PROJECT NAME: 10729 09 MURJ – JEDDAH, KSA

AL MURJAN MEDICAL CENTER; JEDDAH- KSA

PROCUREMENT MEETING MINUTES NO. 12

Date: 03rd of December 2022

Location: Al Murjan Medical Center – Site Meeting Room

Duration: 10:00 AM till 12:00 PM


Agenda: Procurement Meeting

NAME COMPANY CONTACTS EMAIL ADDRESS

1 Wael Al-Agamawi KC E: wael.al-agamawi@klingconsult.com

2 Nabil Mesleh AJ E: nabil_mesleh@aj-group.com

3 Girgis Wissa STS E: girgis@stsksa.com

4 Yasser Alkash STS E: yalkash@stsksa.com

5 Hussein Yosry KC E: hussein.yosry@klingconsult.com

No attachments
Attachments

Distribution All Participants

Author / Issue Date Hussein Yosry 04th of December 2022


Date of
ACTION TARGET
last DESCRIPTION
BY DATE
update

The following list of undelivered materials was under discussion.

1. Resin Panels
KC stated that there was no PO placement yet, although
The approval on samples was issued in June 2022.

STS confirmed PO placement on August 23, 2022.

KC raised concerns about the delay in selecting artwork


03/12/2022 placement and manufacturing.

KC & AJ ask for STS’s PO with Adada for Resin Panels.

STS submitted shop drawings this week. AJ / STS

STS stated that the supplier needs 40 days for


manufacturing, 30 days for delivery, and 25 days for
installation (a total of 95 days) from the date of shop
drawing approval for solid colors (15th January 2023).

KC objected to the late shop drawing submission by STS


and stated that this delay event will be STS’s
responsibility.

2. Wooden Doors
KC and AJ raised their concerns regarding the delivery
time and delivery prioritization.

STS confirmed the following delivery schedule for door


frames:
Delivered 1146
03/12/2022 Remaining 445

STS informed the following is the wooden door leaf


STS
schedule.

Delivered 751
05th Dec 2022 226
Under fabrication 250
undefined 36448+570-

STS to provide a weekly update.

3. Metal Doors

03/12/2022
STS confirmed the delivery of (193) Doors.
Delivered 356 STS
Remaining 214

PROCUREMENT MOM-12 Page 1 of 5


Date of
ACTION TARGET
last DESCRIPTION
BY DATE
update
4. Stainless Steel Doors
AJ confirmed the material approval.
03/12/2022
STS confirmed that PO placement is done.

AJ approved shop drawings and STS to update delivery


dates.
STS
STS confirmed completion of delivery by 30th October 15th
30th November 15th December.

STS confirmed material arrival at the seaport.

STS to provide a weekly update.

5. Patient Room Woodwork

STS confirmed the delivery of 100 rooms by November


03/12/2022 30th, 2022.

STS confirmed receiving (99) Single patient rooms joinery


work from FADEN.

STS confirmed that installation is ongoing for 62 rooms. STS

STS confirmed receiving complete quantities of 4 out of 6


items for 32 rooms from B design, for phase 1.

FADEN and B design started the installation at the site.

6. Wooden Ceiling
AJ confirmed the material approval.
03/12/2022 AJ / STS
STS confirmed that PO placement is done.

AJ issued the shop drawings with code B

STS commenced the installation, expecting completion of


50% of main entrance by 05th December.

7. Counters - Nurse Stations

STS submitted shop drawings and AJ replied with code


03/12/2022 (C). STS / AJ

AJ approved shop drawings with code B.

STS to confirm the delivery time accordingly.

8. Wooden Casework in other areas

AJ confirmed the material approval.


03/12/2022 AJ / STS
STS confirmed that PO placement is done.

PROCUREMENT MOM-12 Page 2 of 5


Date of
ACTION TARGET
last DESCRIPTION
BY DATE
update
AJ issued the shop drawings with code B

STS to confirm the delivery time accordingly.

STS confirmed the delivery of 108 linear meters out of 180.

9. Skylight Covering System


AJ confirmed the material approval.
03/12/2022
STS confirmed the PO placement.
STS is yet to provide the delivery schedule.

STS shall submit revised shop drawings before August


31st, 2022. AJ Approved. STS

Installation of the System from 2nd Jan 2023 to 26th Jan


2023.
Installation of the Glass from 27th Jan to 26 Feb 2023.

10. Wall Protection


AJ confirmed the material approval for all components.

STS confirmed that PO placement is done.


03/12/2022
STS stated that they need 1.5 months for delivery of steel
Skelton and (2) months for cover from the shop drawing
approval (recently submitted).
STS
Shop drawings have been approved on August 30th.

STS confirmed the delivery of the aluminum suspension.

STS confirmed the delivery of Acrovyn will be on the 15th


30th November in Transit.

11. LED Chandeliers

03/12/2022 STS submitted its material submittal on 14th Sept. Under


AJ review

STS is to submit the revised material submittal and AJ/STS


samples ASAP.

STS to confirm the delivery time.


12. Privacy & Shower Curtains

AJ confirmed the material approval.


03/12/2022
STS confirmed that PO placement is done.
AJ/STS
STS is yet to provide the delivery schedule.

STS will provide further samples on 22nd Sept. for color


selection.

PROCUREMENT MOM-12 Page 3 of 5


Date of
ACTION TARGET
last DESCRIPTION
BY DATE
update
AJ to confirm the colors and assured that approved by
tomorrow i.e. (02nd Oct 2022).

AJ informed the contractor/supplier to submit the


material, and shop drawings are still pending.

On 12th November, STS stated that the privacy curtain


is not in the contractor’s scope. KC and AJ rejected this
statement and informed that this was defined in contract
addendum #3.

KC states that this delay event is STS’s responsibility.

13. Marble to Lobby Area


STS confirmed that PO placement is done.
03/12/2022
STS is yet to provide the delivery schedule.
STS
STS confirmed complete Delivery, Installation is in
progress.
14. Landscape
STS and AJ to expedite engineering submissions and
03/12/2022 approvals.

The subcontractor will provide samples this week for


consultant approval.

AJ will issue instructions with color, and pattern before 20th


Sept. AJ / STS

AJ approved Pattern, and Color, AJ will issue


instructions by tomorrow (02nd Oct 22), pertaining to
control/expansion joints.

AJ confirmed that control joints are to be every 6mts as


per calculation.

15. Door Hardware


Most of the door hardware will be delivered within days of
03/12/2022
delivery, (Delivered to the Site).

STS confirmed the delivery of aligns and door closers.

AJ approved the master key chart; STS shall provide 20


Grand master keys.
STS
STS confirmed the partial delivery, to provide a delivery
schedule for the remaining.

STS is to submit a sample board for the remaining


accessories for final approval.

STS submitted the samples, under AJ review.

PROCUREMENT MOM-12 Page 4 of 5


Date of
ACTION TARGET
last DESCRIPTION
BY DATE
update
16. Courtyard
KC and AJ asked for STS confirmation for the following:

03/12/2022
The installation of the southern Courtyard Non-Fire
rated from 24th Nov to 03rd Dec 2022, and Fire rated
from 09th Dec to 24th Dec 2022.

The installation of the northern Courtyard Non-Fire


rated from 26th Dec to 20th Jan 2023, and Fire rated from
03rd Dec to 25th Dec 2022. STS

The aluminum decorative screens’ delivery time will be at


the end of December 2022.

STS confirmed that installation in the southern


courtyard is complete, with the exception of glass
panels, which will begin shortly.

17. Signage System


AJ confirmed the material approval.
03/12/2022
STS confirmed that PO placement is done.

AJ to confirm the selection of internal signage models with


Mediclinic. AJ / STS

AJ approved the submitted shop drawings.

STS is yet to provide the delivery schedule.

AJ will share complete fixation details for external signage.

18. Next Meeting


Will be Sunday 11th December 2022 @ 10:00 am

These minutes are the official record of the meeting. Should additions, deletions, or corrections required please contact the
undersigned in writing within (3) days from the date of issuance, otherwise these Minutes will stand as written.

KC creates consecutively numbered protocols of all meetings. Unless the content of this protocol is incorrect and a revision
proposal is submitted to KC within three working days, then the content of this protocol forms the basis for any further
project work.

PROCUREMENT MOM-12 Page 5 of 5

You might also like