C823-3-DOC-MAT-MEC-021 Rev.02
C823-3-DOC-MAT-MEC-021 Rev.02
MATERIAL SUBMITTAL
Project Name: Construction of Terminal Pumping Station at Doha North STW Package 3-C823/3
Project ID/Code.: PA 2020 C 009 G
Document/Drawing Title: Material Submittal for Fuel System Date Received: 20 August 2022
Submittal No.: C823-3-DOC-MAT-MEC-021 Revision No.: 01
Comments Section/
No. K&A Comment Contractor’s Response Open/Close
by: Page
In accordance with P & ID no. C823-P03-STN-IC-
3301, Vendor supplied items are tentative. Noted and comply. The
calculation for fuel tank capacity is
Based on the above that AJE/OEM has to furnish updated as per the proposed Noted and Refer
Technical /
1 KC the basis/ calculation for the selection of tanks, generator consumption and Pump the comment No.
P&ID
pumps, piping and all other items. Also selection sheet, also pump curved 1.1
Consider fuel consumption by diesel generator added on the pump section Please
(approved) during the sizing of equipment. refer to section 5
Noted. Material submittal for diesel generator is Noted and Comply. The
still not approved. If any changes during the final documents will be revised incase
Technical /
1.1 KC approval of diesel generator, OEM / AJE shall revisit any kind of changes for the
P&ID
the calculations for the selection of tanks, pumps, generator model/fuel
piping and all other items. consumption
Technical AJE / OEM has to furnish the technical data sheet Noted and comply. Please refer to
7 KC Closed
data sheet for the materials instead of catalogue. section 5 attached datasheet
Include the following details in the schedule: Gate valve (Ball Valve) is available
and NRV is added.
• Gate valve & NRV as per compliance
Material Noted and Comply. Open and refer the
9 KC statement and project P& ID.
schedule comment no. 9.1
• Quantity of items Added.
• Flexible hoses Please refer to section 5
AJE/OEM has to provide list of special tools and Special tools will be provided in Open and Refer
19 KC General tackles required for operation and maintenance of the O&M manual and will be the comment no.
fuel system. submitted separately 16.1
Name plates Noted. Name plates for the Open and Refer
Name plates shall be as specified in QCS-2014,
21 KC and Data materials will be supplied as per the comment no.
Section 09, Part -01 for all materials.
Plates the manufacturer standard. 21.1
Noted; Shall be
reviewed when
Fuel Oil Noted and will be updated in the
Cable and wire sizes indicated shall be standardized details are
37 SM Schematic shop drawings submission, will be
to one unit (preferably metric units) submitted. Refer
Drg submitted separately for approval
to Comment # 60
& 61 below
Noted; Shall be
On approval of the material submittal and the reviewed when
Fuel Oil
schematic, the Contract P&ID IC-3301 shall be Noted and will be part of the details are
38 SM Schematic
updated accordingly; besides updating the Legend shop drawing submission submitted. Refer
Drg
Sheet IC-0021 to Comment # 60
& 61 below
Noted; Shall be
Symbols used in general shall match the Contract
reviewed when
Fuel Oil drawings. Any additional legends and symbols are to
Noted and will be part of the details are
39 SM Schematic be incorporated on the Project main P&ID legend
shop drawing submission submitted. Refer
Drg sheet at a later date, once the various systems are
to Comment # 60
finalized and approved.
& 61 below
Noted; Shall be
Fuel Oil reviewed when
Schematic & Tag no. conventions shall follow the Project defined Noted and will be part of the details are
40 SM
Panel wiring norms. shop drawing submission submitted. Refer
Drg to Comment # 60
& 61 below
The wiring diagram, list of
materials for the control panel will
Noted; Shall be
be submitted along with the shop
Front view labels: Fuel Transfer Pump – delete “2” reviewed when
drawings with detailed design
Panel wiring and also instead of stating Duty/Standby, details are
41 SM layouts and schematic drawing
drawings recommend to change as Pump 1 & Pump 2, since submitted. Refer
will be submitted separately for
Pumps alternate duty each start. to Comment # 61
approval (The Control Panel
below
Customized for project operation
as per the final design)
Noted; Shall be
reviewed when
Panel wiring Power cable sizes are to be reviewed. Will 2 core Noted and will be part of the details are
42 SM/AN
drawings cable suffice for power feed? shop drawing submission submitted. Refer
to Comment # 61
below
Noted; Shall be
reviewed when
Panel wiring details are
43 SM Change BMS to PLC/SCADA Noted and Comply
drawings submitted. Refer
to Comment # 61
below
The Wiring diagram for the panel Noted; Shall be
attached in the submittal as reviewed when
Panel wiring Alternating relay circuit is missing; only the contacts sample , The final wiring diagram details are
44 SM
drawings are used! will be submitted along with the submitted. Refer
shop drawing prior to panel to Comment # 61
fabrication below
Noted; Shall be
reviewed when
Panel wiring SCADA interface potential free contacts for fuel details are
45 SM Noted and Comply
drawings filling pump to be corrected (correct the typo error). submitted. Refer
to Comment # 61
below
Interstitial
Open; Refer
Space Sensor Vendor to highlight the proposed specific options, Noted and Comply Please refer to
46 SM Comment # 46.1
& Bund Wall such as material of construction, output type etc. section 5
below
Sensor
Material proposed is same as the level transmitter, The propsed level switch can
47 SM Level Switch which provides only a continuous signal and not provide continuous reading and 4 Noted; closed
discrete switch contact. Please amend. set points can be programmed
Differential
Please clarify the purpose of the differential air
48 SM Air Pressure Not applicable for the System Closed
switch.
Switch
Noted and Comply, Please refer to Open; Refer
Project Specific data sheets to be furnished; not just
49 the attached datasheets Please Comment # 49.1
generic literature or catalogues.
refer to section 5 below
Field
SM Instruments Not complied in full. Highlight specific features
- General proposed for the project. Example level probe shaft
Noted and Comply, Please refer to
49.1 material. Strike-out options that are not applicable
section 5
for better clarity. Also specific instrument model or
order code is to be furnished.
Open; Refer
Instruments and control panels shall comply to the Noted and Comply. Please refer to
50 Comment # 50.1
relevant sections of QCS 2014, as applicable section 8
QCS below
SM
Compliance Compliance as applicable to QCS 2014, Sections 10 Proposed control panel is
50.1 for Control Panels and Instruments as applicable complied with Fuel system
shall be provided. requirements and QCS
Contract requirements Noted; shall be
The referenced drawings shall be used as guideline
drawings reviewed when
51 SM and the minimum interface requirements indicated Noted.
ICA-3301 & the same are
shall be considered.
3302 submitted.
C823-3-DOC-MAT-MEC-021 R.01 Page 11 of 14
Document No. : C823/3-CRS-001
Ashghal approval and country of origin shall be Noted and Comply. Please refer to
52 Open
provided for proposed motor in the submittal. section 11
AJE / OEM is required to provide full compliance Noted and Comply. Please refer to
53 QCS 2014 Open
statement for motor QCS 2014 Section 21 Part 15. section 8
AN Section 21
Part 15 It shall be subject to fully compliant with the QCS Noted and Comply. Please refer to
53.1
2014 requirements. section 8
Noted and Comply. Please refer to
Temperature rise class is not indicating in the motors
54 section 5 (Motor technical Open
Temperature data sheet which need to be clarified.
AN datasheet)
Rise
No further comments subject to fully compliant with
54.1 Noted and Comply
the QCS requirements.
OEM is required to provide and confirm the motor
55 Noted and Confirm Open
Motor protection as per the QCS 2014 requirements.
AN
Protection It shall be subject to successful compliance as
55.1 Noted and Comply
confirmed in contractor’s remark column.
Motor routine test certificate shall be provided in Noted and Comply. Please refer to
56 Open
Test the submittal. section 12( Motor section)
AN
Certificate The test certificate with the specific motor number
56.1 Noted and Comply
shall be provided during the delivery of the
equipment st site.
Proposed GI / PVC Conduit shall be fully complied
57 AN Compliance with the QCS 2014 Section 21 Part 7. AJE / OEM is Noted and Confirm Closed
required to confirm
Approved by:
1. CONTRACT DETAILS
2. LISTED IN PVL
3. SCOPE OF WORK
4. BOQ REFERNCE / SPECIFICATION SECTION / SPECIFIC
REFERNCE DRAWINGS
5. TECHNICAL DATA SHEET
6. COMPANY PROFILE
7. ORGANIZATION CHAT SHOWING QUALITY DEPARTMENT
8. COMPLIANCE STATEMENT
9. VALID CR COPY/COMPANY ID
10. MATERIAL CATALOG AND DATA SHEET
11. COUNTRY OF ORIGIN
12. TEST REPORT
13. SAMPLE WITH MATERIALS. COMPANY AND COUNTRY
DETAILS
14. SPARES
15. WARRANTY CERTIFICATE
16. VALID ISO AND OTHER MANAGEMENT CERTIFICATES
(9001, 14001 & 18001)
17. COPY OF VALID CERTIFICATE / APPROVAL OF THE FIRM
(MANUFACTURER / SUPPLIER) FROM CONCERNED
GOVERNMENT DEPARTMENT
18. LIST OF PROJECTS (COMPLETED AND ONGOING) COPY OF
APPROVAL
19. COPY OF PREVIOUS ASHGHAL APPROVAL
1. CONTRACT DETAILS
CONSTRUCTION OF TERMINAL SEWAGE
PROJECT NAME : PUMPING STATION AT DOHA NORTH STW
PACKAGE – 3, C823/3.
MANUFACTURER : Varies
SUPPLIER : UNIGAZ
Manufacturers Agents
Hager
Hager / Chaina Hager Electro B.V
Country: China Bldg. No.840, Office No.7, Concord Business Cen
Address:
Hager Metal Works Co Ltd , Longgang Industrial Park, Street,
XiashaCDistrict
Ring
Address:
, Shipai Town , Dongguan, China P.O. Box: 31830
P.O. Box: Telephone: (+974) 55682915
Telephone: +86 21 6332 0212, Mob:+86 21 6332 0212Fax: -
Fax: +86 21 6332 0253 Website: https://www.hager.com/
Website: www.hager.com Email: ethan.he@hagersh.com
Email: ethan.he@hagersh.com
Hager / Poland
Country: Poland
Address: Hager Polo Sp. Zo.o, Ul Fabryczna 10, 40-100 Tychy,Poland
P.O. Box:
Telephone: +48 32 32401 40
Fax: +48 32 32401 40
Website: www.hager.com
Email: sekretariat@hager.pl
Hager / France
Country: France
Hager Electro SAS , 132 Boulevard d'Europe, B.P. 78, 67212 Obernai,
Address:
France
P.O. Box:
Telephone: +33 (0)3 88 49 50 50
Fax: +33 (0)3 88 49 50 03
Website: www.hager.com
Email: info@hager.fr
Eaton
Manufacturers Agents
Barton
Country: United Kingdom Address: D-Ring Road, Al Hilal Area, Doha, Qatar
Email: westsales@hublebas.co.uk
REXWAY
Email: info@insteelworld.com
Country: United States Address: SAFWA Bldg, Barwa Commercial Avenue , Doha , Q
Email: elec_custserv@tnb.com
CALIBRE
Address: New Industrial Area, Street 12, Gate 74P.O. Box: 23214
Email: info@calibre-int.com
SMARTr
SMARTr International Pte. Ltd AL BALAGH TRADING & CONTRACTING Co. W.L.L
Address: 66 Kian Teck Road, Singapore P.O. Box: 5777 Doha, Qatar
Email: marketing@smartr.com.sg
03-09-2023
Expiry Date:
Cupra International SDN-BHD
Country: Malaysia Office No.25, West Corner Center Building, Salwa road,
Address:
Roundabout Doha-Qatar
No.61, Jalan Perindustrian 4/KU8, Kawasan Perindustrian Meru Selatan,
Address:
41050 port Klang, Selangor, Malaysia P.O. Box: 11289
Email: sales@cuprainternational.com
Walsall
Country: United Kingdom Address: Al-Jazeera Petrol Station, Salwa Road, Doha, Qata
Fax: - Website:
Website: Email:
Email: pa-info@gb.pepperl-fuchs.com
Walsall Conduits Limited/Caparo Engineering India Limited Lusail Trading & Contracting Company
Product/Model Name: Flexible Conduits and GI Conduits & Fittings Salwa Road Sheika Ghalia Al- Thani Commercial Comple
Address:
Building 180 Unit 5
Country: India
P.O. Box: 21914
Address: Steel Tubes Road, Dewas, Madhya Pradesh 455001 India
P.O. Box: Telephone: +974 4451 2550
Email: sachin.srivastava@caparo.co.in
Syarikat LanRic Industries Sdn. Bhd. Powermax Trading & Contracting Co. W.L.L.
Product/Model Name: GI Conduits & Accessories Barwa Village Building No. 4 Shop No. 1 Street No. 294
Address:
Main Street Doha Qatar
Country: Malaysia
P.O. Box: 20198
Plot 171, Hala Perusahaan mengl embu 1, Falim 30200, Ipoh Perak
Address:
Malaysia Telephone: +974 4443 7586
Website: www.lanric.com
Email: liz@lanric.com
Manufacturers Agents
Qatar Nat. Plastic Factory
Qatar Nat. Plastic Factory/ Qatar Qatar National Plastic Factory
Country: Qatar Address: New Industrial Area, Zone 81, Str. 4, Bldg 13
Address: New Industrial Area, Str. 4, Bldg 135
P.O. Box: 5615
P.O. Box: 5615 Telephone: +974 44689977
Telephone: +974 44689977 Fax: +974 44689922
Fax: +974 44689922 Website: www.qnplast.com
Website: http://www.qnplast.com Email: info@qnplast.com
Email: info@qnplast.com
Alkhyareen
Alkhyareen / Qatar Al Khayarin Electrical Trading
Country: Qatar Address: Gate 18, Street 22, New Industrial Area, Doha- S
Address: New Industrial Area , Street 22 , Gate
P.O.
18 Box: 37461
P.O. Box: 37461 Telephone: +974 4411 4320
Telephone: +974 4411 4320 Fax: +974 4411 4324
Fax: +974 4411 4324 Website: http://www.alkhayarinplastic.com/
Website: http://www.alkhayarinplastic.com/ Email: info@alkhayarinplastic.com
Email: info@alkhayarinplastic.com
3. SCOPE OF WORK
81,*$=4$7$5_
6FRSHRI:RUN
UNIGAZ QATAR
PREQUALIFICATION
DOCUMENTS
4. BOQ REFERNCE / SPECIFICATION
SECTION / SPECIFIC REFERNCE DRAWINGS
STATE OF QATAR ANNEX 2: PRICING DOCUMENTS BILL NO. 4
ASHGHAL SECTION 3: BILL OF QUANTITIES
Carried to Collection QR
Surge Vessel.
Lubrication
Repair Kits
A A
B B
C C
D D
E E
Public Works Authority
P.O.Box 22188
Tel. : (0974) 44950000
Fax. : (0974) 44950999
www.ashghal.gov.qa Qatar Deserves The Best
PA
PROJECTS AFFAIRS
DESIGNS DEPARTMENT
F F
Design Consultant :
SHEEHANIYA TERMINAL PS
INSTRUMENTATION
FUEL TANK AND GENERATOR
P&ID - SHEET 1 OF 2
Drawn: Checked:
K. SHETTY I. KHAN
Designed: Approved:
H K. SHETTY K. PEZHGORSKI H
Date: Scale:
JUNE 2019 NTS
Status:
CONTRACT
Drawing Number: Revision:
C823-P03-STN-IC-3301 CA
1 2 3 4 5 6 7 8 9 10 11 12
1 2 3 4 5 6 7 8 9 10 11 12
A A
B B
C C
D D
E E
Public Works Authority
P.O.Box 22188
Tel. : (0974) 44950000
Fax. : (0974) 44950999
www.ashghal.gov.qa Qatar Deserves The Best
PA
PROJECTS AFFAIRS
DESIGNS DEPARTMENT
F F
Design Consultant :
SHEEHANIYA TERMINAL PS
INSTRUMENTATION
FUEL TANK AND GENERATOR
P&ID - SHEET 2 OF 2
Drawn: Checked:
K. SHETTY I. KHAN
Designed: Approved:
H K. SHETTY K. PEZHGORSKI H
Date: Scale:
JUNE 2019 NTS
Status:
CONTRACT
Drawing Number: Revision:
C823-P03-STN-IC-3302 CA
1 2 3 4 5 6 7 8 9 10 11 12
QCS 2014 Section 21: Electrical Works Page 1
Part 17: Standby Diesel Generator Set
.L
17.2.1 Diesel Generator Set 5
.L
17.2.2 Control Panel 14
17.2.3 Automatic Transfer Switch (A.T.S.) 15
W
17.2.4 System Operation and Performance 16
17.2.5 Manual Operation 16
G
17.2.6 System Responsibility 16
IN
17.2.7 Installation 16
17.2.8 Paint Work R 17
17.2.9 Site Quality Control 17
EE
17.2.10 Commissioning 17
17.2.11 Training of Operation and Maintenance Personnel 18
17.2.12 Reference Data Sheet 19
IN
G
EN
R
BE
JA
AL
QCS 2014 Section 21: Electrical Works Page 2
Part 17: Standby Diesel Generator Set
1 The work of this Section is integral with the whole of the Project Documentation and is not
intended to be interpreted outside that context.
2 Co-ordinate the work with all other services affecting the work of this Section.
.L
1 The Contractor shall supply, install, commission, test and handover in good operable manner
.L
including 400 days guarantee and maintenance of 415 V mains failure, standby diesel
W
generator set and 5 years guarantee for electric motors, as per the Project Documentation.
The set shall be arranged for either automatic or manual start on mains failure, as indicated
on the Project Drawings. The set shall be complete with diesel engine, generator, control
G
panel, batteries, starting motor, built-in air cooled radiator, main fuel storage tank, daily fuel
storage tank, fuel transfer pumps and all other accessories as specified and mentioned in the
IN
BOQ.
Part 7 Conduits
Part 8 Trunking
G
BS 4999 ......................Alternators
BS 5514 ......................Engines
JA
1 Manufacturer's Qualification:
AL
(a) The Diesel Generator Set shall be designed and manufactured complete by a
manufacturer regularly engaged as a manufacturer of such equipment.
(b) The Diesel Generator Set Manufacturer shall have a proven manufacturing experience
of minimum 10 years in this field. Reference of previous approvals in similar
applications and environmental conditions shall be provided for Engineer’s review and
approval.
(c) The DG set manufacture shall have an approved ISO 9001 QA/QC procedure for
design, manufacturing and testing of complete DG set. The DG set Manufacturer shall
provide minimum the following documents as a part of submittal approval.
(i) Quality policy
(ii) Quality Policy manual
(iii) Manufacturing and storage facilities.
QCS 2014 Section 21: Electrical Works Page 3
Part 17: Standby Diesel Generator Set
2 Installer's Qualification:
(a) all the Diesel Generator installation work shall be carried out by a Diesel Generator
sub-contractor. Diesel Generator sub-contractor shall be one who is normally an
agent representing one or more of the approved makes of D/G sets. Diesel
.L
Generator installation shall be supervised, checked and tested by a qualified
representative of the manufacturer and handover the works in perfect running order
.L
to the satisfaction of the Engineer.
W
3 Source Quality Control:
(a) The Diesel Generator Set Manufacturer shall test the complete Diesel Generator set at
G
the manufacturing facilities. The test shall be performed as per the latest BS/IEC
standard and the Factory Acceptance Procedure shall be approved by the
IN
Engineer/Client. Any additional test required by the Engineer during the FAT shall be
performed by the Diesel Generator Manufacturer in his cost. The Diesel Generator set
R
shall not be shipped from the manufacturing facilities until the test reports have been
submitted and approved by the Engineer.
EE
4 Local Agent:
IN
(a) the manufacturer should have an agent in Qatar who is well experienced in
installation and maintenance of diesel generators of the size specified herein. The
G
agent should have been associated with the manufacturer for a minimum period of
five years.
EN
5 Design Criteria:
(a) all materials and equipment shall comply with relevant IEC and BS specifications as
R
(b) the emergency power supply system and its components shall be such as may be
properly maintained and serviced without the necessity of carrying expensive spare
part stocks, or being subjected to interrupted service due to the lack of spare parts
JA
(c) emergency generator set shall be designed to allow easy replacement of major items
subject to wear.
AL
17.1.5 Submittals
1 Shop Drawings:
battery
battery charger
earthing
transfer switch control relays
(ii) interior wiring, terminals and interconnecting wiring
(iii) certified dimensions and weights.
(d) submit a composite wiring diagram of the entire emergency transfer system showing
all wiring between the engine starting panel, engine generator set and the automatic
transfer switches
.L
(e) wiring diagrams shall clearly show:
(i) main current conductors, in heavy lines
.L
(ii) control conductors, with colour and/or number coding
W
(iii) location of relays and apparatus
(iv) description of function, type and catalogue, of all components.
G
(f) alternator Control Panel:
IN
(i) submit a schematic line diagram showing:
R
Interlocks
EE
Protection
Instruments
IN
(g) submit general arrangement drawings of the generator installation and the generator
building layout.
G
(a) submit curves showing the actual performance of a similar engine (same model,
stroke, etc.) to that proposed, superimposed on the standard published performance
curves for continuous, and maximum operation
R
(b) submit the detailed information together with manufacturer's catalogues for the
BE
following:
(i) generating set manufacturer
JA
1 During the maintenance period of 400 days the sub-contractor shall repair and replace
directly, at his own expense, any of the plant, material or work performed or furnished under
the respective works in the Project which may develop under the conditions provided for by
the Project and under proper use in the works or that portion thereof taken over by the
Engineer. The guarantee period for all electric motors shall be 5 years.
2 The sub-contractor shall obtain and submit to the Engineer all guarantees or certificates or
warranty available from the manufacturers, but only as supplementary to the sub-contractor's
.L
own liabilities under the Project and in no way invalidate them.
.L
3 The D/G sub-contractor shall be responsible for the satisfactory operation of the D/G
installation during the Maintenance and Guarantee Period. He shall carry out necessary
W
inspection, preventive maintenance and testing to keep the set ready all the time. The set
shall function satisfactorily during power failures. The D/G sub-contractor shall carry out
G
routine testing of the installation once in every month throughout the Maintenance and
Guarantee Period. The testing shall be carried in presence of Engineer. The sub-contractor
IN
shall himself provide all electrical and mechanical spare parts, grease, lubricating oils, touch-
up paints, etc., required for the maintenance of the D/G installation. The owner shall be
R
responsible only for providing diesel oil as and when required. The D/G sub-contractor shall
prepare log-books listed full details of maintenance work and each log-book entry shall be
EE
countersigned by the Engineer.
17.2 PRODUCTS
IN
1 The Diesel Generator Set shall be of rugged reliable design and built for long trouble free
service under the worst specified climatic conditions and made by an approved reputable
manufacturer.
R
2 Rating:
BE
(a) The Diesel Generator Set output shall be design for prime rating as specified
elsewhere. Detailed design calculations for Engine, Alternator, Cooling system, battery,
etc shall be provided for Engineer’s approval for the proposed Diesel Generator set.
JA
(b) The rated output shall be as specified elsewhere or as indicated on the drawings,
415/240 Volts, 3 phase, 4 wire and 50 Hz or different voltage level as indicated
elsewhere in the Contract specifications (690 V or 3.3 KV).. The rated output shall
AL
mean the net full continuous derated output in Qatar at an ambient temperature up to
50°C at a relative humidity of 95%. The set shall also be capable of 110% load for one
hour under these conditions at the rated speed without undue heating of the engine or
alternator and without mechanical or electrical troubles.
3 Diesel Engine:
(a) The diesel engine shall be of the stationary heavy duty, turbo charged
compression/ignition, multi cylinder 4 stroke operation. The steel base frame shall be
provided with spring type vibration isolators. The engine shall be able to deliver full
load in the shortest possible time after start. The engine speed shall not exceed 1500
r.p.m. The engine construction shall be in such a way as to allow for dismantling of
any engine component for inspection or repair without undue complication i.e. without
dismantling of other non-defective parts. The crank case shall be provided with
inspection windows
QCS 2014 Section 21: Electrical Works Page 6
Part 17: Standby Diesel Generator Set
(b) starting system: The diesel engine shall be equipped with starting system detailed
hereunder and as per Engineer's approval.
(i) Battery Starting System:
batteries for starting shall be of the nickel cadmium type, 24 Volt, heavy
duty diesel starting type and of sufficient capacity to allow 6 consecutive
start attempts each of 15 seconds with 1 minute intervals. It shall be
possible by means of a selector to alter the starting sequence to provide a
single start attempt of 1 minute before lockout and alarm. The battery
used for starting may also be used to energise the diesel plant control
system but shall have enough capacity remaining after 3 engine start
attempts to energise the system continuously for 24 hours. The control
system shall be suitable to continue operating correctly during the voltage
.L
dips occurring on the battery during the engine starts.
(c) Cooling System:
.L
(i) radiator : built-in type with sufficient capacity to dissipate the total joules per hour
W
rejected by the engine cooling system at 110 % full load
(ii) blower fan: to have sufficient pressure to circulate required quantity of air for
G
engine cooling. The fan shall be provided with a suitable guard. D/G room
o
IN
inside temperature should not exceed 56 C
(iii) jacket water heaters: to be provided on engine to facilitate quick starting
R
under low ambient conditions
EE
(iv) the cooling system shall be capable of keeping the temperature of cooling
water at safe limits at all conditions of load required in the specifications.
Maximum temperature of cooling water after 10 hours of continuous running
IN
at full load at worst Qatar climatic conditions shall not exceed the maximum
temperature limits of the diesel engine
G
(v) the cooling system shall include an engine shaft driven circulating water
pump. The water jacket of the engine cylinder shall be so constructed that
EN
(vii) drain valve and a filling valve shall be provided to the radiator for flushing
BE
(ix) the water pump discharge valve shall preferably be a globe valve, the other
valves shall be (sluice) gate valve.
.L
vent/breather pipe
.L
filler pipe connection
W
overflow connection
drain valve and sump drain
G
emergency dump valve operated by the fire alarm system and by a fusible
IN
link mounted over the diesel engine
dial type contents gauge calibrated in gallons and litres
R
level switches to control fuel transfer pump
EE
level switches to operate high and low fuel level alarm circuits in the
diesel alternator set control panel
IN
lifting lugs.
G
The Contractor shall supply and install a cylindrical diesel oil storage tank
with a capacity to operate the associated diesel generator set
continuously on full load for a minimum of 7 days, unless otherwise
AL
.L
baskets
Oil pump set shall be factory assembled on a structural steel channel
.L
beam base to include pumps, motors, flexible couplings and guards.
Pump set shall be suitable for diesel oil
W
Suitable manually operated pump shall be provided.
The installation of Diesel transfer pump set shall be subject of the
G
Engineer’s approval. There shall not be any possibility of flooding of the
diesel transfer pumps.
Tank fittings and pressure fittings shall be made of solid bar stock to
EN
Provide all diesel oil piping from storage tank to day tank fill lines, water
BE
tight fill boxes, vents, vent caps, tank foot valves, and accessories
Provide swing check valves and gate valves at pump inlets. Provide
approved anti-siphon valves at high points of suction lines. Provide
JA
.L
(v) a large capacity oil sump shall be provided and incorporated in the
construction of the bed plate
.L
(vi) the system of lubrication shall ensure that adequate oil is pumped to all
W
rotating parts
(vii) The system shall incorporate a level dipstick, filler cap and tube and
crankcase breather pipe or outlet
G
(viii) the capacity of the lubricating oil system shall be sufficient to enable the
IN
engine to run continuously for 12 hours at any load without replenishment.
(ix) Suitable manual-pumping arrangement for easy draining of the whole
R
quantity of lube-oil into a drum shall be provided.
EE
(f) Exhaust System:
(i) Exhaust pipes shall be of Schedule 40 black steel and of adequate size to
IN
ensure that back pressure does not exceed the value specified by the
manufacturer
G
(ii) The exhaust pipe shall be connected through airtight flexible coupling to the
engine
EN
(iii) Exhaust pipes shall be adequately lagged with 75 mm thick (minimum) rock
wool covered with aluminium sheaths of minimum thickness 1.5 mm so that to
0
take care of exhaust gas temperature in pipes exceeding 500 C. When
R
engine and a condensate trap fitted at the lowest points. Approved rain caps
shall be installed at the discharge end of the exhaust pipes on the roof.
(v) Suitable flexible expansion joints shall be provided along the pipe run to take
care of expansion requirements
(vi) the completed exhaust system shall be capable of limiting the noise level at
the external outlet to 65 dB (A) at three metres from the end of the exhaust
pipe
(vii) suitable guards shall be provided with the exhaust pipe to prevent small
animals/reptiles from entering.
(g) Filters: Cleanable/replaceable elements should be provided.
(i) Fuel Oil System
The system shall have the following filters fitted before the fuel injection pumps:
QCS 2014 Section 21: Electrical Works Page 10
Part 17: Standby Diesel Generator Set
.L
Air is inducted to the engine manifold through
.L
Precleaner
W
Large capacity air cleaner
Both filters are required due to severity of dust storms and dust
G
suspensions in the air
IN
The engine exhaust line shall be fitted with flexible fitting efficient silencer
to give efficient silencing with minimum back pressure and terminated
R
outside the engine room.
EE
(h) Ventilation:
(i) The following ventilation works are required for the diesel engine generator
room.
IN
G
Aluminium inlet louvres with washable metal filters shall be provided for
outside air intake into the engine room. Filters shall be sized to perform
EN
their duty with a face velocity not more than 1 metre per second when the
engine is running. Filters shall be installed in an appropriate arrangement
on the generator room walls. The total filter area shall consider air for
engine intakes and radiator cooling requirements. Filters with handles and
R
manually opened in the event of drive motor failure. Gravity louvres shall
not be allowed for the radiator exhaust.
AL
(iii) the engine vibration shall be the minimum possible and shall comply with
the relevant BS. The vibratory force induced as the engine passed through
resonance revolutions during starting and stopping period shall not cause any
damage to the whole system
(k) Engine Control Panel: The engine-generator control panel shall be of rigid
and robust construction and rust-proof and shall be of the electronic modular
type utilising environmentally sealed, solid state, micro-processor based
modules for engine control and AC metering. The panel shall be capable of
operating under the operating temperature range of 0 degrees to + 70
degrees Celsius. Metering accuracy shall be 0.5% true RMS. The electronic
control system shall employ solid-state transducers for constant monitoring of
oil pressure and coolant temperature through a Single Sire Serial Data Link.
.L
Unless otherwise specified in the Project Documentation, the control panel shall
provide the following features:
.L
(i) automatic start/stop engine control with programmable safety shutdowns and
W
associated flashing LED indicators for low oil pressure, high coolant
temperature, overspeed overcrank and emergency stop
G
(ii) adjustable 1 to 60 second cycle cranking with rest periods
IN
(iii) cool-down timer, adjustable between 0 and 30 sec.
(iv) LCD digital readout for: R
engine oil pressure (N/mg)
EE
0
exhaust gas temperature gauge ( C)
G
engine RPM
system DC Volts
engine run hours
R
generator AC Volts
JA
generator AC Amps
Generator frequency
AL
The system diagnostic codes shall be designed to enhance the system protection and
to allow for trouble shooting by untrained personnel.
(a) the alternator shall be able to withstand the stresses caused by the sudden
application of the loads
(i) Type : Self excited, self ventilated, air cooled, splash-
proof, synchronous alternator
(ii) Output : As per Project Documentation, at Qatar Climatic
Condition
.L
(iii) Voltage : 415V(Or as indicated in Project documents)
.L
(iv) Frequency : 50 Hz
W
(v) No. of poles : 4
(vi) No. of phases : 3, (ungraded neutral to be brought out)
G
(vii) Power factor : 80% lagging
IN
(viii) Commercial efficiency not less than 90 % (including excitation and field losses)
(ix) Voltage regulation : Automatic and static.
R
EE
(b) Class F insulation shall be provided for the alternator and exciter windings with the
temperature rise as Class B and de-rated for the ambient conditions.
IN
(c) the alternator shall be suitable for continuous running duty type S1, BS 2613 (latest
edition)
G
(d) the alternator unit shall be capable of giving 110% of nominal rated output for one
hour under site conditions. The rotor shall be capable of withstanding an over-speed
EN
(f) voltage adjustable range of the output voltage by adjusting the exciter shall be not
BE
less than 3 % of rated voltage at rated load and not less than ± 5 % of rated voltage
under no-load conditions. This adjustment shall be able to be performed from panel
JA
circuits
(i) the alternator shall not be switched on the load until terminal voltage has reached at
least 90 % of the nominal value. It is essential that the voltage regulation equipment
shall have sufficient fast response time so that the alternator is ready to accept load
in the shortest possible time
(j) the voltage regulator shall be designed to maintain the alternator terminal voltage
constant within ± 1 % of the nominal value from no load to full load within normal
variations of engine speed with change in load
(k) the exciter shall be brushless, self excited, rotor mounted type. The rectifying
elements shall be silicon. The silicon diodes of the three phase rectified bridge
assembly shall be protected against surges and overloads such that the generator will
continue to run with a diode failure. Diodes shall have heat sinks suitable for the
ambient conditions described. Means shall be provided to indicate exciter diode
failure on the remote control panel
QCS 2014 Section 21: Electrical Works Page 13
Part 17: Standby Diesel Generator Set
(l) the unit shall be suitably protected so that when there is a sudden variation of load,
the sudden increase of field current in the rotor shall be curtailed and thus the speed
build up of the engine and the voltage build up of generator shall vary
proportionately
(m) alternator protection. The alternator shall be provided with protection against over
speed, over voltage, over current, short circuit, reverse power, single phasing earth
fault and any other found necessary. The neutral points of alternators shall be solid
by connecting to earth
(n) terminals with cable end boxes shall be provided respectively for the alternator and
exciter
(o) the cooling air for alternator and exciter shall be drawn through openings at the non-
drive end and exhausted sideways at the driving end
.L
(p) the alternator shall be fitted with anti-condensation heater to keep the winding in
.L
good, dry and safe condition. The anti-condensation heater shall be automatically cut-
off when the machine is running. Necessary on-off switches shall be provided on the
W
control panel and the operation status of the heater shall be indicated
(q) temperature Rise: Alternator components shall be sound electrically and
G
mechanically in continuous operation lasting over 24 hours at the rated output
IN
(r) insulation Resistance: Insulation resistance of the machine at strategic points shall
be provided along with the submission R
(s) dielectric Strength: The Dielectric strength, the voltage of testing and test procedure
at various points of the machine shall be submitted with the shop drawings
EE
(t) radio and television interference suppression devices shall be provided in accordance
with the requirements of BS. 800. Components used for suppression shall be to BS
IN
613
(u) vibration at the fixed components of the alternator under excited no-load
G
(i) all wiring of battery charger, exciter and control panel shall be P.V.C tropical
BE
(ii) all wiring shall conform to the relevant BS and at least 50 % derated with
2
minimum size of 2.5 mm or its equivalent.
(x) terminal Board
AL
(i) terminal boards shall have pairs of terminals for Incoming and Outgoing
wires and not more than two wires shall be connected to any one terminal
(ii) insulating barriers shall be provided between adjacent connectors. Labels for
wiring designation marks shall be provided on the fixed portion of the
terminal boards as well as wires. No live metal shall be exposed at the back
of the terminal boards
(iii) terminal boards having pressure type terminal lusts or equivalent shall be
used so that no terminal clamp is necessary. 10 % spare terminals shall be
provided for each terminal board assembly.
QCS 2014 Section 21: Electrical Works Page 14
Part 17: Standby Diesel Generator Set
5 Guards
(a) Suitable guards with brackets and securing arrangements of substantial construction
shall protect all exposed rotating or moving parts. All guards shall be mechanically
fixed to the generator set. Special attention shall be given to guarding the flywheel-
coupling and the radiator fan drive.
1 Cabinet
(a) heavy gauge, 2.5 mm thick, sheet steel construction, totally enclosed, dust and water
protected and vermin proof to IP 55
.L
(b) a hinged, lockable door shall give access to control and instruments
(c) "live" parts shall be secured to prevent inadvertent contact with them
.L
(d) controls for diesel engine, alternator, exciter, meters and alarm device shall be
W
positioned to give ample space for removing and installing components.
G
(a) control panel shall include: (unless otherwise specified in the Project Documentation)
IN
(i) 3 pole air circuit breaker with over-current, short circuit and earth fault
protection as specified in this specification. (unless part of a main
R
switchboard, as indicated on the drawings)
EE
(ii) busbar system as specified in this specification (unless part of a main
switchboard, as indicated on the drawings)
IN
(iii) voltmeter (0-500V) with selector switch to read phase to phase and phase to
neutral voltages
G
(viii) microprocessor control unit incorporating, but not limited to the following:
BE
(xii) visual and audible alarm for engine starting, engine running overspeed, high
water temperature, low oil pressure, failure to start, engine stalling or shut down,
low fuel level in tanks, overvoltage and alternator overload.
(xiii) indicator lamps for supply available, battery charger and cooling water
heater
(xiv) manual start, stop, emergency OFF and lamp test push-buttons
(xv) manual and automatic service push-buttons
(xvi) control switch for alternator circuit breaker, ON and OFF
(xvii) mimic diagram with moving coil indicator for position of air circuit breaker
(xviii) battery charger, automatic type, nominal current 10 Amps. for charging
.L
24 volts nickel cadmium starter battery and all required instruments
.L
(xix) all other accessories, fuses, terminal boards, small wiring, etc.
W
17.2.3 Automatic Transfer Switch (A.T.S.)
1 he A.T.S. shall consist of 4 pole, 3 phase, break before make except for the neutral, ted as
G
shown on the Drawings in accordance with QGEWC regulations
IN
2 with the A.T.S. provide manual change-over switches to by-pass the A.T.S. in case of
emergency, maintenance or repair
R
EE
3 the arrangement, wiring and components shall satisfy the requirements of the Diesel
generator Manufacturer. His written approval shall be submitted
IN
4 control voltage of A.T.S. shall be normally fed from the main supply, in case of failure
of the main supply it shall be fed automatically from the emergency supply.
G
5 in addition to transfer switches the A.T.S. arrangement shall be equipped with the
EN
following:
and voltage drop below 70 % of the normal voltage (pick-up and drop-out
voltages and adjustable within the range 70 - 100 % of the normal voltage)
JA
(e) an adjustable time delay relay of 1 - 3 seconds for starting signal to the
Generator set after cutting of main supply
(f) an adjustable time delay relay of 0 - 3 minutes which allows A.T.S. from
Normal to Emergency after the voltage build up relay of the generator has
sensed 90 % rated voltage when frequency within 90 % rated of rated
frequency
(g) an adjustable time delay relay of 1 - 10 minutes to allow A.T.S. from
Emergency to Normal
(h) an adjustable time delay relay of 0.5 - 5 seconds to prevent instantaneous
transition from EMERGENCY to NORMAL i.e. the delay allows time sufficient
For the residual motor voltage to decay to a safe switching level.
QCS 2014 Section 21: Electrical Works Page 16
Part 17: Standby Diesel Generator Set
1 The normal mode of system operation shall provide for unattended automatic transfer of load
for the emergency power system. Emergency power shall be supplied to the system
emergency loads within 10 seconds after interruption of the normal service. Upon receiving a
signal from the ATS indicating a failure or normal power from transformer, the system control
unit will signal engine generator to start. Generator circuit breakers are open at this time and
the emergency busbar is dead. The generating set to reach approximately 90% of rated
frequency and voltage signals to start sensor. The sensor then inhibits the operation of
sensors and initiates a closing signal to circuit breaker, connecting this generating set to the
emergency busbar. The priority control then initiates operation of the designated transfer
switch, applying load up to the total kW rating of the generating set.
.L
2 If the generating set fails to start after cranking for the suitable cranking period, it shall be
locked off the busbar and the overcrank light on its switchboard shall light and the alarm
.L
sound. The control prevents critical transfer switch from operating. The generating set may
receive troubleshooting signals after placing its engine control function switch in the "OFF"
W
position. When the generating set is operational, it may again be placed into automatic
operation by returning its function switch to the "remote" position.
G
3 If a generating set stalls and shuts down during normal operation, its respective switchboard
IN
circuit breaker shall open, removing it from the busbar. The appropriate failure light operates
and the alarm sounds. The load shedding contacts in the control close, tripping a breaker in
the load circuits, reducing system load to the rating of the remaining available generating
R
capacity. After the generating set is made operable, it can be automatically reconnected to
EE
the busbar by resetting the load shed switch and engine control switch.
4 After normal power has been restored and the time delay on stop has expired, it shall be
IN
possible to manually shut down the generator and restore the mains power.
G
1 The manual operation of the Diesel Generator Set shall have the following features:
R
BE
(a) the emergency power system shall have the capacity of being manually operated.
The generator may be started by engine control switch located on the engine control
unit. Once started and stable, the generator may be manually connected to the
JA
facilitate.
1 The generating set, switchboard and automatic transfer switches shall be interconnected
according to building load requirements and to manufacturer's recommendations, to prevent
the emergency generating system from stalling or faltering due to momentary or temporary
overloads beyond system rating, from distribution faults, motor starting loads.
17.2.7 Installation
(a) lift all generator equipment using eyes, yokes and skids provided by the manufacturer
(b) do not store equipment assemblies exposed to weather
QCS 2014 Section 21: Electrical Works Page 17
Part 17: Standby Diesel Generator Set
(c) physically protected all generator equipment against damage from work of other
trades
(d) cover all generator equipment with suitable material to avoid damage to finish.
(e) Contractor shall submit the calculation to prove the adequacy of capacity of the crane
he intends to use for installation of the D-G set
2 Installation:
(a) the engine and generator shall be properly aligned and mounted on a common steel
base through resilient mountings to prevent vibrations. The whole set shall be fixed
on the concrete slabs through suitable number of adjustable spring type vibration
isolators. Foundation and other builder's work shall be as recommended by the
manufacturer and approved by the Engineer
.L
(b) except as may be described in this Section or shown on the drawings carry out
.L
installation strictly in accordance with the manufacturer's recommendation.
W
3 Control Boards:
(a) run all outgoing cables from the generator to the control boards in the floor trench as
G
indicated on the Project Drawings.
IN
4 Record Print:
(a)
R
fix record print of each generator set, framed behind non-glare plexiglass, on a wall
near the generator control room.
EE
1 Paint work of each set shall be of the highest quality to withstand the worst weather
conditions specified. All steel works such as tanks, pipes, frames, louvers, ladders, platform,
G
etc. shall be given two undercoats of anti-rust paint and two enamel finishing.
EN
2 The diesel generator set, day tank internal metalworks and control panel shall be finished to
BS 4800, shade 14E53.
1 Final Testing:
(a) testing shall be carried out at full load after completion of installation by the Engine
JA
17.2.10 Commissioning
(a) engine-generator shall be made ready for automatic operation and started by means
of the test transfer switch on the automatic transfer switch. Unit shall run for the
duration of all time delays and then automatically shut-down. This test shall be made
with unit operating, and twice with unit simulated for a starting failure.
(a) Engine:
(i) the engine shall be tested at site before and after erection to BS 649 and
amendments or equivalent including items which are said to be subject to
QCS 2014 Section 21: Electrical Works Page 18
Part 17: Standby Diesel Generator Set
mutual agreement. The test shall include inspection, after testing the
following parts
(ii) subsequent running test of eight hours shall be carried out of the set
(iii) the engine shall be subjected to vigorous performance tests at site to the
satisfaction of the Engineer and the main items shall include:
Output characteristics
Temperature rise
Checking of valve clearance, fuel pump setting, governor setting, pipeline
connections, exhaust piping and flexible connections
Checking the base and set are level in all directions, checking alignment
.L
of engine and generator and vibration isolators location and proper
installation
.L
Checking of proper operation of engine safety devices
W
Checking of fuel pipelines, fuel pumps, tank level gauges and level control
switches operation.
G
(b) Alternator and Exciter:
IN
(i) the alternator and exciter shall be tested to BS 5000, P.99 amendments
thereof R
(ii) tests at site before erection and after erection prior to handing over shall be
EE
carried out to the satisfaction of the Engineer. The main items of tests
deemed necessary by the Engineer shall be carried out at the expense of the
Contractor. The performance test shall be for 24 hours under the worst
IN
1 The Contractor shall train a number of persons who will be selected by the Engineer for the
R
operation and maintenance of all the works within the Project before these works are handed
over to the Engineer.
BE
2 The training has to be carried out by qualified staff of the Contractor for each specified
service and shall be provided for a one month period following the certificate of completion.
JA
AL
QCS 2014 Section 21: Electrical Works Page 19
Part 17: Standby Diesel Generator Set
1 This Form or similar is to be completed by the Electrical sub-contractor as Well as D/G sub-
contractor and to be submitted for approval to the Engineer unless otherwise Specified.
---------------------------------------------------------------------------------------------------------------------------
1. Name and Address of
D/G sub-contractor
.L
.L
2. Detail of work in hand
now with proposed
W
D/G sub-contractor
---------------------------------------------------------------------------------------------------------------------------
Name of Government Amount of D/G
G
Project Installation Works
---------------------------------------------------------------------------------------------------------------------------
IN
a.
----------------------------------------------------------------------------------------------------------------
R
b.
----------------------------------------------------------------------------------------------------------------
EE
c.
----------------------------------------------------------------------------------------------------------------
d.
IN
----------------------------------------------------------------------------------------------------------------
e.
G
----------------------------------------------------------------------------------------------------------------
EN
We confirm that the Statements given above are true, to the best of our knowledge and it
is known to us that Engineer reserves the right to refuse to award sub-contract to us if
the above Statements are found to be incorrect.
R
Signature Signature
JA
AL
END OF PART
5. TECHNICAL DATA SHEET
MATERIAL SCHEDULE
5/LW $%*67
6$03/(
Pre-Qualification Documents
Project: Construction of Terminal Pumping Station at Doha North STW Package 3-C823/3
Client: M/s Ashghal (PWA)
Subject: Calculation for Fuel Tank Capacity
Input:
Generator Consumption:
Calculation
7 Days x 24 H 168 H Hours for 7 Days Capacity for Total Generator Consumption
Liters Main Tank required for
517 L/H x 168 H 86,856 L
Total Generator Consumption
--------------------------------------------------------------------------------------------------------------
Bund wall
Bund
Capacity
Tank Capacity
Tank Required (120% Bund wall size Remarks
S/N Capacity (m³)
Quantity of tank size) LxWxH (mm) (if B > A)
(Liters)
(m³)
B
A
Bund wall size
1 50000 1 60000 12900x6000x800 61.92
Acceptable
Bund wall size
2 50000 1 60000 12900x6000x800 61.92
Acceptable
Bund wall size
3 3000 1 3600 3000X2500X600 4.50
Acceptable
Bund wall size
4 3000 1 3600 3000X2500X600 4.50
Acceptable
--------------------------------------------------------------------------------------------------------------
VENT
MATERIAL SUBMITTAL
Model 354 Updraft Vent
SPECIFICATION SHEET
Application
Atmospheric updraft vents are installed on the top of storage tank
vent pipes on underground and aboveground fuel storage tanks.
Materials of Construction
354
Body and cap... aluminum die cast
Screen... 40 mesh stainless steel
354T
%RG\DQGFDS7HÀRQ® coated black aluminum
Screen... 40 mesh stainless steel
354T (2Ǝ)
Ƥ
CARB 89-12 (1½ƎDQGƎPRGHOV
9HQWLQJ&DSDFLW\6&)+
,WHP1XPEHU 6L]HVOLSRQ :HLJKWOEV #36,
$9 òƎ
$9 Ǝ
$9 Ǝ
$9 Ǝ 116,900
NOTE
2SHQYHQWVZLOODOORZXQUHVWULFWHGHYDSRUDWLRQRISURGXFW
:$51,1*'2127),//2581/2$')8(/)520$6725$*(7$1.81/(66,7,6&(57$,17+$77+(7$1.9(176:,//23(5$7(3523(5/<
Morrison tank vents are designed only for use on shop fabricated atmospheric tanks which have been built and tested in accordance with UL 142, NFPA 30 &
$DQG$3,DQGLQDFFRUGDQFHZLWKDOODSSOLFDEOHORFDOVWDWHDQGIHGHUDOODZV,QQRUPDORSHUDWLRQGXVWDQGGHEULVFDQDFFXPXODWHLQYHQWRSHQLQJV
and block air passages. Certain atmospheric conditions such as a sudden drop in temperature, below freezing temperatures, and freezing rain can cause
moisture to enter the vent and freeze which can restrict internal movement of vent mechanisms and block air passages. All storage tank vent air passages
PXVWEHFRPSOHWHO\IUHHRIUHVWULFWLRQDQGDOOYHQWPHFKDQLVPVPXVWKDYHIUHHPRYHPHQWLQRUGHUWRLQVXUHSURSHURSHUDWLRQ$Q\UHVWULFWLRQRIDLUÀRZFDQ
FDXVHH[FHVVLYHSUHVVXUHRUYDFXXPWREXLOGXSLQWKHVWRUDJHWDQNZKLFKFDQUHVXOWLQVWUXFWXUDOGDPDJHWRWKHWDQNIXHOVSLOODJHSURSHUW\GDPDJH¿UH
injury, and death. Monthly inspection, and immediate inspection during freezing conditions, by someone familiar with the proper operation of storage tank
YHQWVLVUHTXLUHGWRLQVXUHYHQWLQJGHYLFHVDUHIXQFWLRQLQJSURSHUO\EHIRUH¿OOLQJRUXQORDGLQJDWDQN1RUPDOYHQWVVXFKDVSUHVVXUHYDFXXPDQGXSGUDIW
YHQWVIRUDERYHJURXQGVWRUDJHWDQNVVKRXOGEHVL]HGDFFRUGLQJWR1)3$
FILL BOX
MATERIAL SUBMITTAL
Stainless Steel filling Box
UNIGAZ QATAR | MATERIAL SUBMITTAL
FLEXIBLE HOSE
MATERIAL SUBMITTAL
UNIGAZ QATAR | MATERIAL SUBMITTAL
'$<7$1.
By Generator Supplier
MATERIAL SUBMITTAL
Project: Construction of Terminal Pumping Station at Doha North STW Package 3-C823/3
Client: M/s Ashghal (PWA)
Subject: Bund Wall Capcity Calculation
Bund wall
Bund
Capacity
Tank Capacity
Tank Required (120% Bund wall size Remarks
S/N Capacity (m³)
Quantity of tank size) LxWxH (mm) (if B > A)
(Liters)
(m³)
B
A
Bund wall size
1 50000 1 60000 12900x6000x800 61.92
Acceptable
Bund wall size
2 50000 1 60000 12900x6000x800 61.92
Acceptable
Bund wall size
3 3000 1 3600 3000X2500X600 4.50
Acceptable
Bund wall size
4 3000 1 3600 3000X2500X600 4.50
Acceptable
--------------------------------------------------------------------------------------------------------------
SOLENOID VALVE
MATERIAL SUBMITTAL
SERVO ASSIST SOLENOID VALVE
S1000 SERIES (3/8", 1/2", 3/4",1", 11/4", 11/2", 2")
NORMALLY CLOSED
GENERAL FEATURES
• Wide pressure range, flow rate and orifis options. 2 WAY
• Solenoid valves are used with filters.
PILOT OPERATED
• Solenoid valves can be mounted in any position without
affecting its operation, coil to be used in a vertical position. ΔP=0
• No pressure difference is required.
ELECTRICAL CHARACTERISTICS
Continuous Duty : ED %100
Coil Insulation Class : H (180°C)(IEC 85)
Coil Impregnation : Polyester Fiber Glass ZERO DIFFERENTIAL
Ambient Temperature : -10°C, +60°C PRESSURE
Protection Degree : IP65 (ISO 60529) On request;IP68
Electric Plug Connection : DIN 46340 3– Poles Connector(DIN43650)
Connector Specification : ISO 4400 / EN 175301-803 Form A,
Spade Plug (Cable Ø6-8 mm)
Electrical Safety : IEC 335
Standard Voltages : For C40; AC 12V 15VA, 24V 15VA, 48V 15VA,
110V 15VA, 230V 15VA, 230V 24VA
DC 12V 18W, 24V 18W, 48V 18W, 110V 18W
Dimensions (mm)
For C50; AC 24V 35VA, 110V 30VA,
120V 35VA, 230V 35VA, 230V 42VA G A B C D E H I K
DC 12V 40W, 24V 40W 3/8" 72 97.7 32 45 94.8 76 109 52.5
On request other voltages 1/2" 80 99.2 32 45 96.2 76 110.5 52.5
Voltages Tolerance : AC -15%, +10% DC -5%, +10% 3/4" 78 106 32 45 97.2 76 117.3 52.5
On request; Connector with LED, PWM Socket 11/4" 149 185.5 103 110 63 - - -
Specify coil voltage with order. 11/2" 149 185.5 103 110 63 - - -
2" 149 185.5 103 110 63 - - -
Water
Air, Gas
EPDM
Vıton
NBR
Liquid Lt/min
S1000 G mm Kg
Not: Please look catalogues for more
details. Min. Bar Max. Bar Max. Bar
S1000.02.125 3/8'' 12,5 0 16 16 48 2.55 C40
STANDARDS
• Standard tube connection G (BSP) (ISO S1000.03.145 1/2'' 14,5 0 16 16 70 3.65 C40
228-1) and other tube connections (NPT S1000.04.170 3/4'' 17 0 16 16 70 3.55 C40
(ANSI 1.20.3)) are available on request. S1000.05.170 1'' 17 0 16 16 90 3.98 C40
• TORK solenoid valves 97/23/EC, are
S1000.06.460 11/4'' 46 0 16 3 450 3.50 C50
available for pressure equipment directive
(PED) and 2006/95/ECC low voltage S1000.07.460 11/3'' 46 0 16 3 450 3.20 C50
directive (LVD). S1000.08.460 2'' 46 0 16 3 450 2.98 C50
www.smstork.com
UNIGAZ QATAR | MATERIAL SUBMITTAL
Check Valves
MATERIAL SUBMITTAL
J4XXXX CFS_PD 2015_genvalves.qxp_Layout 1 18/01/2017 09:41 Page 90
CHECK VALVES
D138 D138
Materials
NO. MATERIAL SIZES Dimensional Drawing
Body Bronze BS EN 1982 CC491K All
Cap Bronze BS EN 1982 CC491K All
Disc Brass BS EN 12164 CW614N 3/
8 -1
Disc Bronze BS EN 1982 CC491K 1 1/
4 -3
Hinge Bronze BS EN 1982 CC491K All
Hinge Pin Stainless Steel 3/
8 -2
Hinge Pin Stainless Steel ASTM A182 Gr.F316 21/2 & 3
Hinge Nut Brass BS EN 12164 CW614N All
ID Plate Aluminium All
Drive Pin Steel - Electro Brassed All
Hinge Pin Plug Brass BS EN 12164 CW614N 21/2 & 3
1 0.61 80 49
11/4 1.01 89 56
11/2 1.34 95 65
2 2.12 108 76
21/2 4.08 155 98
3 5.76 190 99 Pressure/Temperature Ratings
TEMPERATURE (°C) -10 to 100 110 120 186
PRESSURE (BAR) 25.0 23.4 21.8 10.5
PRESSURE RATING: PN25 SPECIFICATION: Metal Disc, Screwed in Cap, BSI Kitemark approved.
TEMPERATURE OPERATING RANGE: -10 To 180°c Valves are manufactured in accordance with BS5154:1991 PN25
UK END CONNECTION: Taper threaded to BS EN 10226-2 (ISO 7-1) for Series B ratings.
formerly BS 21 This valve is not suitable for use on Group 1 gases or unstable fluids, as
US END CONNECTION: ANSI B1.20.1 (please add suffix AT to defined by the Pressure Equipment Directive 97/23/EC.*
denote American Thread)
Vaild as of 201216
Every effort has been made to ensure that the information contained in this publication is accurate at the time of publishing. Crane Ltd assumes no responsibility or liability for typographical errors or
omissions or for any misinterpretation of the information within the publication and reserves the right to change without notice.
Y STRAINER
MATERIAL SUBMITTAL
00
STRAINERS
D297
PN32
Bronze Strainer
Scale and dirt in piping systems cause endless trouble and frequently
serious damage to pipeline equipment. Installation of Crane
strainers will help eliminate the problems caused by foreign matter within
piping systems.
The Crane D297 features: Perforated stainless steel screen, Robust
design, Low flow resistance, High Quality Materials, WRAS approved.
Materials
PART MATERIAL SIZES
SIZE WEIGHT A B C D E
(kg) (mm) (mm) (mm) (mm) (mm)
WITHDRAWAL DISTANCE
1
/2|| 0.38 71 79 30 51 61
E APPROX.
3
/4|| 0.63 86 96 38 64 77
1|| 0.96 101 110 47 72 92 THREADED BSEN10226
formerly BS 21 (ISO 7) TAPER
11/4|| 1.81 134 144 56 100 128 OR ANSI B1.20.1 TAPER
11/2|| 2.43 148 157 65 109 139
2|| 4.13 176 183 79 126 160
OPTIONAL BSP TAPPING
Pressure/Temperature Ratings
TEMPERATURE (°C) -10 to 100 200
PRESSURE (BAR) 32 14
Intermediate pressure ratings shall be determined
by interpolation
Every effort has been made to ensure that the information contained in this publication is accurate at the time of publishing. Crane Ltd assumes no responsibility or liability for typographical errors or omissions or for
any misinterpretation of the information within the publication and reserves the right to change without notice.
BALL VALVE
MATERIAL SUBMITTAL
80-100 series
Bronze LP-Gas Ball Valve
Female NPT Thread, 600 CWP (psig), Cold Non-Shock. 250 psig LP-Gas.
150 psig Saturated Steam.
Vacuum Service to 29 inches Hg.
MSS SP-110 compliant. LISTED
FEATURES ul listings
• UL Listed for LP-Gas, natural gas, flammable liquid and heated oil • Guide YSDT: LP-Gas shut-off valve.
• Large ports to reduce pressure drop • Guide YRPV: Gas shut-off valve for use with natural and
• Reinforced seats manufactured gases.
• Blow-out-proof stem design • Guide YRBX: Flammable liquid shutoff valve.
• Adjustable packing gland • Guide MHKZ: No. 6 oil at 250ºF.
• Two piece bronze body
Copyright ©2013 Apollo Valves, Manufactured by Conbraco Industries - Printed in the USA
H-29
flow data
For Apollo® Ball Valves
The listed Cv “factors” are derived from actual flow testing, in the Apollo® Ball Valve Division, Conbraco Industries, Inc., Pageland, South Carolina.
These tests were completed using standard “off the shelf” valves with no special preparation and utilizing standard schedule 40 pipe. It should
be understood that these factors are for the valve only and also include the connection configuration. The flow testing is done utilizing water
as a fluid media and is a direct statement of the gallons of water flowed per minute with a 1 psig pressure differential across the valve/
connection unit. Line pressure is not a factor. Because the Cv is a factor, the formula can be used to estimate flow of most media for valve sizing.
√ √
∆P (∆P) (P2)
Q = CV Q = 1360 CV
SpGr (SpGr) (T)
Copyright ©2013 Apollo Valves, Manufactured by Conbraco Industries - Printed in the USA
M-3
flow data
For Apollo® Ball Valves
FIREMATIC VALVE
MATERIAL SUBMITTAL
UNIGAZ QATAR | MATERIAL SUBMITTAL
MATERIAL SUBMITTAL
)86,%/(/,1.
3$&.$*(6:,7+9$/9(
)/3/76(5,(6µ7+528*+µ137
3$57180%(56
)/3/7
;;;%9)6 LQFOXGHV66SLHFH$3,ÀUHVDIHYDOYH
)/3/7
;;;%9): LQFOXGHV:&%66SLHFH$3,ÀUHVDIHYDOYH
6HOHFWDOLQNWHPSHUDWXUHIURPWKHFKDUWEHORZ
;;;YDOYHVL]HLH µ µ µ
127(/LQNVPXVWEHUHSODFHGRQDQDQQXDOEDVLVDVSDUWRIDUHJXODU
PDLQWHQDQFHSURJUDP/LQNVDUHQRWUDWHGIRUXVHLQFRUURVLYHDWPRVSKHUHV
12
7
8
10
11 10
8
4 6
D 6
10 7
1 5
E
C 2
3 9
SAFETY LINK
A FOR SHIPPING
TOP VIEW ARMED PURPOSES ONLY
SIDE VIEW
B
%,//2)0$7(5,$/6
',0(16,216
635,1*3$&.
&$5%2167((/ 75,33(5$50
&$5%21
02817,1*%5$&.(7 67((/
6,=( µ µ µ
635,1*3$&.$50,1* 62/'(5('
$ &$5%2167((/ )86,%/(/,1.
$66(0%/< 0(7$/
%
9$/9(23(1&/26( 67$,1/(66
/(9(5 67$,1/(66
6723 67((/ 5(7$,1,1*$50 67((/
&
(32;<&2$7(' )86,%/(/,1. 67$,1/(66
'
635,1*3$&. 67((/ 678'6 67((/
( 9$/9(+$1'/(
67$,1/(66
63$&(5
67$,1/(66
67((/ 67((/
:(,*+7
/%6 67$,1/(66 &$5%21
)/02817,1*3/$7( 6$)(7</,1.
67((/ 67((/
7KHSROLF\RI$9.&DUER%RQGLVRQHRIFRQWLQXRXVLPSURYHPHQW:HUHVHUYHWKHULJKWWRDOWHUWKHSURGXFWDVGHVFULEHGDQGLOOXVWUDWHGZLWKRXWQRWLFH
$9.&DUER%RQG%,72549DOYH$XWRPDWLRQ32%R[1/LQODU'U/D)R[,/ZZZELWRUTFRP
Fusible Link Temperature Selection Chart
FL-1: for 05 through 10 Spring Packs (LT, MT)
LINK PART LINK YIELD MAXIMUM AMBIENT
NUMBER TEMPERATURE TEMPERATURE
FL-1-165 165°F/74°C 135°F/57°C
FL-1-212 212°F/100°C 185°F/82°C
FL-1-286 286°F/138°C 253°F/123°C
FL-1-360 360°F/182°C 330°F/166°C
• Factory Mutual approved; UL and C-UL Listed • Fusible Link Halves: Stainless Steel
• Minimum Continuous Load: 5 lbs. (2,3 kg) • Fusible Assembly: Solder, Copper, Stainless Steel
• Maximum Continuous Load: 50 lbs. (22,7 kg)
NOTE: Model FL-1 Fusible Links are not rated for use in corrosive atmospheres.
BI-TORQ® Valve Automation and our soldered fusible link manufacturers suggest the annual
replacement of fusible links as part of scheduled plant maintenance.
'83/(;
FILTER
MATERIAL SUBMITTAL
TURBINE SERIES
300-watt heaters start you in the cold protection you can install. A system that protects your
– thermostats are standard to meet the
requirements of today’s electronic engines. investment in engines and fuel.
Self-venting drain. A single End caps are colour-coded for easy identification and
twist makes draining clean, application – red for 30 micron primary filtration, blue for
fast and easy.
10 micron primary or secondary, and brown for 2 micron
secondary/final filtration.
14
TURBINE SERIES
500FG 900FH 1000FH 75900FHX 751000FHX 791000FHV
MODEL 500FG 900FH 1000FH 75500FGX 75900FHX 731000FH 751000FHX 771000FH 791000FHV
Maximum 60 gph 90 gph 180 gph 120 gph 180 gph 360 gph 180 / 360 gph 540 gph 360 / 540 gph
Flow Rate 227 lph 341 lph 681 lph 454 lph 681 lph 1363 lph 681 / 1363 lph 2044 lph 1363 / 2044 lph
Height 11.5" / 292 mm 17" / 432 mm 22" / 559 mm 11.5" / 292 mm 17" / 432 mm 22" / 559 mm 22" / 559 mm 22" / 559 mm 22" / 559 mm
Width 5.8" / 147 mm 6" / 152 mm 6" / 152 mm 14.5" / 368 mm 18.75" / 476 mm 16.5" / 419 mm 18.75" / 476 mm 21.5" / 546 mm 21.5" / 546 mm
Depth 4.8" / 122 mm 7" / 178 mm 7" / 178 mm 9.5" / 241 mm 11" / 279 mm 12" / 305 mm 11" / 279 mm 12" / 305 mm 12" / 305 mm
Weight 4 lbs / 1.7 kgs 6 lbs / 2.7 kgs 10 lbs / 4.5 kgs 17 lbs / 7.7 kgs 23 lbs / 10.4 kgs 26 lbs / 11.8 kgs 30 lbs / 13.6 kgs 39 lbs / 17.7 kgs 52 lbs / 23.6 kgs
Port Size Std. 3/4"-16 UNF 7/8"-14 UNF 7/8"-14 UNF 3/4"-16 UNF 7/8"-14 UNF 1 3/4" NPT 7/8"-14 UNF 1 1"-11 1/2 NPT 3/4" NPT
(Option) 16 mm x 1.5 22 mm x 1.5 22 mm x 1.5
Clean Pressure 0.25 psi 0.34 psi 0.49 psi 0.70 psi 1.7 psi 1.7 psi 3.7 psi 1.7 psi 2.5 psi
Drop 1.72 kPa 2.4 kPa 3.4 kPa 4.83 kPa 11.7 kPa 11.7 kPa 25.5 kPa 11.7 kPa 17.2 kPa
Maximum 15 psi 15 psi 15 psi 15 psi 15 psi 15 psi 15 psi 15 psi 15 psi
Operating Pres. 103 kPa 103 kPa 103 kPa 103 kPa 103 kPa 103 kPa 103 kPa 103 kPa 103 kPa
Element # 2010 2040 2020 2010 2040 2020 2020 2020 2020
Element 4" / 102 mm 5" / 127 mm 10" / 254 mm 4" / 102 mm 5" / 127 mm 10" / 254 mm 10" / 254 mm 10" / 254 mm 10" / 254 mm
Removal
Clearance
For complete part numbers references please refer to www.racor.com and select 7480 product catalogue from the literature tab.
15
UNIGAZ QATAR | MATERIAL SUBMITTAL
MATERIAL SUBMITTAL
GENESYS+ 7M
GENERAL
Wet stock management up to 32 tanks
Wide graphical display with capacitive graphical 7” TFT 1280x800 touch screen
Easy and smart configuration tools through local graphical interface
Remote web-configuration and web-monitoring
Host communication protocols Gilbarco, Veeder-Root & Modbus
Automatic reconciliation
Dynamic and statically leakage tests
Tank auto-calibration
Deliveries, trends, events, alarms recording
Product level/mm Interface level/mm (water presence detection) display
Gross and compensated volume at 15 °C or 20 °C in liters
Product mean temperature 5 temp. sensors
Volume of empty part in liters (ullage)
SYSTEM
Quad Core Cortex-A9 1.4 GHz
A MMC Boot (Operating System, Application, Configuration is stored at internal memory. SD Card
only for initialization)
1 GB RAM Memory
Internal storage event recording
Gigabit ethernet as default
MECHANICAL
Metal Enclosure
Enclosure dimensions 300 x 180 x 70 mm
ELECTRICAL
Power supply 210-230 Vac
N.2 Digital Input
N.4 Digital Output
Can be extended to N.8 DI and N.16 DO with external I/O Module
RS 485 field bus wiring
N. 2 RS 232 (communication to POS and/or serial printer) Ethernet port
N. 1 USB ports
GENESYS+ 7M BASIC
OPTIONAL (ADDITIONALS)
Embedded GPRS
HDMI Output
GPS
Bluetooth
UNIGAZ QATAR | MATERIAL SUBMITTAL
LEVEL TRANSMITTER
MATERIAL SUBMITTAL
NF-RS
Wired Fuel & Water Probe
NF - RS 5M
GENESYS+
GENERAL
NF RS wired fuel &water probe is a level sensor which measures the level of fuel and
water and the temperature of the liquid in the tank. The measurements are transmitted
via RS485 wired bus.
It’s electronics is based on a powerful microprocessor technology and the
measurements are accurate and sensitive.
Measurement accuracy: +/- 0,5 mm.
Measurement resolution: +/- 0,05 mm.
Temperature accuracy: +/- 0,2°C
It is intrinsically safe suitable for 0 zone, hazardous areas.
Full stainless steel execution
Ultra compact design
Measuring range 0,4 m up to 5,5 m
COMMUNICATION
Baudrate : 9600
Databit : 8
Stopbit : 1
Parity : None
Transmission is wired, maximum transmission distance: up to 1 Km based on standard
of RS485 interface with proper data cable.
Proprietary Rs485 data protocol .
The serial number is unique and corresponds to the probe address for the consequent
configuration into the electronics control.
ELECTRICAL
Ultra low power mode
Nominal power supply 12 Vdc (30Vmax) through an intrinsically safe barrier.
Consumption in normal functioning <15 mA @ 12 Vdc(25mA LPM)
Consumption in sleep mode functioning < 200 uA @12 Vdc
Ui = 30V
Ii = 100mA
Ci = trascurabile/negligible
Li = trascurabile/negligible
MECHANICAL
Stainless steel case, IP68.
Probe shaft Stainless Steel AISI 304 / 316
Dimensions might change according to the shaft length up
p to 500 cm.
ENVIRONMENTAL
Operating Temperature Range: Tamb = -40 +80°C
UNIGAZ QATAR | MATERIAL SUBMITTAL
MATERIAL SUBMITTAL
LS SERIES
GENERAL
Providing a wide range of applications with its polyamide material construction, LS series is level
switches ensuring Normally On or Normally Off contact. it may be attached to the reservoir on the
top or bottom. PP (Polypropylene} material is suitable tor water and dilute acid applications and PA
(Polyamide} material for oil and fuel applications.
Material : PP or PA
Connection: M8 Thread
Quantity of Contact: 1 x NO or NC
APPLICATIONS
Interstitial space of double wall tanks
Containment sumps
Dispenser pans
Other applications requiring the detection of a liquid leak
LS-B LS-I
www.northfalconenergy.com
DUDULLU OSB DES-1/10 ISTANBUL TURKEY
UNIGAZ QATAR | MATERIAL SUBMITTAL
MATERIAL SUBMITTAL
GENESYS+ 5M
GENERAL
Wet stock management up to 32 tanks
Wide graphical display with capacitive graphical 5” TFT 800x600 touch screen
Easy and smart configuration tools through local graphical interface
Remote web-configuration and web-monitoring
Host communication protocols Gilbarco, Veeder-Root & Modbus
Automatic reconciliation
Dynamic and statically leakage tests
Tank auto-calibration
Deliveries, trends, events, alarms recording
Product level/mm Interface level/mm (water presence detection) display
Gross and compensated volume at 15 °C or 20 °C in liters
Product mean temperature 5 temp. sensors
Volume of empty part in liters (ullage)
SYSTEM
Quad Core Cortex-A9 1.4 GHz
A MMC Boot (Operating System, Application, Configuration is stored at internal memory. SD Card
only for initialization)
1 GB RAM Memory
Internal storage event recording
Gigabit ethernet as default
MECHANICAL
Metal Enclosure
Enclosure dimensions 300 x 180 x 70 mm
ELECTRICAL
Power supply 210-230 Vac
Can be extended to N.8 DI and N.16 DO with external I/O Module
RS 485 field bus wiring
N. 2 RS 232 (communication to POS and/or serial printer) Ethernet port
N. 1 USB ports
GENESYS+ 5M BASIC
OPTIONAL (ADDITIONALS)
Embedded GPRS
HDMI Output
GPS
Bluetooth
4 Digital Input + 2 Digital Output
www.northfalconenergy.com
DUDULLU OSB DES-1/10 ISTANBUL TURKEY
UNIGAZ QATAR | MATERIAL SUBMITTAL
LEVEL SWITCH
MATERIAL SUBMITTAL
NF-RSJr
Wired Fuel Sensor
NF - RSJr
GENERAL
NF RS wired fuel sensor is a level sensor which measures the level of fuel and the
temperature of the liquid in the tank. The measurements are transmitted via RS485
wired bus.
It’s electronics is based on a powerful microprocessor technology and the
measurements are accurate and sensitive.
Measurement accuracy: +/- 0,5 mm.
Measurement resolution: +/- 0,05 mm.
Temperature accuracy: +/- 0,2°C
It is intrinsically safe suitable for 0 zone, hazardous areas.
Full stainless steel execution
Ultra compact design
Measuring range 0,4 m up to 5,5 m
COMMUNICATION
Baudrate : 9600
Databit : 8
Stopbit : 1
Parity : None
Transmission is wired, maximum transmission distance: up to 1 Km based on standard
of RS485 interface with proper data cable.
Proprietary Rs485 data protocol .
The serial number is unique and corresponds to the probe address for the consequent
configuration into the electronics control.
ELECTRICAL
Ultra low power mode
Nominal power supply 12 Vdc (30Vmax) through an intrinsically safe barrier.
Consumption in normal functioning <15 mA @ 12 Vdc(25mA LPM)
Consumption in sleep mode functioning < 200 uA @12 Vdc
Ui = 30V
Ii = 100mA
Ci = trascurabile/negligible
Li = trascurabile/negligible
MECHANICAL
Stainless steel case, IP68.
Probe shaft Stainless Steel AISI 304 / 316
Dimensions might change according to the shaft length up to 500 cm.
ENVIRONMENTAL
Operating Temperature Range: Tamb = -40 +80°C
| UNIGAZ QATAR |
CONTROL PANEL
MATERIAL SUBMITTAL
Electric transformers
Voltage Stabilizers
Frequency converters
UPS, Inverters, Power supplies
TECHNICAL SPECIFICATION:
Rated power from 50VA to 3000VA
Input voltage 220-230-240-380-400-415V *
Output voltage 12+12 (24)V or 24+24 (48)V or 55/110V or 110+110 (220)V *
Frequency 50/60 Hz
Grade of protection IP00
Protection class I
Isolation class E
Winding isolation class F-H
Max ambient temperature 40°C
Max temperature rise 90°C
Max full load voltage regulation 3,5%
Short circuit voltage 6% max
Efficiency > 95%
Applied standards CEI EN61558-2-4 or CEI- EN61558-2-6
* different input/output voltages available on request last 3/4 digits of part numbers changing according to voltage combination
FEATURES
Earth connection
Wiring connections on two sides
Rating label
PART NUMBERS
K-FACTOR SRL unipersonale - Via Giotto 9 42014 Castellarano (RE) - Italy - VAT# IT 02422010369
ISO9001
Electric transformers
Voltage Stabilizers
Frequency converters
UPS, Inverters, Power supplies
ELECTRICAL CHARACTERISTIC
On request a version with copper earthed screen between the windings is available
K-FACTOR SRL unipersonale - Via Giotto 9 42014 Castellarano (RE) - Italy - VAT# IT 02422010369
ISO9001
Sample
UNIGAZ QATAR | MATERIAL SUBMITTAL
FUEAL TRANSFER
GEAR PUMP
MATERIAL SUBMITTAL
SAMPLE NAME PUMP PLATES
Note: Kindly consider the above model and series as sample for reference.
VIKING PUMP, INC.
A Unit of IDEX Corporation
406 State Street
Cedar Falls, IA 50613-0008 U.S.A.
Phone: 319-266-1741
Fax: 319-273-8157 International Fax: 319-273-8414
www.vikingpump.com
With reference to the subject enquiry, we wish to confirm that IDEX INDIA PVT LTD are the
manufacturers of DFO Skids for Viking Pump USA & India & hereby are authorized to supply
DFO skids in the Qatar region.
For the subject project, we are hereby authorize M/S Diligent Trading & Contracting to supply
(DFO skids, Spares Parts & Services) as per IDEX Corporation USA Global Sales Policy and
Standards. These supplies are covered under Viking Pump Inc standard sales warranty terms.
This letter is valid till the further notice unless otherwise notified. Pl feel free to contact us for
any clarification.
Khurram Hashmi
Regional Sales Manager-Viking Pump
IDEX Middle East
SUPPLY PUMP - HEAD LOSS CALCULATION (Longest route)
PROJECT NAME : Construction of Terminal Pumping Station at Doha North STW Package 3-C823/3
Design Data FUEL PUMP selected : GG4195
Fluid: Diesel Supply Pump from Main Tank to Day tank
Viscosity : 7Cps Pump Flow (L/s) 0.586
Sp. Gravity : 0.85 Pump Pressure (Bar) 2 bar
Temp.: 50 deg Pipe size ( mm) 40
Flow friction
Pipe Size Nos of Equivalen
Length rate Velocity(V) Re factor Friction Loss
Node Description (D) Fittings t length
(Q) (f)
mm m No. m L/s m/s / / m
Horizintal
1 pipe 40 15 15 0.586 0.47 3115.60 0.04 0.183
90 degree
2 elbow 40 8 7.2 0.586 0.47 3115.60 0.04 0.088
3 ball valve 40 4 1.2 0.586 0.47 3115.60 0.04 0.015
4 Y Strainer 40 2 6.8 0.586 0.47 3115.60 0.04 0.083
check valve 40 1 2.9 0.586 0.47 3115.60 0.04 0.035
Pump Series Pump Size Viscosity Units Differential Pressure Units Specific Gravity
Input Speed: 1450 (RPM) Calculated Flow: 35.9 (L/min) Power at Input Speed: 0.02 (BHP) / NPSHr: 5.6 (Ft H2O)
0.01 (kW)
1 of 2 8/1/2022, 2:14 PM
Curve Generator | Curve Generator https://www.vikingpumpcurve.com/
2 of 2 8/1/2022, 2:14 PM
UNIGAZ QATAR | MATERIAL SUBMITTAL
CS PIPE SCH 40
MATERIAL SUBMITTAL
Oil and Gas Pipes
SEAMLESS PIPES
ASTM A 106/A106 M,
ASTM A 53/A 53 M, ASTM A 333/A 333 M
Application: for producing structures, as well as for steam, water, gas and air pipelines for operations at
low temperatures, and also in general machine-building and tool-making.
Steel grade — A, B, C, Gr 6
— Upon agreement
5
Pipe dimensions and weight
Outside dismeter Wall thickness Weight per length unit
Nominal size Weight class Schedule
in mm in mm lb/ft kg/m
0.156 3.96 7.24 10.78
0.172 4.37 7.95 11.85
0.188 4.78 8.67 12.91 30
0.203 5.16 9.32 13.89
0.219 5.56 10.02 14.91
0.237 6.02 10.80 16.07 STD 40
4 4.500 114.3 0.250 6.35 11.36 16.91
0.281 7.14 12.67 18.87
0.312 7.92 13.97 20.78
0.337 8.56 15.00 22.32 XS 80
0.438 11.13 19.02 28.37 120
0.531 13.49 22.53 33.54 160
0.674 17.19 27.59 41.03 XXS
0.258 6.55 14.63 21.76 STD 40
0.375 9.52 20.79 30.85 XS 80
5 5.563 141.3 0.500 12.7 27.06 40.28 120
0.626 15.88 32.99 49.10 160
0.750 19.05 38.59 57.43 XXS
0.172 4.37 11.87 17.67
0.188 4.78 12.94 19.28
0.203 5.16 13.94 20.76
0.219 5.56 15.00 22.31
0.250 6.35 17.04 25.36
0.280 7.11 18.99 28.26 STD 40
0.312 7.92 21.06 31.32
0.344 8.74 23.10 34.39
6 6.625 168.3
0.375 9.52 25.05 37.28
0.432 10.97 28.60 42.56 XS 80
0.500 12.70 32.74 48.73
0.562 14.27 36.43 54.20 120
0.719 18.26 45.39 67.56 160
0.750 19.05 47.10 70.12
0.864 21.95 53.21 79.22 XXS
0.875 22.23 53.78 80.08
0.250 6.35 22.38 33.31 20
0.277 7.04 24.72 36.31 30
0.312 7.92 27.73 41.24
0.322 8.18 28.58 42.55 STD 40
0.344 8.74 30.45 45.34
0.375 9.52 33.07 49.20
0.406 10.31 35.67 53.08 60
0.438 11.13 38.33 57.08
8 8.625 219.1
0.500 12.70 43.43 64.64 XS 80
0.562 14.27 48.44 72.08
0.594 15.09 51.00 75.92 100
0.719 18.26 60.77 90.44 120
0.812 20.62 67.82 100.92 140
0.875 22.22 72.49 107.88 XXS
0.906 23.02 74.76 111.27 160
1.000 25.40 81.51 121.33
0.250 6.35 28.06 41.76 20
0.279 7.09 31.23 46.49
0.307 7.80 34.27 51.01 30
10 10.750 273.0
0.344 8.74 38.27 56.96
0.365 9.27 40.52 60.29 STD 40
0.438 11.13 48.28 71.87
6
Pipe dimensions and weight
Outside dismeter Wall thickness Weight per length unit
Nominal size Weight class Schedule
in mm in mm lb/ft kg/m
0.500 12.70 54.79 81.52 XS 60
0.594 15.09 64.49 95.97 80
0.719 18.26 77.10 114.70 100
0.844 21.44 89.38 133.00 120
1.000 25.40 104.23 155.09 XXS 140
1.125 28.58 115.75 172.27 160
1.250 31.75 126.54 188.90
0.281 7.14 37.46 55.76
0.312 7.92 41.48 61.70
0.330 8.38 43.81 65.19 30
0.344 8.74 45.69 67.91
0.375 9.53 49.61 73.86 STD
0.406 10.31 53.57 79.71 40
0.438 11.13 57.65 85.82
0.500 12.70 65.48 97.44 XS
0.562 14.27 73.22 108.93 60
0.625 15.88 81.01 120.59
12 12.750 323.8 0.688 17.48 88.71 132.05 80
0.750 19.05 95.21 143.17
0.812 20.62 103.63 154.17
0.844 21.44 107.42 159.87 100
0.875 22.23 111.08 165.33
0.983 23.83 118.44 176.29
1.000 25.40 125.61 186.92 XXS 120
1.062 26.97 132.69 197.43
1.125 28.58 139.81 208.08 140
1.250 31.75 153.67 228.68
1.312 33.32 160.42 238.69 160
0.312 7.92 45.61 67.9 20
0.344 8.74 50.17 74.76
0.375 9.53 54.57 81.33 STD 30
0.406 10.31 59.00 87.79
0.438 11.13 63.44 94.55 40
0.469 11.91 67.84 100.95
0.500 12.7 72.16 107.40
0.562 14.27 80.73 120.12
0.594 15.09 85.05 126.71 60
0.625 15.88 89.36 133.04
14 14.000 355.6 0.688 17.48 97.91 144.76
0.750 19.05 106.13 158.10 80
0.875 22.23 122.17 182.76
0.938 23.83 194.96 130.85 100
1.094 27.79 224.65 150.79 120
1.250 31.75 253.56 170.21 140
1.406 35.71 281.70 189.11 160
2.000 50.8 381.83 256.32
2.125 53.97 401.50 269.50
2.200 55.88 413.01 277.25
2.500 63.5 457.40 307.05
0.344 8.8 57.57 85.71
0.375 9.53 62.64 93.27 STD 30
0.406 10.31 67.68 100.71
0.438 11.13 72.86 108.49
16 16 406.4
0.469 11.91 77.87 115.87
0.500 12.7 82.85 123.31 XS 40
0.562 14.27 92.75 138
0.625 15.88 102.72 152.94
— Upon agreement
7
Pipe dimensions and weight
Outside dismeter Wall thickness Weight per length unit
Nominal size Weight class Schedule
in mm in mm lb/ft kg/m
0.656 16.66 107.76 160.13 60
0.688 17.48 112.62 167.66
0.750 19.05 122.27 181.98
0.812 20.62 131.84 196.18 80
0.844 21.44 136.74 203.54
0.875 22.23 141.48 210.61
0.938 23.83 151.03 224.83
16 16 406.4 1.000 25.4 160.35 238.66 100
1.031 26.19 164.98 245.57
1.062 26.97 169.59 252.37
1.125 28.58 178.89 266.3
1.188 30.18 188.11 280.01 120
1.219 30.96 192.61 286.66
1.250 31.75 197.1 293.35 140
1.438 36.53 223.85 333.21
— Upon agreement
DIN EN 10255
UNALLOYED STEEL TUBES SUITABLE FOR WELDING AND THREADING
Weight per
Wall thickness, Weight per
max. min. Wall thickness. mm length unit,
mm length unit, kg/m
kg/m
26.9 27.3 26.3 3.2 1.87 2.6 1.56
33.7 34.2 33.3 4.0 2.9 3.2 2.41
42.4 42.9 42.0 4.0 3.79 3.2 3.1
48.3 48.8 47.9 4.0 4.37 3.2 3.56
60.3 60.8 59.7 4.5 6.19 3.6 5.03
S 195 Т
76.1 76.6 75.3 4.5 7.93 3.6 6.42
88.9 89.5 88.0 5.0 10.3 4.0 8.36
114.3 115.0 113.1 5.4 14.5 4.5 12.2
139.7 140.8 138.5 5.4 17.9 5.0 16.66
165.1 166.5 163.9 5.4 21.3 5.0 19.88
— Upon agreement
8
9
CARBON STEEL GRADE B PIPES - ASTM A53M, A106M, API 5L, Seamless
Page 1 of 3 www.pietraspa.com 72
SEAMLESS Pipes & Tubes
Engineered for diverse applications
Billets Heating Billet Centering Piercing Elongation Plug Rolling Reeler Rolling Reheating
Tempering Furnace Quenching Austenising Furnace Hydrotesting / NDT Straightening End Cutting Cooling Bed Sizing
Hot Sizing Straightening End Cutting NDT Threading Coupling Screw up Drift Testing Hydrostatic Testing Finishing & Despatch
Maharashtra Seamless Ltd, India
Maharashtra Seamless Limited (“MSL”) a flag-ship company of DP Jindal Group (with combined turnover of around USD 1 Billion)
established for over 25 years is pioneer in manufacturing Seamless/Welded Steel Pipe & OCTG in India. It is the largest manufacturer of
Seamless Steel Pipe and Tubes in India both in terms of capacity and product range. The company specializes in providing Piping
Solutions (Steel, Alloy) to Oil and Gas (Exploration, Drilling Transmission etc.), Petrochemical, Structural & Mechanical Sectors across
the globe.
Product Profile:
Sr. Piping Variant Dimensional Standards & Grades Critical Application Annual
No. Capability (Outer Production
Diameter) Capacity
1 Seamless Line Pipe ½” - 14” API 5L (Grade-B to X-70) Sour, Non Sour 550,000 MT
ASTM (A106 Gr-B, A 53, A333 Gr-6 Structural
EN 10216, EN10210, EN 10255, EN Application
10297. Mechanical
ASME/ASTMSA/A-53/106/ Boiler
178/179/192/209/210/213/ 214/335 Application
2 Seamless Tubing 2 3/8”- 4 ½” API 5CT (J55, K55, N80Q, N80, L80, EUE, NUE
P110, Q125, T95, C110).
3 Seamless Casing 4 ½” - 13 3/8” API 5CT (J55, K55, N80Q, N80, L80, High Collapse,
P110, Q125, T95, C110). Special Drift.
API Connections (BTC, LTC, STC)
4 Coupling Stock Pipe 2 3/8”- 13 3/8” API 5CT (J55, K55, N80Q, N80, L80, For BTC, LTC, STC
and Finished Coupling P110, Q125, T95, C110). connections
5 Drill Pipes 2 3/8 to 5 ½” API 5D, E, X, G & S PSL 1, 2, 3 IUE, EUE & IEUE
6 ERW Line Pipes 8” - 20” API 5L (Grade-B to X-70) Sour, Non Sour 200,000 MT
7 ERW Casings 8 5/8”, 9 5/8” & 10 API 5CT (J55 & N-80)
¾”
8 External Coating 1” – 48” DIN 30670 & DIN 30678 Coating Thickness 300 Sq. Mtr / Hour
3 Layer PE, Upto 3.7mm
3 Layer PP Upto 3.7mm
Single layer FBE Upto 0.5mm
Dual Layer FBE Upto 1mm
9 Internal Epoxy Coating 6”-22” DIN 30670 & DIN 30678 Upto 50 – 60 125 Sq. Mtr / Hour
micron
Major Quality Accreditations: “MSL” manufacturing facilities are accredited with renowned international agencies for
certifications of API 5L, API 5CT, API 5DP, Quality Systems ISO 9001:2008, Environment Management ISO 14001:2008 and
Occupational Health and Safety management Systems OHSAS 18001:2007, PED Certificate, CE Certificate for structur al pipes.
Major International Client Approvals: “MSL” products are on approved list of various national and International end-user Oil
and Gas companies for their Exploration and transportation programs. Our list of clients includes Shell Global Services, Petroleum
Development Company-Oman, Statoil-USA, Kuwait Oil Company-Kuwait, Saudi Aramco-Saudi Arabia, Exxon Mobil-USA, Joint
Operations-Kuwait, Occidental -Oman to name a few.
International Exposure : “MSL” is exporting close to 40% of its turnover to International markets in USA, Canada, Mexico,
Columbia, Brazil, Italy, Spain, Poland, Kuwait, Oman, UAE, Saudi Arabia, Egypt, Vietnam, East Africa etc.
Please write to us at contact@mahaseam.com or sales@gvnfuels.com for all your export related enquiries or any other information
desired by your goodself. For detailed overview, pls. visit our website www.jindal.com.
DIMENSION AND WEIGHT
Nominal SCHEDULE WALL THICKNESS (mm) / WEIGHT (kg/m)
Pipe Size OD Sch Sch Sch Sch STD Sch XS Sch Sch Sch Sch Sch Sch XXS
mm/inch mm 5 10 20 30 40 60 80 100 120 140 160
6 10.3 - 1.24 - - 1.73 1.73 2.41 - 2.41 - - - - -
1/8 - 0.28 - - 0.37 0.37 0.47 - 0.47 - - - - -
8 13.7 - 1.65 - - 2.24 2.24 3.02 - 3.02 - - - - -
1/4 - 0.49 - - 0.63 0.63 0.80 - 0.80 - - - - -
10 17.1 - 1.65 - - 2.31 2.31 3.20 - 3.20 - - - - -
3/8 - 0.63 - - 0.84 0.84 1.10 - 1.10 - - - - -
15 21.3 1.65 2.11 - - 2.77 2.77 3.73 - 3.73 - - - 4.78 7.47
1/2 0.80 1.00 - - 1.27 1.27 1.62 - 1.62 - - - 1.95 2.55
20 26.7 1.65 2.11 - - 2.87 2.87 3.91 - 3.91 - - - 5.56 7.82
3/4 1.03 1.28 - - 1.69 1.69 2.20 - 2.20 - - - 2.90 3.64
25 33.4 1.65 2.77 - - 3.38 3.38 4.55 - 4.55 - - - 6.35 9.09
1 1.29 2.09 - - 2.50 2.50 3.24 - 3.24 - - - 4.24 5.45
32 42.2 1.65 2.77 - - 3.56 3.56 4.85 - 4.85 - - - 6.35 9.70
11/4 1.65 2.69 - - 3.39 3.39 4.47 - 4.47 - - - 5.61 7.77
40 48.3 1.65 2.77 - - 3.68 3.68 5.08 - 5.08 - - - 7.14 10.15
11/2 1.90 3.11 - - 4.05 4.05 5.41 - 5.41 - - - 7.25 9.55
50 60.3 1.65 2.77 - - 3.91 3.91 5.54 - 5.54 - - - 8.74 11.07
2 2.39 3.93 - - 5.44 5.44 7.48 - 7.48 - - - 11.11 13.44
65 73.0 2.11 3.05 - - 5.16 5.16 7.01 - 7.01 - - - 9.53 14.02
21/2 3.69 5.26 - - 8.63 8.63 11.41 - 11.41 - - - 14.92 20.39
80 88.9 2.11 3.05 - - 5.49 5.49 7.62 - 7.62 - - - 11.13 15.24
3 4.52 6.46 - - 11.29 11.29 15.27 - 15.27 - - - 21.35 27.68
90 101.6 2.11 3.05 - - 5.74 5.74 8.08 - 8.08 - - - - -
31/2 5.18 7.41 - - 13.57 13.57 18.64 - 18.64 - - - - -
100 114.3 2.11 3.05 - - 6.02 6.02 8.56 - 8.56 - 11.13 - 13.49 17.12
4 5.84 8.37 - - 16.08 16.08 22.32 - 22.32 - 28.32 - 33.54 41.03
125 141.3 2.77 3.40 - - 6.55 6.55 9.53 - 9.53 - 12.70 - 15.88 19.05
5 9.46 11.56 - - 21.77 21.77 30.97 - 30.97 - 40.28 - 49.12 57.43
150 168.30 2.77 3.40 - - 7.11 7.11 10.97 - 10.97 - 14.27 - 18.26 21.95
6 11.31 13.83 - - 28.26 28.26 42.56 - 42.56 - 54.21 - 67.57 79.22
200 219.10 - - 6.35 7.04 8.18 8.18 12.70 10.31 12.70 15.09 18.26 20.62 23.01 22.23
8 - - 33.32 36.82 42.55 42.55 64.64 53.09 64.64 75.92 90.44 100.93 111.27 107.93
250 273.00 3.40 4.19 6.35 7.80 9.27 9.27 12.70 12.70 15.09 18.26 21.44 25.40 28.58 25.40
10 22.61 27.78 41.76 51.01 60.29 60.29 81.53 81.53 95.98 114.71 133.01 155.10 172.27 155.10
300 323.80 - - - 8.38 9.53 10.31 12.70 14.27 17.48 21.44 25.40 28.58 33.32 25.40
12 - - - 65.19 73.86 79.71 97.44 108.93 132.05 159.87 186.92 208.08 238.69 186.92
350 355.60 - - - 9.53 9.53 11.13 12.70 15.09 19.05 23.83 27.79 31.75 35.71 -
14 - - - 81.33 81.33 94.55 107.40 126.72 158.11 194.98 224.66 253.58 281.72 -
400 406.40 - - - 9.53 9.53 12.70 12.70 16.66 21.44 - - - - -
16 - - - 93.27 93.27 123.31 123.31 160.12 203.54 - - - - -
450 457.00 - - 9.53 11.13 9.53 14.27 12.70 19.05 23.83 - - - - -
18 - - 105.17 122.38 105.17 155.81 139.16 205.75 254.57 - - - - -
500 508.00 - - 9.53 12.70 9.53 15.09 12.70 20.62 26.19 - - - - -
20 - - 117.15 155.13 117.15 183.43 155.13 247.84 311.19 - - - - -
NOTE : Weights are specified for Plain end Pipes.
Applications & Specifications:
AUTOMOTIVE INDUSTRY
HYDROCARBON PROCESS
OIL & GAS SECTOR
API 5L/ ISO 3183 ASTM : A-53, A-333, A-334, ASTM : A-519
A-335 SAE : 1010, 1012,
IS/ ISO 3183
BS : 3602 (Pt-I), 3603 1020, 1040,
API 5CT INDUSTRY 1518, 4130
IS : 6286
API 5DP
DIN : 2391, 1629
BS : 980, 6323 (Pt-V)
IS : 3601, 3074
MECHANICAL, STRUCTURAL,
& GENERAL ENGINEERING
BOILER, HEAT EXCHANGER,
SUPER HEATER & CONDENSER
ASTM : A-106, A-178, A-179, IS : 1239 (Pt-I), 3589, IS 4270 ASTM : A-500, A-501,
A-192, A-209, A-210, A-213, A-519
BS : 1387
A-214
DIN : 1629, 1630,
DIN : 2440, 2441
BS : 3059 (Pt-I & Pt-II), 2391, 17100,
EN 10216 (Pt-I & Pt-II) 17200
3602 (Pt-1)
BS : 980, 1775,
IS : 1914, 2416, 11714, 4923 3601, 6323
DIN : 17175 IS : 1161, 3601, 9295
HYDRAULIC CYLINDER
WATER WELL
RAILWAYS
SAE : 52100
DIN : 100 Cr6
Corporate Office:
Plot No. 30, Institutional Sector - 44, Gurgaon-122 002, Haryana (India)
Tel.: +91 124 2574325 / 26, 4624000 Fax: +91 124 2574327
e-mail: contact@mahaseam.com
website: www.jindal.com
MSL # 13-113
Branch Offices:
Mumbai Kolkata Chennai
402, Sarjan Plaza, 100, Dr. Annie Besant Road, Sukh Sagar Apartment, 3A, Royal Court, No-44, 3rd Floor,
Opp. Telco Show Room, Worli, Flat No. 8 A&B, 8th Floor, Venkatanarayana Road, T. Nagar, Chennai - 600
2/5 Sarat Bose Road, 017 (India)
Mumbai - 400 018 (India)
Tel.: +91 44 24342231, 24328747
Tel.: +91 22 24902570 /72 /74 Kolkata -700 020 (India)
Tel.: +91 33 24559982, 32588626 Fax : +91 44 24347990
Fax : +91 22 24925473 e-mail: chennai@mahaseam.com
Fax : +91 33 24742290
e-mail: mslmum@mtnl.net.in
e-mail: kolkata@mahaseam.com
74
75
Dimensional range, weight and maximum length according to
ASTM A 53:2006, ASTM A 106:2006, ASTM A 333:2005
76
UNIGAZ QATAR | MATERIAL SUBMITTAL
WELDED FITTINGS
MATERIAL SUBMITTAL
UNIGAZ QATAR | MATERIAL SUBMITTAL
THREADED FITTINGS
MATERIAL SUBMITTAL
| UNIGAZ QATAR |
PAINT
MATERIAL SUBMITTAL
!"!
A3896
8 012345637589
37
#$%&'()(!
#&('%!'*&)!(
+,5-.5-.3.7/8.0818997.843156.0236.8.08375945.67.,3-.3.448--.7595-,./57,.7353.448--.37975895.+8.8.
2-6.3-.780837.59.3718-,350.995389197-5
P)%*
J3359F
Q0811966.783.78-56.60R.396.-23-73207235
B3870759F
@257384.783.3./56.3394.87.5962-73534.-7320723-5
STUVW
:))&(;*'&!<!*
=886.>8145397./57,.?@A.=
A.+574..B337.5CDD.783.63.-8456-
E,9.2-6.3-.337.87.39.33896.-0,1.7,5-.1373534.,3-.7,.78448/594.037575037589F
G.H8/.=431.@336.59.300836390./57,.I?.
530759.783.J3359.IK251975.A3896.59.300836390./57,.337-..
396..87.A99..87..6JL.DD.=+B.>86.83.B337-..396..87.A99..87.6JL.=+B>./,9.59.08145390./57,.
6JL.DD.=+B.>86.>,5.M
>89-247.823.N8729.33-973759.783.67354-5
A665758934.037575037-.396.338934-.13.8.39354384.89.3K2-75
O((%&*
300836594.78.084823.0336.396.J247508483.6962-73.7597594.--71.1J>6
#&('%!'!
#&()&!P *!X"!'&' *&)!(
@8456-.8.98421 6@L.CCC DY..Z
[48--.494.1[?.
D.\ 6@L.MC 448--.1DGM
=43-,.8597 6@L.C
b.J7,86. .\>
9-57 034024376 CR4]4
2L>G?@]^894._894 ?@.IBA.17,86.`.17-76 `DD.4]4
2L>GI? 6I
.1DD]]I?.1034024376 `C`.4]4
2L>G>,593 [d]+.CbMGDDb.16@L.MbDG.17-76 `.4]4
+,.389566.6373.5-.75034.783.730783.386206.386207-.-28a07.78.-454,7.933537589.696594.89.0848235
A44.6373.5-.93456.783.156.35975
[48--.6-0357589F.A00836594.78.N8729.B37831390.>837594-c.6759575895
37.87.5--2F M.e89183.D
B34F.]
+,5-.+0,95034.
373.@,7.-23-6-.7,8-.39582-4.5--265
+,.+0,95034.
373.@,7.1+
@.5-.30811966.78.8.336.59.089a2907589./57,.7,.@377.
373.@,7.1@
@.396.7,.
A45037589.[256.1A[.783.7,5-.3862075.=83.823.933-7.48034.N8729.87750.43-.95-57.823./8-57.37.///5a87295081
01234526796
6311
14 6026
57
35241126
0-526712141125.526
5464
1
!"#$%% /0 ; 60 8
&$!"#$%% 10 ; 230 8
' $($!)%*$)+#,)$ 2345 ; 147 9:
.621166
54
'(%$!@$)%#,)+ $%(#($%@A%$P@$#*(+@!)%@)!$%% )A$!$)#4+)#+$$()#
!(#)#)(#G
.621166
546-
6<71
.621166
54
<
6
1 =545 >12141
?()$+%@)!$% ?$)#4+)#+@#+)),$+!(*)A$ ?$)#4+)#+@#+)),$+!(*)A$
!()#,BCDE23F//;/6G2H !()#,BCDE23F//;/6G2H
I7526
54
I7526
541
3
' $*(+@!!)#A$)**$+A
D*)J K%$)$%%%*)G
L@% J M$!($#+$+(%*$!()#,)#+%))$)%G?)$@%A$)"$#()! $N$$
%*$!$++!"#$%%G
M($J O)A$@%$+G?)$@%A$)"$#()! $N$$%*$!$++!"#$%%G
2
5Q54
6
5R<-S71T
U$#,@)+'(*!()?(*V /*)B%H
U$#,@)+?(*L 2 *)B%H
035441WX716454 7S14
]554
6
6.65716-
Z(\\$*B#! :2000HJ 25;2F
14 6026
9+54
64,54
5-1
<=
6
1
1-16
1 >?@, AB@, C?@,
./001"23 )7%1 $7%1 8& !
456623 $91 :7%1 81
D3E0F !! $91 ;1 81
D!2(02/E!0 $92 ;2 82
D3!H20!H! 2 !2202 *2!E1 !2!3'IJ%KF2
EH/1DLMH/1*207
./001"23#M1/23!HI1!H1*I!1/!H2E! *!E
05!7
456623#G!! ! '/10!H0 ///!0I!1* 5F
! *!1*13!02 H7
D3E0F !! #M11! I2'/1N00'**!27
D!2(02/E!0#G!! ! '/10!H0'* 3N*21!22
E! ( 2! 7
O42
54
5-164
75P1
654
1-16
1 AB@,
!/ 91
Q16
1=5=
6421
01-16
1
,4
54= 16T
D3F *1!0 $)&RS $9& RS
5 *2! N7$17
M1 *!2!/*0!E**!7U1!0**! 3//1
*7
2
2-6
5<575
+
D*2!H10N*/10!H3 FE!*! 2*00'2!
0 '!!I!11!*207. N *1I'I7S0V/*0!/!03
0 2!7
E!0# !0*N3F!0!!0F*N3F*N3 !0
.'W0# *N3F*31
14 6026
626
54
5267
N7O1 501124
65412
75
12 75
12
3+/"&#,'"!4,9 876: ;7<=
3+/",5 678 67;
!"!#$%&%"'!&("#'&)*!!"!'""&$"+!$+,"'-$."+#%$# '"+"&(
#!'"&/"!$+ )
6
1
,&#'! !>!&#$+"''&#"+'?$!+"!$+"&/"!$+ )@,!'+!"$+&$+"#&(A'A?
+!$"!#,"'"+#"?"(%&&' %"!"+#$/+$!$+)4+!"$+& !>-,!!$/!(' #)B"+#
?$!'"&)
317175116
CDEF
3+/"&#,'"!4,9 <8+!HI
3+/",5 8G+!HI
J+"&-!'&'$"%$%'"+>#$'!"!#&!&>('"/$"!$+)">$$+$%
$%A!&"%!&!,"$+!K"$!($>L'!!&M$+ ,'!$+)
F6
54
$,&#'!$%&,&% $+" +()",,$'"!&"+#,&"!&">!&"$+#AP,&$+'#"+#"
!'",">$$!("+#K$,+!!$P7!$&"+#",,(!'"!$+/ '&&'!("+#"''&#$+/!Q!+R!'+$'"
#'+!"!$+)9,,$'"!&"+#,&"!&" ",,&,&$"!,&+",&!'!$+K$,+!?+ $+/!$
,&#'!)$/$#$+$/$+>" #+!'&&+!-+?#/%!,&#'!)9+(// !##$"!$+!$!
!$!'+#$!$+ ">%&?"&##!!& ,+ $>Q!+&,& +!"!$%&",,&">%&'+'$+/
!?&-)
S167
3642611
3" > &!,&'"!$+"&(+!$' #$,"(#+!'+!"$+&)T +#&?+!$"!#'+#$!$+ )U
+!$+",&"($!)9$#-$+'+!"'!)V,$"/+!-$+#$#$"!(>&#?$!$!">
'"+ &A","+#?"!&)W( #>?% #?$!?"!&"+##$'""!!+!$+/!$#$"!()
F7X656
54
Y+",,$'">A,&#'!,&$"&$("+!%& " ,&$&&"+!$%$+/ "("$/!'&"&$"!$+
%&>"!'!>"!')V',&#'!"(%"#"+#'"-?+P, #!+$/!"+#?"!&$+/)
9522765O1
14 6026
<**%(=)&%> )
?,9.2-6.3-.337.86.39.33896.-0,1.7,5-.1373534.,3-.7,.68448/594.037565037589@
A.B8/.C431.:336.59.300836390./57,.DE.
530759.683.F3359.DG251975.H3896.59.300836390./57,.337-.I.
396..86.H99..86..JFK.LL.C+M.786.83.M337-.I.396..86.H99..86.JFK.C+M7./,9.59.08145390./57,.
JFK.LL.C+M.786.7,5.N
789-247.823.O8729.33-973759.683.67354-5
H665758934.037565037-.396.338934-.13.8.39354384.89.3G2-75
P(($%)
43.36
"%(&$&
"%(*%Q )X! &%& )%* (
:8456-.8.98421 J:K.]]] IY..Z
[48--.494.1[E.
L.\ J:K.N] 1377.1LA]I
C43-,.8597 J:K.]
c.F7,86. I.\7
9-57 034024376 ]d4^4
2K7AE:^_894.`894 E:.DMH.17,86.a.17-76 aaL.4^4
2K7ADE JD
.1LL^I^DE.1034024376 aI
.4^4
2K7A7,593 [f^+.]cNIALLc.1J:K.NcLA.17-76 aI.4^4
+,.389566.6373.5-.75034.683.630783.386206.386207-.-28b07.78.-454,7.933537589.696594.89.0848235
H44.6373.5-.93456.683.156.35975
[48--.6-0357589@.H00836594.78.O8729.M36831390.7837594-e.6659575895
37.86.5--2@ a.H242-7.L M34@.^I
+,5-.+0,95034.
373.:,7.-23-6-.7,8-.39582-4.5--265
+,.+0,95034.
373.:,7.1+
:.5-.30811966.78.8.336.59.089b2907589./57,.7,.:367.
373.:,7.1:
:.396.7,.
H45037589.[256.1H[.683.7,5-.3862075.C83.823.933-7.48034.O8729.86650.43-.95-57.823./8-57.37.///5b87295081
01234526796
6311
14 651
57
35241126
0-526712141125.526
5464
1
!"#$%% /0 : 50 7
&$!"#$%% 10 : 230 7
' $($!)%*$)+#,)$ 2341 : 146 89
.621166
54
'(%$!F$)%#,)+ $%(#($%FD%$TF$#*(+F!)%F)!$%% )D$!$)#4+)#+$$()#
!(#)#)(#I
.621166
546-
6;71
.621166
54
;
6
1 <545 =12141
C)D(#%$$ >3?@>A1602:2B >)3E?@>A1602:2B
>)#$%%%$$ ' $%F)!$% )D$)#+()! #$ JD)%H$D)%!$)##,()! $H$)
)D)+$+G#(#:$)!)D)%H$% %F)!$*($F%#,)**(H$+#(#:
(D(#+$+D$)! #$()#+ $)!)D)%H$$+)G ! %
)D)%H$*)+%(*))%!)! %F)D$()! $H$)% )*)#+
*)$#($%F)!$)#+($(H$ )#,F)%F)!$*($I
)*(% ($%F)!$I
JF#F ' $%F)!$% )D$)#+()! #$ JD)%H$D)%!$)##,()! $H$)
)D)+$+G#(#:$)!)D)%H$% %F)!$*($F%#,)**(H$+#(#:
(D(#+$+D$)! #$()#+ $)!)D)%H$$+)G ! %
)D)%H$*)+%(*))%!)! %F)D$()! $H$)% )*)#+
*)$#($%F)!$)#+($(H$ )#,F)%F)!$*($I
)*(% ($%F)!$I
K)H)#%$+%$$ ' $%F)!$% )D$!$)#4+)#+ L, DF% D)%#,F%#,#(#:
)**$)G)(F, )#++F*($I $)!)D)%H$$)H#,)!$)#4
(F, )#+$H$#*)$#I
> (**$+%$$ 4!$)#)#+#)!% (**$I JD)%H$%G$*()$#)H$
D)%$+(>)3?@>A1602:2B()
$)%M0N($%F)!$I
C()$+%F)!$% C$)#4+)#+F#+)),$+!(*)D$ C$)#4+)#+F#+)),$+!(*)D$
!()#,?@>A23O//:/5I2B !()#,?@>A23O//:/5I2B
C(#!$$ P(%F$!(#$#)QF6NI P#F/G$$"%!F#,IP(%F$
P$! )#!)*$*)$$$Q%#, !(#$#)QF6NIR$*)$$
!(#!$$%F)!$D%!)DD#,4#$$+$ %F)!$D$)#%($#!(%$+D)%
,F#4$! )#!)+%!,#+#,I % ((+)(#+,#+#,)#+($
)**(*)$$)#%()D)+$$
%F(F#+#,!(#!$$)#+($(H$
))#!$I
A*F*$()#!$4#!F+#,)+ $%(#4!((%(#*($!(#4$)$%%)#!$)#+! $!)$%%)#!$%
)! $H$+G$!($#+$+%F)!$*$*))(#I
S7526
54
14
651
7526
541
3
!"#!$%#&
'!&( )*!%$***!&+
,*( -.."/*%!%"0!"*.!$$!!*+1!.*#!2"!%3
*%/%&/%$.%2"**+
2
5454
6
55678719
:"0!:%.1.; <!=*>
:"0!1., ? !=*>
035441@A716454 7814
%""( B"%""C+?D
H554
6
6I657167
CEE$%=%"F?GGG>( ?JK?L
:**!"EE$=.%"%..>( ?JG#!FM?GG*%
9754
64A54
51
6
6
1
116
1 QRSA TUSA VRSA
'/!=>& M ? OG.%"
N!$2K"K& ?< P+J O
W&3!X.%"%.. Y < O
W%F/*3% ?< D O
].!^%..3!%"0%"3!$*X/;$%!%"_%=;_>/%*+
W&%"0!"%"0%.*!.%"""$$.!*!"$!%3.%%&#$[YJ\X!"
!!3!0/W]!"0/+
'/!=>&(*!/&%"0["*$%0**[%!/%"0*"$!3!"%.%"3!$
!2%"**+
N!$2K"K&(Z%"%..%.#/!%"0!"$!".!$/!//%[%.!"".!2*X
%.%"*&*%!$!.!0+
W&3!X.%"%..(**%.!$$[#/"^!!"#!$%+
W%F/*3%(Z%"%..%.#/!%"0!"#.!""$&^*%""
"3%"."F.%.+
14 651
42
54
5164
751
654
1'16
1 ()*+
!"# $ %&$
:16
1;5;
6421
01'16
1
+4
54; 16@
9178-$241# >?&<= >A& <=
$$12!82-/-1 B& <= C& <=
-D$41-"1!"1- $-E5>"15
F$41-"122!1-1 41#3414125G2#41412$-72"1-2
$41-"125
,-#-./0122- 3-1"2$$12 $41-"12!4 !. 24###$#-
- !/1$$12 2# 2- 11$ 56-122- #2" #!07-#-.272$5
"2!-24-1-272$8 2"1-#-.2272$-32$-1-122- #5
2
2'6
5H575
I
94 !. -#"-E42"1#-.272$83-1"241$12- !4#-2#- 0"2!
#$0- /241!"#5J$E-$42-12/ 0/5= -#K" 124##272$
1#$$ !- 5
13"2#-L 4E784E7$-2#8N#4E78N#2#-
J"02M" #-L -#17#84E7847"1- 8472E-
62@6
54
O
I'5267P
U71 5Q124
6541;
O75
1;P O75
1;P
."-1!1$1=$4G AS>C BS?&
."-1!=$4R >SA >SB
F3"$2-!21-#17$-!#"125,-#-3-1- 24-#D2N- !!3"$2#- 3-17
!"#-1."- 25
6
1
F41!"#$"2021!-##1!- #/- -1."- 25T4# -12-!178#8/
3 -!24-#- !-/-71$2"1#2-- !. 5= -12$"20D4.7#2!56- !
/#-15
3177516
()*+
14
651
!"# !%&'()
!"$ !%&'()
*(!+%(,!,-(&-.-.,/,%%(&!%/0-!,--(-%!12&/!3((&-.
-.4%&.%%&"%5-%0((/6,%%!7(",%!1
86
594
2&("!,%(.!"!.((!-(!-012&""-,%!(!"%!((&--/%4:",&3
%&,"/-%05"%%!:;(%""-0%&,!%(,!,%-0,,!%!<!%=(%,&,-
!,%%!1#""-,%!(!"%!((&--(""!"%"(!-"!%,%!5"%>&(%&(
"!,%12&(-(3/(!%&,%+!>-!.%&"!,%1#0((%3%!%!(%
%&(%,!%!((&--/.!>%!%&("!(/-<!%"(%%3.!""!3-/.!,!,
%&>!+1
?167
364@6A1
B
-(!/(3%&",%!0!%,(("-0!%&,!%1C(>--3%-%,!%!(1D!
!%&-("0(%1#3!(+,!%,%1E"--!%&(+(&!-%-0/!3>%&(%/-
,-(4(!">%1F0((&!-/>--.-(&>%&>%,-%%%!(!&%%-01
8979G656
594
H&""-,/-4"!,%("-0%.!(("(!%.!-(0&3(-&%,!-!3%!(
.!/%,&%!/%,&1E,&"!,%(0.,&-+>&:"!(%!(-&%>%&1
95@27651
2&.!%!%&(!,%(3%!%&/(%!.<!%=(+!>-4/(!-/!%!0%(%
",%,-:",1<!%=("!,%(,!(((7.(&!!(((,&4"!,%(!.%
(,!%!(/0!<!%=(,!%!-1<!%,!%%0%&/%%&5-%0!.%&"!,%
%(-.1I!"!,%3%!(0/"-%!%!,!"-0>%&-!,-5%(1<!%(3(
%&&%%!,&%&3%>%&!%.%&!%,1
C(((&!-->0(,!(-%<!%.!(",.,,!%&-(%/-%0!.%&("!,%.!%&(
(",.,""-,%!",%,(1
*.%&(0,!((%,0/%>..%-(((!.%&(!,%4%&F-(&'C%J!)
3(!>--"3-1
Product description
This is a paint thinner. Designed to improve the flow of a range of Jotun epoxy products. Can also be used as
cleaner for pumps and tools before and after painting.
Typical use
Specially suitable as thinner for epoxies and similar type products except Tankguard series. Recommended
usage as per the specific datasheet or application guide of the product one wish to apply.
Other
Colours
clear
Product data
Property Test/Standard Description
Solids by volume ISO 3233 0± 2 %
Flash point ISO 3679 Method 1 25 °C
Density calculated 0,9 kg/l
VOC-US/Hong Kong US EPA method 24 (tested) 856 g/l
VOC-EU IED (2010/75/EU) (calculated) 866 g/l
VOC-China GB/T 23985-2009 (ISO 11890-1) (tested) 860 g/l
The provided data is typical for factory produced products, subject to slight variation depending on colour.
Packaging (typical)
Volume Size of containers
(litres) (litres)
The volume stated is for factory made colours. Note that local variants in pack size and filled volumes can vary
due to local regulations.
Storage
The product must be stored in accordance with national regulations. Keep the containers in a dry, cool, well
ventilated space and away from sources of heat and ignition. Containers must be kept tightly closed. Handle
with care.
Shelf life at 23 °C
In some markets commercial shelf life can be dictated shorter by local legislation. The above is minimum shelf
life, thereafter the paint quality is subject to re-inspection.
Caution
This product is for professional use only. The applicators and operators shall be trained, experienced and have
the capability and equipment to mix/stir and apply the coatings correctly and according to Jotun's technical
documentation. Applicators and operators shall use appropriate personal protection equipment when using this
product. This guideline is given based on the current knowledge of the product. Any suggested deviation to suit
the site conditions shall be forwarded to the responsible Jotun representative for approval before commencing
the work.
Colour variation
When applicable, products primarily meant for use as primers or antifoulings may have slight colour variations
from batch to batch. Such products may fade and chalk when exposed to sunlight and weathering.
Disclaimer
The information in this document is given to the best of Jotun's knowledge, based on laboratory testing and
practical experience. Jotun's products are considered as semi-finished goods and as such, products are often
used under conditions beyond Jotun's control. Jotun cannot guarantee anything but the quality of the product
itself. Minor product variations may be implemented in order to comply with local requirements. Jotun reserves
the right to change the given data without further notice.
Users should always consult Jotun for specific guidance on the general suitability of this product for their needs
and specific application practices.
If there is any inconsistency between different language issues of this document, the English (United Kingdom)
version will prevail.
We believe that the key factor for our success is our clear mission and vision that we are
highly committed to. Our Mission is to be the first choice for gas solutions and services in
the Middle East driven by our expertise and committed to our values and heritage.
Our Vision is to expand Unigaz business while creating value to our customers through
our highly skilled and professional team.
Our customers do not see us as gas providers only, yet we’re considered as their
strategic partner in every step across the way of establishing reliable and safe gas
systems that fulfill their needs. Our ultimate goal in Unigaz is to promote the usage of
LPG as an alternative clean source to better protect our environment and the world we
live in.
Mahmoud Sidani
Chairman of the Board of Directors
Unigaz Group
Celebrating
the 60th Anniversary
Long history in providing
the region with boundless gas solutions.
60 Years
of Success
What we do best…
Areas of Expertise
Unigaz tailor-made solutions are segmented and designed to meet different channel needs:
Water Renewable
Treatment Energy
Solutions
60 Years
of Success 3
Unigaz Identity
Our identity is a fusion of what we have been doing in the field of Gas for the past 60 years and how
we’re willing to build on it in order to cope with the evolving market needs across different territories.
Our Mission
To be the First Choice for gas solutions and services in the Middle East driven by our expertise and
committed to our heritage.
Our Vision
Expanding Unigaz business and Creating Value to our customers; by providing
convenient safe gas solutions and adopting the most efficient and reliable
processes through our motivated and highly skilled team.
Mission
& Vision
Our Philosophy Our Values
We encourage Diversity to bring across Coaching. Accountability. Recognition.
Innovation that will lead us to Prosperity Dedication. Knowledge. Efficiency. Practicality.
Mission
& Vision 5
Our Presence
Lebanon
Unigaz Industrial
Jordan
Al Nokhba Eng.
Iraq
Unigaz Iraq
UAE
Arabian Unigaz
Qatar
Unigaz Qatar
Oman
Unigaz Oman
KSA
Unigaz Arabia
Regional
Presence
Unigaz has rapidly spread its presence in the Middle East region in the past years
across 3 main sub-regions:
Levant Sub-region
Unigaz Industrial Lebanon
Unigaz Jordan Jordan
Central Sub-region
Unigaz Iraq Kurdistan, Erbil
Unigaz Iraq Iraq, Baghdad
GCC Sub-region
Unigaz Arabia Kingdom of Saudi Arabia
Arabian Unigaz United Arab Emirates
Unigaz Oman Sultanate of Oman
Unigaz Qatar State of Qatar
7
Unigaz Expertise
A diversified service offering from Household to Mega Factories and City Scale Networks
Residential
Gas for Household
Cylinder filling and distribution for 10Kg and 12.5Kg
Design and Installation of safe and secure central gas systems
Gas storage capacities from 200 to 5,000 Liters
Usage of gas for different applications:
Central Heating - Boilers
Power Generation
Hot Water Generation
Fireplace and Chimneys
BBQ and many more
Hospitality
Gas for Commercial Outlets and Restaurants
Cylinder filling and distribution for 35Kg
Design and Installation of safe and secure central gas systems
Gas storage capacities from 500 to 5,000 Liters
7/24 Supply and Service
Design and Installation of safe and secure central gas networks based
on NFPA regulations.
Gas Detection system connected to fire fighting system
7/24 LPG supply by certified PED-ADR Tankers
Customer Relationship Management tool
Periodic check-up and maintenance
Unigaz
Expertise
Industries
Gas for for Governmental Facilities and Industrial Factories
Design and Installation of safe and secure central gas networks based
on NFPA regulations.
Large Gas storage capacities from 5,000 to 500,000 Liters
Vaporizing System
Back-up system for Natural Gas interruptions
Remote Metering System
LPG system with high flow capacities
7/24 Supply and Service
City Networks
Gas for Integrated Communities with Innovative Solutions
Unigaz
Expertise 9
LEBANON JORDAN IRAQ
Gas Import Gas Import
Gas Storage Gas Storage
Cylinder Filling Cylinder Filling
Gas Bulk Supply
Trading of Gas
Water Treatment Water Treatment
Accessories
Solutions Solutions
KSA REGIONAL
Energy Consultancy
Specialized Engineering
Gas Network Design & Contracting Services
Installation
Maintenance
Distribution
& Operation Services
Project Concept
Development
Unigaz
Activities 11
Wherever you are… We deliver gas to you
With Unigaz LPG Barge for Islands
Unigaz Major Projects
Through applying the best in class processes and high quality of services,
Unigaz was able to win key gas projects in the Middle East .
13
We Care...
To promote LP gas as a clean energy
for everyone... every where!
Some of Our Customers in the Middle East region
One of our main pillars in retaining our customers is Trust. We highly believe
in maintaining customer satisfaction to lead us towards success.
Unigaz
Clients 15
Unigaz Offices in the Middle East
Our Local Offices
SELECTED PROJECTS
Special Project
UNIGAZ QATAR
COMPANY
PROFILE
UNIGAZ QATAR | COMPANY
PROFILE
SELECTED PROJECTS
UNIGAZ QATAR
COMPANY
PROFILE
UNIGAZ QATAR | COMPANY
PROFILE
SELECTED PROJECTS
UNIGAZ QATAR
COMPANY PROFILE
7. ORGANIZATION CHA5T SHOWING QUALITY
DEPARTMENT
Organization Structure 2021 – Unigaz Qatar
Group CEO
Country
Manager
Public
Sr. Sales Billing Accountant Procurement Projects Mechanical Projects Projects
Call Agent Relations
Officer Officer (2) (2) In Charge Coordinator Engineer Engineer Engineer (2)
Officer
Cylinder Sales Collection Admin Admin Maintenance Planning Site QAQC Design
Office Boy
Drivers (2) Engineer Driver Assistant Assistant (2) Engineer Engineer Engineer (3) Engineer Engineer
Store Mechanical
Electricians Welders Drivers
Assistant Technicians
COUNTRY MANAGER
HAYTHAM ZAKARIA SAAB
haytham.saab@unigaz.net
OPERATIONS MANAGER
AHMAD JOUNI
ahmad.jouni@unigaz.net (50242858)
Sr.Project Engineer MECHANICAL ENGINEER Sr. Electrical Engineer PROCUREMENT ENGINEERING HSE OFFICER
Ahmed Ghazi Arun Nair ABDUL HAMID SUKUMAR JAGADHEESH SHAMSAD
a.ghazi@unigaz.net arun.nair@unigaz.net mohamed.abdelhamid@unigaz.net murugesan.sukumaran@unigaz.net jegadeesh.manickam@unigaz.net
shamsad.koya@unigaz.net
55467013 50050836 66005280 33219788 66150335
33369334
Office No.12,4th Floor,AlQamra Holding,Bldg.53,Zone 38,P.O.Box: 63711lTel: 44514044 l Fax: 44514041 l www.unigaz.net
Lebanon l Syria l Jordan l K.S.A l U.A.E l Qatar l Oman l Iraq
8. COMPLIANCE STATEMENT
COMPLIANCE STATEMENT
QCS-2014
Section 21, Part 17,
17.2 PRODUCTS
17.2.1 DIESEL GENERATOR SET
17.2.1.(d)ii Daily Fuel tank
Fuel supply to the engine shall be maintained by a separate day tank
located in the room. Daily fuel tank shall be sufficient capacity for
continuous run of 8 hours at full load, unless otherwise specified in the
Noted and Comply
Project Documentation. The daily service tank shall be manufactured
from mild steel to a rectangular shape in accordance with BS 799 and
shall be complete with the following minimum equipment and facilities:-
Inspection cover Noted and Comply
vent/breather pipe Noted and Comply
filler pipe connection Noted and Comply
overflow connection Noted and Comply
drain valve and sump drain Noted and Comply
emergency dump valve operated by the fire alarm system and by a fusible
Noted and Comply
link mounted over the diesel engine
dial type contents gauge calibrated in gallons and litres Comply ATG system will be provided
Will be provided, Integrated with ATG
level switches to control fuel transfer pump Comply
panel
level switches to operate high and low fuel level alarm circuits in the Level switch will be integrated with
Comply
diesel alternator set control panel ATG panel
lifting lugs. Comply
the Contractor shall provide and install an external dump sump As per the IFC Drawing The fuel from
of sufficient capacity to contain the contents of a full day tank and all the day tank will drain to the main
pipework necessary to carry the dumped fuel quickly by gravity, to a safe tank during any emergency event of
location in the event of a fire being detected in the generator house. The Comply fire
sump shall be constructed to contain the fuel without leakage to the Fusible link valve will open during fire
surrounding ground and shall be provided with a lockable cover. Provision to drain the fuel
to allow emptying of the sump by portable pump shall be provided.
17.2.1.(d)iii Main Fuel Storage Tank:
The Contractor shall supply and install a cylindrical diesel oil storage tank
The Main Tank will be provided by
with a capacity to operate the associated diesel generator set
Comply WOQOD and The capacity proposed
continuously on full load for a minimum of 7 days, unless otherwise
as per the IFC
specified in the Project Documentation.
the tank shall be welded mild steel construction suitably protected from
corrosion in accordance with BS. 2594 and shall be installed in the location Comply
indicated on the drawings.
The storage tank shall be complete with pipes, fittings, feed lines,
vents.etc. The tank shall be of the approved type located outside the
diesel engine room. The tank shall be provided with 600 mm inspection Comply
manhole with cover, 50 mm filling pipe with cooped filling terminal, 50 mm
air vent pipe with screen outlets, isolating valve, valved drain etc.
Electronic fuel indicator with an audio/visual alarm shall be provided for
Comply
main fuel storage tank
Also the storage tank and its accessories must comply with the Qatar.Civil
Comply
Defence Regulations for generator installations.
17.2.1.(d)iv Duplex Diesel Oil Pumping Set:
Provide packaged type duplex, self priming, fuel oil pumping and straining
set with a capacity of four times the total fuel consumption of engine at full
load for each individual Diesel Generator Set. Pump sets shall be factory
Comply
assembled, piped, wired and tested. Pumps shall be activated by a
switch in the day tank automatically. All pumps installed in the D/G room
shall be flame-proof and fire-resistant as per NFPA Regulations
Piping shall be complete to suction, discharge and return line
connections. Provide gate valves and unions arranged to permit removal
Comply
of either pump while the system is in operation. Install check valves and
relief valves on pump outlet and gate valves prior to pressure gauges
Suction strainer shall be flanged connection, duplex type, one-piece,
cast-iron body, ASTM A48 Class 30, with 1.2 mm perforation brass Comply
baskets
COMPLIANCE STATEMENT
Suitable manually operated pump shall be provided. Noted as Comply Duty and stand by pump will be provided
The installation of Diesel transfer pump set shall be subject of the Engineer’s
approval. There shall not be any possibility of flooding of the Comply
diesel tTransfer pumps.
17.2.1.(d)v Tank Gauges:
Provide as shown on the Drawings. Each gauge is to be provided with an
aluminium case and calibrated to indicate level of fuel in the tank.
Mounted on gauges shall also be a high/low level alarm switch. The Automatic Tank gauging system will
Comply
switches and gauges shall be designed for operation from a 24 Volt DC, be provided
loop powered system. Locate indicating gauges as shown on the
Drawings or required
Tank fittings and pressure fittings shall be made of solid bar stock to
Comply
prevent leak possibilities.
7.2.1.(d)vi Diesel Oil Piping:
Provide all diesel oil piping from storage tank to day tank fill lines, water
Comply
tight fill boxes, vents, vent caps, tank foot valves, and accessories
Provide swing check valves and gate valves at pump inlets. Provide Check & ball valves are provided. Anti-
approved anti-siphon valves at high points of suction lines. Provide Noted and Comply siphon is not required as the supply
whatever additional valves that may be required by local regulations line located at the tank bottom.
All piping shall be provided with ground joint unions at piece of apparatus to
Comply
facilitate connecting and disconnecting
All piping, unless otherwise specified, shall be schedule 40 standard
Comply
weight black wrought iron pipe
Steel vent pipelines shall run from the fuel oil storage tanks, carried to the
proper height within building construction and terminating with vent fittings.
Comply
Fittings shall be "Bronze Ventilating Brick" with thickness of 20 mesh
bronze wire gauge in front of louvered opening.
Project : Terminal Sewage Pumping Station at Doha North STW Package 3
System : FUEL OIL PIPING SYSTEM
SL.NO DESCRIPTION
1 General
RESPONSE Remark
motors shall be supplied by the manufacturer of the driven Comply,
equipment as specified in this section, and specifically
A outlined in the driven equipment specifications
all motors shall be suitable for operation on a 415V or 690V, Comply, the motor operation is
50 Hz 3 phase supply.
415V,50 Hz, 3 Ph
Different voltage levels may be used as indicated in particular
B
specifications or drawings
C All motors shall be capable of starting 10 times per hour. The Comply
stalled motor current shall not exceed 6 times full load
current
F Terminal Boxes
Terminal boxes shall be cast iron and shall be designed to Noted as Comply for induction motors
accept XLPE or PVC armoured cable as detailed in the
Contract. On non- submersible motors, terminal boxes shall
(i) be mounted on the right hand side when viewed from the
driving end of the motor, unless otherwise required by the
Contract.
The motors shall run in ball and/or roller bearings and the Comply
H weight of the motor shall be carried by thrust bearings
incorporated in the motor body
“Sealed for Life” bearings shall not normally be used. Comply, the shaft guard provided in
However, for small motors the Engineer may allow the use of
the skid
J sealed for life
bearings.
Project Terminal Sewage Pumping Station at Doha North STW Package 3
Motor starters shall be housed in a separate cubicle Proposed Motor starters are housed
Complied as
3 compartment of the relevant motor control centre and in small control panel
noted
each starter cubicle shall contain the following general purpose enclosures.
1 no. triple pole ACB or MCCB or fuse switch, as Incomer MCB is provided for
indicated on the Project Documents, externally protection.
Complied as
a operated and interlocked with the cubicle door. There
noted
shall be provision for
padlocking in the OFF position.
b 1 no. starter, comprising one of the following types, as
indicated on the Project
i direct on line Complied
ii star/delta Not
iii close transition star/delta Not
iv reduced voltage “soft start” Not
v VFD control as per part 5 Not
c 1 no. motor protection relay, as specified in Part 3 Not
Applicable
SN Description Compliance Remarks
d 1 no. set of auxiliary relays and timers required to Complied
provide the necessary indication
and control sequence
e 1 no. set of main motor terminals and auxiliary Complied
terminals for remote controls and
indications.
f 1 no. set of terminals for remote lock-off stop push Complied
g 1 no. control circuit transformer, where applicable Complied
h 1 no. anti-condensation heater Complied
i 1 no. set of power factor correction capacitors with Not
separate fuses for all drives above Applicable
11 kW, to give a power factor of not less than 0.85.
3.1.14 Standards
1 The following standards shall be followed:
BS EN 60255-6, IEC 255 Electrical relays
BS EN 60269, IEC 269 Cartridge fuses for voltages up to and including 1000VAC and 1500 V AC
BS EN 60898, IEC 157-1A Miniature and Moulded Case Circuit Breakers For relevant material
Comply as applicable within our scope of
BS EN 60947, IEC 947-2 Low Voltage circuit breakers
supply
BS EN 61008-1 Earth Leakage circuit breakers
BS EN 61810-1 Electrical Relays
BS88 Cartridge fuses
3.1.5 Overcurrent Protective Device Co-ordination
1 The Contractor shall carry out and provide an overcurrent protective device. Co-ordination study as part of his
material submission, as outlined below:
2 Properly co-ordinated automatically operated overcurrent protective devices shall be provided for this Project. The overcurrent protective Comply
devices shown on the Drawings shall be co-ordinated for adequate continuous current and interrupting capacity to assure proper
overcurrent protective devices operation under normal and fault conditions in the system
All overcurrent protective devices on this Project and the first upstream device of the existing electrical system shall be co-ordinated so Comply using
that they will perform as follows. When two or more overcurrent protective devices (including the first upstream protective device of the Manufacturer`s
3 existing system) in series with each other experience current flow greater than their rated current, the device with the lowest rated proprietery software
current shall trip and/or open the circuit first and thereby prevent the higher rated devices from operating. and our standard
formats
The Supplier of the overcurrent protective devices shall prepare a co-ordination study to verify the above stated performance
4 requirements. The study shall be documented by the Supplier and the documents shall include but not be limited to the following:
This documented co-ordination study shall be submitted for review before the overcurrent devices are supplied for the Project. The study shall be
5 Comply as noted submitted after receipt
of final drawings for
6 The breaking performance of ACB’s and MCCB’s shall be such that service breaking capacity ICS should be Comply
equal to or greater than ultimate breaking capacity ICU.
3.1.6 Quality Assurance
1 The suppliers manufacturing facility shall be certified to the ISO - 9001 series of standards from the International Noted
Standards Organisation.
3.1.7 Manufacturers
1 Preference will be given to one manufacturer of ACB, MCCB and MCB to ensure proper co-ordination in Noted
accordance with Clause 3.1 above.
3.2 PRODUCTS
3.2.1 Air Circuit Breakers Not Applicable
3.2.2 Moulded Case Circuit Breakers Not Applicable
3.2.3 Miniature Circuit Breakers
1 These shall be type C for general purpose uses, suitable for the load they feed, and shall have short circuit rating Comply
of 10 kA.
2 They shall be fault rated so that fuse backup protection is not required. Comply
3 They shall be rated in accordance with BS EN 60898, IEC 898. Comply
4 They shall include the following minimum features: Comply
(a) magnetic and thermal trip elements
(b) trip-free mechanisms Comply
(c) locking of facilities with detachable proprietary brackets and clearly marked ratings.
5 RCBO shall comply with BS EN 61008-1 & BS EN 61009-1 Comply
3.2.4 MCB/ELCB
SN Description Compliance Remarks
1 Combined MCB/ELCB units shall be provided for final circuits supplying socket outlets, water heaters and water Comply
pumps.
2 The units shall have a trip sensitivity of 30 mA. Comply
3.2.5 Earth Leakage Circuit Breakers (ELCB)
Current operated earth leakage circuit breakers shall provide accident protection by interrupting dangerous contact with voltage which
1 may be present in faulty electrical equipment as a result of frame faults, insufficient insulation or misuse. Comply
2 The ELCB shall also provide high degree of protection against earth leakage, fire and electric shock. It shall withstand at least 10 kA or Comply
as specified in the project documents. The breakers shall comply with BS EN 61008-1 and the recommended specification CEE 227 of
the IEC on rules of approval of electrical equipment.
The breaker shall consist of a core balance transformer, a tripping coil with contact assembly, main supply contacts, ON/OFF switch, a
3 test button and a trip free mechanism all enclosed in a robust body of all insulated material. Comply
4 Degree of Protection against earth leakage throughout the electrical installation shall be as indicated on the Comply
Drawings. Unless otherwise indicated, ELCB shall have 30 mA trip settings.
5 The breaker protecting lighting and or power circuits shall be mounted in the panel board enclosure. Comply
3.2.6 Overload Relays
1 Thermal Overload Relay Comply
thermal overload relay where specified shall be of Bi-metallic inverse time-lag type, which shall be used with a contactor in the starter
a circuit enabling switching device to open both control and power circuit (fully isolating the power to the motor terminal box) when the Comply
current in the relay exceeds a predetermined value.
b the thermal overload relay shall fully comply with the requirement of BS EN 60255-8 Comply
c the thermal overload relay shall be simple and robust suitable for direct contactor mounting or if to be mounted Comply
separately shall be used with manufacturer supplied links and associated attachment.
d the thermal overload relay shall be designed to include ambient temperature compensation feature from – 20 Deg Comply as Noted Temperature -20Deg
C to + 65 Deg C eliminating the need of any calibration in the field during operation. to +50Deg
e the thermal overload relay shall provide the following protections:-
(i) over-current/Overload Comply
(ii) single phasing/Phase failure Comply
the thermal overload relay shall have MAN/AUTO field convertible Reset button located on top of the relay for resetting of the relay after
f trip. Additionally a facility shall be provided on the door of starter compartment to reset the relay if so required/specified. Comply
the thermal overload relay shall have two characteristics, the one when the relay bi-metals are in cold state that will break the contacts
of the relay within 8-10 seconds and the other when in hot state the contacts breaking shall be reduced to approximately one third of the
g tripping time as indicated for the cold characteristics. The tripping time may be allowed to vary depending upon the starting of the motor Comply
such as normal/heavy-duty.
h the thermal overload relay shall have been type tested and ASTA certified to achieve Type 2 co-ordination in Comply
accordance with BS EN 60947.
i thermal overload relays shall be used for motors rating up to and including 11 kW. Comply
2 Electronic Motor Protection Relay Not Applicable
3.2.7 Fuses Not Applicable
3.2.8 Fuse Switches Not Applicable
3.2.9 Isolating Switches
The switch when used alone as explained above as an Isolator shall confirm to the utilization category AC23 and shall fully comply with
1 the requirement specified for isolating functions specially the isolating distance in accordance with the applicable standard. Comply
2 terminals. Comply
3 The Isolator shall be capable of carrying currents under normal circuit conditions and carrying for specified time Comply
currents under abnormal conditions such as those of short-circuit.
4 All other features of the Isolator shall be same as specified above for combination fuse switch unit. Comply
3.2.10 Stop Lock-off Push Buttons
1 Stop lock-off push buttons for motors shall be the mushroom headed red stay-put type with automatic latching, the Comply
units having to be key operated to be released.
2 Push buttons shall be housed in a surface mounting weatherproof enclosure to IP 65. Comply
3 Push buttons shall be UV stabilised. Comply
3.2.11 Control Relays/Auxiliary Relays/Interposing Relays
1 All auxiliary relays shall mainly comply with BS EN 116000 and BS EN 116205-7. Comply
2 Where similar relays have different operating voltages and/or different contact configurations, they shall be non- Comply
interchangeable.
3 Voltage at nominal operating temperature and shall not „drop-out‟ at greater than 60 % of the nominal coil voltage. Comply
4 Relays shall be continuously rated and capable of sustaining a voltage 10 % in excess of the nominal coil voltage. Comply
5 Relays shall be fully encapsulated and be of the plug-in type, with terminals protected to a minimum of IP2X. Comply
6 Plug-in relays shall be fitted with transparent dust-proof covers. External connections shall be screw clamp Comply
terminals, which are easily accessible with the relay in position.
7 Relays shall include the provision for manual operation. Comply
8 The pin configuration of the relay shall be printed on the casing and on the bases in order to ensure correct pin Comply
alignment.
9 Relays shall be suitable for operation at plus 10% and minus 20% of their nominal rated voltage.
10 The contacts configuration shall be either normally open/normally closed or changeover contact combinations. Comply
11 The contact material used in the Relay for general logic design shall be AgCdO. Specific applications requiring Comply as applicable
extra low switching current shall have GOLD Flash contacts for minimal voltage drop across the contacts.
It will not be permitted to use mixed voltages on the different contacts of a particular relay. If necessary additional relays shall be used
12 by employing good engineering practices such as operation of add-on relay through auxiliary contact of main relay. Comply
13 Relays Coil shall be vacuum impregnated ensuring satisfactorily operation for the adverse climatic conditions as Comply
specified.
14 The relays shall be mounted on DIN Rail. Comply
15 Relays shall be secured to their bases by retaining bar or clip to prevent malfunction due to the relay being Comply
loosened in its base.
16 Care shall be taken to ensure that relay contacts and associated wiring are suitably fused protected. Comply
All type of relays shall have a means of visual indication e.g. light emitting diode (LED) or neon bulb mounted within their clear covers
17 connected directly across the relay coil to indicate when the relay is energized. These indicators shall be easily seen when the relay Comply
compartment door is opened.
18 reference. Comply
19 Where remote supply voltages are used, a warning label engraved in English and Arabic shall be fitted, clearly Comply English lables shall be
identifying the source of supply. provided as
standard practice
20 The relay shall be designed for minimum 1 Million mechanical operation and 200,000+ electrical operations at Comply
rated load.
3.2.12 Protection Relays
1 Protection relays shall comply with BS EN 60225-6, BS EN 61810-1, IEC 255. Comply
2 Secondary injection shall be easily possible by means of purpose-made voltage and/or current plug-in type test terminal blocks which Comply
automatically open circuit or short circuit the integral voltage transformers or current
transformers respectively and provide termination‟s for the test supply. Disconnection of any permanent wiring will not be acceptable.
2 Timers shall be suitable for operation on a nominal 240 V AC, 110V AC, 24 V AC/DC or other voltage as specified Comply
or deemed necessary for the safe operation.
3 Timers shall have linearly calibrated scales, in units of time, each scale division being a maximum of 5% of full Comply
scale. Repeat accuracy shall be within 0.5% of full scale.
4 Timers shall be provided with “energized” and “timed out” indicators. Comply
5 Plug-in timers shall be fitted with transparent dust-proof covers. External connections shall be screw clamp Comply
terminals which are easily accessible with the timer in position
6 Timers shall be secured to their bases by retaining bar or clip to prevent malfunction due to the relay being Comply
loosened in its base.
7 The pin configuration shall be printed on the casing of the timer and on its associated bases in order to ensure Comply
correct pin alignment.
8 Timer shall be provided with 10 Amps. Rated output relay with DPDT contacts. Comply
9 Unless specified otherwise, timers shall be provided for circuits that require delay on operate, delay on release, Comply
and star-delta starting of a 3-phase induction motor.
10 Multifunction timing relay programmable where specified shall be provided to the satisfaction of the engineer. Comply as per project
SLD
11 mentioned in the particular requirements and the same shall be subjected to the review and approval by the Noted.
engineer.
END OF PART
9. VALID CR COPY/COMPANY ID
><Bar Code
**35195
5000983254 ﺭﻗﻢ ﺍﻟﺘﺴﺠﻴﻞ ﺍﻟﻀﺮﻳﺒﻲ: 35195 ﺭﻗﻢ ﺍﻟﺴﺠﻞ ﺍﻟﺘﺠﺎﺭﻯ:
ﺍﻟﺴﻤﺔ ﺍﻟﺘﺠﺎﺭﻳﺔ: ﺷﺮﻛﺔ ﻳﻮﻧﻴﻐﺎﺯ ﻗﻄﺮ ﺍﻟﻤﺤﺪﻭﺩﺓ ﺍﻷﺳﻢ ﺍﻟﺘﺠﺎﺭﻯ:
21/03/2023 ﺗﺎﺭﻳﺦ ﺍﻧﺘﻬﺎﺀ ﺍﻟﺴﺠﻞ: 22/03/2007 ﺗﺎﺭﻳﺦ ﺍﻧﺸﺎﺀ ﺍﻟﺴﺠﻞ:
200000 ﺭﺍﺱ ﺍﻟﻤﺎﻝ: ﺷﺮﻛﺔ ﺫﺍﺕ ﻣﺴﺌﻮﻟﻴﺔ ﻣﺤﺪﻭﺩﺓ ﺍﻟﺸﻜﻞ ﺍﻟﻘﺎﻧﻮﻧﻰ:
ﻗﻄﺮ ﺟﻨﺴﻴﺔ ﺍﻟﻤﻨﺸﺄﺓ: ﻧﺸﻂ ﺣﺎﻟﺔ ﺍﻟﺴﺠﻞ:
0 ﻋﺪﺩ ﺍﻟﻔﺮﻭﻉ:
ﻣﻌﻠﻮﻣﺎﺕ ﺍﻻﺗﺼﺎﻝ
4622772/5336620 ﺃﺭﻗﺎﻡ ﺍﻻﺗﺼﺎﻝ: 63711 ﺻﻨﺪﻭﻕ ﺍﻟﺒﺮﻳﺪ:
ﺍﻟﺸﺮﻛﺎﺀ
Page 1 of 2
ﺭﻗﻢ ﺍﻟﺴﺠﻞ 35195 :
ﺗﺸﻬﺪ ﻏﺮﻓﺔ ﺗﺠﺎﺭﺓ ﻭ ﺻﻨﺎﻋﺔ ﻗﻄﺮ ﺑﺎﻥ ﺍﻟﻤﻨﺸﺎﺓ ﺍﻟﻤﺬﻛﻮﺭﺓ ﺍﻋﻼﻩ ﺳﺠﻠﺖ ﻟﺪﻳﻨﺎ
Qatar Chamber certifies that the above mentioned establishment has been registered
><Bar Code
ﺍﻷﻧﺸﻄﺔ ﺍﻟﺘﺠﺎﺭﻳﺔ
Page 2 of 2
ﺭﻗﻢ ﺍﻟﺴﺠﻞ 35195 :
ﺗﺸﻬﺪ ﻏﺮﻓﺔ ﺗﺠﺎﺭﺓ ﻭ ﺻﻨﺎﻋﺔ ﻗﻄﺮ ﺑﺎﻥ ﺍﻟﻤﻨﺸﺎﺓ ﺍﻟﻤﺬﻛﻮﺭﺓ ﺍﻋﻼﻩ ﺳﺠﻠﺖ ﻟﺪﻳﻨﺎ
Qatar Chamber certifies that the above mentioned establishment has been registered
><Bar Code
2022/03/17 ﺗﺎﺭﻳﺦ ﺍﻟﻄﺒﺎﻋﺔ:
No 1 of 1 ﺻﻔﺤﺔ ﺭﻗﻢ:
ﺭﺧﺼﺔ ﺗﺠﺎﺭﻳﺔ
**35513
2015/04/09 ﺗﺎﺭﻳﺦ ﺍﺻﺪﺍﺭ ﺍﻟﺮﺧﺼﺔ: 35513 ﺭﻗﻢ ﺍﻟﺮﺧﺼﺔ:
2023/04/17 ﺗﺎﺭﻳﺦ ﺍﻧﺘﻬﺎﺀ ﺍﻟﺮﺧﺼﺔ: ﺷﺮﻛﺔ ﻳﻮﻧﻴﻐﺎﺯ ﻗﻄﺮ ﺍﻟﻤﺤﺪﻭﺩﺓ ﺍﻷﺳﻢ ﺍﻟﺘﺠﺎﺭﻯ:
35195 ﺭﻗﻢ ﺍﻟﺴﺠﻞ ﺍﻟﺘﺠﺎﺭﻯ: ﺷﺮﻛﺔ ﻧﻮﻉ ﺍﻟﻤﻨﺸﺄﺓ ﺍﻟﺘﺠﺎﺭﻳﺔ:
ﺍﻟﺴﻤﺔ ﺍﻟﺘﺠﺎﺭﻳﺔ:
MAIN TANK
MATERIAL SUBMITTAL
UNIGAZ QATAR | MATERIAL SUBMITTAL
SUPPLY BY WOQOD
Documents will be provide along with
delivery
MATERIAL SUBMITTAL
UNIGAZ QATAR |
PREQUALIFICATION
VENT
UNIGAZ QATAR
readan
3826 Sul!arloaf Pkwy, Frederick, MD-21704
Tel: +l 301 7988102 Fax N0:+1 240 341 1400,Email:sales@readaninternatlonal.eom
" Reliable Dartner assiting In the grDwth of your business
Packing List
To: Diligent Trading & Contracting WLL
North Shamal Road, Exit No-10,
Al Khartiyat Street No-455, Building N0:29
Office no: 7
Doha,Qatar
Contact Person :Kumar
Procurement Manager
Petrochemical Division
Email: fuel@dillgentqatar.com
Mob +974 3007 1232
Tel +974 44663404
Authorised Signatory
Readan international
Solenoid Valve
UNIGAZ QATAR
UNIGAZ QATAR | MATERIAL SUBMITTAL
MATERIAL SUBMITTAL
1 Consignor
CRANE FLUID SYSTEMS No. RA 127375 ORIGINAL
CRANE HOUSE
EPSILON TERRACE, WEST ROAD,
IPSWICH
IP3 9FJ, UNITED KINGDOM
EUROPEAN COMMUNITY
2 Consignee
6 Item number; marks, numbers, number and kind of packages; description of goods 7 Quantity
CASE NO:
370862, 370907, 370909, 370910, 371229, 371443, 371559, 371560, 371561, 371562, 371563,
371564, 371608, 371609, 371610, 371746, 371793, 371794, 372149, 372150, 370440, 370441,
370442, 370443, 370444, 370445, 370446, 370450, 370451, 370452, 370466, 370720, 370721,
370722, 370724, 370726, 370916, 370924, 370925, 370926, 370927, 370928, 370929, 370930,
370941, 371289, 372875
8 BOXES OF CATALOGUES
8 THE UNDERSIGNED AUTHORITY CERTIFIES THAT THE GOODS DESCRIBED ABOVE ORIGINATE IN THE COUNTRY SHOWN IN BOX 3
1 9 JUL ZT13
J? r l, ·- � \,\ f I r-. f) �
0
Ball Valve
Brand: Apollo
UNIGAZ QATAR
Manufactured by Conbraco Industries, Inc.
P.O. Box 125 Pageland S.C. 29728
Phone: [843] 672-6161
Fax: [843] 672-1648
www.apollovalves.com
Certificate of Origin
80-105-01 10 BALL VALVE, 1" NPTF, 600 PSI WOG, SP, BRONZE BODY, CHROME BALL
RPTFE SEATS & PKG., LEVER OPERATED, LP GAS, UL LISTED, APOLLO - USA
80-107-01 30 BALL VALVE, 1.1/2" NPTF, 600 PSI WOG, SP, BRONZE BODY, CHROME BALL,
RPTFE SEATS & PKG., LEVER OPERATED, LP GAS, UL LISTED, APOLLO - USA
Respectfully,
John C. Regan
Corporate Quality Assurance Manager ES-1513 REV. A
181
Office Address: 701 Matthews Mint Hill Road | Matthews, NC 28105
ISO 9001: 2008 Certified
UNIGAZ QATAR | MATERIAL SUBMITTAL
FIREMATIC VALVE
MATERIAL SUBMITTAL
readan
3826 Sul!arloaf Pkwy, Frederick, MD-21704
Tel: +l 301 7988102 Fax N0:+1 240 341 1400,Email:sales@readaninternatlonal.eom
" Reliable Dartner assiting In the grDwth of your business
Packing List
To: Diligent Trading & Contracting WLL
North Shamal Road, Exit No-10,
Al Khartiyat Street No-455, Building N0:29
Office no: 7
Doha,Qatar
Contact Person :Kumar
Procurement Manager
Petrochemical Division
Email: fuel@dillgentqatar.com
Mob +974 3007 1232
Tel +974 44663404
Authorised Signatory
Readan international
MATERIAL SUBMITTAL
UNIGAZ QATAR | MATERIAL SUBMITTAL
'83/(;
FILTER
MATERIAL SUBMITTAL
UNIGAZ QATAR | MATERIAL SUBMITTAL
AUTOMATIC TANK
GAUGING SYSTEM
MATERIAL SUBMITTAL
1 111 111ı I I mı ı ı 111111111111111 11111 1111 1 1 1111
(253)8682022062758S0345565
1. İhracatçı ORJİNAL
Consignor
Expediteur
NO S 0345565 ORIGINAL
ORIGINAL
3. Menşe Ülkesi
Country of Origin ITALY
S FLO TRADING WLL
OFFICE #5, BUILDING 54, STREET 830 ZONE 17 Pays d' origine
DOHA QATAR
BY AIR
6. Sıra No; kolilerin marka ve işaretleri, sayı ve türleri; eşyanın tanımı 7. Miktar
ltem number; marks, numbers, number and kind of packages; description of goods Quantity
Numero d'ordre - Marques, numeros, nombre et nature des colis - Designation des marchandises Quantite
8. Yukarıda Tanımlanan Eşyaların 3 Nolu Kutuda Belirtilen Ülke Menşeli Olduğu Tasdik Olunur.
The Undersigned Authority Certifies That The Goods Described Above Originate In The Country Shown ln Box 3
L'autorite soussignee certifie que !es marchandises designees ci-dessus sont originaires du pays figurant dans la case No 3
Control Panel
UNIGAZ QATAR
Gulf Countries
Dear Sir,
Schneider Electric, head quartered in France, has more than 180 manufacturing plants
worldwide. All Schneider Electric manufacturing facilities have a Quality system in place and are
accredited to ISO 9001, ISO 14001 and ISO 18001 standards.
These facilities are wholly owned and operated by Schneider Electric with state-of-the-art
machines, tools, jigs, etc. All products fully comply with international standards to which they are
type tested and are guaranteed by Schneider Electric.
The Products manufactured in any of the facilities (in Europe, USA, Far East, etc) carry the
same Warranty conditions and are fully supported with a strong local presence close to the
customers. Such facilities have been set up in order to serve our customers better by being
closer to them, understanding their needs and providing them faster response.
Best Regards
__________________________________
Prasad Venugopal
Senior Sales Manager – Panel Builders
UNIGAZ QATAR | MATERIAL
SUBMITTAL
Pre-Qualification Documents
No 2 5 3 3 9
1. Goods consigned from (Exporter's business name, address. country)
j Reference No.
CERTIFICATE OF ORIGIN
(NON PREFERENTIAL)
MAYYANNA INTERNATIONAL (Combined Declaration and Certificate)
MAYYANNA BUILDING TC 38/862 Issued in India
MARAKKADA ROAD CHALA P O TRIVANDRUM
THIRUVANANTHAPURAM KERALA 695036 - INDIA
ESTO: 1929
DILIGENT TRADING & CONTRACTING W.LL
PO BOX 15202, DOHA
QATAR
The Memon
Chamber of Commerce
Patharia Palace, 75, Moha mmedali Road,
MUMBAI - 400 003. (INDIA)
Tel.: 2342 1109 • Fax : 2341 3661
E-mail : info@memonchamber.com
3. Means of transport and route (as far as known)- 4. For Official use
BY SEA
FROM NHAVA SHEVA, INDIA TO HAMAD PORT - QATAR
5. Item 6. Marks and 7. Number and kind of packages, 8. Origin 9. Gross weight 10. Number and
No. numbers of description of goods criteria or other quantity date of invoices
packages
QATAR
Importing Country
Authorised Signatory
The Memon Chamber of Commerce
Date: Mumbai. India Place, date and signature of authorised signatory
UNIGAZ QATAR | MATERIAL SUBMITTAL
CABLE
MATERIAL SUBMITTAL
UNIGAZ QATAR |
PREQUALIFICATION
Signal Cables
Brand: Omntec
UNIGAZ QATAR
UNIGAZ QATAR |
PREQUALIFICATION
UNIGAZ QATAR
UNIGAZ QATAR | MATERIAL SUBMITTAL
CS PIPE SCH 40
MATERIAL SUBMITTAL
1. Goods consigned from (Exporter's business name, address, Rererence Nc B2ll
countrY) LLc'TNTERPIPE UKRAINE"
eA912ooc
05g ZZZ 4
Pisazhevskogo str., I a, 49005, Dnipro,
Ukraine
CERTIFICATE OF ORIGIN
2. Goods consigned to (Consignee's name, address, country)
Diligent Trading and Contracting W,L.L,
P.0 BOX 15202, TEL: +97444663404,
NORTH-SHAMAL ROAD, ALKHARTIYAT STREET45s,
tssued in UKRAINE
ico!ntry)
DOHA.QATAR
3. Means of transport and route (as far as known) For official use
By sea kansport
5, ltem 6. Marks and 7. Number and kind of packages; desmiption of goods B. Gross 9. Number
num- numbers of weight and date
ber packages or other of invoices
quantity
gross / net
49 bundles weight, kg
1. Seamless steel holrolled pipes for oil and gas pipelines with plastic caps 97446t MES19t0066
as per API Spec 5L -2012/ ASTM A106/A106M-2018/ASME 96956 dd 28.01.2019
SA1 O6iSA1 O6M.2O1 7/ASTM A53/A53M-20,I 8/ASME SA53/SA53M.201 7/ NACE
MRO175/lSO 15156-2:201S/NACE MRO103-2012, PSLI, steel BX42
dia. 33,4 - 114,3 x 3,38 - 6,02 mm
CS Fittings
Brand:TTU/BIS/BOTHWELL
UNIGAZ QATAR
12. TEST REPORT
UNIGAZ QATAR | MATERIAL SUBMITTAL
MAIN TANK
MATERIAL SUBMITTAL
UNIGAZ QATAR | MATERIAL SUBMITTAL
SUPPLY BY WOQOD
Documents will be provide along with
delivery
MATERIAL SUBMITTAL
UNIGAZ QATAR |
PREQUALIFICATION
VENT
UNIGAZ QATAR
UNIGAZ QATAR |
PREQUALIFICATION
Solenoid Valve
UNIGAZ QATAR
fluid under control
DISTRIBUTOR
smstork.com
DISTRIBUTOR CERTIFICATE
This ceritificate confirms that
WAAREE QATAR WLL
is an official distributor of
SMS TORK ENDÜSTRİYEL OTOMASYON ÜRÜNLERİ SAN. TİC. LTD. ŞTİ.
GENERAL MANAGER
ENVER KAYA
Sms Tork Endüstriyel Otomasyon Ürünleri
San. Tic. Ltd. Şti.
www.smstork.com
UNIGAZ QATAR | MATERIAL SUBMITTAL
Y STRAINER
MATERIAL SUBMITTAL
TELEPHONE: 00 44 (0) 1473 277300
FAX: 00 44 (0) 1743 277301
CERTIFICATE OF CONFORMITY
We hereby certify that the products detailed heron confirm in all respects to the
requirements of the Purchase Order.
Products are constructed from materials, which conform to the relevant product
standards and have been pressure tested, where applicable, to the appropriate
test specification.
BS EN 10204 2.1
Manufactured to BS 7350
MATERIAL SPECIFICATION:
SHELL MATERIAL MEETS THE REQUIREMENTS OF BS970 GRADE 316
TEST SPECIFICATION:
PRESSURE TESTING NOT APPLICABLE
Manufactured to BS 7350
Ball Valve
Brand: Apollo
UNIGAZ QATAR
Page 1 of 1
Material Certification
Component: Material:
GLAND,PKG,1-24X.515,BRS Brass,C36000,ASTM B16
NUT,FLG,7/16-20,STL,ZN PLT, Steel,Plated
PACKING,STEM,BV,RPTFE RPTFE
BEARING,STEM,BV,RPTFE RPTFE
SEAT,RPTFE,BV RPTFE
STEM,1-1/2",70 SER,BRS Brass,C36000,ASTM B16
BALL,BRS,CHRM PLTD Brass,C36000,ASTM B16
RETAINER,3"NPT,BRZ,70 SER Bronze,C84400,ASTM B584
BODY,3"NPT,BRZ,70100 Bronze,C84400,ASTM B584
HANDLE,LVR,L-BV,CS,ZN Steel,Plated
VINYL PLASTISOL,YELLOW, Polyvinyl Chloride
This is to certify that the above materials comply with the requirements of the applicable purchase order and the codes and ratings
shown in our published catalog of products manufactured by Conbraco Industries Inc. or as otherwise specified above. All products
have met the inspection requirements.
Respectfully,
David J. Michaels
Quality Director
Certificate of Compliance
Apollo products comply with the requirements of this purchase order and have been tested and confirmed to meet all relevant approvals
and certifications stated in our published literature.
Respectfully,
David J. Michaels
Quality Director ES-1510 Rev. A
FIREMATIC VALVE
MATERIAL SUBMITTAL
UNIGAZ QATAR | MATERIAL SUBMITTAL
MATERIAL SUBMITTAL
UNIGAZ QATAR | MATERIAL SUBMITTAL
'83/(;
FILTER
MATERIAL SUBMITTAL
UNIGAZ QATAR | MATERIAL SUBMITTAL
AUTOMATIC TANK
GAUGING SYSTEM
MATERIAL SUBMITTAL
DECLARATION OF QUALITY AND CONFORMITY
EN 60079-11:2012- ISO9001:2015
For any further clarification please do not hesitate to contact the undersigned, we
look forward to work with you.
Kind Regards,
Doruk Dogan
Managing Director
-1
-2
-3
-4
-5
500 1.000 1.500 2.000 2.500 3.000
| UNIGAZ QATAR |
CONTROL PANEL
MATERIAL SUBMITTAL
UNIGAZ QATAR | MATERIAL
SUBMITTAL
Pre-Qualification Documents
IDEX INDIA PVT. LTD.
Survey No. 256, Manjusar GIDC, Savli
Vadodara:391770
An ISO 9001 - 2008
Performance Test
Pump 1 Serial no:- V.2111011414 , Motor 1 Serial no :- UHAM14402
Pump 2 Serial no:- V.2111011415 , Motor 2 Serial No :- UHAM14719
Sr. No RPM Diff. Pressure (Bar) Flow (GPM) Flow (LPM) Noise Level (dB) Remarks
TPIA
Remark (If
any)
CABLE
MATERIAL SUBMITTAL
2021-01-31 ﺗﺎﺭﻳﺦ ﺍﻟﻄﺒﺎﻋﺔ : ﻭﺯﺍﺭﺓ ﺍﻟﺪﺍﺧﻠﻴــــﺔ
AM 11:18 ﻭﻗـﺖ ﺍﻟﻄﺒﺎﻋﺔ : ﺍﻻﺩﺍﺭﺓ ﺍﻟﻌﺎﻣﺓ ﻟﻟﺩﻓﺎﻉ ﺍﻟﻣﺩﻧﻲ
PAC21001174 ﺭﻗــﻢ ﺍﻟﻄﻠـﺐ : ﺍﺩﺍﺭﺓ ﺍﻟﻮﻗﺎﻳﺔ
ﺑﻴﺎﻧﺎﺕ ﺍﻟﻤﻨﺸﺄﺓ
ﺗﻔﺎﺻﻴﻞ ﺍﻟﺸﻬﺎﺩﺓ
ﺗﻢ ﻣﺮﺍﺟﻌﺔ ﺍﻟﻄﻠﺐ ﺍﻟﻤﻘﺪﻡ ﻭﺍﺗﻀﺢ ﺑﺄﻧﻪ ﻻ ﻣﺎﻧﻊ ﻣﻦ ﺍﻋﺘﻤﺎﺩ ﺍﻟﻤﻨﺘﺞ /ﺍﻟﻤﻨﺘﺠﺎﺕ ﺍﻟﻤﻮﺿﺤﻪ ﻓﻰ ﺍﻟﺘﻘﺮﻳﺮ ﺍﻟﻔﻨﻰ ﺍﻟﻤﺮﻓﻖ ﺑﻨﺎﺀ ﻋﻠﻰ ﺍﻋﺘﻤﺎﺩﻩ ﻣﻦ ﻗﺒﻞ ﺍﻟﻬﻴﺌﻪ
ﺍﻟﻤﺨﺘﺒﺮﻳﺔ ﺍﻟﻤﻮﺿﺤﻪ ﻓﻰ ﺍﻟﺘﻘﺮﺭ ﺍﻟﻔﻨﻲ ﺍﻟﻤﺮﻓﻖ.
ﻣﻼﺣﻈﺎﺕ
.1ﻳﺠﺐ ﻋﻠﻰ ﺍﻟﺸﺮﻛﻪ ﺍﻻﻟﺘﺰﺍﻡ ﻭﺍﻟﻌﻤﻞ ﺑﻤﺎ ﺟﺎﺀ ﻓﻲ ﺍﺷﺘﺮﺍﻃﺎﺕ ﻗﺴﻢ ﺃﻧﻈﻤﺔ ﺍﻟﺴﻼﻣﻪ ﺍﻟﺘﻲ ﺗﻢ ﺍﻻﻃﻼﻉ ﻭﺍﻟﻤﻮﺍﻓﻘﺔ ﻋﻠﻴﻬﺎ ﻣﻦ ﺧﻼﻝ ﺍﻟﻤﻮﻗﻊ.
.2ﻳﺠﺐ ﺍﻥ ﻳﻘﻮﻡ ﺑﺘﺮﻛﻴﺐ ﻫﺬﺍ ﺍﻟﻤﻨﺘﺞ ﻣﻦ ﻗﺒﻞ ﻣﻬﻨﺪﺳﻴﻦ ﻭﻓﻨﻴﻴﻦ ﻣﻌﺘﻤﺪﻳﻦ ﻣﻦ ﺍﻹﺩﺍﺭﺓ ﺍﻟﻌﺎﻣﺔ ﻟﻠﺪﻓﺎﻉ ﺍﻟﻤﺪﻧﻲ.
.3ﻳﺠﺐ ﺍﻥ ﻳﺤﻤﻞ ﺍﻟﻤﻨﺘﺞ ﺍﻟﻌﻼﻣﺔ ﺍﻟﺘﺠﺎﺭﻳﺔ ﻟﻠﻬﻴﺌﻪ ﺍﻟﻤﺨﺘﺒﺮﻳﺔ ﺍﻟﻤﻌﺘﻤﺪﺓ ﻭﺍﻟﻤﻮﺿﺤﻪ ﻓﻲ ﺍﻟﺘﻘﺮﻳﺮ ﺍﻟﻔﻨﻲ ﺍﻟﻤﺮﻓﻖ .
ﻉ/
Page 1 of 2
ﻭﺯﺍﺭﺓ ﺍﻟﺪﺍﺧﻠﻴﺔ
DATE : 2021-01-31 : ﺍﻟﺘﺎﺭﻳـــــــﺦ
ﺍﻹﺩﺍﺭﺓ ﺍﻟﻌﺎﻣﺔ ﻟﻠﺪﻓﺎﻉ ﺍﻟﻤﺪﻧﻲ
PERMIT # PAC21001174 : ﺭﻗﻢ ﺍﻟﻄﻠﺐ
ﺇﺩﺍﺭﺓ ﺍﻟﻮﻗﺎﻳﺔ
RECOMMENDATIONS ﺍﻟﺘﻮﺻﻴﺎﺕ
Notes:
1.This product approval shall comply with the Design, Inspection, Installation, Testing and Maintenance requirements of
NFPA 70 (and/or other related NFPA Codes / Standards), other acceptable International Codes / Standards, Local
Regulations, Listing Instructions and/or Manufacturer's Published Instructions subject to the technical review and approval
of the Authority Having Jurisdiction / Qatar Civil Defence.
/ﻉ
Page 2 of 2
2022-06-07 ﺗﺎﺭﻳﺦ ﺍﻟﻄﺒﺎﻋﺔ : ﻭﺯﺍﺭﺓ ﺍﻟﺪﺍﺧﻠﻴــــﺔ
AM 10:11 ﻭﻗـﺖ ﺍﻟﻄﺒﺎﻋﺔ : ﺍﻻﺩﺍﺭﺓ ﺍﻟﻌﺎﻣﺓ ﻟﻟﺩﻓﺎﻉ ﺍﻟﻣﺩﻧﻲ
PAC22005898 ﺭﻗــﻢ ﺍﻟﻄﻠـﺐ : ﺍﺩﺍﺭﺓ ﺍﻟﻮﻗﺎﻳﺔ
ﺑﻴﺎﻧﺎﺕ ﺍﻟﻤﻨﺸﺄﺓ
ﺗﻔﺎﺻﻴﻞ ﺍﻟﺸﻬﺎﺩﺓ
ﺗﻢ ﻣﺮﺍﺟﻌﺔ ﺍﻟﻄﻠﺐ ﺍﻟﻤﻘﺪﻡ ﻭﺍﺗﻀﺢ ﺑﺄﻧﻪ ﻻ ﻣﺎﻧﻊ ﻣﻦ ﺍﻋﺘﻤﺎﺩ ﺍﻟﻤﻨﺘﺞ /ﺍﻟﻤﻨﺘﺠﺎﺕ ﺍﻟﻤﻮﺿﺤﻪ ﻓﻰ ﺍﻟﺘﻘﺮﻳﺮ ﺍﻟﻔﻨﻰ ﺍﻟﻤﺮﻓﻖ ﺑﻨﺎﺀ ﻋﻠﻰ ﺍﻋﺘﻤﺎﺩﻩ ﻣﻦ ﻗﺒﻞ ﺍﻟﻬﻴﺌﻪ
ﺍﻟﻤﺨﺘﺒﺮﻳﺔ ﺍﻟﻤﻮﺿﺤﻪ ﻓﻰ ﺍﻟﺘﻘﺮﺭ ﺍﻟﻔﻨﻲ ﺍﻟﻤﺮﻓﻖ.
ﻣﻼﺣﻈﺎﺕ
.1ﻳﺠﺐ ﻋﻠﻰ ﺍﻟﺸﺮﻛﻪ ﺍﻻﻟﺘﺰﺍﻡ ﻭﺍﻟﻌﻤﻞ ﺑﻤﺎ ﺟﺎﺀ ﻓﻲ ﺍﺷﺘﺮﺍﻃﺎﺕ ﻗﺴﻢ ﺃﻧﻈﻤﺔ ﺍﻟﺴﻼﻣﻪ ﺍﻟﺘﻲ ﺗﻢ ﺍﻻﻃﻼﻉ ﻭﺍﻟﻤﻮﺍﻓﻘﺔ ﻋﻠﻴﻬﺎ ﻣﻦ ﺧﻼﻝ ﺍﻟﻤﻮﻗﻊ.
.2ﻳﺠﺐ ﺍﻥ ﻳﻘﻮﻡ ﺑﺘﺮﻛﻴﺐ ﻫﺬﺍ ﺍﻟﻤﻨﺘﺞ ﻣﻦ ﻗﺒﻞ ﻣﻬﻨﺪﺳﻴﻦ ﻭﻓﻨﻴﻴﻦ ﻣﻌﺘﻤﺪﻳﻦ ﻣﻦ ﺍﻹﺩﺍﺭﺓ ﺍﻟﻌﺎﻣﺔ ﻟﻠﺪﻓﺎﻉ ﺍﻟﻤﺪﻧﻲ.
.3ﻳﺠﺐ ﺍﻥ ﻳﺤﻤﻞ ﺍﻟﻤﻨﺘﺞ ﺍﻟﻌﻼﻣﺔ ﺍﻟﺘﺠﺎﺭﻳﺔ ﻟﻠﻬﻴﺌﻪ ﺍﻟﻤﺨﺘﺒﺮﻳﺔ ﺍﻟﻤﻌﺘﻤﺪﺓ ﻭﺍﻟﻤﻮﺿﺤﻪ ﻓﻲ ﺍﻟﺘﻘﺮﻳﺮ ﺍﻟﻔﻨﻲ ﺍﻟﻤﺮﻓﻖ .
ﻉ/
Page 1 of 2
ﻭﺯﺍﺭﺓ ﺍﻟﺪﺍﺧﻠﻴﺔ
DATE : 2022-06-07 : ﺍﻟﺘﺎﺭﻳـــــــﺦ
ﺍﻹﺩﺍﺭﺓ ﺍﻟﻌﺎﻣﺔ ﻟﻠﺪﻓﺎﻉ ﺍﻟﻤﺪﻧﻲ
PERMIT # PAC22005898 : ﺭﻗﻢ ﺍﻟﻄﻠﺐ
ﺇﺩﺍﺭﺓ ﺍﻟﻮﻗﺎﻳﺔ
RECOMMENDATIONS ﺍﻟﺘﻮﺻﻴﺎﺕ
Notes:
1.This product approval shall comply with the Design, Inspection, Installation, Testing and Maintenance requirements of
NFPA 70 (and/or other related NFPA Codes / Standards), other acceptable International Codes / Standards, Local
Regulations, Listing Instructions and/or Manufacturer's Published Instructions subject to the technical review and approval
of the Authority Having Jurisdiction / Qatar Civil Defence.
2.The basic standard used to investigate products in this category is ANSI/UL 1424, "Cables for Power-Limited Fire-Alarm
Circuits."
/ﻉ
Page 2 of 2
UNIGAZ QATAR |
PREQUALIFICATION
UNIGAZ QATAR
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner
Scanned by CamScanner
UNIGAZ QATAR | MATERIAL SUBMITTAL
CS PIPE SCH 40
MATERIAL SUBMITTAL
11118
�
MHTEPnAMn 06lQEa80 C OrPAHM'IEHHOM OTBETOBEHHOCTblO
"MHTEPJJAin HMKO TblO&"
HVIK0Tbl06 Yl(paMHa,r.HMKOnOJ\b,np.Tpy6HMKOB,S6
TE!ll./(f>aKC +38 (05662) 2-10-70
='�NII
TpaHCl1(lpTHOII
AE1572HC/AE5853XX JIMcr 1 JIMcroe 1
Sheet Sheets
21.11.2020.-.
=
ICnacc
HaMUeHO&aHNe N k0,11 TOeapa HaNYeHOBaHNe CTaJIA"PTOII noc:naa, T1111pe:n.6w
Descrlp11on and code of goods Specifications Class of Thread type
delivery
API Spec SL · 2018/ ASTM A106/A106M-2019a/ ASME SA106/SA106M-
Tpy6bl cram,Hble 6eauoBHble ropsNell3TIIHble AJIA
2019/ASTM A53/A53M-2020/ ASME SA53/SA53M-2019/ DIN EN 10216-
HeCj,rera30npoBOAOB PSL1
2:2020/ ISO 3183:2019/ ANSI/NACE MR0175/ISO 15156-2:2015/ ANSI/NACE
Seamless steel hot-rolled pipes for oil and gas pipelines
MR0103/ISO
N9 Ho11ep Ho11epa MapicacranN Ho11ep H011ep Pas11ep1,1
J1()3. naKera Tpyfi n,��4 nnaea, JlaP1l4M Difflnnc"nns
Item Bundle# Pipe# Heat# Inspection .....--,.,.
--1111fo1H3 AflllH3 OOlll3ll WT
�alCTlNl!Cltllii eec
ICpaTiroe creHKM A1111H3 Actual w.:,iaht
No o6o3H3'teHMe Lot# OD wr length !Total lenott piece 6pvno oross tterro net
Brief 1111 MIi M II icr icr
Desionation mm mm m m ko ko
1. 20-12-26375 B/ P265GH TC1 1204104 8692 114.3 6.02 6.00 96,56 16 1 585 1 575
2. 20-12-26376 Bl P265GH TC1 1204104 8692 114.3 6.02 6.00 96,56 16 1 585 1 575
NPS4 Sch40STD TOTALJMToro 193,12 32 3170 3150
BUNDLES/11AKETOB 2
3. 2Q-12-25604 B/ P265GH TC1 1204037 8504 60.3 3.91 6.00 367,83 61 1 985 1 975
4. 2Q-12-25600 B/ P265GH TC1 1204037 8503 60.3 3.91 6.00 367,83 61 1 980 1 970
NPS2 Sch40STD TOTAUMTOro 735,66 122 3965 3945
BUNDLES/JlAKETOB 2
TOTALMToro 928,78 154 7135 7 095
BUNDLES/nAKETOB 4
rpy,onofl}"<ar011•
BUYER KoHrpaKT Ne MEO21/0005
Contract#
3aBOACKOL< 3aKa3 N<009751
CTpaHa Production order #
Country
TpaHcnopTHoe
if.'i;'/:0"�,N> BT6494CNBT0441 XO fil1CT 1 fil1CTOB 1
Sheet Sheets
g:;: 04.03.2021 r.
Knacc
HaMMeHOBaHMe " KOA roeapa HaMMeHOBaHMe CTaHAapTOB nOC'HBKM T11n pe3b6b1
Description and code of goods Specifications Class of Thread type
delivery
API Spec SL- 2018/ ASTM A106/A106M-2019a/ ASME SA106/SA106M-
Tpy6bl CT8JlbHbl8 fieCWOBHble ropR4eKaTaHble A11R
2019/ASTM A53/A53M-2020/ ASME SA53/SA53M-2019/ DIN EN 10216·
Hecj>rera3onpoeoAOB PSL1
2:2020/ ISO 3183:20191 ANSI/NACE MR0175/ISO 15156-2:2015/ ANSI/NACE
Seamless steel hot-rolled pipes for oil and gas pipelines
MR0103/ISO
Ne HoMep HoMepa MapKa cra1111 Ho!,Aep HoMep Pa3Mepb1
no3. naKeTa rpy6 Gra.fo nnaeKw napr1111 Dimensinn<
A113MeTp TOJ1U1�fla A1111Ha 06U,laR <t>aKTwYeCKH� sec
tern Bundle# Pipe# •paTKoe Heat# Inspection WT
CTeHKM AJ111Ha Actual weiaht
No 0Q03Ha4BHl1e Lot# OD wr lenath Total lenath piece 6ovrro aros.sl Herra net
Brief MM MM M M •r Kr
Desionation mm mm m m ko ko
1. 21-12-03280 Bi P265GH TC1 1210679 1234 48.3 3.68 6.00-6.10 548,28 91 2 215 2 205
2. 21-12-03279 Bi P265GH TC1 1210679 1234 48.3 3.68 6.00-6.10 548,28 91 2 210 2 200
3. 21-12-03281 Bi P265GH TC1 1210679 1235 48.3 3.68 6.00-6.10 548,28 91 2 220 2 210
4. 21-12-03285 Bi P265GH TC1 1210679 1239 48.3 3.68 6.00-6.10 548,28 91 2 200 2 190
5. 21-12-03284 Bi P265GH TC1 1210679 1235 48.3 3.68 6.00-6.10 548,28 91 2 205 2 195
6. 21-12-03286 Bi P265GH TC1 1210679 1239 48.3 3.68 6.00-6.10 548,28 91 2 205 2 19.5
7. 21-12-03287 Bi P265GH TC1 1210679 1240 48.3 3.68 6.00-6.10 524,18 87 2 115 2 105
8. 21-12-03272 Bi P265GH TC1 1210679 1230 48.3 3.68 6.00-6.10 548,28 91 2 215 2 205
9. 21-12-03288 Bi P265GH TC1 1210679 1240 48.3 3.68 6.00-6.10 439,83 73 1 780 1 770
NPS 1 1i2 Sch 40 STD TOTAUMTOro 4801,97 797 19 365 19 275
BUNDLES/nAKETOB 9
s
N
0-
Cl. N•
4)
s
i :ll 4)
.
C: ....,.
t; ..c: cr;o s
:,: 4) s E
0 0) Cl. C: C::,: c 0 .,
:,: C: i'! er: �c: "E 4) 4) z
0 :r -�
HoMep ,
0 4) �
Cl. iii
.,_
" ..c:
, Cl
>-
:gi
0 mi&
I�&
�
'C:
'iii
s Cp.3HaYeHMe
lil 1/)
Cl. 1/)
\0 C:
napTMM 'o:
... ,.
0 4)
Lot#
C: 4)
�1iC:
�
1::- C:
4) I!!
C: "'C
3i g>
C: .Q
� UJ
�!l
�� ...
m :;
Cl.
0
Average
.,a. ·uE
:ii 4)
4) 4) Cl. 4) :,:
a. I
C
4)-
c::t.� "0 4) Cl.
�u 4)
�
I .., Cl.
8.
c
>
0
�(J)
Bau.at npe,Q/lo)KeHIIIR no YllyYWeHHto npo.QYK4MIII npocm.A HanpasnRTb. Ha 3/1.a.Qpec / Please send Your proposals for improving the product by e-mail or fax or by phone
info@nstp.interpipe.biz www.interpipe.biz Phone: +380 566-630-133 Fax: +380 566-639-379.
e-mail: info@ae.interpipe.biz. Phone: +97148857411 Fax: +97148857412
3TOT l11HcneK4M0HHb1M cepn1¢>111K8T OTHOa.tTCR TOilbKO K nepe4MCJ1eHH0M B HeM npo,qyK4111111. He.qonyCTHMO BHeceH111e M3MeHeHHM 111IWI ,a.pyroe HenpaeoMepHoe Men cpaKara.
This inspection certificate is only for the listed products. Modification or unauthorized use of the certificate is strictly prohibited. Violations can be considered as fo to prosecution
HHcne•4•0HHbU< cepracpaKaT ccpopMwposaH " nposepeH KOHTponepoM ceprncpaKaropoM nABOEHKO A.C.
nnspection Certificate was dralM'l up and checked by the Certificate Inspector PAVLENKO A.S.
Aara:
n.,..
04.03.2021 noAnMCb MHcneKTopa 3-i< cropoH" :
Signature of 3-rd Part Inspector 1 ... 4 0
//�"----..,..:r
UNIGAZ QATAR |
PREQUALIFICATION
CS Fittings
Brand:TTU/BIS/BOTHWELL
UNIGAZ QATAR
13. SAMPLE WITH MATERIALS, COMPANY
AND COUNTRY DETAILS
NOT APPLICABLE
14. SPARES
Spares List
_______________________________
Authorized Signatory
AMERICAN BASE THE US ARMY THE US ARMY Detailed Design, Engineering, Supply,
3 SHEILD-5 AL SEAL CORPS OF CORPS OF Installation, Testing & Commissioning of
PROGRAMMES ENGINEERS ENGINEERS Fuel System up to Authority Approval
H.E. SHK.
Detailed Design, Engineering, Supply,
FUEL SYSTEM - DAR AL SAOUD BIN
14 SEG QATAR Installation, Testing & Commissioning of
BOULEVARD MALL HANDASAH ABDULLAH AL
Fuel System up to Authority Approval
- THANI
COMMERCIAL MR.
Detailed Design, Engineering, Supply,
BUILDING ABDULLAH BIN
METRIX Delivery to Site, Installation, Testing &
15 (B+G+7P+13F) ON MZP FAHAD
QATAR W.L.L. Commissioning, Handing Over, Warranty
PLOT MARINA GHORAB AL -
& Maintenance of Diesel Fuel System
MIX052 MARRI
Detailed Design, Engineering, Supply,
HALUL REAL
DOHA OASIS MIXED CONSPEL Delivery to Site, Installation, Testing &
16 AECOM INVESTMENT
USE DEVELOPMENT QATAR W.L.L Commissioning, Handing Over, Warranty
COMPANY
& Maintenance of Diesel Fuel System
Construction of
3) Additional Facilities Detailed Design, Engineering, Supply, Delivery to Site,
ROOTS ENERGY & Ashghal - Public
for Community Installation, Testing & Commissioning, Handing Over, ENGINEERING
Erga Qatar
Works Authority
College of Qatar - Warranty & Maintenance of Diesel Fuel System
Boys
LUXURY MIXED
4) Detailed Design, Engineering, Supply, Delivery to Site, TAKYEEF AEB (Arab
USE ARKAZ
DEVELOPMENT AT
Installation, Testing & Commissioning, Handing Over, ELECTROMECHANIC Engineering
INVESTMENT
Warranty & Maintenance of Diesel Fuel System AL WLL Bureau)
LUSAIL
AL MUTAHIDA
5) TOWERS Detailed Design, Engineering, Supply, Delivery to Site, Gulf Engineering & UNITED
Al Seal Contracting &
DEVELOPMENT, Installation, Testing & Commissioning, Handing Over, Trading
Industrial DEVELOPMENT
THE PEARL QATAR Warranty & Maintenance of Diesel Fuel System Consultancy COMPANY.
-THE VIVA BAHRIYA
LIST OF SELECTED ON GOING PROJECTS
S.NO PROJECT NAME
DESCRIPTION CONTRACTOR CONSULTANT CLIENT
CONSTRUCTION
OF GIARDINO MALL
8) AND MARINA Detailed Design, Engineering, Supply, Delivery to Site, ROOTS ENERGY & ARAB UNITED
WORKSHOP Installation, Testing & Commissioning, Handing Over, ENGINEERING ENGINEERING DEVELOPMEN
PACKAGE A, B&C Warranty & Maintenance of Diesel Fuel System SERVICES W.L.L BUREAU T COMPANY
AT THE PEARL
QATAR
QATAR
Detailed Design, Engineering, Supply, Delivery to Site, GENERAL
10) Samko International INSURANCE &
MOZOON TOWERS Installation, Testing & Commissioning, Handing Over, Co. W.L.L.
MZP WLL.
RE
Warranty & Maintenance of Diesel Fuel System INSURANCE
CO.
LIST OF SELECTED CURRENT PROJECTS
S.NO PROJECT NAME
DESCRIPTION CONTRACTOR CONSULTANT CLIENT
11) ISF Sports Facilities Detailed Design, Engineering, Supply, Delivery to Site,
Powermech Dar Al Handasah – Internal Security
and Running Tracks Installation, Testing & Commissioning, Handing Over, Engineering (DAR) Force - (ISF)
– CPC08D Warranty & Maintenance of Diesel Fuel System
DESIGN & BUILD Detailed Design, Engineering, Supply, Delivery to Site, Anel Mep Lusail Real
14) WORKS FOR State
LUSAIL PLAZA
Installation, Testing & Commissioning, Handing Over, Maintenance and DAR
Development
TOWERS Warranty & Maintenance of Diesel Fuel System Operations Company
QǦBAIRAQ
Proposed Hotel &
15) Detailed Design, Engineering, Supply, Delivery to Site, DEVELOPMEN
Apartment Building Ǧ Structural Electro Dara Engineering
Installation, Testing & Commissioning, Handing Over, T&
The Pearl Qatar (P19 Mechanical W.L.L. Consultants
INVESTMENT
& P19A) Warranty & Maintenance of Diesel Fuel System
CO
19. COPY OF PREVIOUS ASHGHAL APPROVAL