Purpose:
This filing philosophy sets the ways and means to file and order all documents produced for
a project in execution.
All staff of the Design Department shall apply this procedure, particularly for the following:
• Suppliers and Equipment documents,
• Internal management,
• Technical documents.
TABLE OF CONTENT
1. ELECTRONIC FILLING ......................................................................................................................................................................2
1.1. Domain of application............................................................................................................................................................................2
1.2. Usage......................................................................................................................................................................................................2
1.3. Description .............................................................................................................................................................................................2
1.3.1. Suppliers' Folder (Yellow folder) ............................................................................................................................................2
Y.0. Proposal Documents............................................................................................................................................................................2
Y.1. General Documentation.......................................................................................................................................................................2
Y.2. Inquiry .................................................................................................................................................................................................3
Y.3. Order Documentation ..........................................................................................................................................................................4
Y.4. Logistics...............................................................................................................................................................................................4
Y.5. Inspection and controls........................................................................................................................................................................4
Y.6. Final Supplier Documentation for the entire plant .............................................................................................................................4
1.3.2. Internal folder (White folder) ..................................................................................................................................................5
W.1. Communication ..................................................................................................................................................................................5
W.2. Project Management...........................................................................................................................................................................5
W.3. Degremont Internal Correspondence .................................................................................................................................................6
W.4. Quality ................................................................................................................................................................................................6
W.5. Safety ..................................................................................................................................................................................................6
W.6. Minutes of internal meetings..............................................................................................................................................................6
1.3.3. Technical folder (Blue folder) ..................................................................................................................................................7
B.0. Proposal technical documentation.......................................................................................................................................................7
B.1. General Documents .............................................................................................................................................................................7
B.2. Process Documentation .......................................................................................................................................................................7
B.3 General Drawings .................................................................................................................................................................................7
B.4. Building drawings................................................................................................................................................................................7
B.5. Electricity, Instrument / Automatic Control Systems .........................................................................................................................7
B.6. Civil Documents ..................................................................................................................................................................................7
B.7. Prefab, erection and piping..................................................................................................................................................................7
2. PAPER FILING .....................................................................................................................................................................................8
2.1. Usage of paper documents.....................................................................................................................................................................8
2.2. General note ...........................................................................................................................................................................................8
2.3. Description .............................................................................................................................................................................................9
2.3.1. White file – GENERAL FILE..................................................................................................................................................9
2.3.2. Blue file – TECHNICAL FILE................................................................................................................................................9
2.3.3. Red file – COMMENT BY CLIENT / CONSULTANT .......................................................................................................9
2.3.4. Yellow file – EQUIPMENT PACKAGE ..............................................................................................................................10
File Y.1: General Documentation .............................................................................................................................................................10
2.3.5. Drawing production filing (Blue file)....................................................................................................................................11
General point.................................................................................................................................................................................................11
2.4. Copy of documents ..............................................................................................................................................................................12
2.5. Drawing filing process.........................................................................................................................................................................13
1. ELECTRONIC FILLING
1.1. Domain of application
This plan is applicable to all Design & Build projects.
This plan is applicable for electronic files only (for hard copies refer to Chapter No2). A
C
dedicated directory for the project should be created including the under-mentioned folders
and sub-folders. For hard copies, the filing plan is done exactly in the same way, except that
for heavy subjects and for easier use, a folder can be split into several binders. The proper
filing of documents is the responsibility of the person in charge of the subject (i.e. MDE for a
specification, CAD Leader for a set of General Assembly Drawings…).
1.2. Usage
Each of the folders in the classification plan defines the level of classification ranging from
general to particular. The first two detailing levels are already specified according to the
project, the third detailing level is optional leaving the choice to the project manager at the
commencement of project execution. The fourth detailing level is flexible.
1.3. Description
1.3.1. Suppliers' Folder (Yellow folder)
This folder contain consultations with suppliers, choice of suppliers, material
specification and order, order follow up, logistics, folders on maintenance of material. It s
structured as follow:
Y.2. Inquiry
Y.2.1. Inquiry follows up
This folder is built by the Procurement Department to follow-up the progress of Enquiries.
Y.2.2 Equipments / Sub contracted services
Model to be duplicated equipment wise (with specification number)
o Y.2.2.1 Inquiry document or specification
Basically, the specification itself with its appendices, additional files if applicable
(drafts, calculation note, extract of tender…)
o Y.2.2.2 Client approval Specification
Basically, the specification itself with its appendices, additional files if applicable
(files received from Vendor to build the specification for approval…)
o Y.2.2.3 Comparative tables and selection
This folder contains the final Technical Comparison Table with recommendations
o Y.2.2.4 Supplier
Model to be duplicated
Y.2.2.4.1 Internal and external correspondence
This folder contains the correspondence (letters, fax, copy of e-mail) and
support documents for correspondence (TQR sheet…)
Y.2.2.4.2 Offer documents
As the commercial/financial offer is entered by the Procurement
Department in Emerald, this folder is normally not used.
Y.2.2.4.3 Design documents
As the technical offer is entered by the Design Department in Emerald,
this folder is normally not used.
Note: in order to avoid numerous folders located in Y.2, it is recommended to add a folder grouping same type
equipment folder Y.2.2.
Example:
Y.2.2 Valves
Y.2.2 Butterfly valves Treated Water – DGT-000-L-SP-EQ-001
Y.2.2.1 Specification for Inquiry
Y.2.2.2 Client approval Specification
Y.2.2.3 Comparative tables and selection
Y.2.2.4 KSB AMRI
Y.2.2.4.1 Internal and external correspondence
Y.2.2.4.2 Offer documents
Y.2.2.4.3 Design documents
Y.2.2.4 ADVANCE VALVES
Y.2.2.4.1 Internal and external correspondence
Y.2.2.4.2 Offer documents
Y.2.2.4.3 Design documents
Y.2.2 Regulating Valve Sand Filter – DGT-131-L-SP-EQ-002
Y.2.2.1 Specification for Inquiry
Y.2.2.2 Client approval Specification
Y.2.2.3 Comparative tables and selection
Y.2.2.4 KSB AMRI
Y.2.2.4.1 Internal and external correspondence
Y.2.2.4.2 Offer documents
Y.2.2.4.3 Design documents
Y.2.2.4 TYCO
Y.2.2.4.1 Internal and external correspondence
Y.2.2.4.2 Offer documents
Y.2.2.4.3 Design documents
o Y.3.1.4. Billing/finance
This sub-folder is created, used and updated by the Procurement Department.
o Y.3.1.5 Technical document / Drawing
This sub-folder is used to file all documents, drawings… received from the
Vendor.
Y.4. Logistics
This folder is created, used and updated by the Procurement and Logistics Department.
Y.4.1. Follow up
o Y.4.1.1. Project Review
o Y.4.1.2. Quotation and invoicing
o Y.4.1.3. Logistics order follow up
o Y.4.1.4. Logistics statutory
o Y.4.1.5. Reporting
Y.4.2. Shipping
o Y.4.2.1 Shipping No. XX
Model to be reproduced
Y.4.2.1.1 Shipping list
Y.4.2.1.2. Bills
Y.4.2.1.3. Certificate of origin
Y.4.2.1.4. Transport documentation
Y.4.2.1.5. Transport insurance
Y.4.2.1.6. Order regularizations
Y.4.2.1.7. Voucher of delivery
Y.4.3. Freight forwarder
o Y.4.3.1. Offers
o Y.4.3.2. Offer Analysis
o Y.4.3.3. Final selection
o Y.4.3.4. Correspondence
Y.4.4.Packing
Y.5. Inspection and controls
This folder is created, used and updated by the Procurement and Quality Control Department.
Y.5.1.Quality Inspection, control and inspection reports
Y.5.2.Shipping Control
Y.5.3. Final Control
Y.5.4. Audit
Y.6. Final Supplier Documentation for the entire plant
This folder is usually built with the same organization than the folder Y.3.1, equipment-wise or
supplier-wise.
W.1. Communication
W.1.1. Presentations
W.1.2. Photos
W.1.3. Videos
W.1.4. Press articles
2. PAPER FILING
For a given folder, all binders shall be of the same type, size and the color shall follow the color
described hereafter.
Each Binder shall be correctly named and shall mention the following:
• Reference of the contract: name and number
• Name of the Binder (content)
• If several binders are required for the same topic, numbering shall be given (ex: 1/3, 2/3, 3/3)
These original documents are required for any reference in case of contractual discussion.
Date
If no date is mentioned on the document, or if the date of submission of the document is different
than the date mentioned in the title block, then the date shall be manually written, besides the
stamp “MASTER”.
Old revision
Old revision document shall be stamped “SUPERSEDED” and kept together with “MASTER”
document.
2.3. Description
2.3.1. White file – GENERAL FILE
These files (3 in number) are for general document filling and contain the following data
C
¾ Design Report ¾ Id System for P & ID
¾ Electrical data (Load list, Cable list, etc)
¾ Instrumentation data (Instrument List, etc.)
Notes:
o Master specifications and specifications shall be filed in this binder.
o Superseded documents shall have a stamp.
o Original documents with signature shall be filed separately (by Technical Assistant)
Written by: T. Clouet Checked by: P. Le Approved by: Y. Bakha
N° : PGE Ω 002
EXECUTION ENGINERING PROCESS Rev. Ver. : C
Dated : May 09
FILING PHILOSOPHY
Page : 11 / 13
General point
We distinguish several categories of drawings:
For study or draft purposes, a print-out or a copy of a document must be stamped according to
the following:
¾ Documents in “Open revision” only must be stamped “DRAFT”
¾ Documents copied from MASTER documents (i.e closed revision) must be
stamped “COPY”
If the document is used for discussion or for hand-over to another user, it may be useful to
mention the name of the user and the name of the recipient.
Cad Leader/
Cad Drawing
in
A0 or A1
Size
Cad Leader
Signature Given to
of all Technical
parties on Assistant
A3 drawing
A3 size to be filed as
Cad Leader original. Previous
/Technical Given to revision to be stamped
Assistant Technical Filing superseded and archived.
Assistant
A3 print to be signed
stamped as master and
Technical Stamp Supersede filed. No original A3
Assistant. ‘Master’ on previous required
A3 signed revision A3
copy master.