Rate Analysis

Based on MSR 2017


Name of work:-Impvt of Ayangpalli road.
Lead Chart
1. Carriage charge of stone aggregate from Bongmol

2 Km. 1 Km. (approach)


Khongnangkarak
290 km 298 km 0 317.0km km 320
Kanglatonbi Sekmai 316 km Imphal Add 12% GST on A
PWD Store 1.80 km
Work site
5.15 km Add 3% Contingency Charges on B

Mean Lead
( 1.80 + 5.15 )/2 = 3.48 km
Say = 3.48 km
Transportation Charges
Lead involved (Lead upto work site)
(i) Stone metal above 40 mm Lead:- ( 317.00 - 290.00 )+ 3.48 + 2.0 = 32.48 km
(ii) Stone metal below 40 mm Lead:- ( 317.00 - 290.00 )+ 3.48 + 2.0 = 32.48 km
(iii) Bitumen ( 317.00 - 316.00 )+ 3.48 = 4.48 km
(iv) Sand gravel ( 317.00 - 298.00 )+ 3.48 + 1.0 = 23.48 km
(v) Sand ( 317.00 - 298.00 )+ 3.48 + 1.0 = 23.48 km
(vi) Steel/Cement ( 320.00 - 317.00 )+ 3.48 = 6.48 km
From source to Mixing plant
(i) Stone metal above 40 mm Lead:- ( 316.00 - 290.00 )+ 2.0 = 28.00 km
(ii) Bitumen = 5.00 km
(iii) Sand ( 316.00 - 298.00 )+ 1.00 = 19.00 km
From Mixing plant to Work site
(i) Mix Material ( 317.00 - 316.00 )+ 3.48 = 4.48 km