Name of Work: Construction of Under Ground Water Reserviour for Generator.

1 Earth work in excavation in all kinds of soil for foundation trenches including layout, providing center lines, local bench-mark pillars,
CES-02-1 levelling, ramming and preparing the base, fixing bamboo spikes and marking layout with chalk powder, providing necessary tools
and plants, protecting and maintaining the trench dry etc., stacking, cleaning the excavated earth at a safe distance out of the area
enclosed by the layout etc. all complete and accepted by the Engineer-in-charge, subject to submit method statement of carrying out
excavation work to the Engineer-in-charge for approval. However, engineer’s approval shall not relieve the contractor of his
responsibilities and obligations under the contract.

(A)Layout and marking for earthwork in excavation in foundation accepted by the Engineer-in-charge. [Plinth area of the structure
02.1.1
shall be considered for measurement]
1 x 14 '- 8 " x 12 '- 8" = 185.78 sft
= 185.78 sft
= 17.26 sqm
@ Tk. 15.00 p/sqm = Tk. 258.89

02.1.3 (B)Earthwork in excavation in foundation trenches up to 1.5 m depth and maximum 10 m lead: in medium stiff clayey soil.
1 x 14 '- 8 " x 12 '- 8 " x 5 '- 0 " = 928.89 cft
= 928.89 cft
= 26.30 cum
@ Tk. 126.00 p/cum = TK 3,314.17
02.1.6 (C)Extra rate for each additional 0.5 meter depth exceeding 1.5 meter.
1 x 14 '- 8 " x 12 '- 8 " x 1 '- 8 " = 309.63 cft
= 309.63 cft
= 8.77 cum
@ Tk. 146.00 p/cum = TK 1,280.08

02.1.8 (D)Extra rate for each additional 0.5 meter depth exceeding 1.5 meter.
1 x 14 '- 8" x 12 '- 8 " x 1 '- 8 " = 309.63 cft
= 309.63 cft
= 8.77 cum
@ Tk. 166.00 p/cum = TK 1,455.43

2 One layer brick flat soling in foundation or in floor with first class/picked jhama bricks including preparation of bed and filling the
CES-3.1 interstices with local sand, levelling etc. complete and accepted by the Engineer-in-charge
1 x 14 '- 8" x 12 '- 0" = 176.00 sft
= 176.00 sft
= 16.35 sqm
@ Tk. 420.00 p/sqm = Tk. 6,867.34

3 Sand filling in foundation trenches and plinth with sand having F.M. 0.5 to 0.8 in 150 mm layers including leveling, watering and
CES-02.10.1 compaction to achieve minimum dry density of 95% with optimum moisture content (Modified proctor test) by ramming each layer up
to finished level as per design supplied by the design office only, all complete and accepted by the Engineer-in-charge.

1 x 14 '- 8" x 12 '- 0 " x 0 '- 10 " = 146.67 cft


= 146.67 cft
= 4.15 cum
@ Tk. 635.00 p/cum = TK 2,637.22

4 Supplying and laying of single layer polythene sheet weighing one kilogram per 6.5 square meter in floor or anywhere below cement
CES-3.7 concrete complete in all respect and accepted by Engineer-in-charge.
1 x 14 '- 8" x 12 '- 0" = 176.00 sft
= 176.00 sft
= 16.35 sqm
@ Tk. 42.00 p/sqm = Tk. 686.70
5 Reinforced cement concrete works with minimum cement content relates to mix ratio 1:1.5:3 having minimum f'cr = 30 MPa,
CES-7.3 satisfying a specified compressive strength f’c = 25 MPa at 28 days on standard cylinders as per standard practice of Code
ACI/BNBC/ASTM, Cement conforming to BDS EN-197-1-CEM-I, 52.5N (52.5 MPa) / ASTM-C 150 Type – I, best quality Sylhet sand
or coarse sand of equivalent F.M. 2.2 and 20 mm down well graded stone chips conforming to ASTM C-33, making and placing
shutter in position and maintaining true to plumb, making shutter water-tight properly, placing reinforcement in position; mixing with
standard mixer machine with hopper, fed by standard measuring boxes or mixing in batching plant, casting in forms, compacting by
vibrator machine and curing at least for 28 days, removing centering-shuttering after specified time approved; including cost of water,
electricity, testing charges of materials and concrete cylinders as required, cost of all materials and other charges etc. all complete,
approved and accepted by the Engineer-in-charge. (Rate is excluding the cost of reinforcement and its fabrication, placing, binding
etc. and the cost of shuttering & centering)

07.3.1 (A)Individual & combined footing, pile cap, raft/mat, floor slab and foundation beam up to plinth level
Concrete
1 x 14 '- 8 " x 12 '- 0 " x 1 '- 0 " = 176.00 cft
= 176.00 cft
= 4.98 cum
@ Tk. 12154.00 p/cum = TK 60,572.11

Centering and shuttering, including strutting, propping etc. (The formwork must be rigid enough both in and out of plane, to make the
7.9 concrete surface true to the designed shape and size by using necessary MS sheets of minimum 16 BWG, angles of minimum size
40 mm x 40 mm x 5 mm, flat bars etc.) and removal of form after hardening of the concrete for:
07.9.1 Individual and combined footing
2 x 14 '- 8" x 1 '- 0" = 29.33 sft
2 x 12 '- 8" x 1 '- 0" = 25.33 sft
= 54.67 sft
= 5.08 sqm
@ Tk. 438.00 p/sqm = Tk. 2,225.04

07.3.2 (B)Pedestals, column, column capital, lift wall and RCC wall up to ground floor
Concrete
2 x 11 '- 8 " x 6 '- 0 " x 1 '- 0 "= 140.00 cft
2 x 8 '- 0 " x 6 '- 0 " x 1 '- 0 "= 96.00 cft
= 236.00 cft
= 6.68 cum
@ Tk. 12367.00 p/cum = TK 82,645.11

Centering and shuttering, including strutting, propping etc. (The formwork must be rigid enough both in and out of plane, to make the
7.9 concrete surface true to the designed shape and size by using necessary MS sheets of minimum 16 BWG, angles of minimum size
40 mm x 40 mm x 5 mm, flat bars etc.) and removal of form after hardening of the concrete for:

07.9.4 Pedestal, column, column capital, lift wall and wall up to ground floor
4 x 11 '- 8 " x 6 '- 0" = 280.00 sft
4 x 8 '- 0 " x 6 '- 0" = 192.00 sft
= 472.00 sft
= 43.85 sqm
@ Tk. 408.00 p/sqm = Tk. 17,890.80

07.3.3 Floor / roof slab, T-beam, L-beam and rectangular beam, tie beam, lintel, stair case slab and steps etc. upto ground floor
Concrete
1 x 11 '- 8 " x 10 '- 0 " x 0 '- 6 " = 58.33 cft
= 58.33 cft
= 1.65 cum
@ Tk. 12240.00 p/cum = TK 20,218.04

Centering and shuttering, including strutting, propping etc. (The formwork must be rigid enough both in and out of plane, to make the
7.9 concrete surface true to the designed shape and size by using necessary MS sheets of minimum 16 BWG, angles of minimum size
40 mm x 40 mm x 5 mm, flat bars etc.) and removal of form after hardening of the concrete for:
07.9.7 Floor and roof slab up to ground floor
1 x 11 '- 8" x 10 '- 0" = 116.67 sft
Side 1 x 43 '- 4" x 0 '- 6" = 21.67 sft
= 116.67 sft
= 10.84 sqm
@ Tk. 532.00 p/sqm = Tk. 5,766.88
6 Supplying, fabrication and fixing to detail as per design : ribbed or deformed bar reinforcement for Reinforced cement concrete,
CES-8.1 produced and marked in accordance with BDS ISO 6935 - 2: 2006 (or standard subsequentley released from BSTI) including
straightening and cleaning rust, if any, bending and binding in position with supply of G.I. wires, conducting necessary laboratory
tests etc. (excluding splices or laps) complete in all respect and accepted by the Engineer-in-charge (Measurement shall be recorded
only on standard mass per unit length of bars, while dia of bars exceeds its standard)
8.1.2 Grade 400 (RB 400 /RB 400W: complying BDS ISO 6935-2:2006) ribbed or deformed bar produced and marked according to
Bangladesh standard, with minimum yield strength, fy (ReH)= 400 MPa but fy not exceeding 450 MPa and whatever is the yield
strength within allowable limit as per BNBC/ ACI 318, the ratio of ultimate tensile strength fu to yield strength fy, shall be at least 1.25
and minimum elongation after fracture and minimum total elongation at maximum force is 16% and 8% respectively : up to ground
floor.

Qnty bf item no-5 base casting portion 4.98 cum x 1.75 % = 684.64 kg
Qnty bf item no-5 wall casting portion 6.68 cum x 2.00 % = 1,049.19 kg
Qnty bf item no-5 slab casting portion 1.65 cum x 1.50 % = 194.50 kg
1928.32 kg
@ Tk. 82.00 p/kg = Tk. 158,122.54

7 Supplying, fitting and fixing ribbed PVC water stopper with non centre bulb of width approx. 250 mm and approx 9 mm thick for
CES-8.5.1 immovable (non working) RCC joints, having minimum tensile strength of 8.27 MPa (approx. 1200 psi) min ultimate elongation 350%,
approximate hardness 50, minimum tear resistance 0.0175 kN/mm (100 lbs/inch) at RCC construction green joints in basements,
approved and in consultation with design office, providing 38 mm x 62 mm wooden batten at the top and bottom of water stopper,
holding in position and keeping the water stopper in true horizontal or vertical by appropriate means as where necessary etc; all
complete and accepted by the Engineer-in-charge.

Roof top 4 x 11 '- 8" = 46.67 sft


Roof top 4 x 8 '- 0" = 32.00 sft
= 78.67 rft
= 23.98 rm
@ Tk. 1017.00 p/cum = TK 24,384.03

8 Providing minimum 12 mm thick cement sand (F.M. 1.2) plaster with neat cement finishing to plinth wall with cement (1:4) up to 150
CES-15.2 mm below ground level including washing of sand, finishing the edges and corners and curing at least for 7 days, cost of water,
electricity, scaffolding and other charges etc. all complete in all respect as per drawing and accepted by the Engineer-in-charge.
(Cement: CEM-II/A-M) ground floor.
Qnty same as item no-5(B)formwork portion = 472.00 sft
Roof top 1 x 11 '- 8" x 10 '- 0" = 116.67 sft
= 588.67 Sqm
@ Tk. 280.00 p/sqm = Tk. 164,826.67
9 38 mm thick artificial patent stone (1:2:4) flooring with cement, best quality coarse sand (50% quantity of Sylhet sand or coarse sand
CES-4.27 of equivalent F.M. 2.2 and 50% best quality local sand of FM 1.2) and 12 mm down well graded brick chips including breaking chips,
screening, laying the concrete in alternate panels, compacting and finishing the top with neat cement and curing at least for 7 days in
all floors including cost of water, electricity and other charges etc. all complete and accepted by the Engineer-in-charge. (Cement:
CEM-II/A-M) In ground floor

Floor 1 x 10 '- 0" x 8 '- 0" = 80.00 sft


= 80.00 Sqm
@ Tk. 468.00 p/sqm = Tk. 37,440.00

10 Supply, fitting and fixing of 600 mm dia C.I. man hole cover etc. all complete approved by the Engineer- in- charge.
CES-26.75
= 2.00 nos
@ Tk. 1,869.00 each = Tk. 3,738.00
11 Earth filling in foundation trenches and plinth in 150 mm layer with earth available within 90 m of the building site to achive
CES-2.13 minimum dry density of 95% with optimum moisture content (Modified proctor test) including carrying, watering, leveling, dressing
and compacting to a specified percentage each layer up to finished level etc. all complete and accepted by Engineer-in-charge.

Qnty bf item no-1 A = 26.30 Cum


Qnty bf item no-1 B = 8.77 Cum
Qnty bf item no-1 B = 8.77 Cum
= 43.84 Cum
Back Filing 1/5 = 8.77 Cum
@ Tk. 149.00 p/Cum = Tk. 1,306.38
Total = Tk. 595,635.41

(Md Iqramul hasan chowdhury) ( A S M Musa)


Sub-Assistant Engineer Sub-Divisional Engineer
Narsingdi PWD Sub-Division-1, Narsingdi PWD Sub-Division-1
Narsingdi. Narsingdi.

(Enamul Haque) (Muhammed Moniruzzman)


Sub-Assistant Engineer Assistant Engineer Executive Engineer
NarsingdiPWD Division Narsingdi PWD Division, Narsingdi PWD Division,
Narsingdi. Narsingdi. Narsingdi.
Name of Work: Construction of Under Ground Water Reserviour for Generator.
1 Earth work in excavation in all kinds of soil for foundation trenches including layout, providing center lines, local bench-mark pillars,
CES-02-1 levelling, ramming and preparing the base, fixing bamboo spikes and marking layout with chalk powder, providing necessary tools
and plants, protecting and maintaining the trench dry etc., stacking, cleaning the excavated earth at a safe distance out of the area
enclosed by the layout etc. all complete and accepted by the Engineer-in-charge, subject to submit method statement of carrying out
excavation work to the Engineer-in-charge for approval. However, engineer’s approval shall not relieve the contractor of his
responsibilities and obligations under the contract.

(A)Layout and marking for earthwork in excavation in foundation accepted by the Engineer-in-charge. [Plinth area of the structure
02.1.1
shall be considered for measurement]
Qty Bf T/MB Page No- 2 Item No 1 = 318.00 sqm

Add E Tp Side 1 x 100 '- 0" x 4 '- 0" = 400.00 sft


= 37.16 sqm
= 355.16 sqm
@ Tk. 20.00 p/sqm

02.1.3 (B)Earthwork in excavation in foundation trenches up to 1.5 m depth and maximum 10 m lead: in medium stiff clayey soil.
Qty Bf T/MB Page No- 2 Item No 1 = 145.39 sqm
Add E Tp Side 1 x 100 '- 0" x 1 '- 6 " x 0 '- 10 " = 125.00 Cft
= 3.54 Cum

= 3.54 Cum

@ Tk. 82.00 p/cum


2 One layer brick flat soling in foundation or in floor with first class/picked jhama bricks including preparation of bed and filling the
CES-3.1 interstices with local sand, levelling etc. complete and accepted by the Engineer-in-charge
Qty Bf T/MB Page No- 2 Item No 1 = 318.00 sqm
Add E Tp Side 1 x 100 '- 0" x 1 '- 6" = 150.00 sft
= 13.94 sqm
= 13.94 sqm
@ Tk. 320.00 p/sqm

3 Sand filling in foundation trenches and plinth with sand having F.M. 0.5 to 0.8 in 150 mm layers including leveling, watering and
CES-02.10.1 compaction to achieve minimum dry density of 95% with optimum moisture content (Modified proctor test) by ramming each layer up
to finished level as per design supplied by the design office only, all complete and accepted by the Engineer-in-charge.

1 x 14 '- 8" x 12 '- 0 " x 0 '- 10 " = 146.67 cft


= 146.67 cft
= 4.15 cum
@ Tk. 635.00 p/cum

4 Supplying and laying of single layer polythene sheet weighing one kilogram per 6.5 square meter in floor or anywhere below cement
CES-3.7 concrete complete in all respect and accepted by Engineer-in-charge.
1 x 14 '- 8" x 12 '- 0" = 176.00 sft
= 176.00 sft
= 16.35 sqm
@ Tk. 42.00 p/sqm

5 Reinforced cement concrete works with minimum cement content relates to mix ratio 1:1.5:3 having minimum f'cr = 30 MPa,
CES-7.3 satisfying a specified compressive strength f’c = 25 MPa at 28 days on standard cylinders as per standard practice of Code
ACI/BNBC/ASTM, Cement conforming to BDS EN-197-1-CEM-I, 52.5N (52.5 MPa) / ASTM-C 150 Type – I, best quality Sylhet sand
or coarse sand of equivalent F.M. 2.2 and 20 mm down well graded stone chips conforming to ASTM C-33, making and placing
shutter in position and maintaining true to plumb, making shutter water-tight properly, placing reinforcement in position; mixing with
standard mixer machine with hopper, fed by standard measuring boxes or mixing in batching plant, casting in forms, compacting by
vibrator machine and curing at least for 28 days, removing centering-shuttering after specified time approved; including cost of water,
electricity, testing charges of materials and concrete cylinders as required, cost of all materials and other charges etc. all complete,
approved and accepted by the Engineer-in-charge. (Rate is excluding the cost of reinforcement and its fabrication, placing, binding
etc. and the cost of shuttering & centering)

07.3.1 (A)Individual & combined footing, pile cap, raft/mat, floor slab and foundation beam up to plinth level
Concrete
1 x 14 '- 8 " x 12 '- 0 " x 1 '- 0 " = 176.00 cft
= 176.00 cft
= 4.98 cum
@ Tk. 12154.00 p/cum

Centering and shuttering, including strutting, propping etc. (The formwork must be rigid enough both in and out of plane, to make the
7.9 concrete surface true to the designed shape and size by using necessary MS sheets of minimum 16 BWG, angles of minimum size
40 mm x 40 mm x 5 mm, flat bars etc.) and removal of form after hardening of the concrete for:
07.9.1 Individual and combined footing
2 x 14 '- 8" x 1 '- 0" = 29.33 sft
2 x 12 '- 8" x 1 '- 0" = 25.33 sft
= 54.67 sft
= 5.08 sqm
@ Tk. 438.00 p/sqm

07.3.2 (B)Pedestals, column, column capital, lift wall and RCC wall up to ground floor
Concrete
2 x 11 '- 8 " x 6 '- 0 " x 1 '- 0 "= 140.00 cft
2 x 8 '- 0 " x 6 '- 0 " x 1 '- 0 "= 96.00 cft
= 236.00 cft
= 6.68 cum
@ Tk. 12367.00 p/cum

Centering and shuttering, including strutting, propping etc. (The formwork must be rigid enough both in and out of plane, to make the
7.9 concrete surface true to the designed shape and size by using necessary MS sheets of minimum 16 BWG, angles of minimum size
40 mm x 40 mm x 5 mm, flat bars etc.) and removal of form after hardening of the concrete for:

07.9.4 Pedestal, column, column capital, lift wall and wall up to ground floor
4 x 11 '- 8 " x 6 '- 0" = 280.00 sft
4 x 8 '- 0 " x 6 '- 0" = 192.00 sft
= 472.00 sft
= 43.85 sqm
@ Tk. 408.00 p/sqm
07.3.3 Floor / roof slab, T-beam, L-beam and rectangular beam, tie beam, lintel, stair case slab and steps etc. upto ground floor
Concrete
1 x 11 '- 8 " x 10 '- 0 " x 0 '- 6 " = 58.33 cft
= 58.33 cft
= 1.65 cum
@ Tk. 12240.00 p/cum

Centering and shuttering, including strutting, propping etc. (The formwork must be rigid enough both in and out of plane, to make the
7.9 concrete surface true to the designed shape and size by using necessary MS sheets of minimum 16 BWG, angles of minimum size
40 mm x 40 mm x 5 mm, flat bars etc.) and removal of form after hardening of the concrete for:
07.9.7 Floor and roof slab up to ground floor
1 x 11 '- 8" x 10 '- 0" = 116.67 sft
Side 1 x 43 '- 4" x 0 '- 6" = 21.67 sft
= 116.67 sft
= 10.84 sqm
@ Tk. 532.00 p/sqm

6 Supplying, fabrication and fixing to detail as per design : ribbed or deformed bar reinforcement for Reinforced cement concrete,
CES-8.1 produced and marked in accordance with BDS ISO 6935 - 2: 2006 (or standard subsequentley released from BSTI) including
straightening and cleaning rust, if any, bending and binding in position with supply of G.I. wires, conducting necessary laboratory
tests etc. (excluding splices or laps) complete in all respect and accepted by the Engineer-in-charge (Measurement shall be recorded
only on standard mass per unit length of bars, while dia of bars exceeds its standard)
8.1.2 Grade 400 (RB 400 /RB 400W: complying BDS ISO 6935-2:2006) ribbed or deformed bar produced and marked according to
Bangladesh standard, with minimum yield strength, fy (ReH)= 400 MPa but fy not exceeding 450 MPa and whatever is the yield
strength within allowable limit as per BNBC/ ACI 318, the ratio of ultimate tensile strength fu to yield strength fy, shall be at least 1.25
and minimum elongation after fracture and minimum total elongation at maximum force is 16% and 8% respectively : up to ground
floor.

Qnty bf item no-5 base casting portion 4.98 cum x 1.75 % = 684.64 kg
Qnty bf item no-5 wall casting portion 6.68 cum x 2.00 % = 1,049.19 kg
Qnty bf item no-5 slab casting portion 1.65 cum x 1.50 % = 194.50 kg
1928.32 kg
@ Tk. 82.00 p/kg

7 Supplying, fitting and fixing ribbed PVC water stopper with non centre bulb of width approx. 250 mm and approx 9 mm thick for
CES-8.5.1 immovable (non working) RCC joints, having minimum tensile strength of 8.27 MPa (approx. 1200 psi) min ultimate elongation 350%,
approximate hardness 50, minimum tear resistance 0.0175 kN/mm (100 lbs/inch) at RCC construction green joints in basements,
approved and in consultation with design office, providing 38 mm x 62 mm wooden batten at the top and bottom of water stopper,
holding in position and keeping the water stopper in true horizontal or vertical by appropriate means as where necessary etc; all
complete and accepted by the Engineer-in-charge.

Roof top 4 x 11 '- 8" = 46.67 sft


Roof top 4 x 8 '- 0" = 32.00 sft
= 78.67 rft
= 23.98 rm
@ Tk. 1017.00 p/cum

8 Providing minimum 12 mm thick cement sand (F.M. 1.2) plaster with neat cement finishing to plinth wall with cement (1:4) up to 150
mm below ground level including washing of sand, finishing the edges and corners and curing at least for 7 days, cost of water,
electricity, scaffolding and other charges etc. all complete in all respect as per drawing and accepted by the Engineer-in-charge.
(Cement: CEM-II/A-M) ground floor.
Providing minimum 12 mm thick cement sand (F.M. 1.2) plaster with neat cement finishing to plinth wall with cement (1:4) up to 150
CES-15.2 mm below ground level including washing of sand, finishing the edges and corners and curing at least for 7 days, cost of water,
electricity, scaffolding and other charges etc. all complete in all respect as per drawing and accepted by the Engineer-in-charge.
(Cement: CEM-II/A-M) ground floor.
Qnty same as item no-5(B)formwork portion = 472.00 sft
Roof top 1 x 11 '- 8" x 10 '- 0" = 116.67 sft
= 588.67 Sqm
@ Tk. 280.00 p/sqm
9 38 mm thick artificial patent stone (1:2:4) flooring with cement, best quality coarse sand (50% quantity of Sylhet sand or coarse sand
CES-4.27 of equivalent F.M. 2.2 and 50% best quality local sand of FM 1.2) and 12 mm down well graded brick chips including breaking chips,
screening, laying the concrete in alternate panels, compacting and finishing the top with neat cement and curing at least for 7 days in
all floors including cost of water, electricity and other charges etc. all complete and accepted by the Engineer-in-charge. (Cement:
CEM-II/A-M) In ground floor

Floor 1 x 10 '- 0" x 8 '- 0" = 80.00 sft


= 80.00 Sqm
@ Tk. 468.00 p/sqm

10 Supply, fitting and fixing of 600 mm dia C.I. man hole cover etc. all complete approved by the Engineer- in- charge.
CES-26.75
= 2.00 nos
@ Tk. 1,869.00 each
11 Earth filling in foundation trenches and plinth in 150 mm layer with earth available within 90 m of the building site to achive
CES-2.13 minimum dry density of 95% with optimum moisture content (Modified proctor test) including carrying, watering, leveling, dressing
and compacting to a specified percentage each layer up to finished level etc. all complete and accepted by Engineer-in-charge.

Qnty bf item no-1 A = #REF! Cum


Qnty bf item no-1 B = #REF! Cum
Qnty bf item no-1 B = #REF! Cum
= #REF! Cum
Back Filing 1/5 = #REF! Cum
@ Tk. 149.00 p/Cum
Total

(Md Iqramul hasan chowdhury) ( A S M Musa)


Sub-Assistant Engineer Sub-Divisional Engineer
Narsingdi PWD Sub-Division-1, Narsingdi PWD Sub-Division-1
Narsingdi. Narsingdi.

(Enamul Haque) (Muhammed Moniruzzman)


Sub-Assistant Engineer Assistant Engineer Executive Engineer
NarsingdiPWD Division Narsingdi PWD Division, Narsingdi PWD Division,
Narsingdi. Narsingdi. Narsingdi.
local bench-mark pillars,
providing necessary tools
e distance out of the area
statement of carrying out
ve the contractor of his

h area of the structure

= Tk. 7,103.22

iff clayey soil.

318.00 20 6360
145.39 82 11922
318.00 320 101760
318.00 15 4770
= Tk. 290.24 48.46 8400 407064
f bed and filling the 79.50 300 23850
10 16 160 50.65 8200 415330
48.76562024 664.75 300 199425
19.99 7500 149925
172.51 300 51753
8929.87 60 535792
= Tk. 4,459.31 160.01437 99.95 110 10995
863.79 180 155482
veling, watering and
y ramming each layer up 2074428
-in-charge.

= TK 2,637.22

anywhere below cement


= Tk. 686.70

m f'cr = 30 MPa,
ractice of Code
best quality Sylhet sand
making and placing
in position; mixing with
n forms, compacting by
d; including cost of water,
arges etc. all complete,
cation, placing, binding

= TK 60,572.11

out of plane, to make the


angles of minimum size

= Tk. 2,225.04

= TK 82,645.11

out of plane, to make the


angles of minimum size

= Tk. 17,890.80
o ground floor

= TK 20,218.04

out of plane, to make the


angles of minimum size

= Tk. 5,766.88

d cement concrete,
m BSTI) including
necessary laboratory
rement shall be recorded

rked according to
whatever is the yield
h fy, shall be at least 1.25
pectively : up to ground

= Tk. 158,122.54

prox 9 mm thick for


ultimate elongation 350%,
n joints in basements,
ttom of water stopper,
re necessary etc; all

= TK 24,384.03

cement (1:4) up to 150


days, cost of water,
Engineer-in-charge.
= Tk. 164,826.67
het sand or coarse sand
ncluding breaking chips,
uring at least for 7 days in
er-in-charge. (Cement:

= Tk. 37,440.00

charge.

= Tk. 3,738.00
g site to achive
ng, leveling, dressing
Engineer-in-charge.

= Tk. #REF!
Total = Tk. #REF!

Musa)

Sub-Division-1
ngdi.

ammed Moniruzzman)
Executive Engineer
rsingdi PWD Division,
6300

11922

101760
4770
407064
23850
415330
99425
149925
51733
535792
10994

155482
1974347

50000
6000
16000
10000
34139
90000
206139
2280567
2074407
206160
355000
5122272.76
19.67
39.34

10.84
Name of Work: Construction of 15000.00 Galloon Under Ground Water Reserviour.
1 Earth work in excavation in all kinds of soil for foundation trenches including layout, providing center lines, local bench-mark pillars,
CES-02-1 levelling, ramming and preparing the base, fixing bamboo spikes and marking layout with chalk powder, providing necessary tools and
plants, protecting and maintaining the trench dry etc., stacking, cleaning the excavated earth at a safe distance out of the area
enclosed by the layout etc. all complete and accepted by the Engineer-in-charge, subject to submit method statement of carrying out
excavation work to the Engineer-in-charge for approval. However, engineer’s approval shall not relieve the contractor of his
responsibilities and obligations under the contract.

(A)Layout and marking for earthwork in excavation in foundation accepted by the Engineer-in-charge. [Plinth area of the structure shall
02.1.1
be considered for measurement]
1 x 30 '- 0 " x 17 '- 0" = 510.00 sft
= 510.00 sft
= 47.38 sqm
@ Tk. 15.00 p/sqm = Tk. 710.70

02.1.3 (B)Earthwork in excavation in foundation trenches up to 1.5 m depth and maximum 10 m lead: in medium stiff clayey soil.
1 x 30 '- 0 " x 17 '- 0 " x 5 '- 0 " = 2550.00 cft
= 2550.00 cft
= 72.21 cum
@ Tk. 126.00 p/cum = TK 9,098.12
02.1.6 (C)Extra rate for each additional 0.5 meter depth exceeding 1.5 meter.
1 x 30 '- 0 " x 17 '- 0 " x 1 '- 8 " = 850.00 cft
= 850.00 cft
= 24.07 cum
@ Tk. 146.00 p/cum = TK 3,514.09

02.1.8 (D)Extra rate for each additional 0.5 meter depth exceeding 1.5 meter.
1 x 30 '- 0" x 17 '- 0 " x 1 '- 8 "= 850.00 cft
= 850.00 cft
= 24.07 cum
@ Tk. 166.00 p/cum = TK 3,995.47

2 One layer brick flat soling in foundation or in floor with first class/picked jhama bricks including preparation of bed and filling the
CES-3.1 interstices with local sand, levelling etc. complete and accepted by the Engineer-in-charge
1 x 30 '- 0" x 17 '- 0" = 510.00 sft
= 510.00 sft
= 47.38 sqm
@ Tk. 420.00 p/sqm = Tk. 19,899.67

3 Sand filling in foundation trenches and plinth with sand having F.M. 0.5 to 0.8 in 150 mm layers including leveling, watering and
CES-02.10.1 compaction to achieve minimum dry density of 95% with optimum moisture content (Modified proctor test) by ramming each layer up to
finished level as per design supplied by the design office only, all complete and accepted by the Engineer-in-charge.

1 x 30 '- 0" x 17 '- 0 " x 0 '- 10 " = 425.00 cft


= 425.00 cft
= 12.03 cum
@ Tk. 635.00 p/cum = TK 7,641.94

4 Supplying and laying of single layer polythene sheet weighing one kilogram per 6.5 square meter in floor or anywhere below cement
CES-3.7 concrete complete in all respect and accepted by Engineer-in-charge.
1 x 30 '- 0" x 17 '- 0" = 510.00 sft
= 510.00 sft
= 47.38 sqm
@ Tk. 42.00 p/sqm = Tk. 1,989.96
5 Reinforced cement concrete works with minimum cement content relates to mix ratio 1:1.5:3 having minimum f'cr = 30 MPa, satisfying
CES-7.3 a specified compressive strength f’c = 25 MPa at 28 days on standard cylinders as per standard practice of Code ACI/BNBC/ASTM,
Cement conforming to BDS EN-197-1-CEM-I, 52.5N (52.5 MPa) / ASTM-C 150 Type – I, best quality Sylhet sand or coarse sand of
equivalent F.M. 2.2 and 20 mm down well graded stone chips conforming to ASTM C-33, making and placing shutter in position and
maintaining true to plumb, making shutter water-tight properly, placing reinforcement in position; mixing with standard mixer machine
with hopper, fed by standard measuring boxes or mixing in batching plant, casting in forms, compacting by vibrator machine and curing
at least for 28 days, removing centering-shuttering after specified time approved; including cost of water, electricity, testing charges of
materials and concrete cylinders as required, cost of all materials and other charges etc. all complete, approved and accepted by the
Engineer-in-charge. (Rate is excluding the cost of reinforcement and its fabrication, placing, binding etc. and the cost of shuttering &
centering)

07.3.1 (A)Individual & combined footing, pile cap, raft/mat, floor slab and foundation beam up to plinth level
Concrete
1 x 30 '- 0 " x 17 '- 0 " x 1 '- 0 " = 510.00 cft
= 510.00 cft
= 14.44 cum
@ Tk. 12154.00 p/cum = TK 175,521.45

Centering and shuttering, including strutting, propping etc. (The formwork must be rigid enough both in and out of plane, to make the
7.9 concrete surface true to the designed shape and size by using necessary MS sheets of minimum 16 BWG, angles of minimum size 40
mm x 40 mm x 5 mm, flat bars etc.) and removal of form after hardening of the concrete for:
07.9.1 Individual and combined footing
2 x 30 '- 0" x 1 '- 0" = 60.00 sft
2 x 17 '- 0" x 1 '- 0" = 34.00 sft
= 94.00 sft
= 8.73 sqm
@ Tk. 438.00 p/sqm = Tk. 3,823.74

07.3.2 (B)Pedestals, column, column capital, lift wall and RCC wall up to ground floor
Concrete
2 x 27 '- 0 " x 8 '- 3 " x 1 '- 0 "= 445.50 cft
2 x 12 '- 6 " x 8 '- 3 " x 1 '- 0 "= 206.25 cft
1 x 12 '- 6 " x 8 '- 3 " x 0 '- 6 "= 51.56 cft
= 703.31 cft
= 19.92 cum
@ Tk. 12367.00 p/cum = TK 246,293.80

Centering and shuttering, including strutting, propping etc. (The formwork must be rigid enough both in and out of plane, to make the
7.9 concrete surface true to the designed shape and size by using necessary MS sheets of minimum 16 BWG, angles of minimum size 40
mm x 40 mm x 5 mm, flat bars etc.) and removal of form after hardening of the concrete for:

07.9.4 Pedestal, column, column capital, lift wall and wall up to ground floor
2 x 27 '- 0 " x 8 '- 3" = 445.50 sft
2 x 14 '- 0 " x 8 '- 3" = 231.00 sft
4 x 12 '- 6 " x 8 '- 3" = 412.50 sft
4 x 12 '- 3 " x 8 '- 3" = 404.25 sft
= 1493.25 sft
= 138.73 sqm
@ Tk. 408.00 p/sqm = Tk. 56,601.84

07.3.3 Floor / roof slab, T-beam, L-beam and rectangular beam, tie beam, lintel, stair case slab and steps etc. upto ground floor
Concrete
1 x 28 '- 0 " x 15 '- 0 " x 0 '- 6 " = 210.00 cft
= 210.00 cft
= 5.95 cum
@ Tk. 12240.00 p/cum = TK 72,784.94

Centering and shuttering, including strutting, propping etc. (The formwork must be rigid enough both in and out of plane, to make the
7.9 concrete surface true to the designed shape and size by using necessary MS sheets of minimum 16 BWG, angles of minimum size 40
mm x 40 mm x 5 mm, flat bars etc.) and removal of form after hardening of the concrete for:
07.9.7 Floor and roof slab up to ground floor
1 x 29 '- 0" x 16 '- 0" = 464.00 sft
= 464.00 sft
= 43.11 sqm
@ Tk. 532.00 p/sqm = Tk. 22,934.52
6 Supplying, fabrication and fixing to detail as per design : ribbed or deformed bar reinforcement for Reinforced cement concrete,
CES-8.1 produced and marked in accordance with BDS ISO 6935 - 2: 2006 (or standard subsequentley released from BSTI) including
straightening and cleaning rust, if any, bending and binding in position with supply of G.I. wires, conducting necessary laboratory tests
etc. (excluding splices or laps) complete in all respect and accepted by the Engineer-in-charge (Measurement shall be recorded only
on standard mass per unit length of bars, while dia of bars exceeds its standard)
8.1.2 Grade 400 (RB 400 /RB 400W: complying BDS ISO 6935-2:2006) ribbed or deformed bar produced and marked according to
Bangladesh standard, with minimum yield strength, fy (ReH)= 400 MPa but fy not exceeding 450 MPa and whatever is the yield
strength within allowable limit as per BNBC/ ACI 318, the ratio of ultimate tensile strength fu to yield strength fy, shall be at least 1.25
and minimum elongation after fracture and minimum total elongation at maximum force is 16% and 8% respectively : up to ground
floor.

Qnty bf item no-5 base casting portion 14.44 cum x 1.5 % = 1,700.31 kg
Qnty bf item no-5 wall casting portion 19.92 cum x 2.0 % = 3,127.44 kg
Qnty bf item no-5 slab casting portion 5.95 cum x 1.0 % = 467.08 kg
5294.83 kg
@ Tk. 82.00 p/kg = Tk. 434,175.65

7 Supplying, fitting and fixing ribbed PVC water stopper with non centre bulb of width approx. 250 mm and approx 9 mm thick for
CES-8.5.1 immovable (non working) RCC joints, having minimum tensile strength of 8.27 MPa (approx. 1200 psi) min ultimate elongation 350%,
approximate hardness 50, minimum tear resistance 0.0175 kN/mm (100 lbs/inch) at RCC construction green joints in basements,
approved and in consultation with design office, providing 38 mm x 62 mm wooden batten at the top and bottom of water stopper,
holding in position and keeping the water stopper in true horizontal or vertical by appropriate means as where necessary etc; all
complete and accepted by the Engineer-in-charge.

4 x 27 '- = 108.00 rft


4 x 14 '- = 56.00 rft
= 164.00 rft
= 49.98 rm
@ Tk. 1017.00 p/cum = TK 50,834.50

8 Providing minimum 12 mm thick cement sand (F.M. 1.2) plaster with neat cement finishing to plinth wall with cement (1:4) up to 150
CES-15.2 mm below ground level including washing of sand, finishing the edges and corners and curing at least for 7 days, cost of water,
electricity, scaffolding and other charges etc. all complete in all respect as per drawing and accepted by the Engineer-in-charge.
(Cement: CEM-II/A-M) ground floor.
Qnty same as item no-5(B)formwork portion = 1493.25 sft
Roof top 1 x 28 '- 0" x 15 '- 0" = 420.00 sft
= 1913.25 Sqm
@ Tk. 280.00 p/sqm = Tk. 535,710.00

9 Supply, fitting and fixing of 600 mm dia C.I. man hole cover etc. all complete approved by the Engineer- in- charge.
CES-26.75
= 2.00 nos
@ Tk. 1,869.00 each = Tk. 3,738.00
Total = Tk. 1,649,268.38

(Md Iqramul hasan chowdhury) ( A S M Musa)


Sub-Assistant Engineer Sub-Divisional Engineer
Narsingdi PWD Sub-Division-1, Narsingdi PWD Sub-Division-1
Narsingdi. Narsingdi.

(Enamul Haque) (Muhammed Moniruzzman)


Sub-Assistant Engineer Assistant Engineer Executive Engineer
NarsingdiPWD Division Narsingdi PWD Division, Narsingdi PWD Division,
Narsingdi. Narsingdi. Narsingdi.