Name : Mr. Mandar Khanvilkar Mr. Brajesh Kumar Prasad Mr. Kamlesh Sagitra
Date
Project Greenfield PVC Additives
DYE PENETRANT TEST Location
Client
Dewas MP
BIAPL
REPORT Date
Format No EFE/SITE/QC/22/00
LINE NO.: RC 08 ( L01 - L 02) Inspection Stage : Root Weld/ Fillet Weld
Location : Production plant - Northside wall
ITEM MAKE BATCH NO EXPIRY DATE Report No : 02
Cleaner ORION R/002/2021 2023 Penetration Time:06 min
Penetrant ORION P/004/2021 2023 Developing time:08 min
Developer ORION D/10/2021 2023 Material :MS ERW PIPE
Accepted Standard:
Sl NO. Location Line No. JOINT. PIPE SIZE WELDER NO. Welding Run OBSERVATION EFEPL MM Remark
NO.
1 Production plant - North side Wall L01 J05 150 NB W03 Final weld OK
2 Production plant - North side Wall L02 J03 150 NB W03 Final weld OK
Name : Mr. MOHMMAD SAMAN Mr. Brajesh Kumar Prasad Mr. Kamlesh Sagitra
Date
Project Greenfield PVC Additives
DYE PENETRANT TEST Location
Client
Dewas MP
BIAPL
REPORT Date
Format No EFE/SITE/QC/22/00
LINE NO.: RC 09 ( L01 - L 06) Inspection Stage : Root Weld/ Fillet Weld
Location : Production plant - Northside wall
ITEM MAKE BATCH NO EXPIRY DATE Report No : 02
Cleaner ORION R/002/2021 2023 Penetration Time:06 min
Penetrant ORION P/004/2021 2023 Developing time:08 min
Developer ORION D/10/2021 2023 Material :MS ERW PIPE
Accepted Standard:
JOINT.
Sl NO. Location Line No. NO. PIPE SIZE WELDER NO. Welding Run OBSERVATION Date Remark
Name : Mr. MOHMMAD SAMAN Mr. Brajesh Kumar Prasad Mr. Kamlesh Sagitra
Date