NAME OF WORK : Providing chain link fencing around the balance OSR Parks (for Phase-II Greenery) at SIPCOT Industrial Park,
Gangaikondan.
Description of work
Section Amount (Rs.)
I Providing Chain link fencing around the OSR Parks no. 1,2pt,7,9,10,11,12,14 & 15
in SIPCOT Industrial Park, Gangaikondan

II Provision for pipe culver in SIPCOT Industrial Park, Gangaikondan

GST 12% on Sub Total

GRAND TOTAL

(Rupees________________________________________________________________________________only)

No of corrections:
No of overwrittings:

CONTRACTOR SE
I. Providing Chain link fencing around the OSR Parks no. 1,2pt,7,9,10,11,12,14 & 15 in SIPCOT Industrial Park, Gangaikondan

Sl. No. Qty Description of item TNPB Rate both in Unit Amount
No. figure and in
words
1 2 3 4 5 6 7
1 154695.00 Sqm Clearing juliflora jungle with uprooting and disposal of the 1 Sqm
(One lakh fifty site etc., complete complying with standard specifications (One
four thousand six and as directed by SIPCOT officers. . square
hundred and metre)
ninety five
square metre)

2 71740.00 Sqm Clearing the light jungle with uprooting as per standard 1 Sqm
(Seventy one specification and dispose them by burning and clearing the (One
thousand seven site etc., complete complying with standard specifications square
hundred and and as directed by SIPCOT Officers. metre)
forty square
metre)

3 12690.00 Sqm Supplying and fixing of 2"x2" 10 gauge PVC coated chain 1 Sqm
(Twelve link fencing and providing 3 Nos. of GI wire 8G (PVC (One
thousand six coated vertical overall 1.80 m height) and 3 Nos. of square
hundred and horizontal direction in between GI pipe centre to centre metre)
ninety square including cost and conveyance and fixing to alignment
metre) etc., complete complying with standard specifications and
as directed by "SIPCOT" officers.

4 4194.00 Nos Manufacturing of RCC precast fencing post with a size of 1 No


(Four thousand 0.15x0.15 m at bottom and 0.1x0.1 m at top with a length (One
one hundred and of 2.40 m with RCC 1:2:4 (20 mm HBG metal) including Number)
ninety four mouldingcuring making holes in the RCC post to easily
numbers) insert the barbed wire to hold good tight for tying of
fencingand tying with the barbed wire with Galvanized
binding wire etc, as directed by the SIPCOT officials during
executing work.

No of corrections:
No of overwrittings:

CONTRACTOR SE
Sl. No. Qty Description of item TNPB Rate both in Unit Amount
No. figure and in
words
1 2 3 4 5 6 7
5 4194.00 Nos Fixing of RCC precast post by earth work excavation in all 1 No
(Four thousand side with the size of 0.45x0.45x0.60 m and laying of PCC (One
one hundred and 1:5:10 etc. complete complying with standard Number)
ninety four specifications and as directed by "SIPCOT" officers.
numbers)

6 22.00 Cum Earth work Excavation for foundation in hard stiff clay 1 Cum
(Twenty two (except in hard rock requiring blasting) with an initial lead (One cubic
cubic metre) of 10m and an initial lift of 2m inclusive of shoring, metre)
shuttering, bailing out water wherever necessary refilling
the foundation with excavated earth other than sandy soil
in layers of not more than 150 mm thick layers well
rammed and depositing the surplus earth with in the
compound in place shown by the "SIPCOT" officers with all
leads & lifts, clearing and levelling the site etc., complete
complying with standard specification SS 20B and as
directed by SIPCOT officers.

7 2.60 Cum Providing and laying of Plain Cement Concrete 1:4:8 (One 1 Cum
(Two point six cement, Four M.sand and eight aggregate) using 40mm (One cubic
zero cubic metre) size Hard broken granite stone jelly for foundation, metre)
flooring bed, dummy columns, mudmat below column
footings, Grade beams etc. laid in layers not exceeding
15cm thick including cost and conveyance of all materials
and labour to work site, mixing of concrete, laying,
compacting, curing with all leads for soft potable water,
hire and fuel charges for all tools and plants including all
other incidental charges such as bailing out water for
forming protective bunds, coffer dams and shoring,
strutting etc., complete complying with standard
specifications and as directed by "SIPCOT" officers.

No of corrections:
No of overwrittings:

CONTRACTOR SE
Sl. No. Qty Description of item TNPB Rate both in Unit Amount
No. figure and in
words
1 2 3 4 5 6 7
8 2.60 Cum Supplying and filling in foundation with filling stone dust in 1 Cum
(Two point six layers of not more than 15 cm thick well watered, rammed (One cubic
zero cubic metre) and consolidated etc., Complete complying with standard metre)
specification and as directed by SIPCOT officers.

9 Providing and laying of Plain Cement Concrete 1:2:4 (One


Cement, Two M.sand and Four hard broken stone jelly)
using 20 mm gauge hard broken granite stone jelly for all
items of works excluding cost of reinforcement grill and
fabricating charges, centering and shuttering but including
laying, vibrating with mechanical vibrators, finishing,
curing and providing holes in the RCC kerb wall for fixing
wherever necessary and bearing surfaces of walls, beams
etc. shall be finished smooth with Cement Mortar 1:3 (One
Cement and Three M-sand) and kraft paper laid over it
without claiming etc., complete complying with standard
specification and as directed by SIPCOT officers.

a 5.60 Cum Below GL 1 Cum


(Five point six (One cubic
zero cubic metre) metre)

b 7.90 Cum Above GL 1 Cum


(Seven point (One cubic
nine zero cubic metre)
metre)

No of corrections:
No of overwrittings:

CONTRACTOR SE
Sl. No. Qty Description of item TNPB Rate both in Unit Amount
No. figure and in
words
1 2 3 4 5 6 7
10 Supplying and erecting centering for sides and soffits
including necessary supports and strutting upto 3.29 M
height for plane surfaces as detailed below in all floors
with all cross bracings using Mild Steel sheets of size 90 x
60 cm and 10 BG stiffened with welded Mild Steel angle of
size 25mm x 25mm x 3 mm for boarding laid over silver
oak joists of size 10cm x 6.50 cm spaced at abote 90 cm
centre to centre and supported by casurina props of 10cm
to 13 cm dia spaced at not more than 75 cm centre to
centre etc., Complete complying with standard
specification and as directed by SIPCOT Officers.

a 35.00 Sqm Below GL


(Thirty five
square metre)

b 62.00 Sqm Above GL 1 Sqm


(Sixty two square (One
metre) square
metre)
11 13.50 Qtl Supplying, Fabricating and placing in position steel 1 Qtl
(Thirteen point reinforcement grills using M.S. / R.T.S. rods(Fe500 D) of (One
five zero quintal) all sizes of reinforcement for all Reinforced cement quintal)
concrete works (for pedestal pillar concrete) including cost
and conveyance of steel, binding wire,spacer bars, cover
blocks, labour charges for unbending of rods, straighteing,
cutting, fabricating, tying, lifting, placing in position,
overlaping to the required length whereever necessary
cover blocks and all other incidental charges etc. complete
complying with standard specifications and as directed by
SIPCOT officers.

No of corrections:
No of overwrittings:

CONTRACTOR SE
Sl. No. Qty Description of item TNPB Rate both in Unit Amount
No. figure and in
words
1 2 3 4 5 6 7
12 62.00 Sqm Special ceiling plastering and finishing the exposed surface 1 Sqm
(Sixty two square of all RCC items of work such as slabs, beams, sunshades, (One
metre) facia, canopy slab, staircase waist slab, landing slab etc., square
with Cement Mortar 1:3 (One Cement and Three P- Sand) metre)
10mm thick including hacking the surfaces, providing
cement mortar nosing, beading for sunshades, staircases,
steps, landing slabs and curing in all floors etc., complete
complying with standard specification and as directed by
SIPCOT officers.
13 1950.00 Kg Fabricating supply and fixing M.S. Grills gate of size 3.60m 1 Kg
(One thousand x 1.80m height (Two Leaf) (pattern / design using M.S (One
nine hundred and Angles/ square rods/ tubes, clamps etc., approved by kilogram)
fifty kilogram) SIPCOT officers) including locking arrangements, hold fast
etc., cost and conveyance of all required materials with
one coat of primer and all labour charges for fabrication,
fixing in position in Concrete/ Masonry/ Wooden frames
etc., complete complying with standard specifications and
as directed by SIPCOT Officers.

14 3860.00 Sqm Painting two coats of newly plastered internal wall surface 1 Sqm
(Three thousand using plastic emulsion paint of first class quality and of (One
eight hundred approved colour over a priming coat including thorough square
and sixty square scrapping, clean removal of dirt, and including necessary metre)
metre) plaster of paris putty, wherever required etc., complete
complying with standard specification and as directed by
SIPCOT Officials.

No of corrections:
No of overwrittings:

CONTRACTOR SE
Sl. No. Qty Description of item TNPB Rate both in Unit Amount
No. figure and in
words
1 2 3 4 5 6 7
15 90.00 Sqm Painting new iron works such as steel doors, windows, 1 Sqm
(Ninety square ventilators, window bars, balustrades etc., with two coats (One
metre) of best approved first quality and colour of synthetic square
enamel paint over the existing red oxide priming coat in metre)
all floors excluding cost of priming coat etc., complete
complying with standard specification and as directed by
SIPCOT Officials.

Section I - 15 items (Fifteen items only) Sub Total


II. Provision for pipe culvert in SIPCOT Industrial Park, Gangaikondan

1 40.00 Rm Supplying and Laying of 300 mm dia RCC non pressure 1 RM


(Fourty running spun pipe with socket and spigot ends NP 3 Class as per IS (One
metre) 458/2003 manufactured with sulphate resistant cement running
with 12 mm HI -alumina lining provided for rubber ring metre)
joints laying at proper levels and location etc., complete
complying with standard specification and as directed by
SIPCOT officers.

2 50.00 Cum Earth work excavation for foundation in all classes of soils 1 Cum
(Fifty cubic and sub-soils and to full depth as may be directed except (One Cubic
metre) in hard rock requiring blasting inclusive of shoring metre)
shuttering, bailing out water wherever necessary and
depositing the surplus earth within the compound in
places shown by the departmental officers with an initial
lead of 10 mts and initial lift of 2 mts. and clearing and
levelling the site, etc., complete complying with standard
specification and as directed by SIPCOT officers.

No of corrections:
No of overwrittings:

CONTRACTOR SE
Sl. No. Qty Description of item TNPB Rate both in Unit Amount
No. figure and in
words
1 2 3 4 5 6 7
3 22.00 Cum Supplying and filling in foundation with filling stone dust in 1 Cum
(Twenty two layers of not more than 15 cm thick well watered, rammed (One Cubic
cubic metre) and consolidated etc., Complete complying with standard metre)
specification and as directed by SIPCOT officers.

4 7.00 Cum Providing and laying plain cement concrete mix 1:4:8 1 Cum
(Seven cubic (One cement, four M.sand and Eight aggregates) for (One Cubic
metre) foundation using 40mm ISS size HBG stone jelly for metre)
foundation including dewatering if found necessary and
laid in layers of not more than 15cm thick well rammed
consolidated and curing etc, complete complying with
Standard specification including cost and conveyance of all
materials to site and as directed by SIPCOT Officers.

Section II - 04 items (Four items only) Sub Total