RAS MARKAZ CRUDE OIL PARK PROJECT (PHASE1)
NON-CONFORMANCE REPORT
NCR Number 9686-OT-NCR-0080
Root Cause
Correction Details
Completion Date
Corrective Action
Completion Date
Remarks:
Actions Taken:
Attachments:
Follow-up Notes
Verified by
(Originator/Inspector) [Name] [Signature] [Date]
Approved By Contracts
Manager [Name] [Signature] [Date]
Approved By Project
Manager (Category 1) [Name] [Signature] [Date]