JETTY

Activity Dur. Start End Vol. Unit


1 PILE WORK _ JETTY Plan 219 24-Mar-22 28-Oct-22
Actual
1.1 ONSHORE Plan 103 24-Mar-22 4-Jul-22
Actual
1.1.1 PHASE 1 Plan 103 24-Mar-22 4-Jul-22
Actual
1.1.1.1 Plan 12 24-Mar-22 3-Apr-22 23 NOS
Material Pile Fabrication
Actual 1
1.1.1.2 Plan 12 5-Apr-22 15-Apr-22 23 NOS
Material Pile Delivery On Site
Actual 1
1.1.1.3 Plan 24 8-Apr-22 1-May-22 23 LS
Preboring
Actual 1
1.1.1.4 Plan 63 10-Apr-22 11-Jun-22 23 NOS
Piling
Actual 1
1.1.1.5 Plan 23 12-Jun-22 4-Jul-22 23 NOS
Cut off pile
Actual 1
1.2 OFFSHORE (GRID 1 - 40) - (SANJAYA 5 BARGE) Plan 179 3-May-22 28-Oct-22
Actual
1.2.1 PHASE 1 (start from AS 40 to AS 28 ) 56 21-Apr-22 15-Jun-22

1.2.1.2 Plan 40 21-Apr-22 30-May-22 78 NOS


Material Pile Fabrication
Actual 1
1.2.1.2 Plan 40 3-May-22 11-Jun-22 78 NOS
Material Pile Delivery On Site
Actual 1
1.2.1.3 Plan 2 6-May-22 7-May-22 1 LS
Barge positioning
Actual 1
1.2.1.4 Plan 38 8-May-22 14-Jun-22 78 NOS
Piling
Actual 1 51
1.2.1.5 Plan 35 12-May-22 15-Jun-22 78 NOS
Cut off pile
Actual 1
1.2.2 PHASE 2 (start from AS 27 to AS 25 ) 48 1-Jun-22 18-Jul-22

1.2.2.1 Plan 11 1-Jun-22 11-Jun-22 19 NOS


Material Pile Fabrication
Actual 1
1.2.2.2 Plan 11 13-Jun-22 23-Jun-22 19 NOS
Material Pile Delivery On Site
Actual 1
1.2.2.3 Plan 2 16-Jun-22 17-Jun-22 1 LS
Barge positioning
Actual 1
1.2.2.4 Plan 9 18-Jun-22 26-Jun-22 19 NOS
Piling
Actual
1.2.2.5 Plan 6 22-Jun-22 27-Jun-22 19 NOS
Cut off pile
Actual 1
1.2.2.6 Plan 21 28-Jun-22 18-Jul-22 1 NOS
Test pile
Actual 1
1.2.3 PHASE 3 (start from AS 24 to AS 7 ) 76 4-Jul-22 17-Sep-22

1.2.3.1 Plan 60 4-Jul-22 1-Sep-22 117 NOS


Material Pile Fabrication
Actual 1
1.2.3.2 Plan 60 16-Jul-22 13-Sep-22 117 NOS
Material Pile Delivery On Site
Actual 1
1.2.3.3 Plan 2 19-Jul-22 20-Jul-22 1 LS
Barge positioning
Actual 1
1.2.3.4 Plan 57 21-Jul-22 15-Sep-22 117 NOS
Piling
Actual 1
1.2.3.5 Plan 55 25-Jul-22 17-Sep-22 117 NOS
Cut off pile
Actual 1
1.2.4 PHASE 4 (start from AS 6 to AS 1 ) - Include Trestle 56 3-Sep-22 28-Oct-22

1.2.4.1 Plan 40 3-Sep-22 12-Oct-22 77 NOS


Material Pile Fabrication
Actual 1
JETTY
Activity Dur. Start End Vol. Unit
1.2.4.2 Plan 40 15-Sep-22 24-Oct-22 77 NOS
Material Pile Delivery On Site
Actual 1
1.2.4.3 Plan 2 18-Sep-22 19-Sep-22 1 LS
Barge positioning
Actual 1
1.2.4.4 Plan 38 20-Sep-22 27-Oct-22 77 NOS
Piling
Actual 1
1.2.4.5 Plan 35 24-Sep-22 28-Oct-22 77 NOS
Cut off pile
Actual 1
1.3 OFFSHORE (GRID 41 - 68) - (PATRA MULIA 3 BARGE) Plan 149 29-May-22 23-Oct-22
Actual
1.3.1 PHASE 1 (start from AS 41 to AS 68 ) 136 29-May-22 10-Oct-22

1.3.1.3 Plan 90 29-May-22 26-Aug-22 178 NOS


Material Pile Fabrication
Actual 1
1.3.1.3 Plan 90 10-Jun-22 7-Sep-22 178 NOS
Material Pile Delivery On Site
Actual 1
1.3.1.3 Plan 2 13-Jun-22 14-Jun-22 1 LS
Barge positioning
Actual 1
1.3.1.4 Plan 118 15-Jun-22 9-Oct-22 178 NOS
Piling
Actual 1
1.3.1.5 Plan 113 21-Jun-22 10-Oct-22 178 NOS
Cut off pile
Actual 1
1.3.2 PHASE 2 (Mooring Dolphin) 28 26-Sep-22 23-Oct-22

1.3.2.1 Plan 9 26-Sep-22 4-Oct-22 15 NOS


Material Pile Fabrication
Actual 1
1.3.2.2 Plan 9 8-Oct-22 16-Oct-22 15 NOS
Material Pile Delivery On Site
Actual 1
1.3.2.3 Plan 2 11-Oct-22 12-Oct-22 1 LS
Barge positioning
Actual 1
1.3.2.4 Plan 9 13-Oct-22 21-Oct-22 15 NOS
Piling
Actual 1
1.3.2.5 Plan 2 22-Oct-22 23-Oct-22 15 NOS
Cut off pile
Actual 1
2 INSTALL _ DECK STRUCTURE FOR JETTY Plan 303 5-May-22 3-Mar-23
Actual
2.1 OFFSHORE (GRID 1 - 40) - (PRECAST 1 BARGE) Plan 216 31-May-22 1-Jan-23
Actual
2.1.1 Offshore Area (start from AS 40 to AS 1 ) 214 5-May-22 4-Dec-22

2.1.1.1 Plan 26 5-May-22 30-May-22 1 LS


Engineering Design
Actual 1
2.1.1.2 Plan 31 31-May-22 30-Jun-22 567 NOS
Precast Preparation
Actual 1
2.1.1.3 Fabrication Plan 152 6-Jul-22 4-Dec-22
Actual 1
a. Plan 85 6-Jul-22 28-Sep-22 250 NOS
Temporary Beam Support Fabrication
Actual 1
b. Plan 81 1-Jul-22 19-Sep-22 240 NOS
Headstock Fabrication
Actual 1
b. Plan 110 11-Jul-22 28-Oct-22 327 NOS
Beam Fabrication
Actual 1
c. Plan 146 12-Jul-22 4-Dec-22 240 NOS
Half Slab Fabrication
Actual 1
2.1.1.4 Mobilization 95 1-Jul-22 3-Oct-22

a. 2 1-Jul-22 2-Jul-22 1 Ls
Platform Mobilization
b. 85 11-Jul-22 3-Oct-22 250 SETS
Temporary Beam Support Mobilization
JETTY
Activity Dur. Start End Vol. Unit
c. 81 15-Jul-22 3-Oct-22 240 NOS
Precast Mobilization
c. Plan 115 20-Jul-22 11-Nov-22 327 NOS
Beam Mobilization
Actual 1
d. Plan 137 4-Aug-22 18-Dec-22 165 NOS
Half Slab Mobilization
Actual 1
2.1.1.5 Construction 180 6-Jul-22 1-Jan-23

a. Plan 102 6-Jul-22 15-Oct-22


Pile Head
Actual 1
Plan 85 6-Jul-22 28-Sep-22 250 SETS
- Install Platform
Actual 1
Plan 85 16-Jul-22 8-Oct-22 250 SETS
- Install Temporary Beam Support
Actual 1
Plan 81 20-Jul-22 8-Oct-22 240 NOS
- Headstock Placement
Actual 1
Plan 85 23-Jul-22 15-Oct-22 250 SETS
- Installasi Tulangan Infill Concrete
Actual 1
b. Plan 147 25-Jul-22 18-Dec-22
Precast Beam install
Actual 1
Plan 110 25-Jul-22 11-Nov-22 327 NOS
- Beam Placement
Actual 1
Plan 139 27-Jul-22 12-Dec-22 165 SETS
- Install Rebar Connection Joint
Actual 1
Plan 139 30-Jul-22 15-Dec-22 165 SETS
- Install Formwork
Actual 1
Plan 139 2-Aug-22 18-Dec-22 165 SETS
- Concreting (Until Top of Precast)
Actual 1
c. 146 9-Aug-22 1-Jan-23 240 NOS
Precast Half Slab Install
2.1.1 Offshore Area (Trestle) 245 5-May-22 3-Jan-23

2.1.1.1 Plan 26 5-May-22 30-May-22 1 LS


Engineering Design
Actual 1
2.1.1.2 Plan 31 31-May-22 30-Jun-22 65 NOS
Precast Preparation
Actual 1
2.1.1.3 Fabrication Plan 17 19-Dec-22 3-Jan-23
Actual 1
a. Plan 12 19-Dec-22 30-Dec-22 33 NOS
Temporary Beam Support Fabrication
Actual 1
b. Plan 12 14-Dec-22 25-Dec-22 33 NOS
Headstock Fabrication
Actual 1
b. Plan 12 24-Dec-22 3-Jan-23 32 NOS
Beam Fabrication
Actual 1
c. Plan 41 25-Dec-22 3-Feb-23 24 NOS
Half Slab Fabrication
Actual 1
2.1.1.4 Mobilization 26 14-Dec-22 8-Jan-23

a. 2 14-Dec-22 15-Dec-22 1 Ls
Platform Mobilization
b. 12 24-Dec-22 4-Jan-23 33 SETS
Temporary Beam Support Mobilization
c. 12 28-Dec-22 8-Jan-23 33 NOS
Precast Mobilization
c. Plan 17 2-Jan-23 17-Jan-23 32 NOS
Beam Mobilization
Actual 1
d. Plan 32 17-Jan-23 17-Feb-23 24 NOS
Half Slab Mobilization
Actual 1
2.1.1.5 Construction 75 19-Dec-22 3-Mar-23
JETTY
Activity Dur. Start End Vol. Unit
a. Plan 29 19-Dec-22 16-Jan-23
Pile Head
Actual 1
Plan 12 19-Dec-22 30-Dec-22 33 SETS
- Install Platform
Actual 1
Plan 12 29-Dec-22 9-Jan-23 33 SETS
- Install Temporary Beam Support
Actual 1
Plan 12 2-Jan-23 13-Jan-23 33 NOS
- Headstock Placement
Actual 1
Plan 12 5-Jan-23 16-Jan-23 33 SETS
- Installasi Tulangan Infill Concrete
Actual 1
b. Plan 37 7-Jan-23 12-Feb-23
Precast Beam install
Actual 1
Plan 12 7-Jan-23 18-Jan-23 32 NOS
- Beam Placement
Actual 1
Plan 29 9-Jan-23 6-Feb-23 33 SETS
- Install Rebar Connection Joint
Actual 1
Plan 29 12-Jan-23 9-Feb-23 33 SETS
- Install Formwork
Actual 1
Plan 29 15-Jan-23 12-Feb-23 33 SETS
- Concreting (Until Top of Precast)
Actual 1
c. 41 22-Jan-23 3-Mar-23 24 NOS
Precast Half Slab Install

2.2 OFFSHORE (GRID 41 - 65) - (PRECAST 2 BARGE) Plan 248 5-May-22 7-Jan-23
Actual
2.2.1 Offshore Area (start from AS 41 to AS 65 ) 248 5-May-22 7-Jan-23

2.2.1.1 Plan 26 5-May-22 30-May-22 1 LS


Engineering Design
Actual 1
2.2.1.2 Plan 31 31-May-22 30-Jun-22 400 NOS
Precast Preparation
Actual 1
2.2.1.3 Fabrication Plan 91 5-Aug-22 3-Nov-22
Actual 1
a. Plan 64 5-Aug-22 7-Oct-22 188 NOS
Temporary Beam Support Fabrication
Actual 1
b. Plan 50 31-Jul-22 18-Sep-22 145 NOS
Headstock Fabrication
Actual 1
b. Plan 86 10-Aug-22 3-Nov-22 255 NOS
Beam Fabrication
Actual 1
c. Plan 96 26-Sep-22 30-Dec-22 150 NOS
Half Slab Fabrication
Actual 1
2.2.1.4 Mobilization 68 6-Aug-22 12-Oct-22

a. 2 6-Aug-22 7-Aug-22 1 Ls
Platform Mobilization
b. 64 10-Aug-22 12-Oct-22 188 SETS
Temporary Beam Support Mobilization
c. 50 14-Aug-22 2-Oct-22 145 NOS
Precast Mobilization
c. Plan 91 19-Aug-22 17-Nov-22 255 NOS
Beam Mobilization
Actual 1
d. Plan 78 19-Oct-22 4-Jan-23 145 NOS
Half Slab Mobilization
Actual 1
2.2.1.5 Construction 150 11-Aug-22 7-Jan-23

a. Plan 75 11-Aug-22 24-Oct-22


Pile Head
Actual 1
Plan 64 11-Aug-22 13-Oct-22 188 SETS
- Install Platform
Actual 1
Plan 64 15-Aug-22 17-Oct-22 188 SETS
- Install Temporary Beam Support
Actual 1
JETTY
Activity Dur. Start End Vol. Unit
Plan 50 19-Aug-22 7-Oct-22 145 NOS
- Headstock Placement
Actual 1
Plan 64 22-Aug-22 24-Oct-22 188 SETS
- Installasi Tulangan Infill Concrete
Actual 1
b. Plan 130 24-Aug-22 31-Dec-22
Precast Beam install
Actual 1
Plan 86 24-Aug-22 17-Nov-22 255 NOS
- Beam Placement
Actual 1
Plan 122 26-Aug-22 25-Dec-22 145 SETS
- Install Rebar Connection Joint
Actual 1
Plan 122 29-Aug-22 28-Dec-22 145 SETS
- Install Formwork
Actual 1
Plan 122 1-Sep-22 31-Dec-22 145 SETS
- Concreting (Until Top of Precast)
Actual 1
c. 76 24-Oct-22 7-Jan-23 150 NOS
Precast Half Slab Install

2.3 ONSHORE PRECAST TEAM Plan 151 5-May-22 2-Oct-22


Actual
2.3.1 Trestle & Galery Area 151 5-May-22 2-Oct-22

2.3.1.1 Plan 26 5-May-22 30-May-22 1 LS


Engineering Design
Actual 1
2.3.1.2 Plan 31 31-May-22 30-Jun-22 31 NOS
Precast Preparation
Actual 1
2.3.1.3 Fabrication Plan 12 1-Aug-22 11-Aug-22
Actual 1
a. Plan 6 1-Aug-22 6-Aug-22 14 NOS
Temporary Beam Support Fabrication
Actual 1
b. Plan 6 27-Jul-22 1-Aug-22 14 NOS
Headstock Fabrication
Actual 1
b. Plan 7 6-Aug-22 11-Aug-22 17 NOS
Beam Fabrication
Actual 1
c. Plan 43 7-Aug-22 18-Sep-22 15 NOS
Half Slab Fabrication
Actual 1
2.3.1.4 Mobilization 20 27-Jul-22 15-Aug-22

a. 2 27-Jul-22 28-Jul-22 1 Ls
Platform Mobilization
b. 6 6-Aug-22 11-Aug-22 14 SETS
Temporary Beam Support Mobilization
c. 6 10-Aug-22 15-Aug-22 14 NOS
Precast Mobilization
c. Plan 12 15-Aug-22 25-Aug-22 17 NOS
Beam Mobilization
Actual 1
d. Plan 34 30-Aug-22 2-Oct-22 14 NOS
Half Slab Mobilization
Actual 1
2.3.1.5 Construction 47 1-Aug-22 16-Sep-22

a. Plan 23 1-Aug-22 23-Aug-22


Pile Head
Actual 1
Plan 6 1-Aug-22 6-Aug-22 14 SETS
- Install Platform
Actual 1
Plan 6 11-Aug-22 16-Aug-22 14 SETS
- Install Temporary Beam Support
Actual 1
Plan 6 15-Aug-22 20-Aug-22 14 NOS
- Headstock Placement
Actual 1
Plan 6 18-Aug-22 23-Aug-22 14 SETS
- Installasi Tulangan Infill Concrete
Actual 1
b. Plan 21 20-Aug-22 9-Sep-22
Precast Beam install
Actual 1
JETTY
Activity Dur. Start End Vol. Unit
Plan 7 20-Aug-22 26-Aug-22 17 NOS
- Beam Placement
Actual 1
Plan 13 22-Aug-22 3-Sep-22 14 SETS
- Install Rebar Connection Joint
Actual 1
Plan 13 25-Aug-22 6-Sep-22 14 SETS
- Install Formwork
Actual 1
Plan 13 28-Aug-22 9-Sep-22 14 SETS
- Concreting (Until Top of Precast)
Actual 1
c. 13 4-Sep-22 16-Sep-22 15 NOS
Precast Half Slab Install

3 CON'C WORK _ UNLOADING DECK STRUCTURE FOR Plan 209 11-Aug-22 7-Mar-23
Actual
3.1 OFFSHORE (GRID 1 - 40) - (INSITU TEAM 1) Plan 181 11-Aug-22 7-Feb-23
Actual
3.1.1 Offshore Area (start from AS 1 to AS 40 ) 181 11-Aug-22 7-Feb-23

3.1.1.1 Installasi Rebar Beam Plan 111 11-Aug-22 29-Nov-22 131 TON
Actual
3.1.1.2 Plan 168 13-Aug-22 27-Jan-23 275 TON
Installasi Rebar Slab
Actual
3.1.1.3 Plan 168 15-Aug-22 29-Jan-23 40 grid
Formwork installation
Actual
3.1.1.4 Plan 111 13-Oct-22 31-Jan-23 165 m3
Slab concrete in situ
Actual 1
3.1.1.5 Finishing Concrete Work Plan 111 20-Oct-22 7-Feb-23 40 grid
Actual
3.1.2 Offshore Area (TRESTLE) 55 12-Jan-23 7-Mar-23

3.1.2.1 Installasi Rebar Beam Plan 12 5-Feb-23 16-Feb-23 12.8 TON


Actual
3.1.2.2 Plan 18 7-Feb-23 24-Feb-23 27.5 TON
Installasi Rebar Slab
Actual
3.1.2.3 Plan 18 9-Feb-23 26-Feb-23 7 grid
Formwork installation
Actual
3.1.2.4 Plan 48 12-Jan-23 28-Feb-23 70 m3
Slab concrete in situ
Actual 1
3.1.2.5 Finishing Concrete Work Plan 48 19-Jan-23 7-Mar-23 7 grid
Actual
3.2 OFFSHORE (GRID 41 - 65) - (INSITU TEAM 2) Plan 119 26-Oct-22 21-Feb-23
Actual
3.2.1 Offshore Area (start from AS 41 to AS 65 ) 119 26-Oct-22 21-Feb-23

3.2.1.1 Installasi Rebar Beam Plan 86 26-Oct-22 19-Jan-23 102 TON


Actual
3.2.1.2 Plan 106 28-Oct-22 10-Feb-23 172 TON
Installasi Rebar Slab
Actual
3.2.1.3 Plan 106 30-Oct-22 12-Feb-23 25 grid
Formwork installation
Actual
3.2.1.4 Plan 98 9-Nov-22 14-Feb-23 145 m3
Slab concrete in situ
Actual 1
3.2.1.5 Finishing Concrete Work Plan 98 16-Nov-22 21-Feb-23 25 grid
Actual
3.2.2 Offshore Area (Mooring Dolphin) 73 28-Oct-22 8-Jan-23

3.2.2.1 Pra-Construction 13 28-Oct-22 9-Nov-22

Plan 6 28-Oct-22 2-Nov-22 15 SETS


- Install Platform
Actual 1
Plan 6 30-Oct-22 4-Nov-22 15 SETS
- Install Temporary Beam Support
Actual 1
JETTY
Activity Dur. Start End Vol. Unit
Plan 9 1-Nov-22 9-Nov-22 23 NOS
- Support Beam Installation
Actual 1
Plan 6 4-Nov-22 9-Nov-22 15 SETS
- Installasi Formwork Plate
Actual 1
3.2.2.2 Construction 60 10-Nov-22 8-Jan-23

Plan 26 10-Nov-22 5-Dec-22 40.5 TON


- Installasi Rebar Slab
Actual
Plan 26 12-Nov-22 7-Dec-22 72 m2
- Formwork installation
Actual
Plan 4 8-Dec-22 11-Dec-22 162 m3
- Slab concrete in situ
Actual 1
- Finishing Concrete Work Plan 15 25-Dec-22 8-Jan-23 1 ls
Actual
3.3 ONSHORE (INSITU TEAM 3) Plan 36 11-Sep-22 16-Oct-22
Actual
3.3.1 Trestle Area (Include Galery) 36 11-Sep-22 16-Oct-22

3.3.1.1 Installasi Rebar Beam Plan 7 11-Sep-22 17-Sep-22 6.8 TON


Actual
3.3.1.2 Plan 12 13-Sep-22 24-Sep-22 17.2 TON
Installasi Rebar Slab
Actual
3.3.1.3 Plan 12 15-Sep-22 26-Sep-22 3 grid
Formwork installation
Actual
3.3.1.4 Plan 21 19-Sep-22 9-Oct-22 30 m3
Slab concrete in situ
Actual 1
3.3.1.5 Finishing Concrete Work Plan 21 26-Sep-22 16-Oct-22 3 grid
Actual
4 FINISHING WORK _ JETTY Plan 234 27-Jul-22 17-Mar-23
Actual
4.1 FINISHING Plan 234 27-Jul-22 17-Mar-23
Actual
4.1.1.1 Cathodic Protection Plan 122 29-Oct-22 27-Feb-23 484 POINT
Actual
4.1.1.2 Plan 122 16-Nov-22 17-Mar-23 484 POINT
Wrapping Pile HDPE
Actual
4.1.1.3 Plan 76 15-Dec-22 28-Feb-23
Install Fender
Actual
a. Plan 69 15-Dec-22 21-Feb-23 17
- Installasi Precast Plank Fender
Actual
b. Plan 69 22-Dec-22 28-Feb-23 17
- Installasi Mechanical Fender
Actual
4.1.1.4 Plan 234 27-Jul-22 17-Mar-23
Install Bolard
Actual 1
a. Plan 139 27-Jul-22 12-Dec-22 17
- Installasi Bollard Anchor
Actual
b. Plan 18 28-Feb-23 17-Mar-23 17
- Installasi Mechanical Bollard
Actual
4.1.1.5 Support for Lighting & Fire Fighting Plan 61 16-Jan-23 17-Mar-23
Actual
a. Plan 61 16-Jan-23 17-Mar-23 7746 m
- Installasi Main Ring Fire Fighting Pipe
Actual
b. Plan 61 16-Jan-23 17-Mar-23 65 Grid
- Installasi Lighting
Actual
4.1.1.6 Earthing Plan 168 13-Aug-22 27-Jan-23
Actual
5 DHII scope Plan 280 18-Mar-23 22-Dec-23
Actual
5.1 CSU INSTALLATION & COMMISIONNING Plan 280 18-Mar-23 22-Dec-23
Actual
JETTY
Activity Dur. Start End Vol. Unit
5.1.1.1 Install _ Rail for Ship Unloading System Plan 74 18-Mar-23 30-May-23
Actual
5.1.1.2 Plan 68 13-Jul-23 18-Sep-23
Install _ Ship Unloader
Actual
5.1.1.3 Install _ Elec. Equipment Work for Ship Unloader Plan 71 14-Aug-23 23-Oct-23
Actual
5.1.1.4 (Comm) Unloading Conveyor & Ship Unloader Test Plan 60 24-Oct-23 22-Dec-23
Actual
STG BUILDING #1
Estimate
NO. Name Start date (Plan) Finish date (Plan) Dur Prod. Unit
Volume

I STG BUILDING #1 1-Jun-22 26-Jan-23 240


A S/S ERECTION (Completidon Date) 1-Jun-22 22-Jul-22 52
A' Main S/S Erection 1-Jun-22 28-Jun-22 28
1-Jun-22 28-Jun-22 28 38 1060 Ton
1-1 S/S Erection (excl. holding area)

1 Row - 13 26-Jun-22 29-Jun-22 4


26-Jun-22 27-Jun-22 2 5 9 m2
1-1 Welding

28-Jun-22 29-Jun-22 2 5 9 m2
1-2 Purlin Installation

2 Row - 12 28-Jun-22 1-Jul-22 4


28-Jun-22 29-Jun-22 2 5 9 m2
2-1 Welding

30-Jun-22 1-Jul-22 2 5 9 m2
2-2 Purlin Installation

3 Row - 11 30-Jun-22 3-Jul-22 4


30-Jun-22 1-Jul-22 2 5 9 m2
3-1 Welding

2-Jul-22 3-Jul-22 2 5 9 m2
3-2 Purlin Installation

4 Row - 10 28-Jun-22 7-Jul-22 10


28-Jun-22 29-Jun-22 2 5 9 m2
4-1 Bolting

30-Jun-22 1-Jul-22 2 5 9 m2
4-2 Plumbness

2-Jul-22 3-Jul-22 2 8 16 m2
4-3 Welding

4-Jul-22 5-Jul-22 2 8 16 m2
4-4 Grouting

6-Jul-22 7-Jul-22 2 1 1 Ton


4-5 Purlin Installation

5 Row - 9 30-Jun-22 9-Jul-22 10


30-Jun-22 1-Jul-22 2 5 9 m2
5-1 Bolting

2-Jul-22 3-Jul-22 2 5 9 m2
5-2 Plumbness

4-Jul-22 5-Jul-22 2 8 16 m2
5-3 Welding

6-Jul-22 7-Jul-22 2 8 16 m2
5-4 Grouting

8-Jul-22 9-Jul-22 2 1 1 Ton


5-5 Purlin Installation

6 Row - 8 2-Jul-22 11-Jul-22 10


2-Jul-22 3-Jul-22 2 5 9 m2
6-1 Bolting

4-Jul-22 5-Jul-22 2 5 9 m2
6-2 Plumbness

6-Jul-22 7-Jul-22 2 8 16 m2
6-3 Welding

8-Jul-22 9-Jul-22 2 8 16 m2
6-4 Grouting

10-Jul-22 11-Jul-22 2 1 1 Ton


6-5 Purlin Installation

7 Row - 7 4-Jul-22 13-Jul-22 10


4-Jul-22 5-Jul-22 2 5 9 m2
7-1 Bolting

6-Jul-22 7-Jul-22 2 5 9 m2
7-2 Plumbness

8-Jul-22 9-Jul-22 2 8 16 m2
7-3 Welding

10-Jul-22 11-Jul-22 2 8 16 m2
7-4 Grouting

12-Jul-22 13-Jul-22 2 1 1 Ton


7-5 Purlin Installation

8 Row - 6 5-Jul-22 14-Jul-22 10


5-Jul-22 6-Jul-22 2 5 9 m2
8-1 Bolting

7-Jul-22 8-Jul-22 2 5 9 m2
8-2 Plumbness

9-Jul-22 10-Jul-22 2 8 16 m2
8-3 Welding
STG BUILDING #1
Estimate
NO. Name Start date (Plan) Finish date (Plan) Dur Prod. Unit
Volume
8-3 Welding

11-Jul-22 12-Jul-22 2 8 16 m2
8-4 Grouting

13-Jul-22 14-Jul-22 2 1 1 Ton


8-5 Purlin Installation

9 Row - 5 6-Jul-22 15-Jul-22 10


6-Jul-22 7-Jul-22 2 5 9 m2
9-1 Bolting

8-Jul-22 9-Jul-22 2 5 9 m2
9-2 Plumbness

10-Jul-22 11-Jul-22 2 8 16 m2
9-3 Welding

12-Jul-22 13-Jul-22 2 8 16 m2
9-4 Grouting

14-Jul-22 15-Jul-22 2 1 1 Ton


9-5 Purlin Installation

10 Row - 4 7-Jul-22 16-Jul-22 10


7-Jul-22 8-Jul-22 2 5 9 m2
10-1 Bolting

9-Jul-22 10-Jul-22 2 5 9 m2
10-2 Plumbness

11-Jul-22 12-Jul-22 2 8 16 m2
10-3 Welding

13-Jul-22 14-Jul-22 2 8 16 m2
10-4 Grouting

15-Jul-22 16-Jul-22 2 1 1 Ton


10-5 Purlin Installation

11 Row - 3 9-Jul-22 18-Jul-22 10


9-Jul-22 10-Jul-22 2 5 9 m2
11-1 Bolting

11-Jul-22 12-Jul-22 2 5 9 m2
11-2 Plumbness

13-Jul-22 14-Jul-22 2 8 16 m2
11-3 Welding

15-Jul-22 16-Jul-22 2 8 16 m2
11-4 Grouting

17-Jul-22 18-Jul-22 2 1 1 Ton


11-5 Purlin Installation

12 Row - 2 11-Jul-22 20-Jul-22 10


11-Jul-22 12-Jul-22 2 5 9 m2
12-1 Bolting

13-Jul-22 14-Jul-22 2 5 9 m2
12-2 Plumbness

15-Jul-22 16-Jul-22 2 8 16 m2
12-3 Welding

17-Jul-22 18-Jul-22 2 8 16 m2
12-4 Grouting

19-Jul-22 20-Jul-22 2 1 1 Ton


12-5 Purlin Installation

13 Row - 1 13-Jul-22 22-Jul-22 10


13-Jul-22 14-Jul-22 2 5 9 m2
13-1 Bolting

15-Jul-22 16-Jul-22 2 5 9 m2
13-2 Plumbness

17-Jul-22 18-Jul-22 2 8 16 m2
13-3 Welding

19-Jul-22 20-Jul-22 2 8 16 m2
13-4 Grouting

21-Jul-22 22-Jul-22 2 1 1 Ton


13-5 Purlin Installation

WBS B MEZZANNINE STEEL DECK & FLOOR CONCRETTING 1-Jul-22 5-Aug-22 36


WBS 1 STEEL DECK 1-Jul-22 5-Aug-22 36
Install Steel Deck, Stud Bolt & End Plate Zone - 1 1-Jul-22 20-Jul-22 20 53 1050 m2
1-1
Grid 13 ~ 11

Install Steel Deck, Stud Bolt & End Plate Zone - 2 11-Jul-22 22-Jul-22 12 53 625.1 m2
1-2
Grid 11 ~ 9

Install Steel Deck, Stud Bolt & End Plate Zone - 3 17-Jul-22 23-Jul-22 7 58 402.46 m2
1-3
Grid 9 ~ 7

Install Steel Deck, Stud Bolt & End Plate Zone - 4 23-Jul-22 28-Jul-22 6 56 333 m2
1-4
Grid 5 ~ 3
STG BUILDING #1
Estimate
NO. Name Start date (Plan) Finish date (Plan) Dur Prod. Unit
Volume

Install Steel Deck, Stud Bolt & End Plate Zone - 5 26-Jul-22 5-Aug-22 11 55 603.5 m2
1-5
Grid 3 ~ 1
WBS 2 CONCRETE WORKS 6-Jul-22 13-Aug-22 39
ACT 2-1 Zone - 1 (Grid 13 ~ 11) 6-Jul-22 28-Jul-22 23
6-Jul-22 25-Jul-22 20 2 21.68 Ton
2-1-1 Rebar Installation

13-Jul-22 28-Jul-22 16 14 220.28 m3


2-1-2 Concrete Pouring

2-2 Zone - 2 (Grid 11 ~ 9) 16-Jul-22 30-Jul-22 15


16-Jul-22 27-Jul-22 12 2 12.91 Ton
2-2-1 Rebar Installation

21-Jul-22 30-Jul-22 10 14 131.14 m3


2-2-2 Concrete Pouring

2-3 Zone - 3 (Grid 9 ~ 7) 22-Jul-22 31-Jul-22 10


22-Jul-22 28-Jul-22 7 2 8.31 Ton
2-3-1 Rebar Installation

25-Jul-22 31-Jul-22 7 13 84.43 m3


2-3-2 Concrete Pouring

2-4 Zone - 4 (Grid 5 ~ 3) 28-Jul-22 5-Aug-22 9


28-Jul-22 2-Aug-22 6 2 6.88 Ton
2-4-1 Rebar Installation

1-Aug-22 5-Aug-22 5 14 69.86 m3


2-4-2 Concrete Pouring

2-5 Zone - 5 Grid 3 ~ 1 31-Jul-22 13-Aug-22 14


31-Jul-22 10-Aug-22 11 2 12.46 Ton
2-5-1 Rebar Installation

4-Aug-22 13-Aug-22 10 13 126.61 m3


2-5-2 Concrete Pouring

C OPERATING STEEL DECK & FLOOR CONCRETTING 24-Jul-22 17-Sep-22 56


1 STEEL DECK 24-Jul-22 9-Sep-22 48
Install Steel Deck, Stud Bolt & End Plate Zone - 1 24-Jul-22 12-Aug-22 20 53 1050 m2
1-1
Grid 13 ~ 11

Install Steel Deck, Stud Bolt & End Plate Zone - 2 3-Aug-22 18-Aug-22 16 53 844 m2
1-2
Grid 11 ~ 9

Install Steel Deck, Stud Bolt & End Plate Zone - 3 9-Aug-22 24-Aug-22 16 53 844 m2
1-3
Grid 9 ~ 7

Install Steel Deck, Stud Bolt & End Plate Zone - 4 19-Aug-22 31-Aug-22 13 52 668.5 m2
1-4
Grid 7 ~ 5

Install Steel Deck, Stud Bolt & End Plate Zone - 5 22-Aug-22 3-Sep-22 13 52 668.5 m2
1-5
Grid 5 ~ 3

Install Steel Deck, Stud Bolt & End Plate Zone - 6 25-Aug-22 9-Sep-22 16 54 850 m2
1-6
Grid 3 ~ 1
2 CONCRETE WORKS 29-Jul-22 17-Sep-22 51
2-1 Zone - 1 (Grid 13 ~ 11) 29-Jul-22 20-Aug-22 23
29-Jul-22 17-Aug-22 20 2 21.68 Ton
2-1-1 Rebar Installation

5-Aug-22 20-Aug-22 16 14 216.77 m3


2-1-2 Concrete Pouring

2-2 Zone - 2 (Grid 11 ~ 9) 8-Aug-22 26-Aug-22 19


8-Aug-22 23-Aug-22 16 2 17.42 Ton
2-2-1 Rebar Installation

13-Aug-22 26-Aug-22 14 13 174.24 m3


2-2-2 Concrete Pouring

2-3 Zone - 3 (Grid 9 ~ 7) 14-Aug-22 1-Sep-22 19


14-Aug-22 29-Aug-22 16 2 17.42 Ton
2-3-1 Rebar Installation

17-Aug-22 1-Sep-22 16 11 174.24 m3


2-3-2 Concrete Pouring

2-4 Zone - 4 (Grid 7 ~ 5) 24-Aug-22 8-Sep-22 16


24-Aug-22 5-Sep-22 13 2 13.80 Ton
2-4-1 Rebar Installation

28-Aug-22 8-Sep-22 12 12 138.01 m3


2-4-2 Concrete Pouring

2-5 Zone - 5 Grid 5 ~ 3 27-Aug-22 11-Sep-22 16


27-Aug-22 8-Sep-22 13 2 13.80 Ton
2-5-1 Rebar Installation

31-Aug-22 11-Sep-22 12 12 138.01 m3


2-5-2 Concrete Pouring

2-6 Zone - 5 Grid 3 ~ 1 30-Aug-22 17-Sep-22 19


30-Aug-22 14-Sep-22 16 2 17.55 Ton
2-6-1 Rebar Installation
STG BUILDING #1
Estimate
NO. Name Start date (Plan) Finish date (Plan) Dur Prod. Unit
Volume
2-6-1 Rebar Installation

3-Sep-22 17-Sep-22 15 12 175.48 m3


2-6-2 Concrete Pouring

D DEAERATOR STEEL DECK & FLOOR CONCRETTING 2-Sep-22 28-Sep-22 27


1 STEEL DECK 2-Sep-22 20-Sep-22 19
Install Steel Deck, Stud Bolt & End Plate Zone - 1 2-Sep-22 7-Sep-22 6 51 304.5 m2
1-1
Grid 13 ~ 11

Install Steel Deck, Stud Bolt & End Plate Zone - 2 5-Sep-22 10-Sep-22 6 56 333.5 m2
1-2
Grid 11 ~ 9

Install Steel Deck, Stud Bolt & End Plate Zone - 3 8-Sep-22 13-Sep-22 6 54 319 m2
1-3
Grid 9 ~ 7

Install Steel Deck, Stud Bolt & End Plate Zone - 4 11-Sep-22 15-Sep-22 5 58 290 m2
1-4
Grid 7 ~ 5

Install Steel Deck, Stud Bolt & End Plate Zone - 5 14-Sep-22 18-Sep-22 5 53 261 m2
1-5
Grid 5 ~ 3

Install Steel Deck, Stud Bolt & End Plate Zone - 6 16-Sep-22 20-Sep-22 5 50 246.5 m2
1-6
Grid 3 ~ 1
2 CONCRETE WORKS 7-Sep-22 28-Sep-22 22
2-1 Zone - 1 (Grid 13 ~ 11) 7-Sep-22 15-Sep-22 9
7-Sep-22 12-Sep-22 6 2 6.11 Ton
2-1-1 Rebar Installation

10-Sep-22 15-Sep-22 6 11 61.13 m3


2-1-2 Concrete Pouring

2-2 Zone - 2 (Grid 11 ~ 9) 10-Sep-22 18-Sep-22 9


10-Sep-22 15-Sep-22 6 2 6.70 Ton
2-2-1 Rebar Installation

13-Sep-22 18-Sep-22 6 12 66.95 m3


2-2-2 Concrete Pouring

2-3 Zone - 3 (Grid 9 ~ 7) 13-Sep-22 21-Sep-22 9


STG BUILDING #1
Estimate
NO. Name Start date (Plan) Finish date (Plan) Dur Prod. Unit
Volume

13-Sep-22 18-Sep-22 6 2 6.41 Ton


2-3-1 Rebar Installation

16-Sep-22 21-Sep-22 6 11 64.04 m3


2-3-2 Concrete Pouring

2-4 Zone - 4 (Grid 7 ~ 5) 16-Sep-22 23-Sep-22 8


16-Sep-22 20-Sep-22 5 2 5.82 Ton
2-4-1 Rebar Installation

19-Sep-22 23-Sep-22 5 12 58.22 m3


2-4-2 Concrete Pouring

2-5 Zone - 5 Grid 5 ~ 3 19-Sep-22 26-Sep-22 8


19-Sep-22 23-Sep-22 5 2 5.24 Ton
2-5-1 Rebar Installation

22-Sep-22 26-Sep-22 5 11 52.40 m3


2-5-2 Concrete Pouring

2-6 Zone - 5 Grid 3 ~ 1 21-Sep-22 28-Sep-22 8


21-Sep-22 25-Sep-22 5 1 4.95 Ton
2-6-1 Rebar Installation

24-Sep-22 28-Sep-22 5 10 49.49 m3


2-6-2 Concrete Pouring

E OVERHEAD CRANE TURBINE (OHC) 1-Jul-22 30-Aug-22 61


1 Preparation Works 1-Jul-22 2-Aug-22 33
1-Jul-22 23-Jul-22 23 1 1 Ls
1-1 Partial Hand Over Civil - Mechanical

6-Jul-22 28-Jul-22 23 1 1 Ls
1-2 Scaffolding Installation

11-Jul-22 2-Aug-22 23 1 1 Ls
1-3 Center Line, Squareness & Surveying Each Coloumn (12 Coloumns)

1-Jul-22 7-Jul-22 7 1 1 Ls
1-4 Rail Mobilisation & Arragement (Lifting & On Based)

2 Rail Aignment and Welding 4-Jul-22 1-Aug-22 29


4-Jul-22 26-Jul-22 23 1 1 Ls
2-1 Alignment

7-Jul-22 29-Jul-22 23 1 1 Ls
2-2 Welding

10-Jul-22 1-Aug-22 23 1 1 Ls
2-3 PT/NDT After Welding

3 Preparation For Girder Lifting 19-Jul-22 24-Jul-22 6


19-Jul-22 20-Jul-22 2 1 1 Ls
3-1 Cleaning Lifting Area

20-Jul-22 20-Jul-22 1 1 1 Ls
3-2 Plate Arragement for Crane

21-Jul-22 22-Jul-22 2 1 1 Ls
3-3 Check & Prepare Access for Multi Axel

21-Jul-22 24-Jul-22 4 1 1 Ls
3-4 Crane Assembly

4 Girder Lifting & On Based (Sliding Method) 2-Aug-22 10-Aug-22 9


2-Aug-22 2-Aug-22 1 1 1 Ls
4-1 Girder I Lifting & On Based

3-Aug-22 3-Aug-22 1 1 1 Ls
4-2 Girder II Lifting & On Based

4-Aug-22 10-Aug-22 7 1 1 Ls
4-3 Both Girder Assembly

5 Miscellanous Works 8-Aug-22 30-Aug-22 23


8-Aug-22 19-Aug-22 12 1 1 Ls
5-1 Install Accessories ( Main Hoist, Aux, Hoist, Cabiin, etc )

8-Aug-22 13-Aug-22 6 1 1 Ls
5-2 Busbar Innstallation

14-Aug-22 19-Aug-22 6 1 1 Ls
5-3 Cable Tray Installation
STG BUILDING #1
Estimate
NO. Name Start date (Plan) Finish date (Plan) Dur Prod. Unit
Volume

20-Aug-22 25-Aug-22 6 1 1 Ls
5-4 Pulling Cable

26-Aug-22 27-Aug-22 2 1 1 Ls
5-5 Power On

28-Aug-22 29-Aug-22 2 1 1 Ls
5-6 Load test

30-Aug-22 30-Aug-22 1 1 1 Ls
5-7 Inspection by Disnaker / Certificate

F ROOFING INSTALLATION 15-Jul-22 24-Aug-22 41


1 MATERIAL DELIVERY 15-Jul-22 30-Jul-22 16
1-1 ZONE - 1 ( Row 13 ~ 8 ) 15-Jul-22 15-Jul-22 1
15-Jul-22 15-Jul-22 1 2114 2114 m2
3-1-1 Trimdek Roof

15-Jul-22 15-Jul-22 1 2114 2114 m2


3-1-2 Perforated Roof

1-2 ZONE - 2 ( Row 8 ~ 1 ) 30-Jul-22 30-Jul-22 1


30-Jul-22 30-Jul-22 1 3510 3510 m2
1-2-1 Trimdek Roof

30-Jul-22 30-Jul-22 1 3510 3510 m2


1-2-2 Perforated Roof

2 ROOFING INSTALLATION 17-Jul-22 18-Aug-22 33


2-1 ZONE - 1 ( Row 13 ~ 8 ) 17-Jul-22 28-Jul-22 12
17-Jul-22 26-Jul-22 10 212 2114.00 m2
2-1-1 Inner Layer Perporated

18-Jul-22 27-Jul-22 10 212 2114.00 m2


2-1-2 Top Span

19-Jul-22 28-Jul-22 10 212 2114.00 m2


2-1-3 Insulation ( Al-Foil & Rock Wool )

19-Jul-22 28-Jul-22 10 212 2114.00 m2


2-1-4 Outer Layer

2-2 ZONE - 2 ( Row 8 ~ 3 ) 29-Jul-22 12-Aug-22 15


29-Jul-22 10-Aug-22 13 205 2660 m2
2-2-1 Inner Layer Perporated

30-Jul-22 11-Aug-22 13 205 2660 m2


2-2-2 Top Span

31-Jul-22 12-Aug-22 13 205 2660 m2


2-2-3 Insulation ( Al-Foil & Rock Wool )

31-Jul-22 12-Aug-22 13 205 2660 m2


2-2-4 Outer Layer

2-3 ZONE - 3 Holding Area ( Row 3 ~ 1 ) 13-Aug-22 18-Aug-22 6


13-Aug-22 16-Aug-22 4 213 850 m2
2-3-1 Inner Layer Perporated

14-Aug-22 17-Aug-22 4 213 850 m2


2-3-2 Top Span

15-Aug-22 18-Aug-22 4 213 850 m2


2-3-3 Insulation ( Al-Foil & Rock Wool )

15-Aug-22 18-Aug-22 4 213 850 m2


2-3-4 Outer Layer

3 FLASHING INSTALLATION 29-Jul-22 24-Aug-22 27


3-1 ZONE - 1 ( Row 13 ~ 8 ) 29-Jul-22 1-Aug-22 4
29-Jul-22 1-Aug-22 4 14 55.00 m1
3-1-1 Flasing Installation

3-2 ZONE - 2 ( Row 8 ~ 3 ) 10-Aug-22 24-Aug-22 15


10-Aug-22 24-Aug-22 15 10 138 m1
3-2-1 Flasing Installation

3-3 ZONE - 3 Holding Area ( Row 3 ~ 1 ) 18-Aug-22 19-Aug-22 2


18-Aug-22 19-Aug-22 2 9 17 m1
3-3-1 Flasing Installation

G CLADDING INSTALLATION (Without Holding Area) 15-Sep-22 26-Jan-23 134


1 MATERIAL DELIVERY 15-Sep-22 26-Jan-23 134
1-1 ZONE - 1 ( Row 13 ~ 8 ) 15-Sep-22 15-Sep-22 1
15-Sep-22 15-Sep-22 1 3850 3850 m2
1-1-1 Trimdek Roof

15-Sep-22 15-Sep-22 1 2114 2114 m2


1-1-2 Perforated Roof

1-2 ZONE - 2 ( Row 8 ~ 1 ) 26-Oct-22 26-Oct-22 1


26-Oct-22 26-Oct-22 1 3510 3510 m2
1-2-1 Trimdek Roof

26-Oct-22 26-Oct-22 1 3510 3510 m2


1-2-2 Perforated Roof
STG BUILDING #1
Estimate
NO. Name Start date (Plan) Finish date (Plan) Dur Prod. Unit
Volume

2 CLADDING INSTALLATION (Without Holding Area) 18-Sep-22 26-Jan-23 131


2-1 ZONE - 1 ( Row 13 ~ 8 ) 18-Sep-22 28-Oct-22 41
18-Sep-22 26-Oct-22 39 99 3850.00 m2
2-1-1 Inner Layer Perporated

19-Sep-22 27-Oct-22 39 99 3850.00 m2


2-1-2 Top Span

20-Sep-22 28-Oct-22 39 99 3850.00 m2


2-1-3 Insulation ( Al-Foil & Rock Wool )

20-Sep-22 28-Oct-22 39 99 3850.00 m2


2-1-4 Outer Layer

2-2 ZONE - 2 ( Row 8 ~ 3 ) 29-Oct-22 16-Dec-22 49


29-Oct-22 14-Dec-22 47 57 2660 m2
2-2-1 Inner Layer Perporated

30-Oct-22 15-Dec-22 47 57 2660 m2


2-2-2 Top Span

31-Oct-22 16-Dec-22 47 57 2660 m2


2-2-3 Insulation ( Al-Foil & Rock Wool )

31-Oct-22 16-Dec-22 47 57 2660 m2


2-2-4 Outer Layer

2-3 NORTH SIDE 17-Dec-22 26-Jan-23 41


17-Dec-22 24-Jan-23 39 49 1908 m2
2-3-1 Inner Layer Perporated

18-Dec-22 25-Jan-23 39 49 1908 m2


2-3-2 Top Span

19-Dec-22 26-Jan-23 39 49 1908 m2


2-3-3 Insulation ( Al-Foil & Rock Wool )

19-Dec-22 26-Jan-23 39 49 1908 m2


2-3-4 Outer Layer
CW INTAKE
NO. Name Start date (Plan) Finish date (Plan) Dur Volume UOM

1 CW PUMP HOUSE
CW INTAKE
NO. Name Start date (Plan) Finish date (Plan) Dur Volume UOM

WBS 1-4 CW PUMP ZONE 13 A 28-Mar-22 24-Sep-22 181


Acti 1.4.1 Lean Concrete 18-Jul-22 20-Jul-22 2 1
Acti 1.4.2 Slab 28-Mar-22 29-Jul-22 123 1
Acti 1.4.3 Wall Stage 1 (TOC EL-6.70) 17-May-22 12-Aug-22 87 1
Acti 1.4.4 Wall Stage 2 (TOC EL-2.20) 17-Jun-22 2-Sep-22 77 1
Acti 1.4.5 Wall Stage 3 (TOC EL+2.20) 11-Jul-22 24-Sep-22 75 1
WBS 1-5 CW PUMP ZONE 13 B 28-Mar-22 1-Oct-22 188
Acti 1.5.1 Lean Concrete 25-Jul-22 27-Jul-22 2 1
Acti 1.5.2 Slab 28-Mar-22 5-Aug-22 130 1
Acti 1.5.3 Wall Stage 1 (TOC EL-6.70) 17-May-22 19-Aug-22 94 1
Acti 1.5.4 Wall Stage 2 (TOC EL-2.20) 17-Jun-22 9-Sep-22 84 1
Acti 1.5.5 Wall Stage 3 (TOC EL+2.20) 11-Jul-22 1-Oct-22 82 1
WBS 1-6 CW PUMP ZONE 17 A 8-May-22 10-Jan-23 248
Acti 1.6.1 Lean Concrete 10-Aug-22 12-Aug-22 2 1
Acti 1.6.2 Slab 8-May-22 5-Sep-22 120 1
Acti 1.6.3 Wall Stage 1 (TOC EL-11.00) 13-Aug-22 10-Oct-22 58 1
Acti 1.6.4 Wall Stage 2 (TOC EL-6.50) 10-Sep-22 9-Nov-22 60 1
CW INTAKE
NO. Name Start date (Plan) Finish date (Plan) Dur Volume UOM

Acti 1.6.5 Wall Stage 3 (TOC EL-2.00) 5-Oct-22 5-Dec-22 61 1


Acti 1.6.6 Wall Stage 4 (TOC EL+2.00) 30-Oct-22 10-Jan-23 72 1
Acti 1.6.7 Top Slab Sec 1 24-Nov-22 30-Dec-22 36 1
WBS 1-7 CW PUMP ZONE 17 B 23-Jul-22 13-Jan-23 175
Acti 1.7.1 Lean Concrete 17-Aug-22 19-Aug-22 2 1
Acti 1.7.2 Slab 23-Jul-22 6-Sep-22 45 1
Acti 1.7.3 Wall Stage 1 (TOC EL-11.00) 20-Aug-22 7-Oct-22 48 1
Acti 1.7.4 Wall Stage 2 (TOC EL-6.50) 12-Sep-22 11-Nov-22 60 1
Acti 1.7.5 Wall Stage 3 (TOC EL-2.00) 6-Oct-22 7-Dec-22 62 1
Acti 1.7.6 Wall Stage 4 (TOC EL+2.00) 1-Nov-22 13-Jan-23 73 1
Acti 1.7.7 Top Slab Sec 2 27-Nov-22 6-Jan-23 40 1
WBS 1-8 AUXILARY COOLING WATER PUMP (ACW) 28-Nov-22 6-Mar-23 99
Acti 1.8.1 Lean Concrete 18-Dec-22 20-Dec-22 2 1
Acti 1.8.2 Bottom Slab 28-Nov-22 5-Jan-23 38 1
Acti 1.8.3 Wall Stage 1 (TOC EL±0.00) 21-Dec-22 27-Jan-23 37 1
Acti 1.8.4 Wall Stage 2 (TOC EL+2.00) 9-Jan-23 15-Feb-23 37 1
Acti 1.8.5 Top Slab ACW 1-Feb-23 6-Mar-23 33 1
WBS 1-9 VALVE PIT 9-Sep-22 10-Nov-22 63
Acti 1.9.1 Lean Concrete 21-Sep-22 23-Sep-22 2 1
Acti 1.9.2 Bottom Slab 9-Sep-22 7-Oct-22 28 1
CW INTAKE
NO. Name Start date (Plan) Finish date (Plan) Dur Volume UOM

Acti 1.9.3 Wall Valve Pit 24-Sep-22 10-Nov-22 47 1


WBS 1-10 REMAINING OUTER PERIMETER WALL (TOC EL +5.3) 17-Dec-22 24-Mar-23 98 1
WBS 1-11 CW PUMP HOUSE ELECTRICAL BUILDING ROOM 4-Jul-22 28-Nov-22 148
Acti 1.11.1 Bored Pile Work 4-Jul-22 11-Jul-22 7 1
Acti 1.11.2 Foundation Work Grid A-B-C 5-Sep-22 11-Sep-22 6 1
Acti 1.11.3 Foundation Work Grid D-E-F 6-Sep-22 12-Sep-22 6 1
Acti 1.11.4 Pedestal Work Grid A-B-C 14-Sep-22 20-Sep-22 6 1
CW INTAKE
NO. Name Start date (Plan) Finish date (Plan) Dur Volume UOM

Acti 1.11.5 Pedestal Work Grid D-E-F 15-Sep-22 20-Sep-22 5 1


Acti 1.11.6 Plinth Beam Work Grid A-B-C 21-Sep-22 28-Sep-22 7 1
Acti 1.11.7 Plinth Beam Work Grid D-E-F 22-Sep-22 28-Sep-22 6 1
Acti 1.11.8 Cable Trench A-B-C 28-Sep-22 6-Oct-22 8 1
Acti 1.11.9 Cable Trench D-E-F 1-Oct-22 11-Oct-22 10 1
Acti 1.11.10 Column Work Line 3 1-Oct-22 8-Oct-22 7 1
Acti 1.11.11 Column Work Line 1-2 (A-C) 1-Oct-22 8-Oct-22 7 1
Acti 1.11.12 Plinth Beam Work (Line C, Line 1, Line F) 16-Oct-22 23-Oct-22 7 1
Acti 1.11.13 Column Work Line 1-2 (D-E-F) 17-Oct-22 23-Oct-22 6 1
Acti 1.11.14 Bottom Slab (A-C) 24-Oct-22 31-Oct-22 7 1
Acti 1.\11.15 Bottom Slab (D-E-F) 26-Oct-22 5-Nov-22 10 1
Acti 1.11.16 Roof Beam (A-C) 3-Nov-22 12-Nov-22 9 1
Acti 1.11.17 Roof Beam (D-E-F) 8-Nov-22 17-Nov-22 9 1
CW INTAKE
NO. Name Start date (Plan) Finish date (Plan) Dur Volume UOM

Acti 1.11.18 Top Slab 5-Nov-22 23-Nov-22 18 1


Acti 1.11.19 Parafet Wall 19-Nov-22 28-Nov-22 9 1
Acti 1.11.20 Architecture Work & Electrical 26-Nov-22 27-Dec-22 31 1
WBS 2 WING WALL
WBS 2-1 Right Side 1-Oct-22 26-Dec-22 86
Acti 2.1.1 Section 1 1-Oct-22 28-Nov-22 58 1
Acti 2.1.2 Section 2 15-Oct-22 6-Dec-22 52 1
Acti 2.1.3 Section 3 29-Oct-22 16-Dec-22 48 1
Acti 2.1.4 Section 4 12-Nov-22 26-Dec-22 44 1
WBS 2-2 Left Side 12-Nov-22 2-Feb-23 82
Acti 2.2.1 Section 1 12-Nov-22 9-Jan-23 58 1
Acti 2.2.2 Section 2 26-Nov-22 17-Jan-23 52 1
Acti 2.2.3 Section 3 10-Dec-22 27-Jan-23 48 1
Acti 2.2.4 Section 4 24-Dec-22 2-Feb-23 40 1
WBS 3 CW FOREBAY 1-Oct-22 10-Feb-23 1
CW INTAKE
NO. Name Start date (Plan) Finish date (Plan) Dur Volume UOM

WBS 4 DREDGING WORK 22-Nov-22 15-Jul-23 1


WBS 5 STEEL STRUCTURE, MECH, ELECTRICAL & COMM WORK 28-Nov-22 6-Mar-23 99
Acti 5-1 Steel Structure 14-Jan-23 14-Mar-23 59 1
Acti 5-2 Mechanical Work 14-Jan-23 29-Apr-23 105 1
CW INTAKE
NO. Name Start date (Plan) Finish date (Plan) Dur Volume UOM

Acti 5-3 Electrical Work 14-Jan-23 13-May-23 119 1


Acti 5-4 Commissioning 16-Apr-23 21-May-23 35 1
STACKER & RECLAIMER
NO. Name Start date (Plan) Finish date (Plan) Dur Prod. Volume Unit

1 STACKER & RECLAIMER


2-1 Bore Pile Works 30-May-22 8-Aug-22 71 816
11-Jun-22 30-Jun-22 20 6 116 Nos
1 Bore Pile Works - Zone 1
30-May-22 5-Jul-22 37 5 171 Nos
1 Bore Pile Works - Zone 2
1-Jul-22 24-Jul-22 24 8 187 Nos
1 Bore Pile Works - Zone 3
6-Jul-22 8-Aug-22 34 5 167 Nos
1 Bore Pile Works - Zone 4
25-Jul-22 6-Aug-22 13 8 93 Nos
1 Bore Pile Works - Zone 5
20-Jun-22 31-Jul-22 42 2 82 Nos
1 Bore Pile Works - Zone 6
2-2 Foundation Works 29-Jun-22 2-Oct-22 96
2-2.1 Foundation Works - Zone 1 9-Jul-22 23-Aug-22 46
9-Jul-22 29-Jul-22 21 207 4338.92 M3
1 Excavation
14-Jul-22 3-Aug-22 21 6 116.00 Nos
2 Cutting Pile
19-Jul-22 8-Aug-22 21 3 60.89 M3
3 Lean Concrete
24-Jul-22 13-Aug-22 21 14 279.60 Ton
4 Rebar Installation
29-Jul-22 18-Aug-22 21 70 1452.45 M2
5 Formwork Installation
3-Aug-22 23-Aug-22 21 107 2236.77 M3
6 Concrete Pouring
2-2.2 Foundation Works - Zone 2 29-Jun-22 23-Aug-22 56
29-Jun-22 29-Jul-22 31 207 6396.17 M3
1 Excavation
4-Jul-22 3-Aug-22 31 6 171 Nos
2 Cutting Pile
9-Jul-22 8-Aug-22 31 3 89.75 M3
3 Lean Concrete
14-Jul-22 13-Aug-22 31 14 412.16 Ton
4 Rebar Installation
19-Jul-22 18-Aug-22 31 70 2141.11 M2
5 Formwork Installation
24-Jul-22 23-Aug-22 31 107 3297.31 M3
6 Concrete Pouring
2-2.3 Foundation Works - Zone 3 29-Jul-22 24-Sep-22 58
29-Jul-22 30-Aug-22 33 212 6994.65 M3
1 Excavation
3-Aug-22 4-Sep-22 33 6 187 Nos
2 Cutting Pile
8-Aug-22 9-Sep-22 33 3 98.15 M3
3 Lean Concrete
13-Aug-22 14-Sep-22 33 14 450.73 Ton
4 Rebar Installation
18-Aug-22 19-Sep-22 33 71 2341.45 M2
5 Formwork Installation
23-Aug-22 24-Sep-22 33 110 3605.83 M3
6 Concrete Pouring
2-2.4 Foundation Works - Zone 4 3-Aug-22 26-Sep-22 55
3-Aug-22 1-Sep-22 30 209 6246.56 M3
1 Excavation
8-Aug-22 6-Sep-22 30 6 167 Nos
2 Cutting Pile
STACKER & RECLAIMER
NO. Name Start date (Plan) Finish date (Plan) Dur Prod. Volume Unit

13-Aug-22 11-Sep-22 30 3 87.66 M3


3 Lean Concrete
18-Aug-22 16-Sep-22 30 14 402.52 Ton
4 Rebar Installation
23-Aug-22 21-Sep-22 30 70 2091.02 M2
5 Formwork Installation
28-Aug-22 26-Sep-22 30 108 3220.18 M3
6 Concrete Pouring
2-2.5 Foundation Works - Zone 5 22-Aug-22 2-Oct-22 42
22-Aug-22 7-Sep-22 17 205 3478.62 M3
1 Excavation
27-Aug-22 12-Sep-22 17 6 93 Nos
2 Cutting Pile
1-Sep-22 17-Sep-22 17 3 48.81 M3
3 Lean Concrete
6-Sep-22 22-Sep-22 17 14 224.16 Ton
4 Rebar Installation
11-Sep-22 27-Sep-22 17 69 1164.46 M2
5 Formwork Installation
16-Sep-22 2-Oct-22 17 106 1793.27 M3
6 Concrete Pouring
2-2.6 Foundation Works - Zone 6 18-Jul-22 26-Aug-22 40
18-Jul-22 1-Aug-22 15 205 3067.17 M3
1 Excavation
23-Jul-22 6-Aug-22 15 6 82 Nos
2 Cutting Pile
28-Jul-22 11-Aug-22 15 3 43.04 M3
3 Lean Concrete
2-Aug-22 16-Aug-22 15 14 197.65 Ton
4 Rebar Installation
7-Aug-22 21-Aug-22 15 69 1026.73 M2
5 Formwork Installation
12-Aug-22 26-Aug-22 15 106 1581.16 M3
6 Concrete Pouring
COAL SHED
Plan/ Productivit Numb of Prod
NO. Name Start date (Plan) Finish date (Plan) Dur Volume Remainin UOM
Actual y Plan (/ Eqp Total
g Volume
Eqp)
1 COAL SHED
1-1 Piling Works 30-May-22 11-Jun-22 12
Plan 30-May-22 11-Jun-22 1.94 2 2.92 12 35.00 Ls
1 Zone - 1 (Remaining Volume)
Actual - 35.00
Plan 30-May-22 5-Jun-22 1.83 1 1.83 6 11.00 Ls
2 Zone - 3 (Remaining Volume)
Actual - 11.00
1-2 FDN Work 17-Jun-22 2-Dec-22 168
A Zone - 1 1-Jun-22 2-Nov-22 154
(Line A Grid 1~ 38)_Pile Cap 1-Jun-22 27-Aug-22 87
Plan 1-Jun-22 30-Jun-22
1 Millestone Piling Work Stacker Zone - 1
Actual
Plan 17-Jun-22 16-Jul-22 214.00 1.00 214.00 30 6,419.32 m3
2 Excavation
Actual - 6,419.32
Plan 24-Jun-22 23-Jul-22 2.00 1.00 2.00 30 55.46 m3
3 Lean Concrete
Actual - 55.46
Plan 1-Jul-22 30-Jul-22 3.00 1.00 3.00 30 76.00 Nos
4 Cuting Pile
Actual - 76.00
Plan 8-Jul-22 6-Aug-22 7.00 1.00 7.00 30 189.84 Ton
5 Rebar Installation
Actual - 189.84
Plan 15-Jul-22 13-Aug-22 70.00 1.00 70.00 30 2,079.50 m2
6 Formwork Installation
Actual - 2,079.50
Plan 22-Jul-22 20-Aug-22 86.00 1.00 86.00 30 2,561.40 m3
7 Concrete Pouring
Actual - 2,561.40
Plan 29-Jul-22 27-Aug-22 84.00 1.00 84.00 30 2,496.60 m3
8 Soil Backfill
Actual - 2,496.60
(Line A Grid 1~ 38)_Tie Beam 3-Aug-22 2-Nov-22 91
Plan 3-Aug-22 1-Sep-22 214.00 1.00 214.00 30 6,419.32 m3
1 Excavation
Actual - 6,419.32
Plan 8-Aug-22 8-Sep-22 2.00 1.00 2.00 32 42.01 m3
1 Lean Concrete
Actual - 42.01
Plan 13-Aug-22 15-Sep-22 4.00 1.00 4.00 34 119.83 Ton
2 Rebar Installation
Actual - 119.83
Plan 18-Aug-22 22-Sep-22 30.00 1.00 30.00 36 1,052.14 m2
3 Formwork Installation
Actual - 1,052.14
Plan 23-Aug-22 3-Oct-22 5.00 1.00 5.00 42 184.98 m3
4 Concrete Pouring
Actual - 184.98
Plan 28-Aug-22 17-Oct-22 40.00 1.00 40.00 51 2,025.50 m2
5 Formwork Removal
Actual - 2,025.50
Plan 2-Sep-22 2-Nov-22 41.00 1.00 41.00 62 2,496.60 m3
6 Soil Backfill
Actual - 2,496.60
B Zone - 2 1-Jul-22 2-Dec-22 154
(Line B Grid 1~ 38)_Pile Cap 1-Jul-22 26-Sep-22 87
Plan 1-Jul-22 30-Jun-22
1 Millestone Piling Work Stacker Zone - 1
Actual
Plan 17-Jul-22 15-Aug-22 194.00 1.00 194.00 30 5,817.57 m3
2 Excavation
Actual - 5,817.57
Plan 24-Jul-22 22-Aug-22 2.00 1.00 2.00 30 55.46 m3
3 Lean Concrete
Actual - 55.46
Plan 31-Jul-22 29-Aug-22 3.00 1.00 3.00 30 76.00 Nos
4 Cuting Pile
Actual - 76.00
Plan 7-Aug-22 5-Sep-22 7.00 1.00 7.00 30 189.84 Ton
5 Rebar Installation
Actual - 189.84
Plan 14-Aug-22 12-Sep-22 70.00 1.00 70.00 30 2,079.50 m2
6 Formwork Installation
Actual - 2,079.50
Plan 19-Aug-22 19-Sep-22 81.00 1.00 81.00 32 2,561.40 m3
7 Concrete Pouring
Actual - 2,561.40
Plan 26-Aug-22 26-Sep-22 79.00 1.00 79.00 32 2,496.60 m3
8 Soil Backfill
Actual - 2,496.60
(Line B Grid 1~ 38)_Tie Beam 2-Sep-22 2-Dec-22 91
Plan 2-Sep-22 1-Oct-22 194.00 1.00 194.00 30 5,817.57 m3
1 Excavation
Actual - 5,817.57
Plan 7-Sep-22 8-Oct-22 2.00 1.00 2.00 32 42.01 m3
1 Lean Concrete
Actual - 42.01
Plan 12-Sep-22 15-Oct-22 4.00 1.00 4.00 34 119.83 Ton
2 Rebar Installation
Actual - 119.83
Plan 17-Sep-22 22-Oct-22 30.00 1.00 30.00 36 1,052.14 m2
3 Formwork Installation
Actual - 1,052.14
COAL SHED
Plan/ Productivit Numb of Prod
NO. Name Start date (Plan) Finish date (Plan) Dur Volume Remainin UOM
Actual y Plan (/ Eqp Total
g Volume
Eqp)
Plan 22-Sep-22 2-Nov-22 11.00 1.00 11.00 42 445.70 m3
4 Concrete Pouring
Actual - 445.70
Plan 27-Sep-22 16-Nov-22 9.00 1.00 9.00 51 445.70 m2
5 Formwork Removal
Actual - 445.70
Plan 2-Oct-22 2-Dec-22 80.00 1.00 80.00 62 4,925.36 m3
6 Soil Backfill
Actual - 4,925.36
A Zone - 3 20-Jun-22 23-Nov-22 156
(Line C Grid 1~ 28)_Pile Cap 20-Jun-22 15-Sep-22 87
Plan 20-Jun-22 30-Jul-22
1 Millestone Piling Work Stacker Zone - 1
Actual
Plan 6-Jul-22 4-Aug-22 154.00 1.00 154.00 30 4,611.25 m3
2 Excavation
Actual - 4,611.25
Plan 13-Jul-22 11-Aug-22 2.00 1.00 2.00 30 39.37 m3
3 Lean Concrete
Actual - 39.37
Plan 20-Jul-22 18-Aug-22 2.00 1.00 2.00 30 56.00 Nos
4 Cuting Pile
Actual - 56.00
Plan 27-Jul-22 25-Aug-22 5.00 1.00 5.00 30 136.14 Ton
5 Rebar Installation
Actual - 136.14
Plan 3-Aug-22 1-Sep-22 51.00 1.00 51.00 30 1,512.00 m2
6 Formwork Installation
Actual - 1,512.00
Plan 10-Aug-22 8-Sep-22 61.00 1.00 61.00 30 1,814.40 m3
7 Concrete Pouring
Actual - 1,814.40
Plan 17-Aug-22 15-Sep-22 84.00 1.00 84.00 30 2,496.60 m3
8 Soil Backfill
Actual - 2,496.60
(Line C Grid 1~ 28)_Tie Beam 24-Aug-22 23-Nov-22 91
Plan 24-Aug-22 22-Sep-22 194.00 1.00 194.00 30 5,817.57 m3
1 Excavation
Actual - 5,817.57
Plan 29-Aug-22 29-Sep-22 1.00 1.00 1.00 32 30.97 m3
1 Lean Concrete
Actual - 30.97
Plan 3-Sep-22 6-Oct-22 3.00 1.00 3.00 34 88.35 Ton
2 Rebar Installation
Actual - 88.35
Plan 8-Sep-22 13-Oct-22 22.00 1.00 22.00 36 775.72 m2
3 Formwork Installation
Actual - 775.72
Plan 13-Sep-22 24-Oct-22 8.00 1.00 8.00 42 328.60 m3
4 Concrete Pouring
Actual - 328.60
Plan 18-Sep-22 7-Nov-22 16.00 1.00 16.00 51 775.72 m2
5 Formwork Removal
Actual - 775.72
Plan 23-Sep-22 23-Nov-22 52.00 1.00 52.00 62 3,215.29 m3
6 Soil Backfill
Actual - 3,215.29
1-3 Precast Post Tension Works 9-Sep-22 22-Mar-23 194
Preparation 1-Jun-22 29-Aug-22 90
Plan 1-Jun-22 29-Aug-22 90
1 Formwork Fabrication
Actual
Precast Production 15-Jun-22 19-Sep-22 97
Plan 1-Jun-22 30-Jun-22
1 Rebar Installation
Actual
Plan 15-Jun-22 12-Sep-22 4.00 1.00 4.00 90 312.00 Nos
2 Concrete Pouring
Actual - 312.00
Plan 15-Jul-22 19-Sep-22 5.00 1.00 5.00 67 312.00 Ls
3 Dellivery
Actual - 312.00
Precast Coloumn Installation 9-Sep-22 15-Mar-23 187
Plan 9-Sep-22 13-Feb-23 1.00 1.00 1.00 158 38.00 38.00 Nos
1 Precast Installation - Zone (1)
Actual
Plan 9-Oct-22 15-Mar-23 1.00 1.00 1.00 158 38.00 38.00 Nos
2 Precast Installation - Zone (3)
Actual -
Plan 30-Sep-22 24-Jan-23 1.00 1.00 1.00 117 28.00 28.00 Nos
3 Precast Installation - Zone (4)
Actual -
Precast Beam Installation 9-Oct-22 22-Mar-23 164
Plan 9-Oct-22 20-Feb-23 1.00 1.00 1.00 135 36.00 72.00 Nos
1 Precast Installation - Zone (1)
Actual 48.00
Plan 8-Nov-22 22-Mar-23 1.00 1.00 1.00 135 36.00 72.00 Nos
2 Precast Installation - Zone (3)
Actual 48.00
Plan 30-Oct-22 31-Jan-23 1.00 1.00 1.00 94 27.00 54.00 Nos
3 Precast Installation - Zone (4)
Actual 36.00
1-3 Steel Structure 27-Nov-22 2-Jun-23 187
Steel Structure 27-Nov-22 2-Jun-23 187
COAL SHED
Plan/ Productivit Numb of Prod
NO. Name Start date (Plan) Finish date (Plan) Dur Volume Remainin UOM
Actual y Plan (/ Eqp Total
g Volume
Eqp)
Plan 27-Nov-22 27-Jan-23 20.00 1.00 20.00 62 1,188.00 Ton
1 Steel main frame erection Actual - 1,188.00
Plan 11-Dec-22 10-Feb-23 8.00 1.00 8.00 62 448.00 Ton
2 Steel sub frame erection Actual - 448.00
COAL SHED
Plan/ Productivit Numb of Prod
NO. Name Start date (Plan) Finish date (Plan) Dur Volume Remainin UOM
Actual y Plan (/ Eqp Total
g Volume
Eqp)
Plan 25-Dec-22 24-Feb-23 29.00 1.00 29.00 62 1,770.00 m2
3 Installing roof girders & wall cladding Actual - 1,770.00
Plan 8-Jan-23 10-Mar-23 1.00 1.00 1.00 62 1.00 Ls
4 Pre-Alignment of Steel Structure Actual - 1.00
Plan 22-Jan-23 24-Mar-23 1.00 1.00 1.00 62 1.00 Ls
5 Bolt Tihghtening Actual - 1.00
Plan 5-Feb-23 7-Apr-23 1.00 1.00 1.00 62 1.00 Ls
6 Final Alignment of Steel Structure Actual - 1.00
Plan 19-Feb-23 21-Apr-23 4.00 1.00 4.00 62 208.00 Nos
7 Final Grouting Actual - 208.00
Plan 5-Mar-23 5-May-23 1,148.00 1.00 1,148.00 62 71,176.00 m2
8 Install roofing sheet Actual - 71,176.00
Plan 19-Mar-23 19-May-23 359.00 1.00 359.00 62 22,234.00 m2
9 Install galvalum wall Actual - 22,234.00
Plan 2-Apr-23 2-Jun-23 1.00 1.00 1.00 62 1.00 Ls
10 Touch Up Aplication Actual - 1.00
BOTTOM ASH
Start date Finish date Start date Finish date
NO. Name Dur NO. Name Dur
(Plan) (Plan) (Plan) (Plan)

1 BOTTOM ASH SILO #1 11-Jun-22 22-Feb-23 256 1 BOTTOM ASH SILO #2 7-Sep-22 28-Mar-23 202
1-1 Pile Work 11-Jun-22 30-Jul-22 49 1-1 Pile Work 7-Sep-22 26-Oct-22 49
11-Jun-22 15-Jun-22 5 7-Sep-22 11-Sep-22 5
1 Preparation 1 Preparation

16-Jun-22 30-Jul-22 45 12-Sep-22 26-Oct-22 45


2 Bore Pile Work (87 Nos) 2 Bore Pile Work (87 Nos)

1-2 Foundation Work 15-Aug-22 22-Oct-22 68 1-2 Foundation Work 3-Nov-22 8-Dec-22 35
1-2-1 Footing 15-Aug-22 22-Oct-22 68 1-2-1 Footing 3-Nov-22 8-Dec-22 35
15-Aug-22 24-Aug-22 10 3-Nov-22 12-Nov-22 10
1 Excavation 1 Excavation

25-Aug-22 13-Sep-22 20 13-Nov-22 22-Nov-22 10


2 Pile Cuting 2 Pile Cuting

14-Sep-22 14-Sep-22 1 23-Nov-22 23-Nov-22 1


3 Lean Concrete 3 Lean Concrete

16-Sep-22 5-Oct-22 20 25-Nov-22 4-Dec-22 10


4 Rebar Footing Installation 4 Rebar Footing Installation

6-Oct-22 20-Oct-22 15 30-Nov-22 6-Dec-22 7


5 Formwork Footing Installation 5 Formwork Footing Installation

21-Oct-22 21-Oct-22 1 7-Dec-22 7-Dec-22 1


6 Inspection 6 Inspection

21-Oct-22 22-Oct-22 2 7-Dec-22 8-Dec-22 2


7 Concrete Pouring Footing 7 Concrete Pouring Footing

1-2-2 Pedestal 26-Oct-22 30-Nov-22 35 1-2-2 Pedestal 12-Dec-22 11-Jan-23 30


1-2-2.1 Pedestal P04a & P02a_SECTION - 1 (4 Nos) 26-Oct-22 20-Nov-22 25 1-2-2.1 Pedestal P04a & P02a_SECTION - 1 (4 Nos) 12-Dec-22 1-Jan-23 20
26-Oct-22 1-Nov-22 7 12-Dec-22 18-Dec-22 7
1 Rebar Installation 1 Rebar Installation

2-Nov-22 8-Nov-22 7 17-Dec-22 23-Dec-22 7


2 Anchor Bolt Installation By. DHII (16 Nos) 2 Anchor Bolt Installation By. DHII (16 Nos)

9-Nov-22 15-Nov-22 7 21-Dec-22 27-Dec-22 7


3 Formwork Installation 3 Formwork Installation

16-Nov-22 16-Nov-22 1 28-Dec-22 28-Dec-22 1


4 Inspection 4 Inspection

17-Nov-22 17-Nov-22 1 29-Dec-22 29-Dec-22 1


5 Concrete Pouring Pedestal 5 Concrete Pouring Pedestal

20-Nov-22 20-Nov-22 1 1-Jan-23 1-Jan-23 1


6 Formwork Demolish 6 Formwork Demolish

1-2-2.2 Pedestal P04a & P02a_SECTION - 1 (4 Nos) 2-Nov-22 30-Nov-22 28 1-2-2.2 Pedestal P04a & P02a_SECTION - 1 (4 Nos) 19-Dec-22 11-Jan-23 23
2-Nov-22 8-Nov-22 7 19-Dec-22 25-Dec-22 7
1 Rebar Installation 1 Rebar Installation

9-Nov-22 13-Nov-22 5 26-Dec-22 30-Dec-22 5


2 Anchor Bolt Installation By. DHII (16 Nos) 2 Anchor Bolt Installation By. DHII (16 Nos)

21-Nov-22 25-Nov-22 5 2-Jan-23 6-Jan-23 5


3 Formwork Installation 3 Formwork Installation

26-Nov-22 26-Nov-22 1 7-Jan-23 7-Jan-23 1


4 Inspection 4 Inspection

27-Nov-22 27-Nov-22 1 8-Jan-23 8-Jan-23 1


5 Concrete Pouring Pedestal 5 Concrete Pouring Pedestal

30-Nov-22 30-Nov-22 1 11-Jan-23 11-Jan-23 1


6 Formwork Demolish 6 Formwork Demolish

1-2-3 Bottom Slab & Drainage 4-Dec-22 22-Feb-23 80 1-2-3 Bottom Slab & Drainage 15-Jan-23 28-Mar-23 72
1-2-3.1 Bottom Slab 4-Dec-22 6-Jan-23 33 1-2-3.1 Bottom Slab 15-Jan-23 10-Feb-23 26
4-Dec-22 10-Dec-22 7 15-Jan-23 21-Jan-23 7
1 Soil Backfill & Compacted 1 Soil Backfill & Compacted

10-Dec-22 11-Dec-22 2 21-Jan-23 22-Jan-23 2


2 Lean Concrete 2 Lean Concrete

13-Dec-22 26-Dec-22 14 24-Jan-23 6-Feb-23 14


3 Rebar Slab Installation 3 Rebar Slab Installation

27-Dec-22 5-Jan-23 10 31-Jan-23 9-Feb-23 10


4 Formwork Slab Installation 4 Formwork Slab Installation

6-Jan-23 6-Jan-23 1 10-Feb-23 10-Feb-23 1


5 Inspection 5 Inspection

6-Jan-23 6-Jan-23 1 10-Feb-23 10-Feb-23 1


6 Concrete Pouirng 6 Concrete Pouirng

1-2-3.2 Bottom Slab - Drainage 10-Jan-23 28-Jan-23 18 1-2-3.2 Bottom Slab - Drainage 14-Feb-23 4-Mar-23 18
10-Jan-23 14-Jan-23 5 14-Feb-23 18-Feb-23 5
1 Excavation 1 Excavation

15-Jan-23 16-Jan-23 2 19-Feb-23 20-Feb-23 2


2 Lean Concrete 2 Lean Concrete

16-Jan-23 22-Jan-23 7 20-Feb-23 26-Feb-23 7


3 Rebar Slab Installation 3 Rebar Slab Installation

23-Jan-23 27-Jan-23 5 27-Feb-23 3-Mar-23 5


4 Formwork Slab Installation 4 Formwork Slab Installation
BOTTOM ASH
Start date Finish date Start date Finish date
NO. Name Dur NO. Name Dur
(Plan) (Plan) (Plan) (Plan)

28-Jan-23 28-Jan-23 1 4-Mar-23 4-Mar-23 1


5 Inspection 5 Inspection

28-Jan-23 28-Jan-23 1 4-Mar-23 4-Mar-23 1


6 Concrete Pouirng 6 Concrete Pouirng

1-2-3.3 Wall - Drainage 1-Feb-23 22-Feb-23 21 1-2-3.3 Wall - Drainage 8-Mar-23 28-Mar-23 20
1-Feb-23 10-Feb-23 10 8-Mar-23 17-Mar-23 10
1 Rebar Wall Installation 1 Rebar Wall Installation

11-Feb-23 20-Feb-23 10 17-Mar-23 26-Mar-23 10


2 Formwork Wall Installation 2 Formwork Wall Installation

21-Feb-23 21-Feb-23 1 27-Mar-23 27-Mar-23 1


3 Inspection 3 Inspection

22-Feb-23 22-Feb-23 1 28-Mar-23 28-Mar-23 1


4 Concrete Pouirng 4 Concrete Pouirng