Professional Documents
Culture Documents
통합 문서1 - Schedule
통합 문서1 - Schedule
a. 2 1-Jul-22 2-Jul-22 1 Ls
Platform Mobilization
b. 85 11-Jul-22 3-Oct-22 250 SETS
Temporary Beam Support Mobilization
JETTY
Activity Dur. Start End Vol. Unit
c. 81 15-Jul-22 3-Oct-22 240 NOS
Precast Mobilization
c. Plan 115 20-Jul-22 11-Nov-22 327 NOS
Beam Mobilization
Actual 1
d. Plan 137 4-Aug-22 18-Dec-22 165 NOS
Half Slab Mobilization
Actual 1
2.1.1.5 Construction 180 6-Jul-22 1-Jan-23
a. 2 14-Dec-22 15-Dec-22 1 Ls
Platform Mobilization
b. 12 24-Dec-22 4-Jan-23 33 SETS
Temporary Beam Support Mobilization
c. 12 28-Dec-22 8-Jan-23 33 NOS
Precast Mobilization
c. Plan 17 2-Jan-23 17-Jan-23 32 NOS
Beam Mobilization
Actual 1
d. Plan 32 17-Jan-23 17-Feb-23 24 NOS
Half Slab Mobilization
Actual 1
2.1.1.5 Construction 75 19-Dec-22 3-Mar-23
JETTY
Activity Dur. Start End Vol. Unit
a. Plan 29 19-Dec-22 16-Jan-23
Pile Head
Actual 1
Plan 12 19-Dec-22 30-Dec-22 33 SETS
- Install Platform
Actual 1
Plan 12 29-Dec-22 9-Jan-23 33 SETS
- Install Temporary Beam Support
Actual 1
Plan 12 2-Jan-23 13-Jan-23 33 NOS
- Headstock Placement
Actual 1
Plan 12 5-Jan-23 16-Jan-23 33 SETS
- Installasi Tulangan Infill Concrete
Actual 1
b. Plan 37 7-Jan-23 12-Feb-23
Precast Beam install
Actual 1
Plan 12 7-Jan-23 18-Jan-23 32 NOS
- Beam Placement
Actual 1
Plan 29 9-Jan-23 6-Feb-23 33 SETS
- Install Rebar Connection Joint
Actual 1
Plan 29 12-Jan-23 9-Feb-23 33 SETS
- Install Formwork
Actual 1
Plan 29 15-Jan-23 12-Feb-23 33 SETS
- Concreting (Until Top of Precast)
Actual 1
c. 41 22-Jan-23 3-Mar-23 24 NOS
Precast Half Slab Install
2.2 OFFSHORE (GRID 41 - 65) - (PRECAST 2 BARGE) Plan 248 5-May-22 7-Jan-23
Actual
2.2.1 Offshore Area (start from AS 41 to AS 65 ) 248 5-May-22 7-Jan-23
a. 2 6-Aug-22 7-Aug-22 1 Ls
Platform Mobilization
b. 64 10-Aug-22 12-Oct-22 188 SETS
Temporary Beam Support Mobilization
c. 50 14-Aug-22 2-Oct-22 145 NOS
Precast Mobilization
c. Plan 91 19-Aug-22 17-Nov-22 255 NOS
Beam Mobilization
Actual 1
d. Plan 78 19-Oct-22 4-Jan-23 145 NOS
Half Slab Mobilization
Actual 1
2.2.1.5 Construction 150 11-Aug-22 7-Jan-23
a. 2 27-Jul-22 28-Jul-22 1 Ls
Platform Mobilization
b. 6 6-Aug-22 11-Aug-22 14 SETS
Temporary Beam Support Mobilization
c. 6 10-Aug-22 15-Aug-22 14 NOS
Precast Mobilization
c. Plan 12 15-Aug-22 25-Aug-22 17 NOS
Beam Mobilization
Actual 1
d. Plan 34 30-Aug-22 2-Oct-22 14 NOS
Half Slab Mobilization
Actual 1
2.3.1.5 Construction 47 1-Aug-22 16-Sep-22
3 CON'C WORK _ UNLOADING DECK STRUCTURE FOR Plan 209 11-Aug-22 7-Mar-23
Actual
3.1 OFFSHORE (GRID 1 - 40) - (INSITU TEAM 1) Plan 181 11-Aug-22 7-Feb-23
Actual
3.1.1 Offshore Area (start from AS 1 to AS 40 ) 181 11-Aug-22 7-Feb-23
3.1.1.1 Installasi Rebar Beam Plan 111 11-Aug-22 29-Nov-22 131 TON
Actual
3.1.1.2 Plan 168 13-Aug-22 27-Jan-23 275 TON
Installasi Rebar Slab
Actual
3.1.1.3 Plan 168 15-Aug-22 29-Jan-23 40 grid
Formwork installation
Actual
3.1.1.4 Plan 111 13-Oct-22 31-Jan-23 165 m3
Slab concrete in situ
Actual 1
3.1.1.5 Finishing Concrete Work Plan 111 20-Oct-22 7-Feb-23 40 grid
Actual
3.1.2 Offshore Area (TRESTLE) 55 12-Jan-23 7-Mar-23
28-Jun-22 29-Jun-22 2 5 9 m2
1-2 Purlin Installation
30-Jun-22 1-Jul-22 2 5 9 m2
2-2 Purlin Installation
2-Jul-22 3-Jul-22 2 5 9 m2
3-2 Purlin Installation
30-Jun-22 1-Jul-22 2 5 9 m2
4-2 Plumbness
2-Jul-22 3-Jul-22 2 8 16 m2
4-3 Welding
4-Jul-22 5-Jul-22 2 8 16 m2
4-4 Grouting
2-Jul-22 3-Jul-22 2 5 9 m2
5-2 Plumbness
4-Jul-22 5-Jul-22 2 8 16 m2
5-3 Welding
6-Jul-22 7-Jul-22 2 8 16 m2
5-4 Grouting
4-Jul-22 5-Jul-22 2 5 9 m2
6-2 Plumbness
6-Jul-22 7-Jul-22 2 8 16 m2
6-3 Welding
8-Jul-22 9-Jul-22 2 8 16 m2
6-4 Grouting
6-Jul-22 7-Jul-22 2 5 9 m2
7-2 Plumbness
8-Jul-22 9-Jul-22 2 8 16 m2
7-3 Welding
10-Jul-22 11-Jul-22 2 8 16 m2
7-4 Grouting
7-Jul-22 8-Jul-22 2 5 9 m2
8-2 Plumbness
9-Jul-22 10-Jul-22 2 8 16 m2
8-3 Welding
STG BUILDING #1
Estimate
NO. Name Start date (Plan) Finish date (Plan) Dur Prod. Unit
Volume
8-3 Welding
11-Jul-22 12-Jul-22 2 8 16 m2
8-4 Grouting
8-Jul-22 9-Jul-22 2 5 9 m2
9-2 Plumbness
10-Jul-22 11-Jul-22 2 8 16 m2
9-3 Welding
12-Jul-22 13-Jul-22 2 8 16 m2
9-4 Grouting
9-Jul-22 10-Jul-22 2 5 9 m2
10-2 Plumbness
11-Jul-22 12-Jul-22 2 8 16 m2
10-3 Welding
13-Jul-22 14-Jul-22 2 8 16 m2
10-4 Grouting
11-Jul-22 12-Jul-22 2 5 9 m2
11-2 Plumbness
13-Jul-22 14-Jul-22 2 8 16 m2
11-3 Welding
15-Jul-22 16-Jul-22 2 8 16 m2
11-4 Grouting
13-Jul-22 14-Jul-22 2 5 9 m2
12-2 Plumbness
15-Jul-22 16-Jul-22 2 8 16 m2
12-3 Welding
17-Jul-22 18-Jul-22 2 8 16 m2
12-4 Grouting
15-Jul-22 16-Jul-22 2 5 9 m2
13-2 Plumbness
17-Jul-22 18-Jul-22 2 8 16 m2
13-3 Welding
19-Jul-22 20-Jul-22 2 8 16 m2
13-4 Grouting
Install Steel Deck, Stud Bolt & End Plate Zone - 2 11-Jul-22 22-Jul-22 12 53 625.1 m2
1-2
Grid 11 ~ 9
Install Steel Deck, Stud Bolt & End Plate Zone - 3 17-Jul-22 23-Jul-22 7 58 402.46 m2
1-3
Grid 9 ~ 7
Install Steel Deck, Stud Bolt & End Plate Zone - 4 23-Jul-22 28-Jul-22 6 56 333 m2
1-4
Grid 5 ~ 3
STG BUILDING #1
Estimate
NO. Name Start date (Plan) Finish date (Plan) Dur Prod. Unit
Volume
Install Steel Deck, Stud Bolt & End Plate Zone - 5 26-Jul-22 5-Aug-22 11 55 603.5 m2
1-5
Grid 3 ~ 1
WBS 2 CONCRETE WORKS 6-Jul-22 13-Aug-22 39
ACT 2-1 Zone - 1 (Grid 13 ~ 11) 6-Jul-22 28-Jul-22 23
6-Jul-22 25-Jul-22 20 2 21.68 Ton
2-1-1 Rebar Installation
Install Steel Deck, Stud Bolt & End Plate Zone - 2 3-Aug-22 18-Aug-22 16 53 844 m2
1-2
Grid 11 ~ 9
Install Steel Deck, Stud Bolt & End Plate Zone - 3 9-Aug-22 24-Aug-22 16 53 844 m2
1-3
Grid 9 ~ 7
Install Steel Deck, Stud Bolt & End Plate Zone - 4 19-Aug-22 31-Aug-22 13 52 668.5 m2
1-4
Grid 7 ~ 5
Install Steel Deck, Stud Bolt & End Plate Zone - 5 22-Aug-22 3-Sep-22 13 52 668.5 m2
1-5
Grid 5 ~ 3
Install Steel Deck, Stud Bolt & End Plate Zone - 6 25-Aug-22 9-Sep-22 16 54 850 m2
1-6
Grid 3 ~ 1
2 CONCRETE WORKS 29-Jul-22 17-Sep-22 51
2-1 Zone - 1 (Grid 13 ~ 11) 29-Jul-22 20-Aug-22 23
29-Jul-22 17-Aug-22 20 2 21.68 Ton
2-1-1 Rebar Installation
Install Steel Deck, Stud Bolt & End Plate Zone - 2 5-Sep-22 10-Sep-22 6 56 333.5 m2
1-2
Grid 11 ~ 9
Install Steel Deck, Stud Bolt & End Plate Zone - 3 8-Sep-22 13-Sep-22 6 54 319 m2
1-3
Grid 9 ~ 7
Install Steel Deck, Stud Bolt & End Plate Zone - 4 11-Sep-22 15-Sep-22 5 58 290 m2
1-4
Grid 7 ~ 5
Install Steel Deck, Stud Bolt & End Plate Zone - 5 14-Sep-22 18-Sep-22 5 53 261 m2
1-5
Grid 5 ~ 3
Install Steel Deck, Stud Bolt & End Plate Zone - 6 16-Sep-22 20-Sep-22 5 50 246.5 m2
1-6
Grid 3 ~ 1
2 CONCRETE WORKS 7-Sep-22 28-Sep-22 22
2-1 Zone - 1 (Grid 13 ~ 11) 7-Sep-22 15-Sep-22 9
7-Sep-22 12-Sep-22 6 2 6.11 Ton
2-1-1 Rebar Installation
6-Jul-22 28-Jul-22 23 1 1 Ls
1-2 Scaffolding Installation
11-Jul-22 2-Aug-22 23 1 1 Ls
1-3 Center Line, Squareness & Surveying Each Coloumn (12 Coloumns)
1-Jul-22 7-Jul-22 7 1 1 Ls
1-4 Rail Mobilisation & Arragement (Lifting & On Based)
7-Jul-22 29-Jul-22 23 1 1 Ls
2-2 Welding
10-Jul-22 1-Aug-22 23 1 1 Ls
2-3 PT/NDT After Welding
20-Jul-22 20-Jul-22 1 1 1 Ls
3-2 Plate Arragement for Crane
21-Jul-22 22-Jul-22 2 1 1 Ls
3-3 Check & Prepare Access for Multi Axel
21-Jul-22 24-Jul-22 4 1 1 Ls
3-4 Crane Assembly
3-Aug-22 3-Aug-22 1 1 1 Ls
4-2 Girder II Lifting & On Based
4-Aug-22 10-Aug-22 7 1 1 Ls
4-3 Both Girder Assembly
8-Aug-22 13-Aug-22 6 1 1 Ls
5-2 Busbar Innstallation
14-Aug-22 19-Aug-22 6 1 1 Ls
5-3 Cable Tray Installation
STG BUILDING #1
Estimate
NO. Name Start date (Plan) Finish date (Plan) Dur Prod. Unit
Volume
20-Aug-22 25-Aug-22 6 1 1 Ls
5-4 Pulling Cable
26-Aug-22 27-Aug-22 2 1 1 Ls
5-5 Power On
28-Aug-22 29-Aug-22 2 1 1 Ls
5-6 Load test
30-Aug-22 30-Aug-22 1 1 1 Ls
5-7 Inspection by Disnaker / Certificate
1 CW PUMP HOUSE
CW INTAKE
NO. Name Start date (Plan) Finish date (Plan) Dur Volume UOM
1 BOTTOM ASH SILO #1 11-Jun-22 22-Feb-23 256 1 BOTTOM ASH SILO #2 7-Sep-22 28-Mar-23 202
1-1 Pile Work 11-Jun-22 30-Jul-22 49 1-1 Pile Work 7-Sep-22 26-Oct-22 49
11-Jun-22 15-Jun-22 5 7-Sep-22 11-Sep-22 5
1 Preparation 1 Preparation
1-2 Foundation Work 15-Aug-22 22-Oct-22 68 1-2 Foundation Work 3-Nov-22 8-Dec-22 35
1-2-1 Footing 15-Aug-22 22-Oct-22 68 1-2-1 Footing 3-Nov-22 8-Dec-22 35
15-Aug-22 24-Aug-22 10 3-Nov-22 12-Nov-22 10
1 Excavation 1 Excavation
1-2-2.2 Pedestal P04a & P02a_SECTION - 1 (4 Nos) 2-Nov-22 30-Nov-22 28 1-2-2.2 Pedestal P04a & P02a_SECTION - 1 (4 Nos) 19-Dec-22 11-Jan-23 23
2-Nov-22 8-Nov-22 7 19-Dec-22 25-Dec-22 7
1 Rebar Installation 1 Rebar Installation
1-2-3 Bottom Slab & Drainage 4-Dec-22 22-Feb-23 80 1-2-3 Bottom Slab & Drainage 15-Jan-23 28-Mar-23 72
1-2-3.1 Bottom Slab 4-Dec-22 6-Jan-23 33 1-2-3.1 Bottom Slab 15-Jan-23 10-Feb-23 26
4-Dec-22 10-Dec-22 7 15-Jan-23 21-Jan-23 7
1 Soil Backfill & Compacted 1 Soil Backfill & Compacted
1-2-3.2 Bottom Slab - Drainage 10-Jan-23 28-Jan-23 18 1-2-3.2 Bottom Slab - Drainage 14-Feb-23 4-Mar-23 18
10-Jan-23 14-Jan-23 5 14-Feb-23 18-Feb-23 5
1 Excavation 1 Excavation
1-2-3.3 Wall - Drainage 1-Feb-23 22-Feb-23 21 1-2-3.3 Wall - Drainage 8-Mar-23 28-Mar-23 20
1-Feb-23 10-Feb-23 10 8-Mar-23 17-Mar-23 10
1 Rebar Wall Installation 1 Rebar Wall Installation