PROJECT SITE STATUS REPORT AS OF APRIL 15,2020 (BATAAN ZAMBALES AREA)

PROJECT SITE NO. OF HOUSEHOLD STATUS HOURS OF OPERATION Q(DISCHARGE) PWL(m) SWL(m) INCIDENT REPORT ACTION TAKEN

no data no data Fire Hydrants were used by local


FCI-LIMAY 460 In Normal Operating Condition, 7-10hours 6 lps Bush fire near Subdivision
submiited submiited firefighter unit

distribution: 1lps by
FCI-MARIVELES 68 In Normal Operating Condition, Continuos Supply ( VFD) pass: 6-8lps none none none N/A

FCI-KEPPEL 113 In Normal Operating Condition, Continuos Supply ( VFD) 1-3 lps 5.3 2.1 none N/A

FCI-MANGANVACA WELL 1 24hours 2.5 lps 17.2 7.4


Sent out Team to check for leaks
Low Water Tank Level due to High Demand brought in the system and continuos
552 Demand is higher than water supplied about by Community Qurantine monitoring of water supply c/o
Foreman Nardz
FCI-MANGANVACA WELL 2 24hours 2-3 lps 16.8 6.6

Continuos Sand Pumping Observed on April 15,2020 Pump ad Motor Pull-out and
FCI-CASTILLEJOS 1000+ Needs Continuos Monitoring Continuos Supply 25lps 12.4 5.3 which resulted to Water Interruption from 4pm Preventive Maintennance by
ownwards Technical Team

HANJIN VILLAGE 969 In Normal Operating Condition, >18hours 4.4 - 6 lps 9.0 3.8 none N/A

PROJECT SITE(PIPELAYING) ACTIVITY STATUS LAST % ACCOMPLISHMENT

FCI-HERMOSA ( PHASE 1&2 / EXTENSION) none pipelaying activity on hold from March
15,2020 until further notice
37.39% Feb-20

FCI-ABUCAY none pipelaying activity on hold from March


15,2020 until further notice
0.00% Feb-20

FCI-ANINGWAY none pipelaying activity on hold from March


15,2020 until further notice

0.00% Feb-20

revised BOM submiited thru Maam Bynes last pipelaying activity on hold from March
THE HAUSLANDS SUBIC 4-3-2020 15,2020 until further notice
0.00% Feb-20

FCI-MARIVELES none pipelaying activity on hold from March


15,2020 until further notice
89.84% Feb-20

OTHER PROJECTS ACTIVITY STATUS

STEEL BOLTED TANK CONSTRUCTION @ FCI- none Steel Roofing Installation on hold until further
HERMOSA notice.

OFFICE CONSTRUCTION @ FCI-HERMOSA For Contract Signing and Downpayment temporarily suspended until further notice

FCI-PAMATAWAN PIPELAYING none no available road survey/subdivision plan at


the moment/Lockdown

Pipelaying activities on hold due to Lockdown


SUBIC BULK PIPELAYING none
and LGU's plea
WALTER MART BULK SUPPLY none no available road survey at the
moment/Lockdown