Procurement Meeting No 12
Procurement Meeting No 12
No attachments
Attachments
1. Resin Panels
KC stated that there was no PO placement yet, although
The approval on samples was issued in June 2022.
2. Wooden Doors
KC and AJ raised their concerns regarding the delivery
time and delivery prioritization.
Delivered 751
05th Dec 2022 226
Under fabrication 250
undefined 36448+570-
3. Metal Doors
03/12/2022
STS confirmed the delivery of (193) Doors.
Delivered 356 STS
Remaining 214
6. Wooden Ceiling
AJ confirmed the material approval.
03/12/2022 AJ / STS
STS confirmed that PO placement is done.
03/12/2022
The installation of the southern Courtyard Non-Fire
rated from 24th Nov to 03rd Dec 2022, and Fire rated
from 09th Dec to 24th Dec 2022.
These minutes are the official record of the meeting. Should additions, deletions, or corrections required please contact the
undersigned in writing within (3) days from the date of issuance, otherwise these Minutes will stand as written.
KC creates consecutively numbered protocols of all meetings. Unless the content of this protocol is incorrect and a revision
proposal is submitted to KC within three working days, then the content of this protocol forms the basis for any further
project work.