Jawa 9&10 Coal Fired Steam Power Plant_Design Review Comment Sheet
From : DHI Document Controller
To : IRT Mr. Salam Syah Comment Sheet Document No : J910-UC07-P0ZEN-100002_CS
Cc : TEPSCO Mr. Kubota Hiroshi
Dwg Title : PLOT PLAN
Dwg No : J910-UC07-P0ZEN-100002
Purpose : FC
Review Category
A = Approved
B = Approved with comments, forward final document B
C = Not Approved
I = Accepted for reference (For information only)

No. Rev. Sheet/ Page/ Sect. O/E Comments Consortium Response Status

Please complete a few details No. 18 in description is blank. If more item is added these kind of
1 A 1 of 1 Closed
number shall be filled.
For safety reason, please consider to re-locate H2 plant not beside the aux boiler H2 plant do not need to be relocated as it is already protected by
2 A 1 of 1 Closed
fence at about 5 m distance around H2 plant.
Please draw the pipeline supply direction to/ from LFO truck unloading (79) adn LFO In this stage pipe line can not be indicated. Separate piping
3 A 1 of 1 Closed
Storage tank (72). arrangement draiwng shall be submitted as per MDR.
Please draw the pipeline supply direction and the steel structure that support the line In this stage pipe line can not be indicated. Separate piping
4 A 1 of 1 Closed
to Unit/ Boiler house. arrangement draiwng shall be submitted as per MDR.
Please draw the pipeline supply direction from/ to LFO truck unloading (79) , LFO In this stage pipe line can not be indicated. Separate piping
5 A 1 of 1 Closed
Storage tank (72) and to Boiler House/ Unit. arrangement draiwng shall be submitted as per MDR.
Please draw the pipeline supply that connected to Unit/ Boiler House, Auxiliary Boiler. In this stage pipe line can not be indicated. Separate piping
6 A 1 of 1 Closed
arrangement draiwng shall be submitted as per MDR.
Please draw the pipeline supply direction and the steel structure that support the line In this stage pipe line can not be indicated. Separate piping
7 A 1 of 1 Closed
to the TurbineGeneratoe Hall/ Unit. arrangement draiwng shall be submitted as per MDR.
Please recheck and make sure this settlement basin size to fit whole plant. Please note that we have considered the size based on the water flow
8 A 1 of 1 and sea water quality. If the sizes chenge during course of Closed
engineering it will be revised and updated in the plot plan.
please draw the pipeline supply direction to the TurbineGenerator Hall/ Unit. In this stage pipe line can not be indicated. Separate piping
9 A 1 of 1 Closed
arrangement draiwng shall be submitted as per MDR.
Please draw the pipeline supply that connected to GeneratorTurbin Hall/ Unit Building. In this stage pipe line can not be indicated. Separate piping
10 A 1 of 1 Closed
arrangement draiwng shall be submitted as per MDR.
Boundary fence around for administration building iis needed. Separate fence for adminig building is not required as per contract
11 A 1 of 1 Closed
requirement.
Please draw the existing PLN building that built here . Due to the existing PLN Builiding only for temporary, we did not
12 A 1 of 1 Closed
include it in the plot plan.
please draw the PLN building that built here and line direction. Due to the existing PLN Builiding only for temporary, we did not
13 A 1 of 1 Closed
include it in the plot plan.
From ESP hopper to ash silo pressurized pipe shall be used for ash
Please explain how to transport fly ash from ESP hopper to fly ash silo.
transport.
35 B 1 of 1 In addition, please explain that in case of vacuum evacuation transfer, you can transfer Close
But in case of ash trasnport system, it is under hold because of ash
even the longest transfer distance.
pond proposal.
Please note that temporary facilities shall not be indicated on plot
plan drawing.
36 B 1 of 1 Would you indicate the temporary jetty, and access road. Close
Please refer "DHKC-TECHQ-000018(Proposal for Temporary Unloading
Jetty)" for temporary unloading jetty.
1. M.S.L is followed as per Topographic survey report. And
topographic survey report is indicated as a reference drawing list.
1. Please explain the reference used for MSL
2. Please refer below coal yard are elevatoin plan.
37 B 1 of 1 Close
- Coal stock yard area : EL. +5m
2. Please explain how to make FDL on coal yard area and elevation 10 area
- North side of power block : EL.+10m
Elevation of each area is already indicated on drawing.
p
3. Area is inidcated as a one(1) unit.
38 B 1 of 1 4. Please explain the width and length for each description 4. Detail dimenions for each building/facilities can be chekced by Close
separated Civil, Architecture drawing.

5. Jetty will be located considering the shore protection details. Will


5. Please explain how to use both side of the jetty without modify the shore protection be updated after shore protection finalisation.

39 B 1 of 1 Close
6. Please update the bathymetry to make sure will it enough for coal ship sized 6. Bathymetry data are available in the document J910-BF05-P0ZEN-
requirement after unit operated 165635 - Bathymetric Survey Report

Reason for changes was already mentioned in response sheet.


40 B 1 of 1 7. Please explain what changes made in the area and it reasons Parking, Admin building and Canteen was shifted because of second Close
gate and related raod changes.
Reason for changes was already mentioned in response sheet.
Sea water discharge was updated as per related drawing.
41 B 1 of 1 8. Please explain what changes made in the area and it reasons Close
- Sea Water Intake and Discharge overall layout (J910-YK09-P0UPC-
165572)
Reason for changes was already mentioned in response sheet.
Below draiwng was updated as per related drawing.
- Sea Water Intake and Discharge overall layout (J910-YK09-P0UPC-
165572)
- Genaral Arrangement Drawing CW Pump House & Intake Facility
(J910-UE00-P0SHA-125147)
42 B 1 of 1 9. Please explain what changes made in the area and it reasons Close
- General Arrangement - Waste Water Treatment System (J910-UE00-
P0GNB-125140)
- General Arrangement Layout Drawing - WTP (J910-UE00-P0GDF-
125136)
11. Stack and road is not changed and boiler GA(with SCR) is already
11. Please explain the relation between SCR requirement and stack , road coordinate submitted without size changes.

12. Please explain why the site/plot plant not drawn 3D to describes more clearly 12. 3D works is under going and this plot plan is extracted from 3D
43 B 1 of 1 Close
model also. And 3D model shall be submitted as per MDR Schedule
13. Please revised base the 13 comments , detail on the attached file , Please make (30%,60%,90%)
sure the document fulfilled the contract requirement 13. Noted.

10. Please explain the interface coal , fire fighting and other system with existing 10. Please note that this area for topo survey is not finalized. Location
44 B 1 of 1 Close
powerplant and route shall be fixed as per site topo survey result.
please consider clause 4.8.3.7.15. such as The jetty shall be placed to have a depth Noted
45 B 1 of 1 alongside the jetty of at least 17 m under MSL and to ensure the required turning Close
basin.
Jetty will be located considering the shore protection details. Will be
the jetty is intersect with shore protection please confirm how come the pile to be
46 B 1 of 1 updated after shore protection finalisation. Close
driven

on the clause 4.8.3.7.7 mentioned to Avoidance of interaction between the cooling Intake location and coal jetty are marked on the plot plan. There will
47 B 1 of 1 water intake and the shipping, please confirm what structure will properly match with not be interaction with the ship (jetty) with the intake. Close
this clause
The evacuation shall be through the plant road. The requirement of
as per first meeting about site plan on 23/10/2019 owner-consortium consider : For
bridge on the outfall channel has not been envisaged.
HAZOP study if during emergency situation let say burning, fire truck from outside
48 B 1 of 1 should be have quick access to coal area or evacuation from project to outside . Close
Should to provided bridge and approached road on outfall area to surround such as to
coal area, main entrance road etc

Road shall be deigned along with contract requirement.


its because not indicate width of the road access please to consider clause 4.8.3.6 such In note 6, it was mentioned for only specified road between stack and
as : The main entrance roads to the Power Station and looped road to the Power Block ESP.
49 B 1 of 1 shall have a minimum of 6.50m wide of pavement. Road shall have minimum 1.00m Close
shoulder on both sides. Sidewalk shall be provided along the road with concrete
paving block. The other access roads shall have 5.00m wide of pavement.

Please refer Layout of Laydown Area (J910-YK08-P0UZE-168002) for


construcation temporary facilities plan.
- batching plant
- storage area of steel structure
Please explain the separately the following items: - temporary assembling area for the boiler structure
- batching plant Coal unloading Jetty with access road is already indicated. For
- storage area of steel structure Temporary jetty location, please refer above response no.7.
- temporary assembling area for the boiler structure - the location of the unloading jetty and acces road.
50 B 1 of 1 Close
- the location of the unloading jetty and acces road. Please refer separate boiler GA draiwng for each fan location.
- location of FD Fan - location of FD Fan
- location of Mill area - location of Mill area
- how to taransport fly ash from ESP hopper to fly ash silo Pipe rack and sleeper for fly ash is already indicated. Detai pipe
arrangment below the ESP area shall be submitted separately as per
MDR.
- how to taransport fly ash from ESP hopper to fly ash silo
Note 4 is revised.
This drawing is conceptual drawing for layout. So for further detail
so regarding note no 4, this drawing will be approved after size,location of building etc engineering and construction work, drawing need to be approved in
51 B 1 of 1 Close
already decided? earlier stage.
Please note that this drawing is updated whenever related drawing is
updated.
52 B 1 of 1 1.a relation between level BM IP 02 mentioned on the contract and EL M.S.L is followed as per Topographic survey report. Close
53 B 1 of 1 please add the coordinate to the major equipment Coordinate is already indicated on plot plan drawing. Close
Jetty will be located considering the shore protection details. Will be
54 B 1 of 1 Please confirm the jetty design clash to shore protection. Close
updated after shore protection finalisation.
Noted. Note 5 is revised. But please note that this drawing is updated
55 B 1 of 1 this drawing should be approved drawing not for preliminary only Close
whenever related design/drawing is changed.
Please note that this area for topo survey is not finalized. Location of
for next Hazop study please consider to study these new connections to existing Power
56 B 1 of 1 building/faciliites shall be finalized as per topo survey and Hazop Close
Plant too.
study alos shall be carried out if required.
for FF line connection to existing power plant please consider in which side the Please note that this area for topo survey is not finalized. Location
57 B 1 of 1 Close
isolating valve/ cross over valve will be installed. and route shall be fixed as per site topo survey result.
- Ammonia storage and handling for SCR is updated.
- Please add the location of SCR
58 B 1 of 1 - this number shall be utilized if additional equipment number is Close
- What is the blank number (no. 18 and 59) refer to?
required.
The correct name should be : Hazardous and Toxic Waste Temporary Storage, not Noted. This is storage building not disposal from this building.
59 B 1 of 1 disposal. Close
We can't dispose any haz. waste on site.
Please check and explain that the angle of access road from/to public road to/from fly EPC is working on the road layout considering the new external ash
60 B 1 of 1 ash silo looks so huge, because the difference of elevation will be more than 10m. handling facilities approach road. It will be updated after finalisation of Close
(Plant area: EL+5m; Public Road around EL+15m) the external ash handling facilities.
61 B 1 of 1 There should be 2 UAT each unit Noted. Close
62 B 1 of 1 add Connusa logo Noted. Close
Consortium understand it means laboratory.
What about the other testing, i.e coal testing, ash testing, and other physical testing.
63 B 1 of 1 Laboratory room location is not fixed and shall be updated along with Close
Where is it be located?
each buildng design.
1. Fire Water Pump house is combined with General Service water
pump house. So fire water pump shall be located In general service
water pump house.
2. Location of Demi water Tank (no.24), Service & Fire Water Tank
(no.25), Potable Water storage tank (no.26) is revised to avoid
iterference with Coal conveyor gallery.
64 N/A N/A Addiontal Changes 3. Angle of Sea Water Aeration Basin is revised as per detail design N/A
and outfall channel also revised along with aeration basin.
4. Oxidation Air Blower Shelter is updated and location is revised.
5. Ammonia Storage and Handling facilities for SCR is updated.
7. CHS Jetty LEB (No.59) is added between coal stock yard and jetty.
8. H2 plant is relocated along with plot plan.
#96 NH3 supply equipment requires Water Curtain wastewater (ammonia water) Same as Site plan
treatment equipment that operates when ammonia gas leaks, so please add this Water spray system will be installed in the ammonia storage area.
65 C 1 of 1 installation space Please refer to the drawing of “ASSEMBLY DWG FOR WATER SPRAY Close
DEVICE (J910-YK10-P0HSJ-540006)” to be submitted as per MDR

EPC should consider to further HAZOP Study on this 96 equipment against wind blows Same as Site plan
direction ! HAZOP Study shall be submitted as per MDR
C 1 of 1
Please envolve it in new updated HAZOP Study.! - Basic Desgin Hazop Report (J910-BV02-P0LF-110002)
- Detail Design Hazop Report (J910-BV02-P0LF-110003)
Regrading HAZOP Study schedule, Please refer DHKC-Email-000359 by
Aconex.
Site Plan/ Plot Plan shall be updated as per HAZOP study if required.
66 Open
Schedule of HAZOP sutdy shall be followed as per below;
EPC should inform the schedule of next HAZOP study that to be conducted al team - Early of May : DHI BOP HAZOP Study.
D 2
together ! - End of May : HK BOP HAZOP Study.
- Ealry of June : Review Result shall be submitted.
- Middle of June : Review with IRT.
- Middle of Aug : Boiler, Turbine HAZOP Sutdy.
- Middle of Sep : HAZOP Sutdy Report shall be submitted.
EPC should consider to this limited area for : Same as Site Plan
1. entrance/ exit procedure for outside people/ visitors/ local authority officers/ local 1. This kind of procedure will be detailed in specific document and
government officers, etc.! required separate discussion between owner and consortium.
2. vehicles parking arrangement ! Consortium will discuss with IRT further for entrance/exit procedure.
3. arrangement of all these building in this area for make it easy to acces each other ! 2 & 3 & 4. Parking lot, Canteen, Admin building shall be re-arranged
4. escape route / escape ways/ muster point / emergency escape procedure for this considering inside/ourside access plan and owner's access requirment.
office area ! Owner requested "The site plan / plot plan shall be reviewed and
5. design green open space around this office arrangement ! assessed by Independent party (for example like by DNV or Lloyd's
6. considering the arrangement against wind blows direction ! Register / and certified Person to do Risk and Hazard assessment,
C 1 of 1 7. additional fence to make sure no access for people/ visitor to outfall structure ! Architectural Engineer shall also be involved, in the work shop".
67 Consrotium will review owner's request and revert separately. Open
5. Noted.
6. EPC consortium has located buildings considering wind direction
and functional requirements.
7. fence for outfall is updated on plot plan.

EPC to finalized the plan for workshop "Risk and Hazard Assessment" to closed this Risk assessment is in progress in parallel, and site plan / plot plan will
D 2
open items be revised accordingly if necessary.
EPC should consider for covering this along outfall line! Same as Site Plan
The outfall is designed as per contract requirements. No covering has
been envisaged. However, fence is considered for safety and to avoid
access to outfall structure.
68 C 1 of 1 Close
Owner concern corrosion(near building,structure, etc.) from outfall.
Consortium make sure building and structures already consider
painting to protect corrosion.

EPC should consider to this limited area for : Same as above no.67

1. arrangement of all these building in this area for make it easy to acces each other !
69 C 1 of 1 Open
2. escape route / escape ways/ muster point / emergency escape procedure for this
central building area !
3. design green open space around this central building arrangement !
EPC should consider to this limited area for : Same as above no.67

1. arrangement of all these building in this area for make it easy to acces each other !
70 C 1 of 1 Open
2. escape route / escape ways/ muster point / emergency escape procedure for this
BOP/ auxiliary area !
3. design green open space around this BOP/ auxiliary arrangement !
EPC should consider for this 72-73 location and prepare better access way/ emergency Same as Site Plan
access to this 72-73 facility building incase any trouble occur, and also how to Approach road or local paved access from main road shall be
71 C 1 of 1 evacuate / localize at the time! developed based on final pump building and oil dyke design . Close

Or any better location option ?

posibility to build acces for ash truck pasing the second gate? Same as Site Plan
72 C 1 of 1 Access road for ash truck shall be updated considering sufficient Close
slope.
1. Please confirm in this document also , the Plot Plan & Site Plan already considered Data has been considered in the respective design criteria and design
73 C 1 of 1 Close
2019 rainy data and other extreme weather condition calculations.
8.a. Please explain what changes made in the area and it reasons in this response a. Additional changes will indicated in comment sheet.
sheet also b. Noted. Revision sign shall be indicated as a different color.
74 C 1 of 1 Close
8b. Please remark the revision sign in next document with not black color for better
understanding
9. Please explain what changes made in the area and it reasons in this response sheet Noted.
75 C 1 of 1 Close
also
10a. Please explain what changes made in the area and it reasons in this response a. Additional changes will indicated in comment sheet.
sheet also b. for shore line protection plan below drawing is referd.
76 C 1 of 1 Close
10b. Please explain the shore protection planed to use in this document also due to - SOIL IMPROVEMENT FOR RECLAIMED AREA_PLAN (J910-XB02-
J910-BN02-P0UZP-165627 not submitted yet P0ZEN-160002)
Note 4 is revised.
This drawing is conceptual drawing for layout. So for further detail
so regarding note no 4, this drawing will be approved after size,location of building etc engineering and construction work, drawing need to be approved in
51 B 1 of 1 Close
already decided? earlier stage.
Please note that this drawing is updated whenever related drawing is
updated.
52 B 1 of 1 1.a relation between level BM IP 02 mentioned on the contract and EL M.S.L is followed as per Topographic survey report. Close
53 B 1 of 1 please add the coordinate to the major equipment Coordinate is already indicated on plot plan drawing. Close
Jetty will be located considering the shore protection details. Will be
54 B 1 of 1 Please confirm the jetty design clash to shore protection. Close
updated after shore protection finalisation.
Noted. Note 5 is revised. But please note that this drawing is updated
55 B 1 of 1 this drawing should be approved drawing not for preliminary only Close
whenever related design/drawing is changed.
Please note that this area for topo survey is not finalized. Location of
for next Hazop study please consider to study these new connections to existing Power
56 B 1 of 1 building/faciliites shall be finalized as per topo survey and Hazop Close
Plant too.
study alos shall be carried out if required.
for FF line connection to existing power plant please consider in which side the Please note that this area for topo survey is not finalized. Location
57 B 1 of 1 Close
isolating valve/ cross over valve will be installed. and route shall be fixed as per site topo survey result.
- Ammonia storage and handling for SCR is updated.
- Please add the location of SCR
58 B 1 of 1 - this number shall be utilized if additional equipment number is Close
- What is the blank number (no. 18 and 59) refer to?
required.
The correct name should be : Hazardous and Toxic Waste Temporary Storage, not Noted. This is storage building not disposal from this building.
59 B 1 of 1 disposal. Close
We can't dispose any haz. waste on site.
Please check and explain that the angle of access road from/to public road to/from fly EPC is working on the road layout considering the new external ash
60 B 1 of 1 ash silo looks so huge, because the difference of elevation will be more than 10m. handling facilities approach road. It will be updated after finalisation of Close
(Plant area: EL+5m; Public Road around EL+15m) the external ash handling facilities.
61 B 1 of 1 There should be 2 UAT each unit Noted. Close
62 B 1 of 1 add Connusa logo Noted. Close
Consortium understand it means laboratory.
What about the other testing, i.e coal testing, ash testing, and other physical testing.
63 B 1 of 1 Laboratory room location is not fixed and shall be updated along with Close
Where is it be located?
each buildng design.
1. Fire Water Pump house is combined with General Service water
pump house. So fire water pump shall be located In general service
water pump house.
2. Location of Demi water Tank (no.24), Service & Fire Water Tank
(no.25), Potable Water storage tank (no.26) is revised to avoid
iterference with Coal conveyor gallery.
64 N/A N/A Addiontal Changes 3. Angle of Sea Water Aeration Basin is revised as per detail design N/A
and outfall channel also revised along with aeration basin.
4. Oxidation Air Blower Shelter is updated and location is revised.
5. Ammonia Storage and Handling facilities for SCR is updated.
7. CHS Jetty LEB (No.59) is added between coal stock yard and jetty.
8. H2 plant is relocated along with plot plan.
7. Please confirm the circle area for 2 (two) Number of Demin water and Potable Same as Site Plan
water tank Number of tanks considered as per the contract requirement. Refer
Water Balance Diagram (J910-XG07-P0GHE-125001)
82 C 1 of 1 Close
EPC has submitted deviation sheet to discuss separately for Owner's
consideration.
Plot Plan shall be updated as per final conclusion.
11. Please explain the area (m3) is for 2 or 1 boiler 11. area is makred as a 1 unit.
11b. Makred area include from mill bay.
83 C 1 of 1 Close
11b. Please explain is the area just for main boiler or include its auxiliaries such as Fan,
pulverizer , Pyrite silo
General Comment : Noted.
84 C 1 of 1 Close
Please consider all of comment in the site plan drawing.
Electrical and civil design (Transmission line between Main transformer and SS) Same as site plan
All the requested documents , calculation & layouts such as sectional
Please show the cross section between the turbine area and the switchyard. drawings, Sag & Tension calculation etc. will be part of Switchyard
85 C 1 of 1 Please calculate the sag of the transmission line and safety distance documentation. It will be submitted to owner for their review & Close
between the line and the land with the height of the transmission towers. approval separately.
Please calculate the necessary gradient of the slope. Consortium will check tower location to raise up the transmission line.

Please check the actual layout of consolidated room. Please make sure the layout of Same as site plan
this eksisting building, I am affraid this building actual layout is located too north, so Main Access road is already indicated. And local paved access shall be
there is no space for building no. 21 (Switchyard Control Building). And if move the updated as per building and substation design progress.
86 C 1 of 1 switchyard control building to the north side, it will be reduce switchyard land area. Consortium will re-check location of sub station & control building Close
considering existing site office location and condition.
If the sub station & control buildng have interference with existing
site office, consortium will re-arrange the building location.
Please explain the philosophy the distance between fire water pump house and the Same as site plan
booster pump house (building no 29 and 88). Fire water pumps in no.29 provide water from Fire water storage tank
87 C 1 of 1 to fire hydrant network. Close
Fire water booster pumps in no.88 provide water from hydrant
network to higher point in boiler.
1. Mobile equipment garage(No.87) is shited 7m to secure
tempororay access road to EL.10M area.
2. Fire Water Booster Pumphouse (No.88) is shifted 5m considering
88 N/A N/A Additional changes underground EDB plan. N/A
3. Road between ESP and boiler is shifted 1m consideirng boiler
support location.

"LFO TRUK UNLOADING AREA" is different from "J910-UE00-P0EGC-125182 Fuel Oil Noted. LFO truck unloading Area shall be updated along with "J910-
89 D 1 Close
Area General Arrangement Drawing". please confirm. UE00-P0EGC-125182 Fuel Oil Area General Arrangement Drawing"
It is impossible to know which is frequency and which is velocity as this is printed in
90 D 1 Noted. Close
monochrome. Please draft by different stile or width of the line.
91 D 1 Correct to style. Noted. Close
Please provide the design this area which consider the traffic safety requirement, It shall be reviewd within Aug, 2021.
92 D 1 Open
velocity of vehicle, road standard design regulation and so on.
93 D 1 Please provide access road / access way to building No. 17, No. 88 & No.39 Noted. Access road shall be indicated. Close
94 D 1 This building should be No. 81 (Canteen). Noted. Close
95 D 1 What's the correct name for this building. Noted. Numbering and desciption shall be corrected. Close
96 D 1 Please provide access road / access way to building No. 77. Noted. Access road shall be indicated. Close
97 D 1 Please indicate drawing for building No. 85 Noted. Numbering and desciption shall be corrected. Close
Detail information for road, it shall be indicated on road & paving
drawing.
98 D 1 Please provide the road radius for this area. Open
EPC shall provide separate drawing to show heavy vehicle accessilbity.
Drawing No. shall be mentioned later.
99 D 1 Please provide access road to building No. 68. Noted. Access road shall be indicated. Close
100 D 1 Please provide the barrier for this area for safety matter. Safety fencing will be provided. Close
Noted.
EPC should indicate the location area and correct number of:
1) Foam storage & pump is indicated along with "Fuel oil Area
1) Foam System (foam storage & pumps) near LFO storage tank (72)
D 1 general arrangement drawing."
101 2) Demin water storage tank to be 2 tanks (24) To be closed
2) 2 demin water staorge tank will be indicated.
3) Potable storage tank to be 2 tanks (26)
3) 2 potable storage tank will be indicated.
E 1 for item no 1) foam system is not yet described ! Foam system is added and indicated.
fixed location for laboratory will be informed later
D 1 EPC should confirm the fixed location for laboratory. EPC will submit final location and laboratory drawing within June.

102 To be closed
EPC should finalized soon for the fixed location of this laboratory,and many documents Laboratory is added
E 1 need to be revised based on this for finalizing (fire protection, risk assesment FERA,
WTP or WWTP, potable water distribution etc.) !
Regrading HAZOP Study schedule, Please refer DHKC-Email-000359 by
Aconex.
Site Plan/ Plot Plan shall be updated as per HAZOP study if required.
Schedule of HAZOP sutdy shall be followed as per below;
General comment : - Early of May : DHI BOP HAZOP Study.
103 D 1 Open
As per clause 4.2.2.11.2 EPC to provide safety fence surrounding hazardous plant area. - End of May : HK BOP HAZOP Study.
- Ealry of June : Review Result shall be submitted.
- Middle of June : Review with IRT.
- Middle of Aug : Boiler, Turbine HAZOP Sutdy.
- Middle of Sep : HAZOP Sutdy Report shall be submitted.
Please don't isolate Control Building (21) from AIS (19) with fence, Control Building
104 D 1 Noted Will be revised if PLN agrees. Open
should be in the same fence with AIS (19).
- Storm water settling basin and location is tentative. We will review
and finalise the number of storm water settling basin and location of
settling basin at later stage once the detail design of all systems and
structures are finalised. It will be taken care in the roads and drains
Point no. 27 Storm water settling basin:
design.
Please explain the consideration from EPC:
- Coal conveyors are covered in gallery and coal spills are not
- why only 1 storm water settling basin is provided
expected. However, coal contaminated rain water in coal storage shed
105 D 1 - why locate the storm water settling basin near to the conveyor belt system. The Open
is treated in coal settling basin L52as per clarification letter on WWTP
conveyor system and transfer tower system are the area that will have potentially coal
capacity submitted.
spills. The water drainage contain leachate from coal spills should be collected and
treated in WWTP, and can't be mixed with storm water system.
Related drawing shall be indicated.
- J910-YK09-P0GUB-165604 STORM WATER DRAIN - SETTLEMENT
BASIN
Noted. Location will be shown. However, size will be mentioned later.
106 D 1 Please provide the coal settling pond layout (both in plot plan and site plan). Coal settiling pond drawing shall be indicated. Open
- J910-YK09-P0EAE-165140 COAL SETTLING POND

Collection point of hazardous waste and toxic waste will be in stored


Noted that EPC has provide Hazardous waste and toxic waste temporary storage at Hazardous waste and toxic waste storage building before transport
building. to landfill facility.
D 1
107 Please add 1 more building for collection point of domestic waste from all area before Temporary domestic waste building will be provided in separate Open
transported to the Cilegon landfill facility. building with temporary hazardous waste building.

Consortium will provide Garbage container instead of the building to


E Please draw the building !
collect the temporary domestic waste before transport to landfill
please consider to move Fire station building to near administration building or
Security building. it's more safe if explosion happen in plant, not impact to fire building There was numbering error.
108 D 1 Close
or limiting fire team to move. if out side plant, fire team will easy go to right point Fire station is already moved to near admin building.
where fire occurs.
Detail information for road, it shall be indicated on road & paving
drawing.
109 D 1 please make cross road bigger, it's will making easier for the vehicle to maneuver. Open
EPC shall provide separate drawing to show heavy vehicle accessilbity.
Drawing No. shall be mentioned later.
Detail information for road, it shall be indicated on road & paving
drawing.
110 D 1 please not make sharp on the edge off cross road Open
EPC shall provide separate drawing to show heavy vehicle accessilbity.
Drawing No. shall be mentioned later.
Access road crossing at outfall as requested by Owner, we will be
Please provide access road crossing the outfall for fire truck for emergency purpose informed later.
111 D 1 Open
asper previous discusssion

112 D 2 EPC to attach the all of the comments from Rev.A. Noted. Previous comment shall be indicated on CRS. Close
113 D 5 Please indicate this response in the drawing. Noted. Changes shall be marked as a cloud mark. Close
1. As per Ash Pond Addtion, There are some changes as per below.
But detail shall be updated while related eningeering design progress.
- Ash Disposal Blower Shelter(no.98) is added in power plant area.
2. Coal conveyor from TP 2.1 is deleted. and Coal Conveor and Trasfer
114 N/A N/A Additional changes in Rev.E drawing. N/A
tower descriptions are updated along with LAYOUT_COAL HANDLING
SYSTEM (J910-UC08-P0ECC-620001_Rev.D)
3. Main Transformer and Unit Aux Transformer outline and location is
updated. and gantry tower between transformer and road is updated.
no new recommendation EPC to finalized open items that already discuss in the
115 E 1 Noted. This drawing shall be updated continusoly to close open items. Open
engineering meeting on June 7, 2021
116 E 1 Delete mark 55. Noted and corrected. To be closed
It need to be checked in architecture drawing for CHS control &
117 E 1 make sure the coal handling area can be seen clearly from the CHS control building electrical building. To be closed
Please refer and check when the related separte drawing is submitted.
1. below building/facilties location with layout is updated as per detail
design.
- General Service Water and Fire Water Pump House (no.29)
- Demi. /Service&fire/ Potable Water tanks (no.25, 26, 27)
- Water Treatment Plant (no.22)
- Waste Water Treatment Plant (no.28)
129 N/A N/A Additional changes in Rev.1 drawing. N/A
- Fuel oil area (no.72)
2. Access road for Coling water pump house(no.8) and intake structure
is revised.
3. Access paving for boiler is added.
4. Coal Shed (no.52) is extetended along with LAYOUT_COAL
HANDLING SYSTEM(J910-UC08-P0ECC-620001)
3. Please explain the Control , electrical and storage building to Operate SCR unit 9 Same as site plan
and 10 3. Control and electrical is located in CCB.
3b. Consortium will check possiblity to relocated to unit 9 area.
C 1 of 1
3b. Please explain why not located the SCR system at boiler unit 9 ( North side) due to - When the ash pond proposal is finalized, SCR relocation shall be
77 Close
boiler unit 10 closer to public road and administration building updated because ash silo could be removed as per ash pond
proposal.
EPC to finalized the position of SCR and consider the Owner comment to put in the
D 3 Noted. NH3 for SCR shall be moved to north side.
Boiler Unit 9 (North side)
2. Please change the container type to the suitable Aux Boiler Control House building Same as Site Plan
As Aux boiler will operate only during plant startup, we have
considered contained type building to save schedule time.
Consortium check type of Aux Boiler building regarding 30 years
operation and maintenance point of view.
As Aux boiler will operate only during plant startup, we have
considered contained type building as below advantage:
- Easy to transport : Using containers are easy to handle and can be
moved from one position to another without dismantling interior
equipment.
C 1 of 1
- Structure stability : Containers are also virtually indestructible. These
containers are designed to bear heavy loads, withstand harsh climatic
78 conditions and extremely safe for natural disaster-prone areas. Close
- Save construction schedule: Containerized electrical rooms fully
equipped at the manufacturers premises with a wide variety of control
gear, distribution equipment and PLC equipment. The interconnection
of this equipment is completed prior to testing Units are subjected to
full functional tests prior to dispatch and can be pre-commissioned
and pre-configured before dispatch.

EPC to provide the permanent building for Aux Boiler Control and Aux Boiler (Building
D 4 no. 15 and 16) regarding to the life time 30 years for operation and maintenance Agreed with Owner requested, EPC will provide permanent Building.
purpose.
EPC shall change the Aux Boiler description no 16 on page 1 (EPC response previously Noted. Description is changed to aux boiler building.
0 12
agreed to provide Permanent building and not container type) Layout will be updated as per engineering progress.
4a. Please explain why this access road and distance between CCB and Boiler unit 9 a. CCB is located considering SWGR room in TG buidling so it is not
and 10 different (not symmetries) ? symmetric.

79 C 1 of 1 Close
4b. Please explain the difference between Boiler unit 9 and 10 base on this lay out and B. difference between boiler unit 9 and 10 is connection with bottom
its reason ash silo. Bottom ash silo location need to be consider truck access.

5. Please explain why the fire water pump house description deleted 5. Fire water pump is located in general service water pump house
80 C 1 of 1 Close
(no.29)
6. Please explain the philosophy for numbering the description due some equipment Numereing is considered similar system or area.
81 C 1 of 1 such as no 73,74 which equipment with adjacent numbers is not in adjacent equipment Close
locations
Noted. Location will be shown. However, size will be mentioned later.
106 D 1 Please provide the coal settling pond layout (both in plot plan and site plan). Coal settiling pond drawing shall be indicated. Open
- J910-YK09-P0EAE-165140 COAL SETTLING POND

Collection point of hazardous waste and toxic waste will be in stored


Noted that EPC has provide Hazardous waste and toxic waste temporary storage at Hazardous waste and toxic waste storage building before transport
building. to landfill facility.
D 1
107 Please add 1 more building for collection point of domestic waste from all area before Temporary domestic waste building will be provided in separate Open
transported to the Cilegon landfill facility. building with temporary hazardous waste building.

Consortium will provide Garbage container instead of the building to


E Please draw the building !
collect the temporary domestic waste before transport to landfill
please consider to move Fire station building to near administration building or
Security building. it's more safe if explosion happen in plant, not impact to fire building There was numbering error.
108 D 1 Close
or limiting fire team to move. if out side plant, fire team will easy go to right point Fire station is already moved to near admin building.
where fire occurs.
Detail information for road, it shall be indicated on road & paving
drawing.
109 D 1 please make cross road bigger, it's will making easier for the vehicle to maneuver. Open
EPC shall provide separate drawing to show heavy vehicle accessilbity.
Drawing No. shall be mentioned later.
Detail information for road, it shall be indicated on road & paving
drawing.
110 D 1 please not make sharp on the edge off cross road Open
EPC shall provide separate drawing to show heavy vehicle accessilbity.
Drawing No. shall be mentioned later.
Access road crossing at outfall as requested by Owner, we will be
Please provide access road crossing the outfall for fire truck for emergency purpose informed later.
111 D 1 Open
asper previous discusssion

112 D 2 EPC to attach the all of the comments from Rev.A. Noted. Previous comment shall be indicated on CRS. Close
113 D 5 Please indicate this response in the drawing. Noted. Changes shall be marked as a cloud mark. Close
1. As per Ash Pond Addtion, There are some changes as per below.
But detail shall be updated while related eningeering design progress.
- Ash Disposal Blower Shelter(no.98) is added in power plant area.
2. Coal conveyor from TP 2.1 is deleted. and Coal Conveor and Trasfer
114 N/A N/A Additional changes in Rev.E drawing. N/A
tower descriptions are updated along with LAYOUT_COAL HANDLING
SYSTEM (J910-UC08-P0ECC-620001_Rev.D)
3. Main Transformer and Unit Aux Transformer outline and location is
updated. and gantry tower between transformer and road is updated.
no new recommendation EPC to finalized open items that already discuss in the
115 E 1 Noted. This drawing shall be updated continusoly to close open items. Open
engineering meeting on June 7, 2021
116 E 1 Delete mark 55. Noted and corrected. To be closed
It need to be checked in architecture drawing for CHS control &
117 E 1 make sure the coal handling area can be seen clearly from the CHS control building electrical building. To be closed
Please refer and check when the related separte drawing is submitted.
Noted. Hold mark is indicated and shall be released as per design
118 E 1 Please add HOLD mark in this area since the design status is not finalized yet. Open
progress.
( General Comment ) If any change happened in mech,Elect, civil and Arch Engineering
119 E 1 Noted. This drawing shall be updated as per related design. To be closed
regarding Building/equipment arrangement, Please up date this drawing accordingly
Road plan near NH3 storage area is revised considering NH3 tank
parking.
Please describe the shape of the road at the NH3 receiving point by the NH3 tank
Pipe support will be updated as per below drawing.
truck accurately.
120 E 1 - PIPING ARRANGEMENT DRAWING FOR UNIT 1 ESP AND FGD AREA To be closed
Please add the piping rack (NH3 piping, service water, N2 piping, control signal line,
(J910-XH01-P0ZEN-131010)
air piping, etc.) between the NH3 system and the SCR / boiler.
- PIPING ARRANGEMENT DRAWING FOR UNIT 2 ESP AND FGD AREA
(J910-XH01-P0ZEN-131020)
Please add HOLD mark for fencing area since the status is waiting for finalized decision
121 E 1 Noted. This drawing shall be updated as per related design. Open
from PLN
122 E 1 Please add HOLD mark for fencing this area since the status is to be confirmed to PLN Noted. This drawing shall be updated as per related design. Open
Ash disposal shelter is added as per ash landfill facility.
Consortium understand Ash landfill facility is different contract. So it
123 E 15 Please submit soon the document related to item no 1) Ash disposal blower shelter ! shall be submitted separately as per MDR schedule for ash landfill To be closed
facility.

1. Access road for main transformer is indicated.


2. NH3 Storage & handing SCR (no.96) layout is updated as per GA
drawing.
124 N/A N/A Additional changes in Rev.0 drawing. 3. FGD & ESP Contol and Electrical building (no. 39) coordinate is N/A
revised as per detail design.
4. N2 & CO2 bottle storage shelter(no.75) location is revised as per
laboratory location.
If any change happened of engineering regarding changes in the position of the
Noted. Site plan shall be updated consistently based on related design
125 0 1 building, the addition of buildings ,equipment and landscaping, etc, including the To be closed
progress.
Administration Building, please update this Site plan drawing accordingly.
126 0 1 Water intake barrier structure is required here! Water Intake barrier is updated. To be closed
Foam tanks are already indicated near foam pump shed.
17 0 1 foam tanks need to be indicated here! For detail information, please refer fuel oil area - general arrangement To be Closed
drawing (J910-UE00-P0EGC-125182)
Coal Handling system from existing plant is deleted. So related access
EPC to consider the coal stock area from existing PS in GL+10m area, and access
128 0 1 conveyor is not required in GL.+10m area. To be closed
conveyor system from GL+10m to JAWA 9&10 coal handling system.
1. below building/facilties location with layout is updated as per detail
design.
- General Service Water and Fire Water Pump House (no.29)
- Demi. /Service&fire/ Potable Water tanks (no.25, 26, 27)
- Water Treatment Plant (no.22)
- Waste Water Treatment Plant (no.28)
129 N/A N/A Additional changes in Rev.1 drawing. N/A
- Fuel oil area (no.72)
2. Access road for Coling water pump house(no.8) and intake structure
is revised.
3. Access paving for boiler is added.
4. Coal Shed (no.52) is extetended along with LAYOUT_COAL
HANDLING SYSTEM(J910-UC08-P0ECC-620001)