You are on page 1of 12

Form No: ALUNILE-001

No of Pages:1 of 1
Attachments: None
TAKING OVER CERTIFICATE SECTION OF Original to: SODIC
SECTIONS OR PARTS OF THE WORKS ALUNILE
Copies to: MZECH
Allegria Project - Phase (2) DESIGN CONSULTANT : MZECH
Km 38, Alexandria Road, Sheikh Zaid City CS CONSULTANT : MZECH
CLIENT : SODIC

Contract No.: PK (AL-04-CC-41)


Supply & Installation of Aluminum Works
Contractor: Alu-Nile- Aluminum works

This document is being issued to certify that the designated Sections of the Works as indicated below
has been reviewed and found substantially completed pursuant to Clause 48.2 and 48.3

Villas : Zone: D

D004, D008, D017, D018, D019, D020, D021, D022, D023, D023Y, D083, D094, D097, D099, D102, D103,
D121, D122, D123, D124, D125, D126, D127, D127Y (Total: 24 Villas)

Notes:
a) Taking Over Certificate date for the above mentioned parts of the works is: 31 December 2012
b) In the
Parts event
of the of different
Permanent Defects
Works, the Liability
expirationPeriods
of thehaving become
Defects Liabilityapplicable
Period in to thecase
such different Sections
be deemed to or
mean
the
the expiration
expiration latest
of the of suchofperiods.
latest such periods.

Upon the issue of a Taking Over Certificate in respect of Part of the Permanent Works before completion
of the whole of the works, the Contractor shall deemed to have undertaken to complete with
due expedition any outstanding work in that part of the Permanent Works within the first thirty (30)
days of the Defects Liability Period.

The Failure to include a list of deficiencies or incomplete work does not alter the responsibility of the
contractor to complete all work in accordance with the Contract Documents pursuant to Clause 48.4

Nashaat Nosshy 12/31/2012


ALUNILE BY DATE

Ahmed Salah BY 12/31/2012


MZECH

Frank Konings 12/31/2012


SODIC BY DATE
Form No: ALUNILE-002
No of Pages:1 of 1
Attachments: None
TAKING OVER CERTIFICATE SECTION OF Original to: SODIC
SECTIONS OR PARTS OF THE WORKS ALUNILE
Copies to: MZECH
Allegria Project - Phase (2) DESIGN CONSULTANT : MZECH
Km 38, Alexandria Road, Sheikh Zaid City CS CONSULTANT : MZECH
CLIENT : SODIC

Contract No.: PK (AL-04-CC-41)


Supply & Installation of Aluminum Works
Contractor: Alu-Nile- Aluminum works

This document is being issued to certify that the designated Sections of the Works as indicated below
has been reviewed and found substantially completed pursuant to Clause 48.2 and 48.3

Villas : Zone: E

E014, E016, E018, E020, E022, E023, E031, E046, E054, E056, E069, E070 (Total: 12 Villas)

Notes:
a) Taking Over Certificate date for the above mentioned parts of the works is: 31 December 2012
b) In the
Parts event
of the of different
Permanent Defects
Works, the Liability
expirationPeriods
of thehaving become
Defects Liabilityapplicable
Period in to thecase
such different Sections
be deemed to or
mean
the
the expiration
expiration latest
of the of suchofperiods.
latest such periods.

Upon the issue of a Taking Over Certificate in respect of Part of the Permanent Works before completion
of the whole of the works, the Contractor shall deemed to have undertaken to complete with
due expedition any outstanding work in that part of the Permanent Works within the first thirty (30)
days of the Defects Liability Period.

The Failure to include a list of deficiencies or incomplete work does not alter the responsibility of the
contractor to complete all work in accordance with the Contract Documents pursuant to Clause 48.4

Nashaat Nosshy 12/31/2012


ALUNILE BY DATE

Ahmed Salah BY 12/31/2012


MZECH

Frank Konings 12/31/2012


SODIC BY DATE
Form No: ALUNILE-003
No of Pages:1 of 1
Attachments: None
TAKING OVER CERTIFICATE SECTION OF Original to: SODIC
SECTIONS OR PARTS OF THE WORKS ALUNILE
Copies to: MZECH
Allegria Project - Phase (2) DESIGN CONSULTANT : MZECH
Km 38, Alexandria Road, Sheikh Zaid City CS CONSULTANT : MZECH
CLIENT : SODIC

Contract No.: PK (AL-04-CC-41)


Supply & Installation of Aluminum Works
Contractor: Alu-Nile- Aluminum works

This document is being issued to certify that the designated Sections of the Works as indicated below
has been reviewed and found substantially completed pursuant to Clause 48.2 and 48.3

Villas : Zone: G

G027, G055, G032, G065 (Total: 4 Villas)

Notes:
a) Taking Over Certificate date for the above mentioned parts of the works is: 31 December 2012
b) In the
Parts event
of the of different
Permanent Defects
Works, the Liability
expirationPeriods
of thehaving become
Defects Liabilityapplicable
Period in to thecase
such different Sections
be deemed to or
mean
the
the expiration
expiration latest
of the of suchofperiods.
latest such periods.

Upon the issue of a Taking Over Certificate in respect of Part of the Permanent Works before completion
of the whole of the works, the Contractor shall deemed to have undertaken to complete with
due expedition any outstanding work in that part of the Permanent Works within the first thirty (30)
days of the Defects Liability Period.

The Failure to include a list of deficiencies or incomplete work does not alter the responsibility of the
contractor to complete all work in accordance with the Contract Documents pursuant to Clause 48.4

Nashaat Nosshy 12/31/2012


ALUNILE BY DATE

Ahmed Salah BY 12/31/2012


MZECH

Frank Konings 12/31/2012


SODIC BY DATE
Form No: ALUNILE-004
No of Pages:1 of 1
Attachments: None
TAKING OVER CERTIFICATE SECTION OF Original to: SODIC
SECTIONS OR PARTS OF THE WORKS ALUNILE
Copies to: MZECH
Allegria Project - Phase (2) DESIGN CONSULTANT : MZECH
Km 38, Alexandria Road, Sheikh Zaid City CS CONSULTANT : MZECH
CLIENT : SODIC

Contract No.: PK (AL-04-CC-41)


Supply & Installation of Aluminum Works
Contractor: Alu-Nile- Aluminum works

This document is being issued to certify that the designated Sections of the Works as indicated below
has been reviewed and found substantially completed pursuant to Clause 48.2 and 48.3

Villas : Zone: D

D001, D003, D005, D007, D009, D011, D012, D015, D016, D024, D025, D026, D027, D028, D029, D030,
D031, D033, D038, D043, D046, D050, D051, D052, D053 (Total: 25 Villas)

Notes:
a) Taking Over Certificate date for the above mentioned parts of the works is: 31 January 2013
b) In the
Parts event
of the of different
Permanent Defects
Works, the Liability
expirationPeriods
of thehaving become
Defects Liabilityapplicable
Period in to thecase
such different Sections
be deemed to or
mean
the
the expiration
expiration latest
of the of suchofperiods.
latest such periods.

Upon the issue of a Taking Over Certificate in respect of Part of the Permanent Works before completion
of the whole of the works, the Contractor shall deemed to have undertaken to complete with
due expedition any outstanding work in that part of the Permanent Works within the first thirty (30)
days of the Defects Liability Period.

The Failure to include a list of deficiencies or incomplete work does not alter the responsibility of the
contractor to complete all work in accordance with the Contract Documents pursuant to Clause 48.4

Nashaat Nosshy 31/01/2013


ALUNILE BY DATE

Ahmed Salah BY 31/01/2013


MZECH

Frank Konings 31/01/2013


SODIC BY DATE
Form No: ALUNILE-005
No of Pages:1 of 1
Attachments: None
TAKING OVER CERTIFICATE SECTION OF Original to: SODIC
SECTIONS OR PARTS OF THE WORKS ALUNILE
Copies to: MZECH
Allegria Project - Phase (2) DESIGN CONSULTANT : MZECH
Km 38, Alexandria Road, Sheikh Zaid City CS CONSULTANT : MZECH
CLIENT : SODIC

Contract No.: PK (AL-04-CC-41)


Supply & Installation of Aluminum Works
Contractor: Alu-Nile- Aluminum works

This document is being issued to certify that the designated Sections of the Works as indicated below
has been reviewed and found substantially completed pursuant to Clause 48.2 and 48.3

Villas : Zone: D
D054, D055, D059, D060, D064, D065, D066, D067, D068, D069, D074, D076, D077, D089, D093, D095,
D096, D098, D100, D101, D104, D106, D107, D108, D109, D110, D118, D119, D129, D130 (Total: 30
Villas)
Notes:
a) Taking Over Certificate date for the above mentioned parts of the works is: 31 January 2013
b) In the
Parts event
of the of different
Permanent Defects
Works, the Liability
expirationPeriods
of thehaving become
Defects Liabilityapplicable
Period in to thecase
such different Sections
be deemed to or
mean
the
the expiration
expiration latest
of the of suchofperiods.
latest such periods.

Upon the issue of a Taking Over Certificate in respect of Part of the Permanent Works before completion
of the whole of the works, the Contractor shall deemed to have undertaken to complete with
due expedition any outstanding work in that part of the Permanent Works within the first thirty (30)
days of the Defects Liability Period.

The Failure to include a list of deficiencies or incomplete work does not alter the responsibility of the
contractor to complete all work in accordance with the Contract Documents pursuant to Clause 48.4

Nashaat Nosshy 31/01/2013


ALUNILE BY DATE

Ahmed Salah BY 31/01/2013


MZECH

Frank Konings 31/01/2013


SODIC BY DATE
Form No: ALUNILE-006
No of Pages:1 of 1
Attachments: None
TAKING OVER CERTIFICATE SECTION OF Original to: SODIC
SECTIONS OR PARTS OF THE WORKS ALUNILE
Copies to: MZECH
Allegria Project - Phase (2) DESIGN CONSULTANT : MZECH
Km 38, Alexandria Road, Sheikh Zaid City CS CONSULTANT : MZECH
CLIENT : SODIC

Contract No.: PK (AL-04-CC-41)


Supply & Installation of Aluminum Works
Contractor: Alu-Nile- Aluminum works

This document is being issued to certify that the designated Sections of the Works as indicated below
has been reviewed and found substantially completed pursuant to Clause 48.2 and 48.3

Villas : Zone: E

E002, E004, E005, E006, E008, E009, E010, E011, E012, E015, E017, E019, E021, E024, E025, E026, E027,
E028, E029, E030, E032, E036, E037, E038, E041, E043, E045, E047, E048, E049 (Total: 30 Villas)

Notes:
a) Taking Over Certificate date for the above mentioned parts of the works is: 31 January 2013
b) In the
Parts event
of the of different
Permanent Defects
Works, the Liability
expirationPeriods
of thehaving become
Defects Liabilityapplicable
Period in to thecase
such different Sections
be deemed to or
mean
the
the expiration
expiration latest
of the of suchofperiods.
latest such periods.

Upon the issue of a Taking Over Certificate in respect of Part of the Permanent Works before completion
of the whole of the works, the Contractor shall deemed to have undertaken to complete with
due expedition any outstanding work in that part of the Permanent Works within the first thirty (30)
days of the Defects Liability Period.

The Failure to include a list of deficiencies or incomplete work does not alter the responsibility of the
contractor to complete all work in accordance with the Contract Documents pursuant to Clause 48.4

Nashaat Nosshy 31/01/2013


ALUNILE BY DATE

Ahmed Salah BY 31/01/2013


MZECH

Frank Konings 31/01/2013


SODIC BY DATE
Form No: ALUNILE-007
No of Pages:1 of 1
Attachments: None
TAKING OVER CERTIFICATE SECTION OF Original to: SODIC
SECTIONS OR PARTS OF THE WORKS ALUNILE
Copies to: MZECH
Allegria Project - Phase (2) DESIGN CONSULTANT : MZECH
Km 38, Alexandria Road, Sheikh Zaid City CS CONSULTANT : MZECH
CLIENT : SODIC

Contract No.: PK (AL-04-CC-41)


Supply & Installation of Aluminum Works
Contractor: Alu-Nile- Aluminum works

This document is being issued to certify that the designated Sections of the Works as indicated below
has been reviewed and found substantially completed pursuant to Clause 48.2 and 48.3

Villas : Zone: E
E050, E051, E052, E053, E055, E057, E058, E059, E060, E061, E062, E063, E064, E066, E067, E068, E071,
E072, E073, E074, E075, E078, E079, E080, E084, E085, E086, E087, E088, E089, E090, E091 (Total: 32
Villas)
Notes:
a) Taking Over Certificate date for the above mentioned parts of the works is: 31 January 2013
b) In the
Parts event
of the of different
Permanent Defects
Works, the Liability
expirationPeriods
of thehaving become
Defects Liabilityapplicable
Period in to thecase
such different Sections
be deemed to or
mean
the
the expiration
expiration latest
of the of suchofperiods.
latest such periods.

Upon the issue of a Taking Over Certificate in respect of Part of the Permanent Works before completion
of the whole of the works, the Contractor shall deemed to have undertaken to complete with
due expedition any outstanding work in that part of the Permanent Works within the first thirty (30)
days of the Defects Liability Period.

The Failure to include a list of deficiencies or incomplete work does not alter the responsibility of the
contractor to complete all work in accordance with the Contract Documents pursuant to Clause 48.4

Nashaat Nosshy 31/01/2013


ALUNILE BY DATE

Ahmed Salah BY 31/01/2013


MZECH

Frank Konings 31/01/2013


SODIC BY DATE
Form No: ALUNILE-008
No of Pages:1 of 1
Attachments: None
TAKING OVER CERTIFICATE SECTION OF Original to: SODIC
SECTIONS OR PARTS OF THE WORKS ALUNILE
Copies to: MZECH
Allegria Project - Phase (2) DESIGN CONSULTANT : MZECH
Km 38, Alexandria Road, Sheikh Zaid City CS CONSULTANT : MZECH
CLIENT : SODIC

Contract No.: PK (AL-04-CC-41)


Supply & Installation of Aluminum Works
Contractor: Alu-Nile- Aluminum works

This document is being issued to certify that the designated Sections of the Works as indicated below
has been reviewed and found substantially completed pursuant to Clause 48.2 and 48.3

Villas : Zone: G
G001, G002, G003, G004, G005, G006, G007, G008, G009, G010, G011, G012, G013, G014, G015, G016,
G017, G018, G019, G020, G021, G022, G023, G024, G025, G026, G029, G030, G034, G035, G036, G037,
G040, G042, G043, G044, G045, G046 (Total: 38 Villas)
Notes:
a) Taking Over Certificate date for the above mentioned parts of the works is: 31 January 2013
b) In the
Parts event
of the of different
Permanent Defects
Works, the Liability
expirationPeriods
of thehaving become
Defects Liabilityapplicable
Period in to thecase
such different Sections
be deemed to or
mean
the
the expiration
expiration latest
of the of suchofperiods.
latest such periods.

Upon the issue of a Taking Over Certificate in respect of Part of the Permanent Works before completion
of the whole of the works, the Contractor shall deemed to have undertaken to complete with
due expedition any outstanding work in that part of the Permanent Works within the first thirty (30)
days of the Defects Liability Period.

The Failure to include a list of deficiencies or incomplete work does not alter the responsibility of the
contractor to complete all work in accordance with the Contract Documents pursuant to Clause 48.4

Nashaat Nosshy 31/01/2013


ALUNILE BY DATE

Ahmed Salah BY 31/01/2013


MZECH

Frank Konings 31/01/2013


SODIC BY DATE
Form No: ALUNILE-009
No of Pages:1 of 1
Attachments: None
TAKING OVER CERTIFICATE SECTION OF Original to: SODIC
SECTIONS OR PARTS OF THE WORKS ALUNILE
Copies to: MZECH
Allegria Project - Phase (2) DESIGN CONSULTANT : MZECH
Km 38, Alexandria Road, Sheikh Zaid City CS CONSULTANT : MZECH
CLIENT : SODIC

Contract No.: PK (AL-04-CC-41)


Supply & Installation of Aluminum Works
Contractor: Alu-Nile- Aluminum works

This document is being issued to certify that the designated Sections of the Works as indicated below
has been reviewed and found substantially completed pursuant to Clause 48.2 and 48.3

Villas : Zone: G
G047, G048, G049, G051, G052, G053, G054, G056, G057, G058, G059, G060, G062, G063, G064, G067,
G072, G073, G074, G075, G076, G078, G079, G080, G082, G083, G084, G086, G087, G090, G091, G092,
G093, G094, G097, G098, G101, G102, G103, G106, G107 (Total: 41 Villas)
Notes:
a) Taking Over Certificate date for the above mentioned parts of the works is: 31 January 2013
b) In the
Parts event
of the of different
Permanent Defects
Works, the Liability
expirationPeriods
of thehaving become
Defects Liabilityapplicable
Period in to thecase
such different Sections
be deemed to or
mean
the
the expiration
expiration latest
of the of suchofperiods.
latest such periods.

Upon the issue of a Taking Over Certificate in respect of Part of the Permanent Works before completion
of the whole of the works, the Contractor shall deemed to have undertaken to complete with
due expedition any outstanding work in that part of the Permanent Works within the first thirty (30)
days of the Defects Liability Period.

The Failure to include a list of deficiencies or incomplete work does not alter the responsibility of the
contractor to complete all work in accordance with the Contract Documents pursuant to Clause 48.4

Nashaat Nosshy 31/01/2013


ALUNILE BY DATE

Ahmed Salah BY 31/01/2013


MZECH

Frank Konings 31/01/2013


SODIC BY DATE
Sn. TOC No. Date Zone

1 1 ### D

2 2 31-Dec E

3 3 31-Dec G

4 4 31-Jan D

5 5 31-Jan D

6 6 31-Jan E

7 7 31-Jan E

8 8 31-Jan G

9 9 31-Jan G

10
11
12
13
14
15
16
17
18
19
20
Number
villas ID
of villas
D004, D008, D017, D018, D019, D020, D021, D022, D023,
D023Y, D083, D094, D097, D099, D102, D103, D121, D122, 24
D123, D124, D125, D126, D127, D127Y
E014, E016, E018, E020, E022, E023, E031, E046, E054, E056,
12
E069, E070
G027, G055, G032, G065 4
D001, D003, D005, D007, D009, D011, D012, D015, D016,
D024, D025, D026, D027, D028, D029, D030, D031, D033, 25 40
D038, D043, D046, D050, D051, D052, D053

D054, D055, D059, D060, D064, D065, D066, D067, D068,


D069, D074, D076, D077, D089, D093, D095, D096, D098,
30
D100, D101, D104, D106, D107, D108, D109, D110, D118,
D119, D129, D130

E002, E004, E005, E006, E008, E009, E010, E011, E012, E015,
E017, E019, E021, E024, E025, E026, E027, E028, E029, E030, 30 196
E032, E036, E037, E038, E041, E043, E045, E047, E048, E049

E050, E051, E052, E053, E055, E057, E058, E059, E060, E061,
E062, E063, E064, E066, E067, E068, E071, E072, E073, E074,
32
E075, E078, E079, E080, E084, E085, E086, E087, E088, E089,
E090, E091

G001, G002, G003, G004, G005, G006, G007, G008, G009,


G010, G011, G012, G013, G014, G015, G016, G017, G018,
G019, G020, G021, G022, G023, G024, G025, G026, G029, 38
G030, G034, G035, G036, G037, G040, G042, G043, G044,
G045, G046

G047, G048, G049, G051, G052, G053, G054, G056, G057,


G058, G059, G060, G062, G063, G064, G067, G072, G073,
G074, G075, G076, G078, G079, G080, G082, G083, G084, 41
G086, G087, G090, G091, G092, G093, G094, G097, G098,
G101, G102, G103, G106, G107

236
236

You might also like