equations
12
Sisnughari Muhan Irrigation Project, Nuwakot 2020
The next step is to define the cropping pattern. The cropping pattern of the study area was
collected from the past report and field visit. Both case collecting data from the field or
district level office. Some data were taken from the literature. The software calculates the
CWR of each crop. Than after deduction the effective rainfall from the CWR, irrigation water
requirement was obtained for each crop. Finally, after summing up the all water requirement
in corresponding time period, total scheme water requirement can be obtained. After
applying efficiency-coefficient in scheme water requirement, total water required in source
can be obtained. For this study, he cropping pattern was obtained from the field data. All
climatic data were obtained from DHM, Nepal. Figure 4.1 shows the steps to calculate the
irrigation water demand. The cropping pattern and the corresponding cultivated area were
taken from the field during field survey. The scheme water requirement or water required in
the source was calculated by using the scheme efficiency 30%.
The present water requirement will be calculated by using the present cropping system and
current climate scenario where as the future crop water requirement will be calculated by
using the future cropping pattern.
The study assumes that the climatic parameters, such as wind speed, sunshine hour and
humidity, are assumed to be the same in the future under different analysis scenarios. In case
of Sisnughari Muhan irrigation project, there is no meteorological stations inside the
command area so the nearby Nuwakot stations data are used.
The crop water requirement in present and future condition has calculated by Penman
equations. The evapotranspiration was calculated by using the Penman Monith equation. The
meteorological data from the Nuwakot stations was used to calculate the crop water
requirement in the present condition. The sunshine hour, wind speed and relative humidity
was also taken from the nearby Kathmandu airport. The proposed (future) cropping pattern
was used to calculate the crop water requirement during present and future condition. The
PET is very important factor to calculate the CWR. the table 4.2 and figure 4.4 shows the
PET of the study area under the present cropping condition.
14
Sisnughari Muhan Irrigation Project, Nuwakot 2020
Table 4.2. PET in the study area under present climatic condition
15
Sisnughari Muhan Irrigation Project, Nuwakot 2020
The proposed cropping pattern and the meteorological data is shown in the table 4.4 and 4.5
respectively, in which traditional paddy remains the main monsoon crop, with supplementary
irrigation to increase yields. Other major seasonal crops are the wheat, maize, pulses, oilseed,
potato, seasonal vegetables etc. The choices of crops are made analyzing the land use
capability, water availability and preference made by the farming communities and also
taking account of market opportunities. The cropping intensity under the proposed plan is as
high as 274% from the current 152%.
After confirmed the present and future cropping pattern, the irrigation water requirement is
calculated. By taking the thirty percent of the scheme efficiency, scheme water for the project
is calculated. Table 4.3 shows the scheme water under future cropping pattern.
The maximum water demand is 28.9 lps in the June. Hence the system has been designed
for the 29 lps capacity.
16
Sisnughari Muhan Irrigation Project, Nuwakot 2020
Month Jan Jan Feb Feb Mar Mar Apr Apr May May Jun Jun Jul Jul Agu Aug Sep Sep Oct Oct Nov Nov Dec Dec
Area Area
Crop (ha) (%) I II I II I II I II I II I II I II I II I II I II I II I II
Monsoon Paddy 11 58
Maize 7 37
Wheat 5 26
Potato 5 26
Musturd 1 5
winter Vegetable 8 42
spring Vegetable 7 37
Monsoon vegetable 8 42
Total cropping intensity (%) 274
17
Sisnughari Muhan Irrigation Project, Nuwakot 2020
Table 4.5. Climatic data used to calculate the crop water requirement
18
Sisnughari Muhan Irrigation Project, Nuwakot 2020
Here are some difficulties to calculate the production cost. To calculate the total production
cost all costs should be measured, whether purchased or owner supplied. The basic concept
is that if it is necessary for production, then it must be valued. Cost items that are purchased
and expended during the production period include inputs such as seed, fertilizer and
pesticides. Farmer can also be hired capital expenses such as rented machinery or bullock
livestock. Costs also include all charges for labor whether paid for or not, hired or owner
provided, paid in kind or in cash or sourced to unpaid family members. Cost items whose
service life extends over several production periods, such as capital service costs
(depreciation on owned machinery and buildings), also need to be measured. In the present
study we have calculated the production cost as per the privilege norms and market price.
The table 4.9 shows the production cost for the different type of crops.
19
Sisnughari Muhan Irrigation Project, Nuwakot 2020
20
Sisnughari Muhan Irrigation Project, Nuwakot 2020
40.00 100.00 20.00 18.00 25.00 1,000.00 1.00 1.50 1.50 20.00 40.00
1 Seed
Price 50.00 50.00 50.00 60.00 60.00 20.00 2,000.00 2,000.00 2,000.00 50.00 50.00
Value 2,000.00 5,000.00 1,000.00 1,080.00 1,500.00 20,000.00 2,000.00 3,000.00 3,000.00 1,000.00 2,000.00
2 Organic Fertilizer 2.00 2.00 3.00 1.00 1.00 3.00 3.00 3.00 3.00 3.00 2.00
Price 2,000.00 2,000.00 2,000.00 2,000.00 2,000.00 2,000.00 2,000.00 2,000.00 2,000.00 2,000.00 2,000.00
Value 4,000.00 4,000.00 6,000.00 2,000.00 2,000.00 6,000.00 6,000.00 6,000.00 6,000.00 6,000.00 4,000.00
3 Nitrogen, N 100.00 100.0 60.00 60.00 35.00 70.00 70.00 70.00 70.00 60.00 100.00
Required Urea 191.87 174.86 104.91 104.91 54.82 109.64 109.64 109.64 109.64 104.91 191.87
Price 19.42 19.42 19.42 19.42 19.42 19.42 19.42 19.42 19.42 19.42 19.42
Value 3,726.14 3,395.75 2,037.45 2,037.45 1,064.61 2,129.22 2,129.22 2,129.22 2,129.22 2,037.45 3,726.14
4 Phosphorus P 30.00 50.00 30.00 30.00 25.00 50.00 50.00 50.00 50.00 30.00 30.00
Required DAP 65.22 108.70 65.22 65.22 54.35 108.70 108.70 108.70 108.70 65.22 65.22
Price 46.42 46.42 46.42 46.42 46.42 46.42 46.42 46.42 46.42 46.42 46.42
Value 3,027.39 5,045.65 3,027.39 3,027.39 2,522.83 5,045.65 5,045.65 5,045.65 5,045.65 3,027.39 3,027.39
5 Potassium K 30.00 25.00 30.00 30.00 30.00 40.00 40.00 40.00 40.00 30.00 30.00
Required MOP 50.00 41.67 50.00 50.00 50.00 66.67 66.67 66.67 66.67 50.00 50.00
Price 32.42 32.42 32.42 32.42 32.42 32.42 32.42 32.42 32.42 32.42 32.42
Value 1,621.00 1,350.83 1,621.00 1,621.00 1,621.00 2,161.33 2,161.33 2,161.33 2,161.33 1,621.00 1,621.00
6 Pesticide 1,000.00 1,000.00 1,000.00 1,000.00 1,000.00 2,500.00 2,500.00 2,500.00 2,500.00 1,000.00 1,000.00
7 Farm Labour 100.00 96.00 90.00 60.00 60.00 144.00 100.00 100.00 100.00 90.00 100.00
Price 400.00 400.00 400.00 400.00 400.00 400.00 400.00 400.00 400.00 400.00 400.00
Value 40,000.00 38,400.00 36,000.00 24,000.00 24,000.00 57,600.00 40,000.00 40,000.00 40,000.00 36,000.00 40,000.00
8 Animal Labour 48.00 40.00 40.00 40.00 40.00 60.00 60.00 60.00 60.00 40.00 48.00
Price 500.00 500.00 500.00 500.00 500.00 500.00 500.00 500.00 500.00 500.00 500.00
Value 24,000.00 20,000.00 20,000.00 20,000.00 20,000.00 30,000.00 30,000.00 30,000.00 30,000.00 20,000.00 24,000.00
Input per ha 79,374.53 78,192.23 70,685.84 54,765.84 53,708.44 125,436.21 89,836.21 90,836.21 90,836.21 70,685.84 79,374.53
21
Sisnughari Muhan Irrigation Project, Nuwakot 2020
The detail design is shown in the volume 2. As a sample design, the summary of the design
of core wall is shown in table 5.1. The main and branch pipe layout system and corresponding
command area is shown in the figure 5.1.
22
Sisnughari Muhan Irrigation Project, Nuwakot 2020
w3
Existing RBL
1.200
w1
w4
1.00
sat.
earth
P1 w2
D C B A Max. Anticipated scour
0.20 level
0.20
0.20
w5
D' C' B' A'
1.25
23
Sisnughari Muhan Irrigation Project, Nuwakot 2020
25.35
36.90
41.52
Pressure distribution
26
Sisnughari Muhan Irrigation Project, Nuwakot 2020
27
Sisnughari Muhan Irrigation Project, Nuwakot 2020
Figure 5.1. Main canal/ pipe, branches, offtake, and command area of the Sisnughari Muhan
Irrigation System in site plan and google map.
28
Sisnughari Muhan Irrigation Project, Nuwakot 2020
6 INSTITUTIONAL ASPECT
6.1 Introduction
The success of an irrigation project will often depend on various socio-economic factors. The
idea behind the active participation and cost sharing by the users in the development of
irrigation system is to develop a sense of ownership among users and subsequent efficient
operation and maintenance by them so as to make the project sustainable and effective. At
present, the entire command area is suffered by lack of irrigation facilities. As a result, the
cropping intensity is low and yield of the crop is also less than average of the district.
Therefore, the living standard of the farmers is low with less economic activities. The
production of the crops is not sufficient for fulfilling farmers demand. So the farmers are
compelled to buy food grains. To boost up economic status of the farmer's cash crops like
vegetables farming is proposed.
arise during any stage of implementation of project can easily be solved by the management
at the beneficiary's level.
30
Sisnughari Muhan Irrigation Project, Nuwakot 2020
Assist WUA with the help of COs to drafts constitutions, by-laws, rules and
regulations of WUA, approach of them through general assembly of WUA and
regulate them properly in practice.
Assist WUA for organizational set - up and formal registration of WUA.
Assist WUA with the help of COs for enrolment of members, information
dissemination organizes meetings of WUA and general assembly.
Assist WUA with the help of COs to organize different sub- committee like
construction supervision, O&M, agricultural and livelihood enhancement and
facilitate training them in necessary subject matters.
Assist WUA with the help of COs to appoint manager and treasurer and provide them
financial, administrative and accounting training as needed.
Assist WUA with the help of COs to finalize and collect the contribution in cash,
kind and labour based on the beneficiary's list for developing sub-project.
Assist to organize general assembly meeting to discuss and finalize the detail design
and cost sharing arrangements of sub-project development. The NGO will be a
signatory of the minutes of this meeting.
Facilitate the signing of the Memorandum of Agreement (MOA) by the concerned
parties. (SMU, WUA).
Assist WUA to prepare and implement of the Resettlement Plan.
Monitor and assist the COs to carry out all activities of social mobilization and
institutional development and implementation.
6.10 CO Support
The project has envisaged the concept of organization and strengthens of WUA through
deployment of COs among the competent beneficiaries. The basic roles of COs are as
follows:
Motivate the project beneficiaries in cooperation with AO and NGO.
Door to door visit within command area for all types of information campaign
regarding sub-project development.
Prepare complete list of beneficiaries' households with landholdings and other related
data and information.
Prepare list of other relevant stakeholders like landless people, dalits, and local
leaders. etc.
Facilitate in organizational set of WUA, drafting constitution, by laws, rules and
regulation of WUA and approval by general assembly.
Facilitate in organizing meeting of WUA, meeting of general assembly and
beneficiaries of different reaches as when needed.
Assist in enrolment of beneficiaries ' membership.
31
Sisnughari Muhan Irrigation Project, Nuwakot 2020
32
Sisnughari Muhan Irrigation Project, Nuwakot 2020
34
Sisnughari Muhan Irrigation Project, Nuwakot 2020
35
Sisnughari Muhan Irrigation Project, Nuwakot 2020
IEE
Actions Affecting Environmental Damages to Environment Recommended Feasible (D)
Resources and Value (B) Protection Measures No Significant Significant Impact
(A) (C) Impact Small Moderate Major
D1 D2 D3 D4
a. Environmental Effects Due to site Selection
i Encroachment into forests/swamplands i Loss of precious natural resources i Careful planning /design/
operation plus offsetting
ii Impediment to movements of wildlife cadre ii Impediment of wildlife and ii Careful
and people disruption of local economic /socio- planning/design/operation
economic
iii Impediment of historical/cultural iii Loss of precious value
monuments, buildings and values
iv Conflicts in water supply rights iv Socio-economic inequities
v Regional flooding/drainage hazards
b. Problems from Oversight in Planning and
Design
i Watershed erosion i Project benefits impaired i Appropriate attention in
project formulation
ii Downstream water quality problem ii Impairment of downstream ii Careful planning/design
beneficial uses operation
iii Suitability of water supply quality for iii Project benefits impaired iii Careful planning/design
irrigation operation
iv Land tenure problem iv Water right conflicts, salinization, iv Careful planning/design
ground Subsidence operation
36
Sisnughari Muhan Irrigation Project, Nuwakot 2020
IEE
Actions Affecting Environmental Damages to Environment Recommended Feasible (D)
Resources and Value (B) Protection Measures No Significant Significant Impact
(A) (C) Impact Small Moderate Major
D1 D2 D3 D4
v Over pumping of groundwater v Project benefits impaired v Careful planning/design
operation
vi Land tenure problems vi Project benefits impaired vi Careful planning/design
operation
vii Farmer Credit Limitation vii Project benefits impaired vii Careful planning/design
operation
viii Feasibility cooperatives viii Project benefits impaired viii Careful planning/design
operation
ix Feasibility of water user’s association ix Project benefits impaired ix Careful planning/design
operation
x Disruption of existing farmer cooperative x Project benefits impaired x Careful planning/design
system operation
xi Use of agricultural chemicals xi Project benefits impaired plus xi Careful planning/design
damage to downstream water quality operation
xii Selection of pesticides xii Project benefits impaired plus xii Careful planning/design
environmental contamination operation
xiii Land use conflicts xiii Social conflicts/project benefits xiii Careful planning/design
impaired operation
xiv Inequities in water distribution xiv Social conflicts/project benefits xiv Careful planning/design
impaired operation
37
Sisnughari Muhan Irrigation Project, Nuwakot 2020
IEE
Actions Affecting Environmental Damages to Environment Recommended Feasible (D)
Resources and Value (B) Protection Measures No Significant Significant Impact
(A) (C) Impact Small Moderate Major
D1 D2 D3 D4
xv Canal maintenance xv Project benefits impaired xv Careful planning/design
operation
xvi Passageways xvi Loss of wildlife plus disruption xvi Careful planning/design
operation
c. Problems During Construction Stage
i Erosion control i Loss of soil plus damage to i Careful construction stage
downstream water quality planning plus monitoring
ii Other construction stage hazards ii Adverse environmental effects ii Careful construction stage
planning plus monitoring
iii Monitoring during construction iii Without this, serious adverse effects iii Provision of monitoring
likely to occur
d. Problems Stemming from Deficiencies in
Operation
i Inadequate O & M i Loss in project efficiency i Careful operation plus
monitoring
ii Adverse soil modification ii Loss in project efficiency ii Careful operation plus
monitoring
iii Change in groundwater hydrology iii Adverse effects on other water and iii Careful operation plus
land use monitoring
iv Water-oriented disease hazards iv Increase in communicable disease in iv Careful operation plus
service area and region monitoring
38
Sisnughari Muhan Irrigation Project, Nuwakot 2020
IEE
Actions Affecting Environmental Damages to Environment Recommended Feasible (D)
Resources and Value (B) Protection Measures No Significant Significant Impact
(A) (C) Impact Small Moderate Major
D1 D2 D3 D4
v Toxic chemicals hazard v Adverse effects on aquaculture and v Careful use of agricultural
downstream water quality chemicals including trainings
Vi Fertilizer runoff hazard vi Adverse effects on aquaculture and vi Careful use of agricultural
downstream water quality chemicals including trainings
vii Operations monitoring vii If not provided, operations vii Provision of monitoring
inefficiency is likely
viii Aquaculture water supply viii Serious aquaculture losses viii Careful operation to ensure
continuing supply
e. Realization of Enhancement Potential
i Community water supply in service area i Nonrealization of very valuable i Project component for this
socioeconomic gains
ii Aquaculture in service area ii Nonrealization of very valuable ii Project component for this
socioeconomic gains
f. Overall Environmental Review Criteria
i Unwanted losses in precious resources i Long-term environmental and i Careful planning
economic losses
ii Unwanted accelerated use of resources for ii Long-term environmental and ii Careful planning
short term gains economic losses
iii Adverse effects on national energy iii Adverse effects on national iii Careful planning
exchange situation economics
iv Unwanted hazards to undaunted species iv Long term environmental losses iv Careful planning
39
Sisnughari Muhan Irrigation Project, Nuwakot 2020
IEE
Actions Affecting Environmental Damages to Environment Recommended Feasible (D)
Resources and Value (B) Protection Measures No Significant Significant Impact
(A) (C) Impact Small Moderate Major
D1 D2 D3 D4
v Undesirable population migration to urban v Identification of urban socio- v Careful planning
sector economic problems
vi Increase in affluent/poor income gap vi Identification of national vi Careful planning
socioeconomic imbalance
40
Sisnughari Muhan Irrigation Project, Nuwakot 2020
8.1.2 Earthworks
Earthworks mainly comprise of foundation excavation and roadway excavation for approach
road in boulder mixed soil.
8.1.3 Backfilling
The backfilling items mainly comprise of sand or granular materials excavated from the
foundation. The sand and find sand obtained from excavation is preserved to be used for
backfilling of the abutments. Whole backfilling shall be followed by ramming with portable
vibro-rammer.
41
Sisnughari Muhan Irrigation Project, Nuwakot 2020
workmanship and equipment hiring including their operation and maintenance. It also
includes all indirect expenses as contractor's profit at 15% of direct expenses.
Abstractof Cost
Name of Sub-Project : Sisnughari Irrigation Project
Location : Tadi-5, Nuwakot
S.N. Particulars Quantity Unit Rate Amount Remarks
A Civil Works
Cutting thick vegetation, their roots & disposal
1 2,440.00 m2 32.20 78,568.00
upto 25m far from construction site.
E/W in excavation in hard clay and soil mixed with
2 soft moorum stones for foundation of pipeline 1,317.60 m3 663.32 873,990.43
with all lead and lifts.
E/W in Excavation at Foundation in boulder mixed
3 155.71 m3 1,318.35 205,280.27
soil.
E/W in Excavation at Foundation in Soft Moorum
4 63.86 m3 2,487.45 158,848.55
Rocks
Earthwork in filling with hand compaction from
5 1,040.10 m3 207.29 215,602.32
excavated soil .
6 Filling with stones at the foundation and levelling 3.48 m3 6,047.16 21,044.11
8 PCC (1:2:4)-M15 concrete works for RCC works 15.72 m3 21,684.35 340,771.53
9 PCC (1:1:2)-M25 concrete works for RCC works 17.14 - 29,997.24 514,152.76
43
Sisnughari Muhan Irrigation Project, Nuwakot 2020
44
Sisnughari Muhan Irrigation Project, Nuwakot 2020
Discount rate 10
NPV (Benefit) million 10.52
NPV (Cost) million 7.76
NPV (million) 2.76
B/C Ratio 1.36
The sensitivity analysis shows the project benefits are low/disappointing in all the five
parameters including the B/C ratio. Hence, it can be summed that the project needs to be
cautiously looked upon and in the event of price fluctuation and benefits being downsized it
can only be justified from the social aspect and not from the economic aspect.
45
Sisnughari Muhan Irrigation Project, Nuwakot 2020
9.1 Conclusions
Sisnughari Muhan Irrigation Project is a demand driven project. At present, only limited area
of the proposed command area has paddy, wheat and vegetables cultivation is carried out by
present physical infrastructure. With the construction of this project, the proposed command
area is expected to be provided with year round irrigation facility. Furthermore, the project
will be able to fulfill the demand of around 19 ha of command area. Consequently, the
agriculture yield will be increased substantially and eventually, the living standard of the
people living within the command area will rise.The total cost of the project has been
estimated to be NRs. 63,11,000 (as per rates of 2076/77) and the internal rate of return is
18.01%.
9.2 Recommendations
Since this Sisnughari Muhan Irrigation Project is new type. The study is carried out on the
different aspects of the project especially regarding the acquisition of land for headworks,
pipe for main and branch canals, reservoir tank etc. The need for implementing this sub
project is adequately reflected in study here and the benefits arising thereof is also
considerable. In view of the above points and the location of the project, the Sisnughari
Muhan Irrigation Project is therefore, technically feasible, economically justifiable,
environmentally acceptable and socially beneficial and hence recommended for
IMPLEMENTATION.
46