Professional Documents
Culture Documents
Dear Sir,
We are pleased to submit our best price for the above mentioned subject as per your enquiry.we hope
that our submitted offer will meet your requirements.should you require any further clarification,please feel free
to contact us.
Rate/Qty Amount
SNo Description Size Unit Total Qty
(SAR) (SAR)
1 Additional Support Fabrication 1 223889 223,889.00
VAT 5% 11,194.45
235,083.45
1. Our Scope includes all Manpower and equipment required to execute the JOB.
2. 30% Advance balance Payment 30 Days after invoice submission
3. VAT ADDITIONAL AS PER SAUDI LAW
PROJECT: ARAMCO Annex- II
RESPONSIBILITY MATRIX
Sl# DESCRIPTION Sub- Contractor CLIENT
SITE EXECUTION:
1 Weld Joining/Installation x
2 Supply of Materials x
3 Site Mobilization and demobilization x
4 Consumables x
5 Skilled Workforce x
6 Certification of technicians x
7 Supervision x
8 Accommodation x
9 Food x
10 Local Transport of S/c Employees to/from Client Site & S/c xCamp
11 x
Tools, Tackles, Hand-tools & Equipment as required to carry-out the work
12 Safety officer (1 No) x
13 QA/QC x
14 Work Permit receiver x
15 Site Office facilities - (02 Desks) x
16 Fabrication Shop, Storage area etc. x
17 Gate passes and ID's, if required x
18 Loading and unloading at site (Forklift) x
19 Materials/Pipe Transport etc. x
20 x drawing.
Placement and rough alignment of pipes & pipe fitting as per
21 Hydro test of pipes including manifold x
22 Manpower Assistance for loading/unloading of Materials/Pipe Transport etc., if required
x
23 Electricity x
24 Third party inspector, if required x
25 Utility services etc. @ Site x
26 Scaffolding, Lighting & Const. Equipment’s @ as & when required basis x
Disposal of Debris / Insulation Materials
27 x
at Plant Designated Area
28 Hydro test Water x
29 Third party Joint Testing x
Hamco Arabia
Signed By : Sinuchandran
Date 9/3/2018