PEMBANGUNAN CENTRAL PROCESSING PLANT (CPP) AREA GUNDIH

PROYEK PENGEMBANGAN GAS JAWA BAGIAN TIMUR

SPECIFICATION

SITE PREPARATION

FINAL ISSUED FOR BID DOCUMENT

REV. DESCRIPTION CHK'D APPV'D

TOTAL OR PARTIAL REPRODUCTION AND/OR UTILIZATION OF THIS DOCUMENT ARE FORBIDDEN

WITHOUT PRIOR WRITTEN AUTHORIZATION OF THE OWNER

DOCUMENT NO.

PROYEK PENGEMBANGAN GAS JAWA BAGIAN TIMUR PPGJ-CIV-SPC-001


PEMBANGUNAN CENTRAL PROCESSING PLANT (CPP) AREA GUNDIH
PROYEK PENGEMBANGAN GAS JAWA BAGIAN TIMUR

TABLE OF CONTENT

1.1 Measurement Survey 4


1.2 Clearing and Removal 5
1.3 Design of Irrigation Channel Relocation 5
1.4 Backfilling Works 6
1.5 Compacting 6
1.6 Checking of Compacting Quality 7
1.7 Temporary Fence and Security Post 7
1.8 Temporary electric lighting 8
1.9 Allocation of Project Office 8
1.10 Temporary Road and Traffic Signs 8
1.11 Temporary Drainage 10
1.12 Tool Kit and Safety Equipment 11
1.13 Taking Care of Permits 11

MOBILIZATION SECTION
DESCRIPTION PAGE

2.0 PURPOSE 3

3.0 GENERAL REQUIREMENTS 3

4.0 DESIGN REQUIREMENTS 4


5.0 11

Document No. PPGJ-CIV-SPC-001 SITE PREPARATION Page 2


PEMBANGUNAN CENTRAL PROCESSING PLANT (CPP) AREA GUNDIH
PROYEK PENGEMBANGAN GAS JAWA BAGIAN TIMUR

1. TUJUAN 1. PURPOSE

Tujuan dari spesifikasi ini adalah untuk The purpose of this specification is to
menjelaskan ketentuan minimal untuk describe the minimum requirements to be
digunakan pada perencanaan dan used on planning and actuation of site
pelaksanaan pekerjaan persiapan lokasi/site preparation works. This specification will
preparation. Spesifikasi ini akan diberlakukan apply at the project site such as at the activity
dilokasi proyek seperti pada kegiatan of determination of bench mark point,
penentuan titik Bench Mark (BM), penentuan determination of area boundary, clearing of
patok-patok batasan area, pembersihan lokasi, location, garbage dump, digging, backfilling,
pembuangan sampah, penggalian, making of dike, other land works supplied and
pengurugan, pembuatan tanggul, pekerjaan required to make a graded site, reference
tanah lainnya yang didatangkan yang coordinate (supplementary Bench Mark) to
diperlukan untuk membuat elevasi akhir determine plot plan, infrastructure,
(graded site), koordinat referensi (BM bantu) improvement, and other facilities required for
untuk menentukan plot plan, sarana dan safety and smoothness at CPP-GUNDIH
prasarana serta fasilitas lainnya yang FIELD, Desa Sumber, Kecamatan Kradenan,
diperlukan untuk keamanan dan kelancaran di Kabupaten Blora, Central Java, belonged to
CPP-LAPANGAN GUNDIH, Desa Sumber, PT. PERTAMINA EP (Persero) - PPGJ.
Kecamatan Kradenan, Kabupaten Blora. Jawa
Tengah, milik PT. PERTAMINA EP (Persero)-
PPGJ.

2. PERATURAN UMUM 2. GENERAL REQUIREMENTS

Persyaratan yang diterapkan dalam persiapan Requirements applied in site preparation shall
lokasi harus mengikuti standar dan spesifikasi observe the following standards and
dibawah ini. specifications:

PERTAMINA-PPGJ Specifications

PPGJ-CIV-SPC-002 Earth Work

PPGJ-CIV-SPC-003 Construction Office Specification

PPGJ-CIV-SPC-005 Civil & Structure Work Specification

PPGJ-CIV-SPC-009 Landscape Specification

PPGI-CIV-SPC-014 Fence Work specification

PPGJ-CIV-DWG-013 CPP Site Location Map

PPGJ-CIV-DWG-014 Cross Section (include FGL Project) Drawing

Document No. PPGJ-CIV-SPC-001 SITE PREPARATION Page 3


PEMBANGUNAN CENTRAL PROCESSING PLANT (CPP) AREA GUNDIH
PROYEK PENGEMBANGAN GAS JAWA BAGIAN TIMUR

3. SYARAT PERENCANAAN 3. DESIGN REQUIREMENTS

3.1 Survei Pengukuran 3.1 Measurement Survey

Melakukan survei pengukuran untuk Applied topograpic survey to be determined


menentukan posisi Bench Mark (BM) CPP- the CPP-GUNDIH FIELD bench mark (BM)
LAPANGAN GUNDIH sesuai referensi Bench conforming to the Bench Mark reference from
Mark dari PERTAMINA EP seperti dibawah ini. PERTAMINA EP as follows:

Batasan-batasan terluar dari CPP-LAPANGAN CPP-GUNDIH FIELD limit areas:


GUNDIH (limit area) yaitu :

Batasan Utara/Barat : BM.CPP-L1 North /West Limit: BM.CPP-L1

Batasan Utara/Timur : BM.CPP-R1 North /East Limit: BM.CPP-R1

Batasan Timur/Selatan : BM.CPP-R2 East /South Limit: BM.CPP-R2

Batasan Selatan/Barat : BM.CPP-L2 South /West Limit: : BM.CPP-L2

Elevasi muka akhir tanah, disingkat dengan The ground level elevation abbreviated with
“FGL +0.000” sama dengan +42.000 mm “FGL +0.000”, is similar with +42.000 mm
(MSL) pada posisi CPP.0, sedangkan elevasi (MSL) at CPP.0 position, meanwhile the
muka akhir tanah pada batasan limit area ground level elevation at perimeter of area
CPP-LAPANGAN GUNDIH + 41.400 MM limit is CPP-GUNDIH FIELD + 41,400 mm
(MSL). (MSL).
Elevasi muka akhir tanah “FGL +0.000” harus The ground level elevation “FGL +0.000” must
sudah diperiksa terhadap elevasi muka air been checked with 100 years period flood
banjir untuk periode ulang 100 tahunan. level. Where the ground level elevation has to
Dimana elevasi muka akhir tanah “FGL be higher minimally 1 meter from 100 years
+0.000” harus lebih tinggi minimal 1 meter dari period flood level.
elevasi muka air banjir periode ulang 100 Flood design discharge calculation must
tahunan. referred to the current code and standard.
Perhitungan debit banjir harus mengacu pada Flood level calculation must considered every
standar yang berlaku. aspect which contribute to the hydraulics
Penentuan elevasi muka air banjir harus sudah calculation.
memperhitungkan semua aspek yang
berpengaruh dalam perhitungan hidraulik.

Document No. PPGJ-CIV-SPC-001 SITE PREPARATION Page 4


PEMBANGUNAN CENTRAL PROCESSING PLANT (CPP) AREA GUNDIH
PROYEK PENGEMBANGAN GAS JAWA BAGIAN TIMUR

KOORDINAT WGS ’84


WGS ’84 COORDINATES

No. TITIK KOORDINAT H msl


POINT NO. COORDINATE

BM-41 E. 550.558.673 N. 9.203.776.328 + 42.869


BM-41A E. 550.581.014 N. 9.203.692.500 + 43.141
BM-A1.1 E. 550.333.205 N. 9.203.612.514 + 43.992
BM-A1.2 E. 550.470.743 N. 9.203.577.454 + 43.167
BM.CPP-1 E. 551.515.280 N. 9.203.547.657 + 41.106
BM.CPP-1A E. 551.496.296 N. 9.203.715.996 + 41.365
BM.CPP-0 E.551.482.791 N. 9.203.647.872 + 41.241
BM.CPP-L1 E.551.232.791 N. 9.203.947.872 -
BM.CPP-R1 E.551.732.791 N. 9.203.947.872 -
BM.CPP-L2 E.551.232.791 N. 9.203.347.872 -
BM.CPP-R2 E.551.732.791 N. 9.203.347.872 -

Melakukan pekerjaan persiapan dan survei Conducting preparation work and topografic
pengukuran batas-batas area lokasi dan survey of site area limits and making of limit
pembuatan patok-patok batas diarea lokasi/set posts at set out area, survey level
out, pengukuran elevasi mendatar/leveling measurement and additional right of way work
serta pekerjaan pembuatan penambahan 6 meters width around the location perimeter.
bantaran selebar 6 meter di sekitar perimeter Prior to commence of work, it shall be
lokasi. Sebelum memulai pekerjaan harus proposed to PERTAMINA EP for approval.
diajukan untuk disetujui PERTAMINA EP.

3.2 Pembersihan dan Pembongkaran 3.2 Clearing and Removal

Area di dalam batas-batas wilayah yang Areas within the boundary limits as shown in
ditunjukkan dalam gambar perencanaan harus the design drawing shall be cleared of all
dibersihkan dari semua pohon, tanaman yang trees, plants, roots, bushes, top soil and other
tumbuh, akar, semak-semak, humus serpihan existing obstruction. Removal or Disposal of
dan hambatan lainnya yang ada. Membuang bad soil /top soil with thickness referring to
atau memindahkan tanah jelek/tanah humus soil investigation report and bore log data.
dengan ketebalan yang mengacu pada soil The top soil can be reused to fertilize the
investigation report dan data bor log. Tanah plants. The stumps from cut trees shall be
humus dapat digunakan kembali untuk removed by digging down to the roots and the
keperluan penyuburan tanaman. Bonggol dari dug holes are filled and compacted.
pohon-pohon yang ditebang harus disingkirkan
dengan cara penggalian sampai ke akar-
akarnya dan bekas galian nya diurug dan
dipadatkan.

3.3 Perencanaan Relokasi Saluran Irigasi 3.3. Design of Irrigation Channel


Relocation

Kontraktor harus mengajukan perencanaan Contractor shall propose a redesigning of new


kembali sistem irigasi baru yang mengacu irrigation system referring to existing irrigation

Document No. PPGJ-CIV-SPC-001 SITE PREPARATION Page 5


PEMBANGUNAN CENTRAL PROCESSING PLANT (CPP) AREA GUNDIH
PROYEK PENGEMBANGAN GAS JAWA BAGIAN TIMUR

pada sistim irigasi yang ada/existing dengan system with detailed description and shall be
penjelasan secara rinci dan harus on PERTAMINA EP’s approval prior to
mendapatkan persetujuan PERTAMINA EP commence of removal and clearing works.
sebelum pekerjaan pembongkaran dan
pembersihan dimulai.

Kontraktor harus mengadakan peninjauan The Contractor shall perform a review of


sistem irigasi yang ada/existing pada lokasi existing irrigation system at loctions near
dan sekitar lokasi CPP-LAPANGAN GUNDIH CPP-GUNDIH FIELD to build, making
yang akan dibangun, membuat perhitungan engineering calculation conforming to existing
engineering sesuai dengan data survey yang survey data and to rebuild new irrigation
ada dan membangun kembali sistem irigasi system adjusted to the limits of CPP-GUNDIH
yang baru yang disesuaikan dengan batas- FIELD.
batas CPP-LAPANGAN GUNDIH.

3.4 Pekerjaan Timbunan 3.4 Backfilling Works

Pekerjaan timbunan dimaksudkan untuk Backfilling work is intended to get a grade


memperoleh elevasi tanah permukaan yang elevation suitable for a particular construction
sesuai dengan rencana konstruksi tertentu. plan. All CPP- GUNDIH FIELD sites are
Untuk seluruh lokasi CPP - LAPANGAN backfill soil, the original soil in this area is a
GUNDIH adalah merupakan tanah timbunan, vast rice filed area with little plantation area.
tanah asli lokasi ini merupakan areal
persawahan yang sangat luas dengan sedikit
areal perkebunan.

Yang termaksud dalam pekerjaan timbunan What is mean by backfilling work is the work
adalah pekerjaan pemilihan dan pemeriksaan of selection and inspection of soil, removal of
tanah, pemindahan tanah humus / tanah jelek, top soil / bad soil, moving of soil which meets
memindahan tanah yang memenuhi the requirement to the site, laying,
persyaratan ke lokasi, penghamparan, compacting, checking of soil quality and
pemadatan, pemeriksaan kualitas tanah dan quantity for areas where construction works
kuantitas untuk daerah yang akan dilakukan will commence.
pekerjaan konstruksi di atasnya.

3.5 Pemadatan 3.5 Compacting

Faktor yang mempengaruhi hasil pekerjaan Factors affecting the soil compacting work
pemadatan tanah adalah : are:

kadar air, jumlah dan tipe alat pemadat dan Water content, quantities and type of
jenis tanah. Pekerjaan pemadatan pada compactors equipment and type of soil.
dasarnya adalah usaha penyusunan kembali Compacting work is basically an effort to
partikel / butir tanah, dengan mengurangi rearrange soil particles /grains, by reducing
rongga-rongga antar butiran bahan yang terlalu extra spaces between soil grains, to reach a
besar, sehingga dicapai letak butiran yang closely packed grains to reduce soil porosity
tersusun rapat satu sama lain agar porositas and to make interlocks. The purpose of soil
tanah berkurang dan saling mengunci. Tujuan compacting is to get a soil layer that gives
pemadatan adalah agar didapatkan lapisan maximum bearing capacity and reducing its
tanah yang mempunyai daya dukung maksimal absorption capability (to reach optimum water
serta daya isapnya terhadap air berkurang content).
(optimum water content).

Document No. PPGJ-CIV-SPC-001 SITE PREPARATION Page 6


PEMBANGUNAN CENTRAL PROCESSING PLANT (CPP) AREA GUNDIH
PROYEK PENGEMBANGAN GAS JAWA BAGIAN TIMUR

3.6 Pemeriksaan Kualitas Pemadatan 3.6 Checking of Compacting Quality

Kontrol kepadatan dengan Sand Cone Test Compactness control using a Sand Cone Test
atau Rubber Ballon pada lapis pertama dan or Rubber Ballon on the first layer and
berikutnya sebanyak 40 titik sesuai AASHTO thereafter, at 40 points conforming to
191-61. Untuk itu harus dikirimkan sampel AASHTO 191-61. Thus, soil sample shall be
tanah ke laboratorium untuk mengetahui kadar sent to the lab to find its optimum water
air optimum dan dry density maximum. content and dry density maximum. Soil works
Pekerjaan tanah dilakukan lapis perlapis are done layer by layer until 95% dry density
hingga mencapai kepadatan 95% dry density maximum is reached.
maximum.

3.7 Pagar Sementara dan Pos Jaga 3.7 Temporary Fence and Security Post

Area lokasi CPP-LAPANGAN GUNDIH selama The CPP-GUNDIH FIELD site, during the
pelaksanaan konstruksi harus dibuat pagar construction period shall have a temporary
pengamanan sementara disekeliling lokasi security fence around the site 2.0 m high
dengan tinggi 2.0 meter dari permukaan tanah. above the ground.

Pagar pengaman sementara terbuat dari tiang- Temporary security fence is made of dolken
tiang dolken dengan diameter minimal 7,5 cm posts with minimum diameter of 7.5 cm and
dan jarak antara tiang-tiang dolken adalah 3,0 interval between dolken posts of 3.0 meters.
meter. Tiang-tiang dolken ditanam kedalam The dolken posts are embedded in ground to
tanah sehingga berdiri dengan kokoh untuk stand rigidly to prevent the possibility of
menghindari dari kemungkinan roboh. Pagar collapsing. Barbed wire is installed on the
pengaman sementara dipasang kawat berduri temporary security fence between the dolken
diantara tiang-tiang dolken yang berjarak 20,0 posts spaced 20.0 cm along all fence height.
cm keseluruh tinggi pagar.

Pagar pengaman sementara harus The temporary security fence shall provide
menyediakan pintu masuk utama dan pintu main entry gate and main exit gate
keluar utama sesuai dengan kebutuhan conforming to site requirements an in
dilokasi dan pada tempat-tempat tertentu particular areas, if required, emergency exits
apabila diperlukan dipasang pintu-pintu are installed.
darurat.

Pagar pengaman sementara dipasang pada Temporary security fence is installed on the
bagian sebelah luar dan berjarak minimal 1.0 outside and is spaced minimum 1.0 meter
meter dari pagar permanent/tetap dengan from permanent fence for smoothness of
maksud dan tujuan untuk kelancaran permanent fence construction.
pembuatan pagar tetap.

Pada pintu masuk utama dan pintu keluar Main entry and exit gates shall have adequate
utama harus dilengkapi dengan bangunan Pos security posts for the needs of security
Jaga yang cukup memadai untuk keperluan officers.
para petugas jaga.

Pagar pengaman sementara dan bangunan The temporary security fence and the security
pos jaga harus direncanakan dan dan harus posts shall be designed and shall be on
mendapat persetujuan dari PERTAMINA. approval from PERTAMINA.

Document No. PPGJ-CIV-SPC-001 SITE PREPARATION Page 7


PEMBANGUNAN CENTRAL PROCESSING PLANT (CPP) AREA GUNDIH
PROYEK PENGEMBANGAN GAS JAWA BAGIAN TIMUR

3.8 Penerangan Listrik Sementara 3.8 Temporary electric lighting

Untuk kelancaran kegiatan pekerjaan dan For the smoothness of work activity and
keamanan di area lokasi CPP-LAPANGAN security on CPP-GUNDIH FIELD site,
GUNDIH harus disediakan penerangan listrik sufficient electric lighting shall be provided on
yang cukup dan memadai pada bangunan- temporary support buildings, at particular
bangunan penunjang sementara, pada tempat- places considered required during the site
tempat tertentu bilamana dianggap perlu preparation work performance period and
selama masa pelaksanaan pekerjaan during the construction work period.
persiapan lokasi/site preparation dan selama
masa pekerjaan konstruksi.

Harus disediakan Tenaga Listrik/Generator Set Shall be supplied the electricity power
yang cukup dan instalasi listrik yang memenuhi /generator sets sufficiently and electrical
syarat pemakaian dan keamanan untuk installation confroming to the used and safety
keperluan menjamin tersedianya penerangan requirements for ensuring of necessary the
listrik di area lokasi CPP-LAPANGAN electric lighting availability on the CPP-
GUNDIH. GUNDIH FIELD site.

Penyediaan Tenaga Listrik /Generator Set dan Temporary Electricity /Generator set supply
rencana instalasi penerangan listrik sementara and electric lighting installation plan, prior to
sebelum dikerjakan harus mendapat commence, shall gain an approval from
persetujuan dari PERTAMINA EP. PERTAMINA EP.

3.9 Peruntukan Direksi Keet 3.9 Allocation of Project Office

Melakukan pekerjaan pengukuran, pembuatan Performing measurement works, making


patok-patok dan pekerjaan pemadatan tanah posts and land compacting and levelling to
serta meratakan permukaan tanah /grade prepare the base area for project office
elevasi untuk menyiapkan area tapak allocation.
peruntukan direksi keet.

Tapak peruntukan direksi keet harus mengacu The allocation base of the project office shall
kepada gambar rencana yang sudah disetujui refer to the design drawing already approved
oleh PERTAMINA EP. by PERTAMINA EP.

3.10 Jalan Sementara dan Rambu-Rambu 3.10 Temporary Road and Traffic Signs
Lalu Lintas

Lalu lintas keluar dan masuk area CPP- Entry and exit traffic of the CPP-GUNDIH
LAPANGAN GUNDIH serta lalu lintas didalam FIELD and the traffic inside the CPP-GUNDIH
area CPP-LAPANGAN GUNDIH harus FIELD area shall be designed with temporary
direncanakan pembuatan jalan sementara roads for smoothness of material and
untuk kelancaran mobilisasi barang dan orang personnel mobilization during the site
selama masa pelaksanaan pekerjaan preparation execution and during the
persiapan lokasi/site preparation dan selama construction work execution.
masa pelaksanaan pekerjaan konstruksi.

Lokasi pembuatan jalan sementara harus Temporary road construction location shall
mencapai atau menjangkau seluruh lokasi reach all activity locations during site
aktivitas/kegiatan selama masa pelaksanaan preparation period and during the construction
pekerjaan persiapan lokasi/site preparation dan period.

Document No. PPGJ-CIV-SPC-001 SITE PREPARATION Page 8


PEMBANGUNAN CENTRAL PROCESSING PLANT (CPP) AREA GUNDIH
PROYEK PENGEMBANGAN GAS JAWA BAGIAN TIMUR

selama masa pelaksanaan pekerjaan


konstruksi.

Bilamana memungkinkan lokasi pembuatan Where possible, road construction location


jalan sementara harus mengacu kepada lokasi shall refer to the permanent /rigid pavement
pembuatan jalan permanent/rigid pavement access roads designed and approved by
access road yang telah direncanakan dan PERTAMINA EP.
disetujui oleh PERTAMINA EP.

Apabila lokasi jalan sementara mengunakan If the temporary road location uses permanent
lokasi jalan permanent/rigid pavement access /pavement access road, the construction of
road, pembuatan dasar jalan/subgrade dan the road subgrade and base shall refer to the
pondasi jalan/base harus mengacu kepada technical specification of rigid pavement
spesifikasi teknis dari rigid pavement access access road (PPGJ-CIV-SPC-023), for
road (PPGJ-CIV-SPC-023), untuk lapisan surface layer / pavement made of 10 cm thick
permukaan/perkerasan dihampar dengan good gradation of sand and stone or 12 cm
lapisan sirtu bergradasi baik setebal 10 cm thick steel plate, if required.
atau lembaran plat besi tebal 12 mm bila
diperlukan.

Untuk lokasi jalan sementara yang tidak For temporary road location not using
menggunakan lokasi jalan permanent / rigid permanent /rigid pavement access road,
pavement accsess road yang telah designed and approved by PERTAMINA EP,
direncanakan dan disetujui oleh PERTAMINA compacting is required on construction of
EP perlu dilakukan pekerjaan pemadatan pada subgrade with sufficient dry compactness
pembuatan dasar jalan/subgrade dengan nilai value to support maximum axle load of
kepadatan kering yang cukup mampu untuk vehicles of traffic capacity, while for pavement
mendukung tekanan gandar maksimal dari directly placed on the road subgrade with
kendaraan lalulintas yang melintasinya, layer pitrun 10 cm thick good gradation of
sedangkan untuk lapisan perkerasan yang sand and stone or 12 cm thick steel plate, if
langsung di hampar diatas permukaan dasar required.
jalan/subgrade menggunakan lapisan pitrun
bergradasi baik dengan ketebalan 10 cm atau
lembaran plat besi tebal 12 mm bila diperlukan.

Jalan sementara harus dilengkapi dengan The temporary road shall be equipped with
pemasangan rambu-rambu lalu lintas di dalam installation of traffic signs inside and outside
dan diluar area CPP-LAPANGAN GUNDIH of the CPP-GUNDIH FIELD area and from
serta dari jalan umum menuju ke lokasi CPP- public road to the CPP-GUNDIH FIELD
LAPANGAN GUNDIH dengan maksud dan location intended and on the purpose of
tujuan untuk kelancaran, ketertiban dan smoothness, discipline, and safety of vehicles
keamanan kendaraan dan orang selama and personnel during activities in applied
aktifitas dalam pelaksanaan pekerjaan. works.

Kontraktor harus membuat perencanaan jalan The Contractor shall be made a plan for the
sementara dan penempatan rambu-rambu lalu temporary road and placement of traffic signs
lintas untuk mendapat persetujuan dari to get PERTAMINA EP’s approval prior to
PERTAMINA EP sebelum pelaksanaan executed of the site preparation works.
pekerjaan persiapan lokasi/site preparation ini.

Document No. PPGJ-CIV-SPC-001 SITE PREPARATION Page 9


PEMBANGUNAN CENTRAL PROCESSING PLANT (CPP) AREA GUNDIH
PROYEK PENGEMBANGAN GAS JAWA BAGIAN TIMUR

3.11 Drainasi Sementara 3.11 Temporary Drainage

Selama masa pelaksanaan pekerjaan During the site preparation period and during
persiapan lokasi/site preparation dan selama the consruction work period, to prevent
masa pelaksanaan pekerjaan konstruksi, untuk flooding and water puddles, a temporary
mencegah terjadi nya banjir dan genangan air drainage system shall be made to collect and
harus dibuat sistim saluran drainasi sementara flows surface water of from all CPP-GUNDIH
untuk menampung dan menyalur/ mengalirkan FIELD locations due to rainfall and to collect
air permukaan dari seluruh lokasi CPP- and flow sewer water from existing support
LAPANGAN GUNDIH akibat dari turunnya buildings in the CPP-GUNDIH FIELD sites
hujan dan menampung dan menyalur outside of the CPP-GUNDIH FIELD location.
/mengalirkan air pembuangan dari bangunan-
bangunan penunjang yang ada di area lokasi
CPP-LAPANGAN GUNDIH ke luar dari lokasi
CPP-LAPANGAN GUNDIH

Sistim saluran drainasi sementara The temporary drainage channel is designed


direncanakan berbentuk trapesium dengan trapezium shaped with wet profile area, slope,
luas profil basah, kemiringan, dan kapasitas and capacity sufficient to collect and flows
yang cukup untuk manampung dan surface water or sewer water from support
menyalurkan /mengalirkan air permukaan buildings in a relatively rapid time to
ataupun air pembuangan dari bangunan- temporary ponds provided outside thet CPP-
bangunan penunjang dalam waktu yang relatif GUNDIH FIELD area and afterward, from the
cepat ke kubangan /balong sementara yang pond, it travels or flows to local drainage
telah disediakan diluar lokasi CPP-LAPANGAN system available in the vicinity of the CPP-
GUNDIH dan seterusnya dari kubangan GUNDIH FIELD location.
/balong disalurkan atau dialirkan ke sistim
saluran drainasi lokal yang ada disekitar lokasi
CPP-LAPANGAN GUNDIH.

Dilokasi area CPP-LAPANGAN GUNDIH harus Several ponds shall made of soil digging shall
disediakan beberapa buah kubangan/balong be provided at the CPP-GUNDIH FIELD sites,
yang terbuat dari penggalian tanah yang functioning as temporary containment prior to
berfungsi untuk penampung sementara forwarded to local drainage system existing
sebelum diteruskan ke sistim saluran drainasi near the CPP-GUNDIH FIELD site. The
lokal yang ada disekitar lokasi CPP- ponds shall be refilled and compacted
LAPANGAN GUNDIH. Kubangan/balong properly if no longer required after a
tersebut harus diurug kembali dan dipadatkan permanent drainage system construction has
dengan cukup bilamana tidak diperlukan lagi been completed and functions properly as a
setelah sistim saluran drainasi yang permanen drainage channel system.
t/tetap sudah selesai dikerjakan
pambangunanya dan berfungsi dengan baik
sebagai suatu sistim saluran drainasi.

Lokasi saluran drainasi sementara harus The temporary drainage channel shall refered
mengacu kepada rencana saluran drainasi to the permanent drainage to be made in the
permanent/tetap yang akan dibuat di area CPP-GUNDIH FIELD site and has been
lokasi CPP-LAPANGAN GUNDIH dan telah approved by PERTAMINA EP.
disetujui oleh PERTAMINA EP.

Document No. PPGJ-CIV-SPC-001 SITE PREPARATION Page 10


PEMBANGUNAN CENTRAL PROCESSING PLANT (CPP) AREA GUNDIH
PROYEK PENGEMBANGAN GAS JAWA BAGIAN TIMUR

Peralatan kerja dan Peralatan Keselamatan 3.12 Tool Kit and Safety Equipment
Kerja/Tool Keet and Safety Equipment

Kontraktor harus menyediakan dan membuat Contractor shall provide and to be made a
dalam bentuk daftar isian dari peralatan kerja form of tool kit and safety equipment required
dan keselamatan kerja yang diperlukan untuk during site preparation and during
selama masa pelaksanaan pekerjaan construction.
persiapan lokasi/site preparation dan dan
selama masa pelaksanaan pekerjaan
konstruksi.

Peralatan keselamatan kerja seperti safety The safety equipment such as safety shoes,
shoes, helmet dan gloves dan lain-lain helmet, gloves, etc shall be provided at the
sebagainya harus disediakan dengan jumlah same with the a number of personnel
yang sama dengan jumlah personil yang assigned during site preparation, and
ditugas kan selama masa pelaksanaan thereafter, proportional available of the
pekerjaan persiapan lokasi /site preparation number of personnel assigned during the
dan seterusnya disediakan sebanding dengan construction period, and shall meet the
jumlah personil yang ditugaskan selama masa standards. The quality of tool kit and safety
pelaksanaan pekerjaan konstruksi dan harus equipment used shall be on approval from
memenuhi standard. Kualitas dari peralatan PERTAMINA EP.
kerja dan keselamatan kerja yang digunakan
harus mendapat persetujuan dari PERTAMINA
EP.

3.13 Pengurusan Ijin – ijin 3.13 Taking Care of Permits

Kontraktor harus mengadakan pengurusan The Contractor shall manage permits in


perijinan dalam rangka pelaksanaan pekerjaan conducting this CPP-GUNDIH FIELD works.
CPP-LAPANGAN GUNDIH ini.

Pengurusan perijinan yang dimaksud adalah The permits to manage are as follows:
sebagai berikut :

Perijinan kepada Pemerintah Daerah setempat Permits from Local Government related to
yang menyangkut dengan pengurusan Ijin Building Permit, road usage permit from the
Mendirikan Bangunan (IMB), ijin pemakaian Road Traffic Office (DLLJ).
jalan dari Dinas Lalu Lintas Jalan (DLLJ).
Perijinan kepada Dinas Pekerjaan Umum Permit from the Public Work Office of
Pengairan, Direktorat Jenderal Pengairan, Irrigation, the Directorate General of Irrigation,
Badan Pelaksana Proyek Pengembangan Air Ground Water Development Project
Tanah (BP P2AT) Jawa Tengah yang Executive Agency (BP P2AT) of Central Java
menyangkut dengan perubahan sistim irigasi related to the change of irrigation system and
dan rencana penggunaan air tanah. Seluruh ground water usage plan. All costs of the
biaya dari perijinan-perijinan tesebut diatas aforementioned permits shall be included in
harus sudah termasuk dalam biaya penawaran the bid price in conducting this CPP-GUNDIH
dalam pelaksanaan pekerjaan CPP- FIELD work.
LAPANGAN GUNDIH ini.

4. MOBILISASI 4. MOBILIZATION

Sebelum melaksanakan pekerjaan persiapan Prior to executted of site preparation, site

Document No. PPGJ-CIV-SPC-001 SITE PREPARATION Page 11


PEMBANGUNAN CENTRAL PROCESSING PLANT (CPP) AREA GUNDIH
PROYEK PENGEMBANGAN GAS JAWA BAGIAN TIMUR

lokasi/site preparation harus sudah personnel, heavy equipment, tool kit, safety
dipersiapkan site personil, peralatan equipment, and required office equipment
berat/heavy equipment, peralatan kerja/tool shall have been provided on site such as
keet, peralatan keselamatan kerja/safety furniture, writing tools, desktop computer
equipment peralatan kantor yang diperlukan complete with network system and medicines
dilokasi seperti furniture atau meubelair, alat to take /bring to the project location.
tulis dan peralatan tulis, desktop computer
lengkap dengan sistem jaringan dan obat-
obatan untuk dibawa/mobolisasi ke lokasi
proyek.

Site Personil untuk melaksanakan pekerjaan Site Personnel to conduct the site preparation
persiapan lokasi/site preparation dan untuk and to run construction work from managerial
melaksanakan pekerjaan konstruksi dari level level to technician or operator level shall be
manajerial hingga ke level teknisi atau operator experienced and have capabilities in running
harus yang sudah berpengalaman dan Oil & Gas Project.
mempunyai kemampuan dalam mengerjakan
proyek Oil & Gas.

Semua peralatan-peralatan tersebut diatas All the above mentioned equipment shall be
sebelum dibawa ke lokasi area CPP- brought to the CPP-GUNDIH FIELD site in
LAPANGAN GUNDIH harus dalam kondisi use worthy condition, functions properly and
layak pakai, berfungsi dengan baik untuk during mobilization, is maintained to prevent
digunakan dan pada waktu melakukan damage, and if possible, shall utilize
mobilisasi dijaga agar tidak terjadi kerusakan expedition procedure standard.
dan bilamana memungkinkan harus
menggunakan standar prosedur pengiriman
/expedisi.

Pada waktu pekerjaan mobilisasi lebih dulu Mobilization work shall be on approval from
harus mendapat persetujuan dari PERTAMINA PERTAMINA EP.
EP.

Kontraktor harus bertanggung jawab atas Contractor shall be responsible on every


segala kerusakan property milik pihak ketiga damage on any properties owned by third
yang disebabkan oleh pelaksanaan mobilisasi, parties due to mobilization, such as public
seperti jalan umum. road