Professional Documents
Culture Documents
Management Walkthrough (11.03.22)
Management Walkthrough (11.03.22)
#1
Action by : HSE/
Issued Date : November 3, 2022 Status: Closed Completion Date: November 3, 2022
Operation
#2
Action by : HSE/
Issued Date : November 3, 2022 Status: Closed Completion Date:November 3, 2022
Operation/
#3
Action by : HSE/
Issued Date : November 3, 2022 Status: Closed Completion Date:November 3, 2022
Operation/
#4
1/3
#4
Action by : HSE/
Issued Date : November 3, 2022 Status: Closed Completion Date: November 3 , 2022
Operation/
#5
Comment: To improve the cover of the electrical panel. Corrective Action: .Electrical panel cover was improved.
Action by : HSE/
Issued Date: November 3, 2022 Status: Closed Completion Date:November 5, 2022
Operation
#6
#7
2/3
#8
#9
#10
Prepared by: Jaymar L. Tacang Reviewed by: Jessen Canaling Noted by: Jayson Regalado
Safety Officer OSH Practitioner Project Manager
3/3