DETAILED ESTIMATE
Item Description Quantity Unit Unit Cost ESTIMATED MARK-UPS IN PERCENT Total Mark-Up VAT TOTAL TOTAL
No. Direct Cost OCM(12%) Profit (8%) % VALUE 5%[(5)+(6)+(7)] DIRECT COST COST
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12)
I. MOBILIZATION 1 lot 22,757.03 22,757.03 3,413.55 2,275.70 5,689.26 1,422.31 7,111.57 29,868.60
II. GENERAL REQUIREMENT 1 lot 572,444.00 572,444.00 85,866.60 57,244.40 143,111.00 35,777.75 178,888.75 751,332.75
III. REMOVAL OF EXISTING ENDWALL 1 lot 80,000.00 80,000.00 12,000.00 8,000.00 20,000.00 5,000.00 25,000.00 105,000.00
IV. CONSTRUCTION OF ENDWALL LOUVERS 1 lot 788,726.40 788,726.40 118,308.96 78,872.64 197,181.60 49,295.40 246,477.00 1,035,203.40
V. PAINTING WORKS (strut and endwall) 1 lot 170,289.00 170,289.00 25,543.35 17,028.90 42,572.25 10,643.06 53,215.31 223,504.31
VI. REPAINTING OF QUONSET ROOFING (exter 1 lot 660,435.00 660,435.00 99,065.25 66,043.50 165,108.75 41,277.19 206,385.94 866,820.94
PROGRAM OF WORKS
DETAILED COST ESTIMATE
REPAIR-2020-NCR-MARIKINA CITY-0067
Prepared by :
109,960.00
50,476.58
163,924.43
1,235,888.55
162,876.45
40,073.40
231,000.00
2,522,507.34
1,054,814.10
266,400.14
7,310,695.34
Contract Reference Number
Name of the project
Name of the Procuring Entity Location of the project
BILL OF QUANTITIES
Item Description Quantity Unit Unit Cost VAT TOTAL TOTAL Amount in Words
No. DIRECT COST COST
I. MOBILIZATION 1 lot 22,757.03 1,422.31 7,111.57 29,868.60 Twenty Nine Thousand Eight Hundred Sixty Eight & 60/100
II. GENERAL REQUIREMENT 1 lot 572,444.00 35,777.75 178,888.75 751,332.75 Seven Hundred Fifty One Thousand Three Hundred Thirty Two & 75/100
III. REMOVAL OF EXISTING ENDWALL 1 lot 80,000.00 5,000.00 25,000.00 105,000.00 One Hundred Five Thousand Pesos
IV. CONSTRUCTION OF ENDWALL LOUVERS 1 lot 788,726.40 49,295.40 246,477.00 1,035,203.40 One Million Thirty Five Thousand Two Hundred Three & 40/100
V. PAINTING WORKS (strut and endwall) 1 lot 170,289.00 10,643.06 53,215.31 223,504.31 Two Hundred Twenty Three Thousand Five Hundred Four & 31/100
VI. REPAINTING OF QUONSET ROOFING (exterior) 1 lot 660,435.00 41,277.19 206,385.94 866,820.94 Eight Hundred Sixty Six Thousand Eight Hundred Twenty & 94/100
Amount in Words
PESOS ONLY.
City Government of Marikina Contract Reference Number : Mkna- GSO- 17 - 095
Name of the Contract : PROPOSED MULTI-PURPOSE GYMNASIUM( STEEL STRUCTURE) PHASE 1
Standard Form Number: SF_INFR-05 Location of the contract: FVR ROAD, BRGY. IVC, MARIKINA CITY
Revised on: July 29, 2004
Submitted By:
DATE : FEBRUARY 17, 2020
MA. CRISTINA B. SANTOS
PRESIDENT
Crystal Dreams Development Corporation
Date :
Project : Proposed Refurbishment of Gymnasium at Marina Elem. School
Location : Sta. Elena , Marikina City
Subject : Actual Expenses:
786,875.00
Mobilization : 9-Mar-20
Contract Price: 3,011,730.00
Date DR # Qty Description Unit Price Total Cost
37/2020 542699 4 Paint Thinner 230.00 920.00
2 Pulley 180.00 360.00
1 Nylon Rope 3,300.00 3,300.00
3/9/2020 542933 40 BI 1 1/2" #20 680.00 27,200.00
3 B/S 600 QDE 620.00 1,860.00
542923 1 Koten 30 A 650.00 650.00
1 Safari 750.00 750.00
5 Outlet 3G 75.00 375.00
5 Plug 35.00 175.00
1 Flatcord 16 2,720.00 2,720.00
5 Flourescent 40W 330.00 1,650.00
5 Switch 35.00 175.00
1 PhilFlex 3.50 2,970.00 2,970.00
5 E.tape 35.00 175.00
20 Black Screw 2 1.50 30.00
20 Black Screw 1 1/2 0.50 10.00
20 Masking Tape 30.00 600.00
20 3/8Formply 580.00 11,600.00
1 Level Bar 250.00 250.00
200 Swivel Clamp 1 1/2 65.00 13,000.00
3/6/2020 542678 5 DV 4429 595.00 2,975.00
5 DV 4642 585.00 2,925.00
1 DV 4420 595.00 595.00
1 DV4665 480.00 480.00
1 DV 4494 620.00 620.00
1 DV 4623 500.00 500.00
1 DV 4671 600.00 600.00
20 Masking Tape 30.00 600.00
5 Steel Brush 45.00 225.00
3 Riveter 330.00 990.00
1 Golden Butter 2,100.00 2,100.00
4 B/S 600 QDE 620.00 2,480.00
2 Polytuff 600.00 1,200.00
3 Hardener 190.00 570.00
542685 20 Tubular 2x6x1.20 1,220.00 24,400.00
1 Welding Rod 6013 1,480.00 1,480.00
2 Cutting Disk 14 250.00 500.00
15 Grinding Disk 4 100.00 1,500.00
2 Blue Sack 2,000.00 4,000.00
3 Epoxy Primer Gray 600.00 1,800.00
15 S/P # 100 15.00 225.00
10 P.Brush 2 35.00 350.00
10 P.Brush 3 60.00 600.00
15 B.Roller T 35.00 525.00
15 B.Roller F 35.00 525.00
2 Basahan 60.00 120.00
3/10/2020 40 BI 1 1/2" #20 630.00 25,200.00
3/11/2020 100 Swivel Clamp 1 1/2 55.00 5,500.00
1 GI Wire 16 1,500.00 1,500.00
10 B/S 600 QDE 620.00 6,200.00
3 P.Thinner 230.00 690.00
3/14/2020 543936 10 Cutting Disk 12 cm 100.00 1,000.00
5 1x1x10 100.00 500.00
20 Glove Cotton 15.00 300.00
LEXUS-NIGEL 200 GI PIPE 11/2x1.60mm 622.00 124,400.00
4/22/2020 544572 11 Royu Switch 1G 65.00 715.00
11 Blank Plate 40.00 440.00
100 Black Screw 1 0.50 50.00
30 Black Screw 2 1.50 45.00
1 Flexible hose 1/2 350.00 350.00
5 E.tape 35.00 175.00
10 PVC U-Box 15.00 150.00
10 DSK 650.00 6,500.00
5 Neltex 185.00 925.00
50 ABC Tile Adhesive 260.00 13,000.00
50 Blue Elbow 1/2 25.00 1,250.00
4 M.Acid 130.00 520.00
2 Lacquer Thinner 720.00 1,440.00
3 Basahan 60.00 180.00
4/25/2020 544573 2 Tansi 20.00 40.00
15 Level Hose 25.00 375.00
2 Electrode Holder 450.00 900.00
25 Cutting Disk 4 100.00 2,500.00
5 Chalkstone 5.00 25.00
4/27/2020 544796 20 3/8 Formply 580.00 11,600.00
200 Swivel Clamp 1 1/2 65.00 13,000.00
1 Lacquer Thinner 200.00 200.00
3 Epoxy Primer Gray 200.00 600.00
4 B.Roller Tela 35.00 140.00
16 Tubular 2x6x1.20 1,225.00 19,600.00
5/6/2020 545488 1 P.Thinner 230.00 230.00
2 B/S 600 QDE 630.00 1,260.00
5/9/2020 546325 5 B.Roller Tela 35.00 175.00
4 B/S 600 QDE 600.00 2,400.00
2 Lacquer Thinner 200.00 400.00
5/25/2020 546881 2 Basahan 60.00 120.00
5 B.Roller Tela 130.00 650.00
2 Paint Thinner 230.00 460.00
5/11/2020 545640 10 Cutting Disk 100.00 1,000.00
6/2/2020 ARNATE 1 LOUVER 390,000.00 390,000.00
5/23/2020 546861 20 B/S Royal Blue 530.00 10,600.00
6 B/S QDE 600 630.00 3,780.00
7 B.Roller Tela 35.00 245.00
1 P.Thinner 230.00 230.00
6/15/2020 549996 16 B/S QDE Royal Blue 530.00 8,480.00
2 T/C Thalo Green 100.00 200.00
1 Davies Azure Blue 595.00 595.00
6/9/2020 549094 1 Davies Maroon 495.00 495.00
1 Davies Whisper Beige 620.00 620.00
10 Roller #7 25.00 250.00
10 Baby Roller -T 30.00 300.00
1 P.Thinner 870.00 870.00
5 Basahan 60.00 300.00
10 P.Brush 11/2 35.00 350.00
10 P.Brush 11/2 30.00 300.00
5 T/C Hansa Yellow 110.00 550.00
5 T/C Lamp Black 70.00 350.00
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
30.51%
Crystal Dreams
V. Gomez St., San Roque, Marikina City 3
Tel. Nos. : 645-2164 / 994-4206
Telefax No. : 646-1837
DEVELOPMENT CORPORATION E-mail : crystaldev1998@yahoo.com
PROJECTED EXPENSES