Air Separation Unit (ASU) Project

2A Hernadi 1-Sept- Agung R. 1-Sep-2022 Riky Novfriska 1-Sep-2022 Issued for Construction


2022
1A Hernadi 22-Aug- Agung R. 22-Aug-2022 Riky Novfriska 22-Aug-2022 Issued for Approval
2022
Name Date Name Date Name Date
Rev Document Type
Prepared by Reviewed by Approved by

PROJECT Air Separation Unit (ASU) Project

OWNER PT AMMAN Mineral Industri

PMC TATA Consulting Engineers Limited

CONTRACTOR PT JGC Indonesia

SUB CONTRACTOR

Document Title Site Inspection Test Plan For Building


Document ID ACCS-40-411-AS01-S-PLN-0201 Rev
Sheet 1
All rights reserved, no part of this document may be reproduced or transmitted in any form or by any means without the prior permission in writing from PT. JGC
Indonesia.
1/1
Construction

r Approval

ument Type

ted

2A            
OF 6
1 / 103
Air Separation Unit (ASU) Project
Document Title Site Inspection Test Plan For Building
Document AMIN ID ACCS-40-411-AS01-S-PLN-0201
Document JIND ID S-A000-1670-201
Date 1-Sept-2022 Rev 2A      
Sheet 2 OF 6
PT. JGC INDONESIA
Name Signature Date
Prepared by: Hernadi 1 September 2022
Reviewed by: Agung R. 1 September 2022
Approved by: Riky Novfriska 1 September 2022
PMC/AMIN
Name Position Signature Date

CODES
(A) Approved.Proceed with Fabrication/Construction (D) Returned without review, reasons as enclosed /
marked. Work shall not proceed.

Approved with comments. Proceed with Documents retained for information only.
Fabrication/Construction incorporating our comments
(B) and resubmit for final (E)
approval.
Commented. Document to be resubmitted for approval
incorporating our comments. Work shall not proceed.
(C)

Only valid when sealed


with the technical stamp of
PT. JGC Indonesia
Date
1 September 2022
1 September 2022
1 September 2022

Date

review, reasons as enclosed /


all not proceed.

ed for information only.


Air Separation Unit (ASU) Project
Document Title Site Inspection Test Plan For Building
Document AMIN ID ACCS-40-411-AS01-S-PLN-0201
Document JIND ID S-A000-1670-201
Date 1-Sept-2022 Rev 2A      
Sheet 3 OF 6
Revision List Table

No Date Revision Page Description Remarks


1 22-Aug-2022 1A All Issued for Approval
1 1-Sep-2022 2A All Issued for Construction
Air Separation Unit (ASU) Project
Document Title Site Inspection Test Plan For Building
Document AMIN ID ACCS-40-411-AS01-S-PLN-0201
Document JIND ID S-A000-1670-201
Date 1-Sept-2022 Rev 2A      
Sheet 4 OF 6
TABLE OF CONTENTREVISION LIST TABLE 31.
31. GENERAL
Air Separation Unit (ASU) Project
Document Title Site Inspection Test Plan For Building
Document AMIN ID ACCS-40-411-AS01-S-PLN-0201
Document JIND ID S-A000-1670-201
Date 1-Sept-2022 Rev 2A      
Sheet 5 OF 6
1. GENERAL
PT Amman Mineral Industri (AMIN) is in the process of setting up a Captive Copper Smelter Project with capacity 900 KTPA copper
concentrate at Sumbawa Island, West Nusa Tenggara, Indonesia. The smelter product will be 222 KTPA of copper cathode with purity
99.99% Cu and 830 KTPA sulfuric acid with purity 98.5%.
For Copper smelter will require a continuous supply of Oxygen & Nitrogen gases. Therefore, it is proposed to have a dedicated Air
Separation Unit (ASU) for uninterrupted supply of oxygen & nitrogen gases.

This document is intended to provide Site Inspection and Test Item for Building Works to be required during construction stage for
Air Separation Unit (ASU) Project. The inspection and test item provided in this document includes intervention of ‘Witness’. ‘Spo
Witness’, ‘Review’, or ‘Hold’ points of each party involved in the inspection and test, i.e: SUBCONTRACTOR, CONTRACTOR,
OWNER.
2. DEFINITION & ABBREVIATION
PROJECT Air Separation Unit (ASU) Project
OWNER PT. Amman Mineral Industri
CONTRACTOR PT JGC Indonesia
SUBCONTRACTOR Any organization who provides service of construction/installation of
equipment and material for the project.
3. REFERENCE DOCUMENT
JIND Document No. AMIN Document No. Document Title

S-A000-1340-001 ACCS-40-411-AS01-G-SPC-0001 GENERAL SPECIFICATION FOR


BUILDING
S-A000-1520-001 ACCS-40-411-AS01-Q-PLN-0001 QC EXECUTION PLAN
S-A000-1520-006 ACCS-40-411-AS01-Q-SPC-0006 NON-CONFORMITY CONTROL
PROCEDURE
QUALITY CONTROL
S-A000-1670-001 ACCS-40-411-AS01-Q-SPC-0008 REQUIREMENTS TO
SUBCONTRACTOR.
4. RESPONSIBILITIES
SUBCONTRACOTR shall be responsible to prepare and submit Inspection & Test Plan (ITP) related to their scope of work to
CONTRACTOR for review and approval prior to commence the construction / installation work.
CONTRACTOR shall be responsible to review and approve the ITP submitted by SUBCONTRACTOR. When required by contract,
SUBCONTRACTOR’s ITP shall also be reviewed and approved by OWNER.

5. PROCEDURES
5.1 General Requirement
As required by Contract, each SUBCONTRACTOR shall prepare the ITP (Inspection and Test Plan) with refer to this procedure and item
as shown in Attachment-1: Inspection and Test Plan Items.

Determination of intervention point of SUBCONTRACTOR, CONTRACTOR and OWNER, shall be discussed and establish
during Pre-Inspection Meeting (PIM) or Kick of Meeting (KOM)
The following letters and abbreviations are to be used in the Inspection and Test Plan:
H (Hold Point)
pacity 900 KTPA copper
opper cathode with purity

o have a dedicated Air

uring construction stage for


ervention of ‘Witness’. ‘Spot
ACTOR, CONTRACTOR,

FOR

TROL

TROL
TO

scope of work to

en required by contract,

er to this procedure and items

l be discussed and established


Air Separation Unit (ASU) Project
Document Title Site Inspection Test Plan For Building
Document AMIN ID ACCS-40-411-AS01-S-PLN-0201
Document JIND ID S-A000-1670-201
Date 1-Sept-2022 Rev 2A      
Sheet 6 OF 6
Intervention point shall align with QC requirement to Subcontractor S-A000-1670-001 Attachment-1
W (Witness Point)
CONTRACTOR / COMPANY intends to witness the test/inspection, however SUBCONTRACTOR can proceed with the test /
inspection when the CONTRACTOR inspector is not present at the notified time. SUBCONTRACTOR shall submit inspection
notification to CONTRACTOR.
SW (Spot Witness)
Spot witness specified the operation test / examination where the CONTRACTOR’s Inspector must be notified in advance and may
present during the specified activity. SUBCONTRACTOR shall submit inspection notification to CONTRACTOR.

R (Record Review)
Record and/or document review.
Subcontractor shall provide CONTRACTOR with certificates, reports and records as applicable for review and approval.

M (Implementation)
Preparation and execution of inspection by measurement, observation, examination and / or testing include reporting.

5.2 Inspection and Test Item


Inspection and test item includes its intervention point of each party for each work category required during construction stage of project
execution at site is given in Attachment-1: Site Inspection and Test Item.

Inspection and test item specified in this document comprise the following work categories:
(1) EXTERIOR & INTERIOR WORKS
(2) PLUMBING WORK
(3) FIRE FIGTHING WORK
(4) ELECTRICAL WORKS
(5) HVAC WORKS
(6) FIRE ALARM WORKS

Inspection and test item for concrete and steel structure work for building shall refer to document no S- A000-1670-101 (ACCS-40
411-AS01-C-PLN-0011), SITE INSPECTION AND TEST PLAN FOR CIVIL WORKS & STEEL STRUCTURE.

6. ATTACHMENT
0-001 Attachment-1

UBCONTRACTOR can proceed with the test /


SUBCONTRACTOR shall submit inspection

R’s Inspector must be notified in advance and may be


n notification to CONTRACTOR.

s as applicable for review and approval.

n and / or testing include reporting.

gory required during construction stage of project

ategories:

er to document no S- A000-1670-101 (ACCS-40-


L WORKS & STEEL STRUCTURE.
AIR SEPARATION UNIT (ASU) INSPECTION AND TEST PLAN (ITP) FOR BUILDING COMPANY No. : ACCS-40-411-A

PROJECT INTERIOR & EXTERIOR FINISHING WORK CONTRACTOR No. : S-A000-167

Contract No :

Contractor : JGC Indonesia Location : Sumbawa, West Nusa Tenggara, Indonesia


Work Scope : Building

A : Approval R : Review S/C : SUBCONTRACTOR


W : Witness SW : Spot Witness P : Provide JGC : JGC Indonesia
H : Hold Point M : Monitor AMIN : PT. Amman Mineral Industry
V : Verification

Inspection Level
No Activity Description Reference Document Acceptance Criteria Verify Doc.
S/C JGC

1 Material Receiving

1.1 Visual

- Packaging ITR-GEN-001 M W

- Storage ITR-GEN-001 M W
Approved Specification, Approved Drawing & As per Material Approval Request, Approved Procedure /
Procedure Manufacturer Recommendation
1.2 Type & size, free from damages ITR-GEN-001 M W

1.3 Documents review (certificates, etc.) ITR-GEN-001 M R

2 Ceiling Works

2.1 Material : accepted and conformed to specification prior installation Material Approval Request, Approved Drawing &
Procedure
ITR-4000-001 M W

2.2 To check M&E items installation above ceiling has been completed Completed signed of hand over M&E installation above
ceiling
ITR-4000-001 M W

2.3 Type, elevation of edge moldings & ceiling hanger Material Approval Request & Approved Drawing ITR-4000-001 M W

2.4 Verify location and size of ceiling mount M&E equipment / fixtures Approved Drawing ITR-4000-001 M W

Approved Specification, Approved Drawing &


2.5 Location, alignment, elevation and rigidity of ceiling suspension system Procedure - Alignment ITR-4000-001 M W

- Elevation

- Rigidity

2.6 Ceiling Panel & Insulation board / blanket installation Material Approval Request & Approved Drawing ITR-4000-001 M W

2.7 Surface condition for exposed ceiling frame and panel boards Material Approval Request ITR-4000-001 M W

3 Wall / Partition Work

3.1 Masonry : Hollow Concrete Block

3.1.1 Material : accepted and conformed to specification prior installation Material Approval Request, Approved Drawing &
Procedure
ITR-4000-002 M W

3.1.2
Setting-out, marking center and both side of block Approved Drawing ITR-4000-002 M W

3.1.3 Dowels and anchors location, incl. mortar fill around dowel and use of chemical for anchor Approved Drawing & Procedure ITR-4000-002 M W

3.1.4 Mixing of grout / mortar using approved proportion and gauge boxes Mix proportion 1 : 5 (cement : sand) common wall ITR-4000-002 M W

Mix proportion 1 : 3 (cement : sand) for trassam wall

3.1.5 Alignment and plumbness of walls - Alignment ITR-4000-002 M W

- Plumbness

Approved Specification, Approved Drawing &


3.1.6 Arrangement of stiffener columns and bond beams
Procedure
Approved Drawing ITR-4000-002 M W

3.1.7 Size and location of joints, control and expansion joints Approved Drawing ITR-4000-002 M W

3.1.8 Ties and vertical - horisontal reinforcement bar / mesh arrangement Approved Drawing ITR-4000-002 M W

3.1.9 Location of electrical conduit, box and sleeve pipe, etc. Approved Drawing & Procedure ITR-4000-002 M W

3.1.10 Location and size of openings and penetrations Approved Drawing ITR-4000-002 M W

3.1.11 Grouting / Mortar test Procedure Subcont form report M W

Cleaning Procedure ITR-4000-002 M W


3-Jan-2012

3-Jan-2013 Curing at least carried out of 7 days, 2 times each day ITR-4000-002 M W

3.2 Plastering

3.2.1 Material : accepted and conformed to specification prior installation Approved Drawing & Procedure ITR-4000-003 M W

3.2.2 Protections for permanent finishes and fittings Procedure ITR-4000-003 M W

3.2.3 Check concealed M & E items has been installed (all embeded Material) Completed signed of hand over M&E installation inside
wall plastered
ITR-4000-003 M W

3.2.4 Condition of application surfaces (i.e: Roughness / scratching prior to plastering) Procedure ITR-4000-003 M W

3.2.5 Corner and joint beads setting Plumbness tolerance ±2 mm/M ITR-4000-003 M W

3.2.6 Location and size of openings and penetrations Approved Drawing ITR-4000-003 M W

3.2.7 Mixing of mortar using approved proportion and gauge boxes Mix proportion 1 : 4 (cement : sand) ITR-4000-003 M W

3.2.8 Application of bonding agent and base coat Manufacturer standard ITR-4000-003 M W
3.2.9 Thickness reference for vertical & horisontal direction of plastering - Vertical reference minimum @1000 mm maximum 1200
mm, start 300 mm from corner side
ITR-4000-003 M W

- Horisontal 300 mm bottom from ceiling elevation and


300 mm above floor finish
3.2.10 Thickness, Straightness, Flatness and Appearance - Thickness ITR-4000-003 M W

- Straightness & flatness : 80 gr thick of paper not pass


when jidar aluminium pinned to the plastered surface

3.2.11 Cleaning around permanent finishes and fittings Procedure ITR-4000-003 M W

3-Feb-2012 Mortar test Procedure Subcont form Report M W

Curing at least carried out of 7 days, 2 times each day ITR-4000-003 M W


3-Feb-2013
Approved Specification, Approved Drawing &
Procedure
A : Approval R : Review S/C : SUBCONTRACTOR
W : Witness SW : Spot Witness P : Provide JGC : JGC Indonesia
H : Hold Point M : Monitor AMIN : PT. Amman Mineral Industry
V : Verification

Inspection Level
No Activity Description Reference Document Acceptance Criteria Verify Doc.
S/C JGC

3.3 Tile Work (Wall)

3.3.1 Material : accepted and conformed to specification prior installation Material Approval Request & Approved Drawing ITR-4000-004 M W

3.3.2 Layout, marking, starting point position, elevation reference and check of substrate Approved Drawing ITR-4000-004 M W

3.3.3 Check location and size of concealed M&E items (if any) Completed signed of hand over M&E installation inside ITR-4000-004 M W

To check waterproofing requirement for wet wall area and make sure the work has been
3.3.4
completed
Completed signed of leakage test document ITR-4000-004 M W

3.3.5 Verify type, pattern and layout of tiles Material Approval Request & Approved Drawing ITR-4000-004 M W

3.3.6 Corner, plinth and joint beads setting Procedure ITR-4000-004 M W


Approved Specification, Approved Drawing &
Procedure
3.3.7 Method, type, mixing ratio and application of bedding mortar / grout or adhesive Mix bedding mortar 1 : 3 (cement : sand) ITR-4000-004 M W

3.3.8 Alignment, level and flatness / evenness of installed tiles - Flatness ITR-4000-004 M W

3.3.9 Conditions of cut tile edges and projection round embedded pipes and fitting Procedure ITR-4000-004 M W

3.3.10 Check adhesion of tiles by sounding (void) & surface appearance Procedure ITR-4000-004 M W

3.3.11 Type, color and application of grout for tile joints Material Approval Request ITR-4000-004 M W

3.3.12 Cleaning and polishing Procedure ITR-4000-004 M W

3.4 Gypsum Board Partition

3.4.1 Material : accepted and conformed to specification prior installation Material Approval Request & Approved Drawing ITR-4000-005 M W

3.4.2 Layout, elevation and marking Approved Drawing ITR-4000-005 M W

3.4.3 Location and size of wall openings Approved Drawing ITR-4000-005 M W

3.4.4 Alignment, spacing and rigidity of runners / studs - Alignment ITR-4000-005 M W

- Rigidity

3.4.5 Reinforcement for wall openings, wall mounted M&E items, equipment, fixtures and fittings etc. Procedure ITR-4000-005 M W

3.4.6 Check concealed M&E items has been completed Completed signed of hand over M&E installation inside
partition
ITR-4000-005 M W

3.4.7 Insulation board / blanket installation Procedure ITR-4000-005 M W

3.4.8 Type and thickness of wall board Material Approval Request & Approved Drawing ITR-4000-005 M W

3.4.9 Wall board layout, height, number and spacing of tapping screws Material Approval Request & Approved Drawing ITR-4000-005 M W

3.4.10 Treatment of cut board edges, board joints and corner beads Manfacturer standard ITR-4000-005 M W

3.4.11 Straightness, verticality and flatness ± 2mm / 1.2 M flatness verticality tolerance ITR-4000-005 M W

3.4.12 Seal for penetrations of fire rated wall


Approved Specification, Approved Drawing &
Procedure ITR-4000-005 M W
Procedure
4 Floor Work

4.1 Tile Work (Floor)

4.1.1 Material : accepted and conformed to specification prior installation Material Approval Request & Approved Drawing ITR-4000-006 M W

4.1.2 Layout, marking, starting point position and check of substrate / underlayer Approved Drawing ITR-4000-006 M W

4.1.3 Check location and size of concealed M&E items Completed signed of hand over M&E installation under
tile floor
ITR-4000-006 M W

4.1.4To check waterproofing requirement (if any), make sure the work has been completed and no
leakage found
Completed signed of leakage test document ITR-4000-006 M W

4.1.5 Verify type, pattern and layout of tiles Material Approval Request & Approved Drawing ITR-4000-006 M W

4.1.6 Corner and joint beads setting Procedure ITR-4000-006 M W


Approved Specification, Approved Drawing &
Procedure
4.1.7 Method, type, mixing ratio and application of bedding mortar / grout or Adhesive Mix bedding mortar 1 : 3 (cement : sand) ITR-4000-006 M W

4.1.8 Alignment, level and flatness / evenness of installed tiles ± 3mm / 1.2 M for flatness tolerance ITR-4000-006 M W

4.1.9 Conditions of cut tile edges and projection around embedded pipes and fitting Procedure ITR-4000-006 M W

4.1.10 Check adhesion of tiles by sounding Procedure ITR-4000-006 M W

4.1.11 Type, color and application of grout for tile joints Material Approval Request \ ITR-4000-006 M W
4.1.12 Cleaning and polishing Procedure ITR-4000-006 M W
COMPANY No. : ACCS-40-411-AS01-S-PLN-0201

CONTRACTOR No. : S-A000-1670-201

Contract No :

Revision: 2A

Inspection Level
REMARKS
JGC AMIN

W R

W R

W R

R R

&R R

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R R

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R R

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW
&R SW

&R SW

&R SW

&R SW

&R SW

Inspection Level
REMARKS
JGC AMIN

&R R

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R R

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R R

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW
&R SW
AIR SEPARATION UNIT (ASU) INSPECTION AND TEST PLAN (ITP) FOR BUILDING COMPANY No. : ACCS-40-411-A

PROJECT INTERIOR & EXTERIOR FINISHING WORK CONTRACTOR No. : S-A000-167

Contract No :

Contractor : JGC Indonesia Location : Sumbawa, West Nusa Tenggara, Indonesia


Work Scope : Building

A : Approval R : Review S/C : SUBCONTRACTOR


W : Witness SW : Spot Witness P : Provide JGC : JGC Indonesia
H : Hold Point M : Monitor AMIN : PT. Amman Mineral Industry
V : Verification

Inspection Level
No Activity Description Reference Document Acceptance Criteria Verify Doc.
S/C JGC

4.2 Raise Floor

4.2.1 Material : accepted and conformed to specification prior installation Material Approval Request & Approved Drawing ITR-4000-007 M W

4.2.2 Conditions of sub floor Procedure ITR-4000-007 M W

4.2.3 Marking and verification of panel layout Approved Drawing & Procedure ITR-4000-007 M W

4.2.4 Location and elevation of steel support for instrument / electrical panel Approved Drawing ITR-4000-007 M W

4.2.5 Alignment, elevation and rigidity of pedestals installed per manufacturer's recommendation. Procedure ITR-4000-007 M W

4.2.6 Location and number of floor openings / penetrations Approved Drawing ITR-4000-007 M W
Approved Specification, Approved Drawing &
Procedure
4.2.7 Level and flatness check of floor ± 3 mm / 1.2 M for flatness tolerance ITR-4000-007 M W

4.2.8 Treatment of cut panel edges Procedure ITR-4000-007 M W

4.2.9 Expansion gap at all abutments with seal Procedure ITR-4000-007 M W

4.2.10 Seal for penetrations of floor panels Procedure ITR-4000-007 M W

4.2.11 Electrical continuity and earth bonding Approved Drawing ITR-4000-007 M W

4-Feb-2012 Cleaning Procedure ITR-4000-007 M W

5 Doors & Windows

5.1 Material : accepted and conformed to specification prior installation Material Approval Request & Approved Drawing ITR-4000-008 M W

5.2 Setting-out Approved Drawing ITR-4000-008 M W

5.3 Location and size of structural opening Approved Drawing ITR-4000-008 M W

5.4 Type, size, location and orientation of door / window being installed Material Approval Request & Approved Drawing ITR-4000-008 M W

5.5 Conditions of anchors / fasteners Procedure ITR-4000-008 M W

5.6 Grouting for threshold Procedure ITR-4000-008 M W

5.7 Alignment, plumb, elevation and orientation ± 2 mm / 1.2 M for plumbness tolerance ITR-4000-008 M W

5.8 Rigidity of frame fit-up / fixing with structure Procedure ITR-4000-008 M W

5.9 Grouting for gap between frame and structure Procedure ITR-4000-008 M W

5.10 Paint finish Material Approval Request & Manufacturer Standard ITR-4000-008 M W

5.11 Type of glass and face direction for installation Approved Drawing ITR-4000-008 M W

5.12 Bead / Seal conditions for glass panels Approved Drawing ITR-4000-008 M W

5.13 Type, location and orientation of Hardware fitting (hinge, lock case, keys, handle, panic bar) Material Approval Request & Approved Drawing ITR-4000-008 M W

5.14 Accessories : Door stoper, door closer, Earth bonding Material Approval Request & Approved Drawing ITR-4000-008 M W

5.15 Labels for fire rated doors / windows Procedure ITR-4000-008 M W

5.16 Functional / operational check


Approved Specification, Approved Drawing &
Procedure ITR-4000-008 M W
Procedure
6 Coating Waterproofing

6.1 Material : accepted and conformed to specification prior installation Material Approval Request & Approved Drawing ITR-4000-009 M W

6.2 Location of upstand, drain, etc. Approved Drawing ITR-4000-009 M W

6.3 Surface conditions (dry, clean, smooth, undamaged, etc.) Procedure ITR-4000-009 M W
Approved Specification, Approved Drawing &
Procedure
6.4 Application of primary waterproofing Material Approval Request & Manufacturer Standard ITR-4000-009 M W

6.5 Installation of coating waterproofing at corners, risers, end stop, penetrations and drain Procedure & manufacturer standard ITR-4000-009 M W

6.6 Water leak test / ponding test Procedure ITR-4000-014 M W

7 Painting for Building

7.1 Material : accepted and conformed to specification prior application Material Approval Request & Approved Drawing ITR-4000-010 M W

7.2 Mock up Procedure ITR-4000-010 M W

7.3 Check Surface condition, moisture content, flatness, wall filler already applied Moisture content shall be less 20 % ITR-4000-010 M W

7.4 Ensure the correct tools is implemented as manufacturer recommendation Approved Specification, Approved Drawing & Material Approval Request & Procedure ITR-4000-010 M W
Procedure
Approved Specification, Approved Drawing &
Procedure
7.5 Ensure the application condition (Weather, Relative Humidity) as per
manufacturing standard & specification
Material Approval Request & Procedure ITR-4000-010 M W

7.6 Coat thickness each layer (wet thickness) Manufacturer standard ITR-4000-010 M W

7.7 To check the straightness of painting line when meet floor skirting, ceiling & corner line Procedure ITR-4000-010 M W
COMPANY No. : ACCS-40-411-AS01-S-PLN-0201

CONTRACTOR No. : S-A000-1670-201

Contract No :

Revision: 2A

Inspection Level
REMARKS
JGC AMIN

&R R

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R R

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R R

&R SW

&R SW

&R SW

&R SW

W SW

&R R

&R SW

&R SW

&R SW
&R SW

&R SW

&R SW
AIR SEPARATION UNIT (ASU) INSPECTION AND TEST PLAN (ITP) FOR BUILDING COMPANY No. : ACCS-40-411-A

PROJECT INTERIOR & EXTERIOR FINISHING WORK CONTRACTOR No. : S-A000-16

Contract No :

Contractor : JGC Indonesia Location : Sumbawa, West Nusa Tenggara, Indonesia


Work Scope : Building

A : Approval R : Review S/C : SUBCONTRACTOR


W : Witness SW : Spot Witness P : Provide JGC : JGC Indonesia
H : Hold Point M : Monitor AMIN : PT. Amman Mineral Industry
V : Verification

Inspection Level
No Activity Description Reference Document Acceptance Criteria Verify Doc.
S/C JGC

8 Stair & Handrail

8.1 Material : accepted and conformed to specification prior installation Approved Drawing & Specification ITR-4000-011 M W

8.2 Verify location as specified in drawing Approved Drawing ITR-4000-011 M W

8.3 Verify material are clean, undamaged & properly stored Procedure ITR-4000-011 M W

8.4 Verify stair & handrail installation : support, fixings as per drawing spec. Approved Specification, Approved Drawing & Approved Drawing ITR-4000-011 M W
Procedure
8.5 Check dimension (height, width) as per specification and drawing Approved Drawing ITR-4000-011 M W

8.6 Check handrail column is installed firmly Procedure ITR-4000-011 M W

8.7 Straightness & Alignment handrail Procedure ITR-4000-011 M W

9 Fence, Louvers, Grill and Bird Screen (if Any)

9.1 Material : accepted and conformed to specification prior installation Approved Drawing & Specification ITR-4000-012 M W

9.2 Verify Location as specified in drawing Approved Drawing ITR-4000-012 M W

9.3 Verify material are clean, undamaged & properly stored Procedure ITR-4000-012 M W

9.4 Verify partition installation : support, fixings as per drawing spec. Approved Specification, Approved Drawing & Approved Drawing ITR-4000-012 M W
Procedure
9.5 Check fence column is installed firmly Procedure ITR-4000-012 M W

9.6 Check door installed firmly and accessories installed as per drawings - specification. Approved Drawing ITR-4000-012 M W

9.7 Plumbnesss and allignment the fence Procedure ITR-4000-012 M W

10 Floor Hardener Topping

10.1 Material : accepted and conformed to specification prior installation Approved Drawing & Specification ITR-4000-013 M W

10.2 Protection for permanent finishes and fittings Procedure ITR-4000-013 M W

10.3 Condition of concrete base surfaces, shall be roughened Procedure & manufacturer standard ITR-4000-013 M W

10.4 Alignment, level and flatness Procedure ITR-4000-013 M W

10.5 Points and control joint board / beads setting (if any) Approved Drawing ITR-4000-013 M W

10.6 Application of bonding agent Procedure & manufacturer standard ITR-4000-013 M W


Approved Specification, Approved Drawing &
Procedure
10.7 Mixing of granolithic cement concrete topping using approved proportion and gauge boxes Manufacturer standard ITR-4000-013 M W

10.8 Laid floor hardener 2 to 3 hours after topping concrete laid Procedure ITR-4000-013 M W

10.9 Granolithic cement concrete test Procedure ITR-4000-013 M W

10.10 Finishing, level and flatness ± 3 mm / 1.2 M for flatness tolerance ITR-4000-013 M W

10.11 Cleaning & curing Procedure ITR-4000-013 M W

10.12 Seal for expansion / control joints (if any) Procedure ITR-4000-013 M W

Approved Specification, Approved Drawing &


ITR-4000-015 &
10 Final Visual Inspection of Building Works Approved Drawing & Procedure M W
Procedure Punchlist
COMPANY No. : ACCS-40-411-AS01-S-PLN-0201

CONTRACTOR No. : S-A000-1670-201

Contract No :

Revision: 2A

Inspection Level
REMARKS
JGC AMIN

&R R

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R R

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R R

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW

&R SW
ITR LIST

No Description

1 Material Receiving
2 Ceiling Works
3 Wall / Partition Work
3.1 Masonry : Hollow Concrete Block
3.2 Plastering
3.3 Tile Work (Wall)
3.4 Gypsum Board Partition
4 Floor Work
4.1 Tile Work (Floor)
4.2 Raise Floor
5 Doors & Windows
6 Coating Waterproofing
7 Painting for Building
8 Stair & Handrail
9 Fence, Louvers, Grill and Bird Screen (if Any)
10 Floor Hardener Topping
11 Final Visual Inspection of Building Works
12 Grouting / Mortar test
13 Waterproofing Leak test
T

ITR

ITR-GEN-001
ITR-4000-001

ITR-4000-002
ITR-4000-003
ITR-4000-004
ITR-4000-005

ITR-4000-006
ITR-4000-007
ITR-4000-008
ITR-4000-009
ITR-4000-010
ITR-4000-011
ITR-4000-012
ITR-4000-013
ITR-4000-015 & Punchlist
Subcont form Report
ITR-4000-014
ITR-GEN-001
Doc.No.:
AIR SEPARATION UNIT (ASU) PROJECT
Contract No :

SUBJECT : MATERIAL INSPECTION REPORT Project No : Rev.2A

Project AIR SEPARATION UNIT (ASU) PROJECT

Client PT. AMMAN MINERAL INDUSTRY


Location
Reff. Dwg.
Material/Equipment identification
a. Material /Equipment Name :
b. Equipment Tag Number :
c. Purcahse Order Number :
d. Suplier/ Manufacture Name :
e. Material Approval Request (MAR No) :
f. Data Sheet No :
g. Batch no (if any) :
h. Packing List :
i. Inspection Release Certificate :

NO DESCRIPTION QTY CONFORMANCE TO SPECT. REMARKS


YES NO

Prepared By: Checked / Approved By: Reviewed / Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name
Signature
Date
ITR-4000-001
AIR SEPARATION UNIT (ASU) Doc.No :
Contract No:
PROJECT

Subject : CEILING WORK Project No : Rev.2A

Project : AIR SEPARATION UNIT (ASU) PROJECT Date :

Client : PT. Amman Mineral Industri RFI No :

General

a. Area/Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification
e. Type of Ceiling (Mark the inspected item) Suspended Weather Resistant
Gypsumboard WR Board
Gypsum Tyle WR Tile
Expose

No Activities ACC REJ N/A Remarks


1 Check Material :accepted and conformed to specification prior installation
2 Marking and verification of ceiling panel layout
3 Ensure that M&E items above ceiling has been completed
4 Type and elevation of edge moldings
5 Type, size and spacing of ceiling hangers
6 Verify the location and size of ceiling mount M&E equipment / fixtures

7 Location, alignment and rigidity of ceiling suspension system


8 Elevation & Flatness of ceiling suspension system
9 Insulation board / blanket installation
10 Type and thickness of ceiling panels / boards
11 Ceiling panels / boards installation
12 Treatment of cut panel / board edges and board joints
13 Surface condition for exposed ceiling frame and panel boards

Remarks :

Prepared by Checked/ Reviewed / Witnessed by


Approved by
SUBCONTRACTOR CONTRACT COMPANY
Print Name OR

Signature

Date
ITR-4000-002
AIR SEPARATION UNIT (ASU) Doc.No :
Contract No:
PROJECT

Subject : Wall/Partition Work (Masonry : Concrete Block) Project No : Rev.2A

Project : AIR SEPARATION UNIT (ASU) PROJECT DATE :

Client : PT. AMMAN MINERAL INDUSTRI RFI.NO :

General
a. Area/Building Name
b. System / Sub-System
c. Part/ Location
d. Reference Drawing/Specification

No Activities ACC REJ N/A Remarks


1 Check Material : accepted and conformed to specification prior installation
2 Setting out, marking center & both side of block line
3 Dowels and anchors location
4 Pre-wetting of concrete block before use
5 Mixing of grout / mortar using approved proportion
6 Mortar speciment preparation as per specification
7 Alignment and plumbness of walls
8 Arrangement of stiffener columns and bond beams
9 Total Thickness Check as per specification
10 Size and location of joints, control and expansion joints
11 Ties and vertical - horisontal reinfrocement bar / mesh arrangement
12 Location and type of electrical conduit, box and sleeve pipe etc
13 Location and size of openings and penetrations
14 Grouting / Mortar test
15 Cleaning
16 Curing
Remarks :

Prepared by Checked/Approved by Reviewed / Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
ITR-4000-003
Doc.No :
AIR SEPARATION UNIT (ASU) Contract No:
PROJECT

Subject : Wall/Partition Work ( Plastering) Project No : Rev.2A

Project : AIR SEPARATION UNIT (ASU) PROJECT Date :

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification

No Activities ACC REJ N/A Remarks


1 Check Material : accepted and conformed to specification prior installation

2 Protections for permanent finishes and fittings

3 Check concealed M & E items has been installed (all embeded Material)

4 Condition of application surfaces

5 Corner and joint beads setting

6 Location and size of openings and penetrations

7 Mixing of mortar using approved proportion

8 Application of bonding agent and base coat

9 Thickness, Straightness, Flatness and Appearance

10 Cleaning around permanent finishes and fittings

11 Mortar Test

12 Curing

Remarks :

Prepared by Checked/Approved by Reviewed / Witnessed


SUBCONTRACTOR CONTRACTOR by COMPANY
Print Name

Signature

Date
ITR-4000-004
AIR SEPARATION UNIT (ASU) Doc.No :
PROJECT Contract No:

Subject : Wall/Partition Work (Tile Work for Wall) Project No : Rev.2A

Project : AIR SEPARATION UNIT (ASU) PROJECT Date :

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification

No Activities ACC REJ N/A Remarks

1 Check Material : accepted and conformed to specification prior installation

2 Layout, marking and check of substrate


3 Check location and size of concealed M&E items
4 Verify the type, pattern and layout of tiles
5 Corner, plinth and joint beads setting
Method, type, mixing ratio and application of bedding mortar / grout or
6
adhesive
7 Alignment, level and flatness / evenness of installed tiles

8 Conditions of cut tile edges and projection round embedded pipes and fitting

9 Check adhesion of tiles by sounding (void) & surface appearance


10 Check gap of tiles prior to grout application
11 Type, color and application of grout for tile joints
12 Type, color and application of seal for control joints
13 Cleaning and polishing
Remarks :

Prepared by Checked/Approved by Reviewed / Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
ITR-4000-005
AIR SEPARATION UNIT (ASU) Doc.No :
Contract No:
PROJECT

Subject : Wall/Partition Work (Gypsumboard Partition) Project No : Rev.2A

Project : AIR SEPARATION UNIT (ASU) PROJECT Date :

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification

No Activities ACC REJ N/A Remarks


1 Check Material : accepted and conformed to specification prior installation

2 Layout and marking

3 Location and size of wall openings

4 Location, alignment, spacing and rigidity of runners / studs installed Per


manufacturer's recommendation

5 Reinforcement for wall openings, wall mounted M&E items, equipment,fixtures


and fittings etc

6 Check concealed M&E items has been completed

7 Insulation board / blanket installation

8 Type and thickness of wall board

9 Wall board layout, height, number and spacing of tapping screws

10 Treatment of cut board edges, board joints and corner beads

11 Straightness and flatness

12 Expansion / control joint

13 Seal for penetrations of fire rated wall

Remarks :

Prepared by Checked/Approved by Reviewed / Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
ITR-4000-006
AIR SEPARATION UNIT (ASU) Doc.No :
PROJECT Contract No:

Subject : Tiles Work (Floor) Project No : Rev.2A

Project : AIR SEPARATION UNIT (ASU) PROJECT Date :

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification

No Activities ACC REJ N/A Remarks


1 Check Material : accepted and conformed to specification prior installation

2 Layout, marking and check of substrate

3 Check location and size of concealed M&E items

4 Verify the type, size, pattern and layout of tiles

5 Corner and joint beads setting

6 Method, type, mixing ratio and application of bedding mortar / grout or


Adhesive
7 Alignment, level and flatness / evenness of installed tiles

8 Conditions of cut tile edges and projection around embedded pipes and fitting

9 Check adhesion of tiles by sounding

10 Check gap of tiles prior to grout application

11 Type, color and application of grout for tile joints

12 Type, color and application of seal for control joints

13 Cleaning and polishing


Remarks :

Prepared by Checked/Approved by Reviewed / Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
ITR-4000-006
AIR SEPARATION UNIT (ASU) Doc.No :
PROJECT Contract No:

Subject : Tiles Work (Floor) Project No : Rev.2A

Project : AIR SEPARATION UNIT (ASU) PROJECT Date :

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification

No Activities ACC REJ N/A Remarks


1 Check Material : accepted and conformed to specification prior installation

2 Layout, marking and check of substrate

3 Check location and size of concealed M&E items

4 Verify the type, size, pattern and layout of tiles

5 Corner and joint beads setting

6 Method, type, mixing ratio and application of bedding mortar / grout or


Adhesive
7 Alignment, level and flatness / evenness of installed tiles

8 Conditions of cut tile edges and projection around embedded pipes and fitting

9 Check adhesion of tiles by sounding

10 Check gap of tiles prior to grout application

11 Type, color and application of grout for tile joints

12 Type, color and application of seal for control joints

13 Cleaning and polishing


Remarks :

Prepared by Checked/Approved by Reviewed / Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
ITR-4000-007
AIR SEPARATION UNIT (ASU) Doc.No :
PROJECT Contract No:

Subject : Raised Floor Project No : Rev.2A

Project : AIR SEPARATION UNIT (ASU) PROJECT Date :

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification

No Activities ACC REJ N/A Remarks


1 Check Material : accepted and conformed to specification prior installation
2 Conditions of sub floor
3 Marking and verification of panel layout
4 Location and elevation of steel support for instrument / electrical panel
5 Alignment, elevation and rigidity of pedestals installed per manufacturer's
recommendation.
6 Location and number of floor openings / penetrations
7 Level and flatness check of floor
8 Treatment of cut panel edges
9 Expansion gap at all abutments with seal
10 Seal for penetrations of floor panels
11 Anti static
12 Cleaning
Remarks :

Prepared by Checked/Approved by Reviewed / Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
ITR-4000-008
Doc.No :
AIR SEPARATION UNIT (ASU) Contract No:
PROJECT

Subject : Doors & windows Project No : Rev.2A

Project : AIR SEPARATION UNIT (ASU) PROJECT Date :

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification

No Activities ACC REJ N/A Remarks


1 Check Material : accepted and conformed to specification prior installation
2 Setting out
3 Location and size of structural opening
4 Type, size, location and orientation of door / window being installed
5 Conditions of anchors/fasteners for frame
6 Grouting for threshold
7 Alignment plumb elevation and orientation
8 Rigidity of frame fit-up / fixing with structure
9 Grouting for gap between frame and structure
10 Paint finish
11 Type of glass and face direction for installation
12 Bead / Seal conditions for glass panels
13 Type, location and orientation of Hardware fitting
14 Earth bonding
15 Labels for fire rated doors / windows
16 Functional / operational check
Remarks :

Prepared by Checked/Approved by Reviewed / Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
ITR-4000-009
Doc.No :
AIR SEPARATION UNIT (ASU) Contract No:
PROJECT

Subject : Waterproofing Project No : Rev.2A

Project : AIR SEPARATION UNIT (ASU) PROJECT Date :

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification

No Activities ACC REJ N/A Remarks


1 Check Material : accepted and conformed to specification prior installation
2
Location of up-stands, pipe penetration, fondation bases, raisers, drain etc
3 Cant installation / Corner fillet sand cement mortar
4 Surface conditions (dry, clean, smooth etc.)
5 Type & application of waterproofing
6 Waterproofing membrane direction, lap length, joint treatment etc
7 Installation of waterproofing membrane at corners, risers, end stop,
penetrations and drain
8 Water leak test:
9 Installation of insulation board, vapor barrier, fabric etc
10 Seal for joints and gaps
11 Protection gravel
12 Protection concrete / mortar
Remarks :

Prepared by Checked/Approved by Reviewed / Witnessed


SUBCONTRACTOR CONTRACTOR by COMPANY
Print Name

Signature

Date
ITR-4000-010
Doc.No :
AIR SEPARATION UNIT (ASU) Contract No:
PROJECT

Subject : Painting Project No : Rev.2A

Project : AIR SEPARATION UNIT (ASU) PROJECT Date :

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification

No Activities ACC REJ N/A Remarks


1 Check Material : accepted and conformed to specification prior installation

2 Mock up

3 Check Surface condition, moisture content, flatness, wall filler already applied

4 Ensure the correct tools is implemented as manufacturer recommendation

5 Ensure the application condition (Weather, Relative Humidity) as per


manufacturng standard & specification
6 Coat thickness each layer (wet thickness)

Remarks :

Prepared by Checked/Approved by Reviewed / Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
ITR-4000-011
Doc.No :
AIR SEPARATION UNIT (ASU) Contract No:
PROJECT

Subject : Stair & Handrail Project No : Rev.2A

Project : AIR SEPARATION UNIT (ASU) PROJECT Date :

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification

No Activities ACC REJ N/A Remarks


1 Material : accepted and conformed to specification prior installation

2 Verify location as specified in drawing

3 Verify material are clean, undamage & properly stored

4 Verify stair & handrail installation : support, fixings as per drawing and
specification
5 Check dimension (height, widht) as per specification and drawing

6 Check handrail column is installed firmly

7 Straightness & Alignment handrail

Remarks :

Prepared by Checked/Approved Reviewed / Witnessed by


SUBCONTRACTOR byCONTRACTOR COMPANY
Print Name

Signature

Date
ITR-4000-012
Doc.No :
AIR SEPARATION UNIT (ASU) Contract No:
PROJECT

Subject : Fence & Bird Screen Project No : Rev.2A

Project : AIR SEPARATION UNIT (ASU) PROJECT Date :

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification

No Activities ACC REJ N/A Remarks


1 Material : accepted and conformed to specification prior installation

2 Verify Location as specified in drawing

3 Verify material are clean, undamage & properly stored

4 Verify partition installation : support, fixings as per drawing spec.

5 Check fence column is installed firmly

6 Check door installed firmly and accesories installed as per drawings -


specification.
7 Plumb the fence and door

Remarks :

Prepared by Checked/ Approved by Reviewed / Witnessed by

SUBCONTRACTOR CONTRACTOR COMPANY


Print Name

Signature

Date
ITR-4000-013
Doc.No :
AIR SEPARATION UNIT (ASU) Contract No:
PROJECT

Subject : Floor Hardener Topping Project No : Rev.2A

Project : AIR SEPARATION UNIT (ASU) PROJECT Date :

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification

No Activities ACC REJ N/A Remarks


1 Check Material : accepted and conformed to specification prior installation

2 Check concealed M & E items has been completed


3 Protections for permanent finishes and fittings
4 Condition of application surfaces
5 Points and control joint board / beads setting
6 Application of bonding agent and base coat
7 Wire mesh / re-bar installation
8 Mixing of mortar using approved proportion
9 Prepation of speciment
10 Mortar Test at a delivery (Slump)
11 Finishing, level and flatness
12 Cleaning around permanent finishes and fitting
13 Curing
14 Seal for expansion / control joints
Remarks :

Prepared by Checked/ Reviewed / Witnessed by


SUBCONTRACTOR Approved by
CONTRACT COMPANY
Print Name OR

Signature

Date
ITR-4000-014
Doc.No :
AIR SEPARATION UNIT (ASU) Contract No:
PROJECT

Project No : Rev.2A
Subject : LEAKAGE WATER TEST FOR ROOFING

Project : AIR SEPARATION UNIT (ASU) PROJECT Date :

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification

Start Finish Result Note


Grid Line /
No Reference Drawing No Filling Media
Room Height Height
Time Time ACC REJ
(cm) (cm)
1

Remarks :

Prepared by Checked/Approved by Reviewed/Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
ITR-4000-015
Doc.No : Contract No:
AIR SEPARATION UNIT (ASU)
PROJECT

Subject : Final Inspection Project No : Rev.2A

Date :
Project : AIR SEPARATION UNIT (ASU) PROJECT

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification

STATUS
No Activities ITR No Not Remarks
Complete N/A
Complete
1 Ceiling Works
2 Wall / Partition Work
2.1 Masonry : Hollow Concrete Block
2.2 Plastering
2.3 Tile Work (Wall)
2.4 Gypsum Board Partition
3 Floor Work
3.1 Tiles Work (Floor)
3.2 Raise Floor
5 Doors & Windows
6 Waterproofing
7 Mortar screed
8 Painting for Building
9 Furniture
10 Stair & Handrail
11 Ladder
12 Fence and Bird Screen (if Any)
13 Wallpaper (if Any)
14 Metal Light Partition(if Any)
15 Grating
16 GRC Light Ornament

Prepared by Checked/ Reviewed /


SUBCONTRACTOR Approved by
CONTRACTOR Witnessed
COMPANYby
Print Name

Signature

Date
AIR SEPARATION UNIT (ASU) PROJECT

SUBJECT : PUNCH LIST REPORT

Project Title : AIR SEPARATION UNIT (ASU) PROJECT

Client : PT. Amman Mineral Industry

Area / Location Ref. Drawing No : Punch List No


: Unit / Facility

Item Punch List Category


No. Punch List Description A/B/C/D Approved
JGC AMIN

Note Category Description : : Signifies that the Punch list item, defect, or omission must be repaired or completed before issuance of SYSTEM CONSTRUCTION COMP
ABCD : Signifies that the Punch list item, defect,or omission may be completed after Construction Completion during Pre-Commissioning. All Categ
HANDOVER CERTIFICATE.
: Signifies that the Punch list item, defect, or omission can be repaired and/or completed after System HANDOVER, but must be done before
CONTRACTOR and COMPANY.
: Recognized as an item that is desirable to Operations, but is outside the project work scope agreement, is not operationally critical to the fa
Category "D" items will not prevent HANDOVER, TURNOVER, or ACCEPTANCE.

SUBCONTRACTOR CONTRACTOR
Prepared As Punch List Completed
Print Name

Signature

Date
Report No
Doc. No :

Contract No:

Project No: Rev.2A

System / Sub- :
System
Area :
Reference Dwg :
:
:

Target Date Accepted


Date Cleared S/C JGC AMIN Remarks

YSTEM CONSTRUCTION COMPLETION CERTIFICATE.


ing Pre-Commissioning. All Category "B" items must be corrected before issuance of a System

DOVER, but must be done before TURNOVER. Deviations must be agreed to in writing between

s not operationally critical to the facility, process, or people, and willbe rectified at COMPANY expense.

ACTOR COMPANY
Completed As Punch List Completed
Inspection and Test Plan for Building
AIR SEPARATION UNIT (ASU) PROJECT
Plumbing Work
Contractor : JGC Indonesia Location : Sumbawa, West Nusa Tenggara,
Work Scope : Building

A W : Approval R : Review S/C : Sub-Contractor/Vendor


H V : Witness SW : Spot Witness P : Provide JGC : JGC Indonesia
: Hold Point M : Monitor/Surveillance AMIN : PT. Amman Mineral Industry
: Verification

Activity No. Activity Description Reference Document Acceptance Criteria

PREPARATION
A

Field Material Inspection


1

Material Approval Request (MAR),


1.1 Receiving Approved Design Drawing and Specification Approved Design Drawing and
Specification

ON GOING CONSTRUCTION
B

Installation
2

2.1 Cold Water Pipe Installation

Black Water Pipe Installation


2,2 As per Approved Procedures, Approved
Approved Procedures, Approved Design Drawing
Design Drawing
Grey Water Pipe Installation
2.3

Vent Pipe Installation


2.4

Plumbing & Sanitary Fixtures Installation Approved Procedures, Approved Design Drawing As per Approved Procedures, Approved
2.5 Design Drawing

Bio STP Installation


2.6

Rainwater Drainage Installation


2.7

TEST
C

Leakage Test (Black & Grey Water Piping)


3

As per Approved Procedures, Approved


4 Pressure Test (Cold Water Piping) Approved Procedures, Approved Design Drawing
Design Drawing

Water Flow Test


5

A W : Approval R : Review S/C : Sub-Contractor/Vendor


H V : Witness SW : Spot Witness P : Provide JGC : JGC Indonesia
: Hold Point M : Monitor/Surveillance AMIN : PT. Amman Mineral Industry
: Verification

Activity No. Activity Description Reference Document Acceptance Criteria

D FINAL INSPECTION/ RE-INSTATEMENT Approved Design Drawing Approved Design Drawing


Plan for Building COMPANY No.

CONTRACTOR No. : S-A000-1670-201


Contract No
Rev.2A

Inspection Level
Verify Doc. REMARKS
S/C JGC AMIN

ITR-GEN-001 M W, R R

ITR-4000-601 M W, R SW

ITR-4000-602 M W, R SW

ITR-4000-603 M W, R SW

ITR-4000-604 M W, R SW

ITR-4000-605 M W, R SW

ITR-4000-606 M W, R SW

ITR-4000-607 M W, R SW

ITR-4000-608 M W, R SW

ITR-4000-609 M W, R SW

ITR-4000-610 M W, R SW

Inspection Level
Verify Doc. REMARKS
S/C JGC AMIN

ITR-4000-611 & Punchlist M W, R SW, R


AIR SEPARATION UNIT
(ASU) PROJECT

RFI. No :
Issue Date :
Rev No : Rev.2A
REQUEST FOR INSPECTION (RFI)
Attn  : Mr…….                                      Project Construction Manager
Project Title : AIR SEPARATION UNIT (ASU) PROJECT
Gentlement,
We would like to have your presence for inspection according to the following schedules.
Civil Telecomunication Instrument Mech. Static
Piping Electrical Pipeline Mech. Rotating
Date and time Place / Area Inspection Item Remarks

Comments :

Prepared by Checked / Approved by Reviewed/Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name
Signature

Date
ITR LIST
No Activity Description

1 Material Receiving Inspection

2 Cold Water Pipe Installation

4 Black Water Pipe Installation

5 Grey Water Pipe Installation

6 Vent Pipe Installation

7 Plumbing & Sanitary Fixtures Installation

8 Bio STP Installation

10 Rainwater Drainage Installation

12 Leakage Test (Black & Grey Water Piping) for Plumbing Work

13 Pressure Test (Cold Water Piping) for Plumbing Work

14 Water Flow Test for Plumbing Work

15 FINAL INSPECTION
Verify Doc.

ITR-GEN-001

ITR-4000-601

ITR-4000-602

ITR-4000-603

ITR-4000-604

ITR-4000-605

ITR-4000-606

ITR-4000-607

ITR-4000-608

ITR-4000-609

ITR-4000-610

ITR-4000-611 &
Punchlist
AIR SEPARATION UNIT (ASU) PROJECT

SUBJECT : MATERIAL RECEIVING INSPECTION REPORT (MRIR)


Project : AIR SEPARATION UNIT (ASU) PROJECT

Location :                                                                             
Material/Equipment Identification
a. Material /Equipment Name :
b. Equipment Tag Number :
c. Purchase Order Number :
d. Suplier / Manufacture Name :
e. Material Approval Request (MAR No) :
f. Datasheet No :
g. Batch no (if any) :
h. Packing List :
i. Inspection Release Certificate :

NO DESCRIPTION QTY CONFORMANCE TO SPEC


YES

Prepared By: Checked / Approved By:


SUBCONTRACTOR CONTRACTOR
Print Name

Signature

Date
ITR-GEN-001
Doc.No.:

Contract No :

Project No: Rev.2A


Reff.Dwg. :                                         
Date :                                         

NFORMANCE TO SPEC REMARKS


NO

Checked / Approved By: Reviewed / Witnessed by


CONTRACTOR COMPANY

33 / 103
ITR-4000-601
Doc.No :
AIR SEPARATION UNIT (ASU) Contract No:
PROJECT

Subject : COLD WATER PIPE INSTALLATION Project No : Rev.2A

Project : AIR SEPARATION UNIT (ASU) PROJECT Date :

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification

No Activities ACC REJ N/A Remark


1 Verify Pipe Route is correct as per approved drawings

2 Verify Pipe Accessories have been completed ( Valve, Automatic Air Vent, etc.)
as per design drawing.

3 Verify Material of Pipe is correct as per approved specification

4 Verify Pipe Size is correct as per approved drawings

5 Verify Pipe Level is correct as per approved drawings

6 Verify Tightening Connection of Pipes

7 Verify Hangers and Pipe Supports

8 Verify Penetration Pipe On Wall / Roof / Floor

9 Verify piping identification is correct

Remarks :

Prepared by Checked/Approved by Reviewed/Witnessed


SUBCONTRACTOR CONTRACTOR by, COMPANY
Print Name

Signature

Date
ITR-4000-602
Doc.No :
AIR SEPARATION UNIT (ASU) Contract No:
PROJECT

Subject : BLACK WATER PIPE INSTALLATION Project No : Rev.2A

Project : AIR SEPARATION UNIT (ASU) PROJECT Date :

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification

No Activities ACC REJ N/A Remark


1 Verify Pipe Route is correct as per approved drawings

2 Verify Pipe Accessories have been completed ( Clean Out, Vent Cap etc.) as per
design drawing.
3 Verify Material of Pipe is correct as per approved speciffication
4 Verify Pipe Size is correct as per approved drawings
5 Verify Pipe Level is correct as per approved drawings
6 Verify Pipe Slope is correct
7 Verify Tightening Connection of Pipes
8 Verify Hangers and Pipe Supports
9 Verify Penetration Pipe On Wall / Roof / Floor
10 Verify Piping Identification is correct
Remarks :

Prepared by Checked/Approved by Reviewed/Witnessed by,


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
ITR-4000-603
Doc.No :
AIR SEPARATION UNIT (ASU) Contract No:
PROJECT

Subject : GREY WATER PIPE INSTALLATION Project No : Rev.2A

Project : AIR SEPARATION UNIT (ASU) PROJECT Date :

:
Client : PT. AMMAN MINERAL INDUSTRI RFI No

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification

No Activities ACC REJ N/A Remark


1 Verify Pipe Route is correct as per approved drawings

2 Verify Pipe Accessories have been completed ( Clean Out, Trap, Vent Cap
etc.) as per design drawing.
3 Verify Material of Pipe is correct as per approved speciffication
4 Verify Pipe Size is correct as per approved drawings
5 Verify Pipe Level is correct as per approved drawings
6 Verify proper venting on Black Water Piping Installation
7 Verify proper venting on Grey Water Piping Installation
8 Verify Tightening Connection of Pipes
9 Verify Hangers and Pipe Supports
10 Verify location of Clean Out is correct
11 Verify Penetration Pipe On Wall / Roof / Floor
12 Verify Piping Identification is correct
Remarks :

Prepared by Checked/Approved by Reviewed/Witnessed by,


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
ITR-4000-604
Doc.No :
AIR SEPARATION UNIT (ASU) Contract No:
PROJECT

Subject : VENT PIPE INSTALLATION Project No : Rev.2A

Date :
Project : AIR SEPARATION UNIT (ASU) PROJECT

:
Client : PT. AMMAN MINERAL INDUSTRI RFI No

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification
e. Equipment Tag Number
f. Manufacture Name
g. Model Number
h. Serial Number

No Activities ACC REJ N/A Remark


1 Verify Pipe Route is correct as per approved drawings

2 Verify Pipe Accessories have been completed ( Vent Cap, etc.) as per design
drawing.
3 Verify Material of Pipe is correct as per approved speciffication
4 Verify Pipe Size is correct as per approved drawings
5 Verify Pipe Level is correct as per approved drawings
6 Verify proper venting on Black Water Piping Installation
7 Verify proper venting on Grey Water Piping Installation
8 Verify Tightening Connection of Pipes
9 Verify Hangers and Pipe Supports
10 Verify Vent Cap location is correct
11 Verify Penetration Pipe On Wall / Roof / Floor
12 Verify Piping Identification is correct
Remarks :

Prepared by Checked/Approved by Reviewed/Witnessed by,


SUBCONTRACTOR CONTRACTOR COMPANY

Print Name

Signature
Date
ITR-4000-605
Doc.No :
AIR SEPARATION UNIT (ASU) Contract No:
PROJECT

Subject : PLUMBING & SANITARY FIXTURES INSTALLATION Project No : Rev.2A

Project : AIR SEPARATION UNIT (ASU) PROJECT Date :

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification
e. Equipment Tag Number
f. Manufacture Name
g. Model Number
h. Serial Number

No Activities ACC REJ N/A Remark


1 Verify Type of Plumbing Fixture is correct as per specification

2 Verify Location Pipe Sleeve of Plumbing Fixture as per drawing


Verify Location of Plumbing Fixture as per drawing, and clearance between
3 plumbing fixtures and from fixtures to adjacent wall are correct.

4 Verify alignment and level of Plumbing Fixture as per drawing


5 Penetration On Wall / Roof/ Floor have been caulked.
6 Verify cleanliness of plumbing fixture installation.
Remarks :

Prepared by Checked/Approved by Reviewed/Witnessed


by,
SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
ITR-4000-606
Doc.No :
AIR SEPARATION UNIT (ASU) Contract No:
PROJECT

Subject : BIO STP INSTALLATION Project No : Rev.2A

Project Date :
: AIR SEPARATION UNIT (ASU) PROJECT

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification
e. Equipment Tag Number
f. Manufacture Name
g. Model Number
h. Serial Number

No Activities ACC REJ N/A Remark


1 Ensure Biotech Tank is not damage

Verify excavation was done according to dimensions specified for each type of
2 tank.

3 Ensure excavation bottom has been covered with a 15 cm-thick layer of sand,
and correctly leveled.
4 A 15 cm-thick layer of concrete has been poured over the sand bed and correctly
leveled.
5 Verify Aeration Pipe in Biotech Tank has been installed and support correctly

6 Verify slope and support of black water piping to inlet pipe of Biotech Tank is
correct.
7 Tank input and output pipes have been installed correctly.

8 A vent pipe has been installed correctly at top of tank.

Verify Biotech Tank has been filled completely with water before backfill their
9 surrounding area.

10 Ensure debris-free fine ballast shall be used as excavation backfill material.

11 Ensure tank integrity was not compromised during compaction.


12 Ensure excavation was back filled without compacting directly over tank or pipes.

13 Verify concrete slab was built over septic tank excavation area is correct.

14 Verify a concrete cover was installed over septic tank inspection lid is correct.

15 Verify Blower has been installed correctly.

16 Verify Sewage Water Lift Pump has been installed correctly.

Remarks :

Prepared by Checked/Approved by Reviewed/Witnessed by,


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature
Date
ITR-4000-607
Doc.No :
AIR SEPARATION UNIT (ASU) Contract No:
PROJECT

Subject : RAINWATER DRAINAGE INSTALLATION Project No : Rev.2A

Date :
Project : AIR SEPARATION UNIT (ASU) PROJECT

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification
e. Equipment Tag Number
f. Manufacture Name
g. Model Number
h. Serial Number

No Activities ACC REJ N/A


1 Verify Pipe Route is correct

2 Verify Pipe Accessories have been completed ( Roof Drain etc.) as per design
drawing.
3 Verify Material of Pipe is correct
4 Verify Pipe Size is correct
5 Verify Pipe Level is correct
6 Verify Pipe Slope is correct
7 Verify Tightening Connection of Pipes
8 Verify Hangers and Pipe Supports
9 Verify Penetration Pipe On Wall / Roof / Floor
10 Verify Piping Identification is correct
Remarks :

Prepared by Checked/Approved by Reviewed/Witnessed by,


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
Rev.2A

Remarks
ITR-4000-608
AIR SEPARATION UNIT (ASU) Doc.No :
Contract No:
PROJECT

Subject : LEAKAGE WATER TEST FOR PLUMBING WORK Project No : Rev.2A

Date :
Project : AIR SEPARATION UNIT (ASU) PROJECT

:
Client : PT. AMMAN MINERAL INDUSTRI RFI No

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification
e. Equipment Tag Number
f. Manufacture Name
g. Model Number
h. Serial Number

Start Finish Result


No Line No Reference Drawing No Filling Media
Height Height
Time Time ACC REJ
(cm) (cm)
1

Remarks :

Prepared by Checked/Approved by Reviewed/Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
Rev.2A

Note
ITR-4000-609
Doc.No :
AIR SEPARATION UNIT (ASU) Contract No:
PROJECT

Subject : PRESSURE TEST FOR PLUMBING WORK Project No : Rev.2A

Date :
Project : AIR SEPARATION UNIT (ASU) PROJECT

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification
e. Equipment Tag Number
f. Manufacture Name
g. Model Number
h. Serial Number
Spesific
a. Piping Class
b. P & ID No
c. Design Pressure
d. Test Pressure
e. Test Medium
f. Holding Time
g. Pressure Gauge No & Calibration
Validity

Start Finish Result


Filling
No Line No Reference Drawing No
Media
Press Time Press Time ACC REJ

Remarks :

Prepared by Checked/Approved by Reviewed/Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
Rev.2A

Note
ITR-4000-610
Doc.No :
Contract No:
AIR SEPARATION UNIT (ASU) PROJECT

Project No :
Subject : WATER FLOW TEST FOR PLUMBING WORK Rev.2A

Date :
Project : AIR SEPARATION UNIT (ASU) PROJECT

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location

d. Reference Drawing/Specification

e. Equipment Tag Number


f. Manufacture Name
g. Model Number
h. Serial Number

Plumbing Fixture No. Plumbing Fixture Water Flow Test of Plumbing RESULT
No Reference Drawing No. Name Fixture
ACC REJ N/A

Flow of Supply Water


Flow of Drainage Water
Flow of Supply Water
Flow of Drainage Water
Flow of Supply Water
Flow of Drainage Water
Remarks

Prepared by Checked/Approved by Reviewed / Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
Remarks
ITR-4000-611
Doc.No :
AIR SEPARATION UNIT (ASU) Contract No:
PROJECT

Subject : Final Inspection Project No : Rev.2A

Date :
Project : AIR SEPARATION UNIT (ASU) PROJECT

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General

a. Area/ Building Name


b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification
We certify the scope of work definied in the above mentioned ITP is completed and is verified in accordance with attached list of ITR's. All acceptence
criteria described in the above mentioned ITP are met.

STATUS
No Activities ITR No Remarks
Complete Not Complete N/A
1 Cold Water Pipe Installation
2 Black Water Pipe Installation
3 Grey Water Pipe Installation
4 Vent Pipe Installation
5 Plumbing & Sanitary Fixtures Installation
6 Bio STP Installation
7 Panel STP Installation
8 Rainwater Drainage Installation
9 Leakage Test (Black & Grey Water Piping) For Plumbing
10 Work
Pressure Test (Cold & Hot Water Piping) For Plumbing Work
11 Water Flow Test For Plumbing Work
Remarks

Prepared by Checked/Approved by Reviewed / Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
Report No :

Doc. No :
AIR SEPARATION UNIT (ASU) PROJECT
Contract No:

SUBJECT : PUNCH LIST REPORT Project No:

Project Title : AIR SEPARATION UNIT (ASU) PROJECT System / Sub-


System
Client : PT. Amman Mineral Industry Area
Reference Dwg
Area / Location Ref. Drawing No : Punch List No Unit / :
: Facility :

Item Punch List Category Target Date


No. Punch List Description A/B/C/D Approved Date Cleared
JGC AMIN

Note Category Description : : Signifies that the Punch list item, defect, or omission must be repaired or completed before issuance of SYSTEM CONSTRUCTION COMPLETION CERTIFICATE.
ABC : Signifies that the Punch list item, defect,or omission may be completed after Construction Completion during Pre-Commissioning. All Category "B" items must be correc
D CERTIFICATE.
: Signifies that the Punch list item, defect, or omission can be repaired and/or completed after System HANDOVER, but must be done before TURNOVER. Deviations m
and COMPANY.
: Recognized as an item that is desirable to Operations, but is outside the project work scope agreement, is not operationally critical to the facility, process, or people, and
items will not prevent HANDOVER, TURNOVER, or ACCEPTANCE.

SUBCONTRACTOR CONTRACTOR
Prepared As Punch List Completed
Print Name

Signature

Date
Report No :

Doc. No :

Contract No:

Project No: Rev.2A

System / Sub- :
System
Area :
Reference Dwg :

Date Accepted
Cleared S/C JGC AMIN Remarks

TION COMPLETION CERTIFICATE.


ng. All Category "B" items must be corrected before issuance of a System HANDOVER

e done before TURNOVER. Deviations must be agreed to in writing between CONTRACTOR

tical to the facility, process, or people, and will be rectified at COMPANY expense. Category "D"

COMPANY
As Punch List Completed
AIR SEPARATION UNIT (ASU) INSPECTION AND TEST PLAN (ITP) FIRE
PROJECT PROTECTION SYSTEM FOR BUILDING

Contractor : JGC Indonesia Location : Sumbawa, West Nusa Tenggara, Indonesia


Work Scope : Building

A W : Approval R : Review S/C : Sub-Contractor/Vendor


H V : Witness SW : Spot Witness P : Provide JGC : JGC Indonesia
: Hold Point M : Monitor/Surveillance AMIN : PT. Amman Mineral Industry
: Verification

Activity No. Activity Description Reference Document

1 MATERIAL RECEIVING INSPECTION

Approved Specification, Packing List / Material


1.1 Material Receiving Inspection
Certificate

2
2.1
PORTABLE FIRE EXTINGUISHER

Final inspection of Portable Fire Extinguisher Installation Approved Drawing


ION AND TEST PLAN (ITP) FIRE COMPANY No.

TION SYSTEM FOR BUILDING CONTRACTOR No.

CONTRACT NO

West Nusa Tenggara, Indonesia Rev.2A

ndor

al Industry

Inspection Level
Acceptance Criteria Verify Doc. REMARKS
S/C JGC AMIN

ITR-GEN-001
As per Approved Specification, Packing List / Material
M W,R R
Certificate

As per Approved Drawing ITR-4000-401 M W,R SW, R


AIR SEPARATION UNIT
(ASU) PROJECT

RFI. No :
Issue Date :
Rev No :
REQUEST FOR INSPECTION (RFI)
Attn  : Mr…….                                      Project Construction Manager
Project Title : AIR SEPARATION UNIT (ASU) PROJECT
Gentlement,
We would like to have your presence for inspection according to the following schedules.
Civil Telecomunication Instrument Mech. Static
Piping Electrical Pipeline Mech. Rotating
Date and time Place / Area Inspection Item Remarks

Comments :

Prepared by Checked / Approved by Reviewed/Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name
Signature

Date
ITR LIST
No ITR Description

1 MATERIAL RECEIVING INSPECTION REPORT


2 INSTALLATION CHECK PORTABLE FIRE EXTINGUISHER
ITR No

ITR-GEN-001
ITR-4000-401
AIR SEPARATION UNIT (ASU) PROJECT

SUBJECT : MATERIAL RECEIVING INSPECTION REPORT


Project AIR SEPARATION UNIT (ASU) PROJECT
Client PT. Amman Mineral Industry
Location                                                                        Reff.Dwg.                                                                       
Material/Equipment Identification
a. Material /Equipment Name :
b. Equipment Tag Number :
c. Purchase Order Number :
d. Suplier / Manufacture Name :
e. Material Approval Request (MAR No) :
f. Datasheet No :
g. Batch no (if any) :
h. Packing List :
i. Inspection Release Certificate :

NO DESCRIPTION QTY CONFORMANCE TO SPEC


YES

Prepared By:
SUBCONTRACTOR
Print Name
Signature

Date
SU) PROJECT ITR-GEN-001
Doc.No.:

Contract No :

Project No :

                                               

CONFORMANCE TO SPECT. REMARKS


YES NO

Checked / Approved By: Reviewed / Witnessed by


CONTRACTOR COMPANY

49 / 103
ITR-4000-401
Doc.No : Contract No:
AIR SEPARATION UNIT (ASU)
PROJECT

Subject : INSTALLATION CHECK PORTABLE FIRE EXTINGUISHER Project No : Rev. 2A

Date :
Project : AIR SEPARATION UNIT (ASU) PROJECT

Client : PT. AMMAN MINERAL INDUSTRI RFI No :

General
a. Area/ Building Name
b. System / Sub-System
c. Part/Location
d. Reference Drawing/Specification
e. Equipment Tag Number
f. Manufacture Name
g. Model Number
h. Serial Number

No Activities ACC REJ N/A

1 Check the Portable Fire Extinguisher according to approved specification

2 Check the Portable Fire Extinguisher is installed as per approved drawings

3 Check tag number of fire extinguisher as per approved drawings

4 Check the safety sign showing the location of fire extinguisher is installed above each
extinguisher
5 Check Portable Fire Extinguisher is clean and undamaged

6 Check easy access available for Portable Fire Extinguisher location

7 Check sign already installed

8 Ensure the pressure of portable fire extinguisher still in good condition and ready for used

9 Ensure the tagging already installed and correct

Remarks :

Prepared by Checked/Approved Reviewed/Witnessed


SUBCONTRACTOR byCONTRACTOR by, COMPANY
Print Name

Signature

Date
Rev. 2A

REMARKS
AIR SEPARATION UNIT (ASU) PROJECT

SUBJECT : PUNCH LIST REPORT

Project Title : AIR SEPARATION UNIT (ASU) PROJECT

Client : PT. Amman Mineral Industry

Area / Location Ref. Drawing No : Punch List No Unit /


: Facility

Item Punch List Description Punch List Category


No. A/B/C/D

Note Category Description : : Signifies that the Punch list item, defect, or omission must be repaired or completed before issuance of SYSTEM CONSTRUC
AB : Signifies that the Punch list item, defect,or omission may be completed after Construction Completion during Pre-Commission
CD CERTIFICATE.
: Signifies that the Punch list item, defect, or omission can be repaired and/or completed after System HANDOVER, but must b
CONTRACTOR and COMPANY.
: Recognized as an item that is desirable to Operations, but is outside the project work scope agreement, is not operationally c
Category "D" items will not prevent HANDOVER, TURNOVER, or ACCEPTANCE.

SUBCONTRACTOR CONTRACTOR
Prepared As Punch List
Print Name

Signature

Date
Report No :

Doc. No :
PROJECT
Contract No:

Project No:

System / Sub- :
System
Area :
Reference Dwg :
Punch List No Unit / :
Facility :

Punch List Category Target Date Accepted Remarks


Approved Date Cleared S/C JGC AMIN
JGC AMIN

d before issuance of SYSTEM CONSTRUCTION COMPLETION CERTIFICATE.


ruction Completion during Pre-Commissioning. All Category "B" items must be corrected before issuance of a System HANDOVER

eted after System HANDOVER, but must be done before TURNOVER. Deviations must be agreed to in writing between

ork scope agreement, is not operationally critical to the facility, process, or people, and will be rectified at COMPANY expense.

CONTRACTOR COMPANY
s Punch List Completed As Punch List Completed

51 / 103
AIR SEPARATION UNIT (ASU) PROJECT Inspection and Test Plan COMPANY No.

Electrical Work for Buiding & Infrastructure CONTRACTOR No.

Contract No.

Contractor : JGC Indonesia Location : Sumbawa, West Nusa Tenggara


Work Scope : Building

A W : Approval R : Review S/C : SUBCONTRACTOR


H V : Witness SW : Spot Witness P : Provide JGC : JGC INDONESIA
: Hold Point M : Monitor AMIN : PT. AMMAN MINERAL INDUSTRY
: Verification

Inspection Level
Activity No. Activity Description Reference Document Acceptance Criteria Verify Doc.
S/C

1 CABLE TRAY

1.1 PREPARATION

a). Material receiving inspection Data Sheet, Material certificate, DO,PO Material specification, Material ITR-GEN-001 M
certificate, DO,PO

1.2 INSTALLATION

Complied with approve drawings and


1 Inspection of cable tray support installation Installation details, Layout drawing Installation Detail ITR-4000-201 M

Complied with approve drawings and


2 Inspection of cable tray installation Installation details, Layout drawing Installation Detail ITR-4000-201 M

3 Completeness check of installation (fittings & accessories) Complied with approve drawings and
Installation details, Layout drawing Installation Detail ITR-4000-201 M

INSTALLATION FOR ELECTRICAL CABLES INSIDE BUILDING


2

2.1 PREPARATION

Material specification, Material


a). Material receiving inspection Data Sheet, Material certificate, DO,PO certificate, DO,PO ITR-GEN-001 M

Insulation Resistance /Continuity tests and Inspection of b). cables Cable drum schedule/cable schedule, Manufacturer ’s Complied with approve drawings and
before installation (on drum ), prior to release to instructions Installation Detail ITR-4000-204 M
site for installation

2.2 CABLE INSTALLATION INSIDE BUILDING

a). Cable glanding Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-202 M
Drawing,
b). Cable Termination Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-202 M
Drawing,
c). Cable Identification/markers Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-202 M
Drawing,

2.3 TESTING

a). Insulation Resistance and Continuity test after glanding and termination As Approved Procedure & Design
Approved Procedure & Design Drawing Drawing, ITR-4000-202 M
COMPANY No.

CONTRACTOR No.

Contract No.

Rev. 2A

Inspection Level
REMARKS
JGC AMIN

W,R R

W,R SW , R

W,R SW , R

W,R SW , R

W,R R

W,R R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW, R
AIR SEPARATION UNIT (ASU) PROJECT Inspection and Test Plan COMPANY No.

Electrical Work for Buiding & Infrastructure CONTRACTOR No.

Contract No.

Contractor : JGC Indonesia Location : Sumbawa, West Nusa Tenggara


Work Scope : Building

A W : Approval R : Review S/C : SUBCONTRACTOR


H V : Witness SW : Spot Witness P : Provide JGC : JGC INDONESIA
: Hold Point M : Monitor AMIN : PT. AMMAN MINERAL INDUSTRY
: Verification

Inspection Level
Activity No. Activity Description Reference Document Acceptance Criteria Verify Doc.
S/C

3 CONDUIT INSTALLATION

3.1 PREPARATION

a). Material receiving inspection Data Sheet, Material certificate, DO,PO Material specification, Material ITR-GEN-001 M
certificate, DO,PO

3.2 INSTALLATION

a). Conduit support installation check


Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-205 M
Drawing,
b) Conduit & fitting installation check
Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-205 M
Drawing,
c) Conduit system bonding check
Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-205 M
Drawing,
d) Check for conduit wall penetration
Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-205 M
Drawing,
e) Final Inspection Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-205 M
Drawing,

4 POWER DISTRIBUTION SYSTEM

4.1 PREPARATION

Data Sheet, Material specification,


a). Material receiving inspection Data Sheet, Material certificate, DO,PO Material certificate, DO,PO ITR-GEN-001 M

4.2 INSTALLATION

Verify name plate details of small power devices, small a). power As Approved Procedure & Design
distribution boards, sockets outlets and welding Approved Procedure & Design Drawing Drawing, ITR-4000-205 M
outlets

As Approved Procedure & Design


b). Installation of Junction Boxes Approved Procedure & Design Drawing Drawing, ITR-4000-205 M

Installation of Lighting and small power distribution boards and power


c). As Approved Procedure & Design
devices Approved Procedure & Design Drawing Drawing, ITR-4000-205 M

As Approved Procedure & Design


d). Electrical earthing connections to the earthing system Approved Procedure & Design Drawing Drawing, ITR-4000-205 M

As Approved Procedure & Design


e). Check cable connection and tagging correct Approved Procedure & Design Drawing Drawing, ITR-4000-205 M

As Approved Procedure & Design


f). Final Inspection of Equipment Approved Procedure & Design Drawing Drawing, ITR-4000-205 M

As Approved Procedure & Design


g). Insulation Resistance Measurement Approved Procedure & Design Drawing Drawing, ITR-4000-205 M

4.3 TESTING (COMMISIONING)

As Approved Procedure & Design


a) Function Test Approved Procedure & Design Drawing Drawing, ITR-4000-207 M
COMPANY No.

CONTRACTOR No.

Contract No.

Rev. 2A

Inspection Level
REMARKS
JGC AMIN

W,R R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW

W,R R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW

W,R SW , R

W SW
AIR SEPARATION UNIT (ASU) PROJECT Inspection and Test Plan COMPANY No.

Electrical Work for Buiding & Infrastructure CONTRACTOR No.

Contract No.

Contractor :JGC Indonesia Location : Sumbawa, West Nusa Tenggara


Work Scope : Building

AW : Approval
R : Review S/C : SUBCONTRACTOR
HV : Witness
SW : Spot Witness JGC : JGC INDONESIA
: Hold Point
P : Provide AMIN : PT. AMMAN MINERAL INDUSTRY
: Verification
M : Monitor

Inspection Level
Activity No. Activity Description Reference Document Acceptance Criteria Verify Doc.
S/C

5 LIGHTING AND RECEPTACLE INSTALLATION

5.1 PREPARATION

Data Sheet, Material specification,


a. Material receiving inspection
Data Sheet, Material certificate, DO,PO Material certificate, DO,PO ITR-GEN-001 M

5.2 INSTALLATION (INSIDE BUILDING)

a). Check Lighting fixture installation, orientation and alignment Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-211 M
Drawing,
b). Check installation of receptacle/socket outlet Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-211 M
Drawing,
c). Check Instalation of Circuit Lighting as per Approved Drawing Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-211 M
Drawing,
d). Final Check of Installation prior to Test of Lighting
Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-211 M
Drawing,

5.3 TESTING (COMMISIONING)

a. Lighting & Receptacle circuit test Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-212 M
Drawing,
b. Illumination quality check Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-213 M
Drawing,

6 GROUNDING AND LIGHTNING PROTECTION SYSTEM

6.1 PREPARATION

Data Sheet, Material specification,


a). Material receiving inspection Data Sheet, Material certificate, DO,PO Material certificate, DO,PO ITR-GEN-001 M

6.2 INSTALLATION

a). Underground grounding cable installation check Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-214 M
Drawing,
b). Check Installation of Exothermic Weld Joints for Underground Cable Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-214 M
Drawing,
c). Installation of grounding electrode Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-214 M
Drawing,
d). Installation of grounding bar Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-214 M
Drawing,
e). Aboveground grounding cable installation check Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-214 M
Drawing,
f). Installation of lightning protection Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-214 M
Drawing,
g). Grounding connection check Approved Procedure & Design Drawing As Approved Procedure & Design ITR-4000-214 M
Drawing,
h). Final Check Approved Procedure & Design Drawing As Approved Procedure & Design 'ITR-4000-214 / 'ITR-4000- M
Drawing, 215

6.3 TESTING

a). Earthing continuity test (Electrode-Earth Bar/Plant Earth Ring) Approved Procedure & Design Drawing As Approved Procedure & Design 'ITR-4000-214 / 'ITR-4000- M
Drawing, 215
b). Inspection resistance of each electrodes (Individual electrode) Approved Procedure & Design Drawing As Approved Procedure & Design 'ITR-4000-214 / 'ITR-4000- M
Drawing, 215
c). Inspection total resistance looping grounding
Approved Procedure & Design Drawing As Approved Procedure & Design 'ITR-4000-214 / 'ITR-4000- M
Drawing, 215
COMPANY No.

CONTRACTOR No.

Contract No.

Rev. 2A

Inspection Level
REMARKS
JGC AMIN

W,R R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW

W SW

W SW

W,R R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW

W,R SW, R

W,R SW, R

W,R SW, R
ITR LIST

No Activity Description

1 MATERIAL RECEIVING INSPECTION REPORT (MRIR)

2 INSPECTION INSTALLATION OF CABLE TRAY

3 INSPECTION OF ELECTRICAL CABLE INSTALLATION AND TERMINATION

4 INSPECTION & TEST RECORD OF JOINTING CABLE

5 INSULATION RESISTANCE AND CONTINUITY TEST RECORD ELECTRICAL CABLE DRUM BEFORE
INSTALLATION
6 INSPECTION INSTALLATION OF CONDUIT

7 INSPECTION INSTALLATION OF LIGHTING AND SMALL POWER DISTRIBUTION BOARD and TEST
RECORD
8 FUNCTION & PHASE SEQUENCE TEST RECORD

9 INSTALLATION OF SOCKET OUTLETS/WELDING OUTLETS

10 INSPECTION LIGHTING INSTALLATION OUTSIDE BUILDING

11 INSPECTION LIGHTING INSTALLATION INSIDE BUILDING

12 INSPECTION RECEPTACLE INSTALLATION

13 LIGHTING AND RECEPTACLE VOLTAGE CIRCUIT TEST RECORD

14 ILLUMINATION LEVEL MEASUREMENT TEST RECORD

15 INSPECTION OF SYSTEM EARTHING INSTALLATION and TEST RECORD

16 INSPECTION OF LIGHTNING PROTECTION SYSTEM INSTALLATION AND TEST RECORD


ITR NO

ITR-GEN-001

ITR-4000-201

ITR-4000-202

ITR-4000-203

ITR-4000-204

ITR-4000-205

ITR-4000-206

ITR-4000-207

ITR-4000-208

ITR-4000-209

ITR-4000-210

ITR-4000-211

ITR-4000-212

ITR-4000-213

ITR-4000-214

ITR-4000-215
AIR SEPARATION UNIT
(ASU) PROJECT

Doc. No :                                       
Issue Date :                                       
REQUEST FOR INSPECTION (RFI)
Attn  : Mr…….                                  Project Construction Manager
Project Title : AIR SEPARATION UNIT (ASU) PROJECT
Gentlement,
We would like to have your presence for inspection according to the following schedules.
Civil Telecomunication Instrument Mech. Static
Piping Electrical Pipeline Mech. Rotating
Date and time Place / Area Inspection Item Remarks

Comments :

Prepared by Checked / Approved by


SUBCONTRACTOR CONTRACTOR
Print Name

Signature

Date
Manager

h. Static
. Rotating
Remarks

Reviewed/Witnessed by
COMPANY
AIR SEPARATION UNIT (ASU) PROJECT

SUBJECT : MATERIAL RECEIVING INSPECTION REPORT (MRIR)


Project : AIR SEPARATION UNIT (ASU) PROJECT
Location :                                      
Material/Equipment Identification
a. Material /Equipment Name :
b. Equipment Tag Number :
c. Purchase Order Number :
d. Suplier / Manufacture Name :
e. Material Approval Request (MAR No) :
f. Datasheet :
g. Batch no (if any) :
h. Packing List :

i. Inspection Release Certificate :

NO DESCRIPTION QTY CONFORMANCE TO SPE


YES

Prepared By:
SUBCONTRACTOR
Print Name

Signature

Date
SU) PROJECT ITR-GEN-001
Doc.No.:

Contract No :

Project No:
Reff Dwg Date :
:

CONFORMANCE TO SPECT. REMARKS


YES NO

Checked / Approved By: Reviewed / Witnessed by


CONTRACTOR COMPANY

57 / 103
AIR SEPARATION UNIT ITR-4000-201
(ASU) PROJECT
Contract No :

INSPECTION INSTALLATION OF CABLE TRAY


Project No. Client : PT. Amman Mineral Industry Date Page Doc. No. : 1 of
Main Contractor : PT. JGC Indonesia :
Sub-Contractor : :
:

Tag/ID No. System : Area/Location Sub-System No. :


No. System Desc. : Sub-System Desc. :
Layout Dwg No. : Rev. :
: :

No. Checks Description Result REMARKS


YES NO N/A
1 Check for material in accordance to Project Specification, verify quality and
condition.
2 Check supports are in accordance with design drawings.
3 Check size, routing, spacing and elevation are in accordance with
design drawings.
4 Verify correct type/size nut/bolt/washer are provided on each joints.

5 Ensure no sharp edges and confirm all rough edges removed.


6 Check insulation barriers provided between cable tray/rack and steel
supports, where applicable.
7 Check bending radius is satisfactory, installation of bends, change of
direction and supports.
8 Confirm all fasteners are tightened properly.

9 Verify adequate supports provided for cable tray system as per


actual site conditions.
10 Check cable tray system complies with typical installation details.

11 Verify installation of expansion joints at specified intervals and


supported.
12 Check repair of damaged galvanized coating after site fabrication
have been made good.
13 Correct type of nut/bolt/washer used and properly tightened (if applicable)

Remarks:

Prepared by, Checked / Approved by, Reviewed / Witnessed by,


SUBCONTRACTOR CONTRACTOR COMPANY
Name

Signature

Date
1

REMARKS

ewed / Witnessed by,


COMPANY
AIR SEPARATION UNIT (ASU) ITR-4000-202
PROJECT
Contract No. :

INSPECTION OF ELECTRICAL CABLE INSTALLATION AND TERMINATION


Project No. :
Date :
Client : PT. Amman Mineral Industry Page : 1 of 1
Main Contractor : JGC Indonesia Doc. No. :
Sub-Contractor : Rev. :

Cable Tag No. :                                                                            System No. :                                                                       System Desc. :                                                          
System No. :                                                                       Cable Type :                                                                            Rated Voltage :                                                                       N
:                                                                            Test Voltage : VDC
Manufacturer :                                                                            Ambient Temperature : °C Area/Location :                                                                           
:                                                                       Cable Schedule No. : Rev. :

NO CHECK DESCRIPTION RESULT


YES NO N/A
1 Verify type/size of cable gland
2 Verify that correct IP washer is fitted
3 All gland components are correctly assembled and tightened
4 Ensure that armour is not visible
5 Shroud provided wherever applicable
6 Correct earth bonding provided, if applicable
7 Correct wire/terminal lugs used
8 Verify terminations at both ends are as per phase colour code/core numbering and
identification
9 No physical damage or kinks on conductor inside the enclosure
10 Conductor is not touching with the cable entry component
11 Properly dressed inside the enclosure
12 Verify wire twisting is maintained close to termination point
13 Correct cable marker and core marker provided
14 No loose crimping or connections
15 Wires are terminated at correct terminals
16 Verify cables are reconnected & tightened after testing (torque if required shall be executed)

Continuity IR of Power Cable (MΩ)


Three Phase Single Phase
L1 - All other L2 - All other L3 - All other N - All other P - All N - All
cores/E cores/E cores/E cores/E Shield - E other other
cores/E cores/E

Test Equipment Type Manufacture Model No. Serial No.

Remarks :
Prepared by, Checked / Approved by, Reviewed / W
SUBCONTRACTOR CONTRACTOR COMP
Name

Signature

Date
MINATION

: 1 of 1
:
:

Sub-
:                                                                           
:                                                                       No. of Cores & Size

:                                                                            Weather

SULT REMARKS
N/A

IR of Control Cable (MΩ)

Core-Core Core - E

Cal Due Date


Reviewed / Witnessed by,
COMPANY
AIR SEPARATION UNIT (ASU) ITR-4000-203
PROJECT
Contract N o :
.

INSPECTION & TEST RECORD OF JOINTING CABLE


Project No. Client : Date Page
Main Contractor Sub- : PT. Amman Mineral Industry Doc. No.
Contractor : JGC Indonesia Rev.
:

Area/Location: Tag No.: System No:

Drawing No. : Rev. :

Cable Manufacturer: No.of Cores & Size: Voltage Rating:

From: To:

Details of Cable Joint/Termination kit

Manufacturer: Type: Part No:

Title of Installation Instruction Manual:

Installation Instruction Manual No: Voltage Rating:

Details of Technician

Name: Company:

Certificate No: Certificate Issued by:

Cert. Issued on: Certificate Valid up to:

Insulation Resistance and Continuity Test Results (Test Voltage: V DC )


Before Splice Joint After Splice Joint

A-Supply Side(M Ω) Continuity B-Load Side (MΩ) Continuity Side A&B (MΩ) Contin
L1-L2: L1 : L1-L2: L1 : L1-L2: L1 :
L2-L3: L2 : L2-L3: L2 : L2-L3: L2 :
L1-L3: L3 : L1-L3: L3 : L1-L3: L3 :
L1/L2/L3 to Shield : L1/L2/L3 to Shield : L1/L2/L3 to Shield :
Armour/Earth: Armour/Earth: Armour/Earth:

Shield to Shield to Shield to


Armour/Earth: Armour/Earth: Armour/Earth:

Visual Inspection Result


YES NO
1. Verify kit components against packing list and ensure that joint kit is suitable for the cable.

2. Verify joint/termination kit label and title of the installation instruction.

3. Manufacturer’s recommended process/instructions followed.

4. Physical appearance is acceptable.

Test Equipment Type: Manufacture Model: Serial No.


Remarks :

Prepared by, Checked / Approved by, Reviewed / W


SUBCONTRACTOR CONTRACTOR COMP

Name

Signature

Date
LE
Date Page : 1 of 1
Doc. No. :
Rev. :
:

Sub-System No:

e Rating:

o:

V DC )
After Splice Joint

Continuity
L1 :
L2 :
L3 :
Shield :

Result REMARKS
N/A

Cal due date:


Reviewed / Witnessed by,
COMPANY
AIR SEPARATION UNIT (ASU)
PROJECT

INSULATION RESISTANCE AND CONTINUITY TEST RECORD ELECTRICAL CAB


Project No. Client :
Main Contractor Sub-Contractor : PT. Amman Mineral Industry
: JGC Indonesia
:

Cable Schedule No./Dwg No. :


Manufacturer: Test Voltage: VDC
Insulation

Three Phase
Rated
No. Cable Drum No Cable Type No. of Cores& Size L1- All other L2- All other cores/ Armour/E
voltage

Continuity
cores/ Armour/E

1
2
3
4
5
6
7
8
9
10
Test Equipment Type Manufacture Model No

Remarks :

Prepared by,
SUBCONTRACTOR

Name
Signature

Date
ITR-4000-204
UNIT (ASU) Contract No. :

RECORD ELECTRICAL CABLE DRUM BEFORE INSTALLATION


Date Page : 1 of 1
Doc. No. Rev. :
:
:

Rev: System No: Sub-System No:


Ambient Temperature: °C
Insulation Resistance of Power Cables (MΩ) IR of Control Cables
(MΩ)
Three Phase Single Phase
L2- All other cores/ Armour/E L3- All other N- All other *Shield- P- All other cores/ Core - Core –
cores/ Armour/E cores/ Armour/E Armour/E Armour/E Core Armour/E

Model No Serial No. Cal Due Date

epared by, Checked / Approved by, Reviewed / Witnessed by,


ONTRACTOR CONTRACTOR COMPANY

61 / 103
ITR-4000-205

AIR SEPARATION UNIT (ASU) Contract No. :


PROJECT

INSPECTION INSTALLATION OF CONDUIT


Project No. :
Date :
Client : PT. Amman Mineral Industry Page : 1 of 1
Main Contractor : JGC Indonesia Doc. No. :
Sub-Contractor :

Tag No : System No : Sub-system No :

Tag Desc. : System Desc. : Sub-system Desc. :

Layout Drawing No : Rev :

Area/Location : Building No :

From : To :

RESULT
NO. CHECK DESCRIPTION
YES NO N/A

1 Check for material in accordance to project specification, verify quality and condition.

2 Support spaced/secured according to installation drawings.

3 Sizing as per layout drawings.

4 Routing as per layout drawings.

5 Spacing from other conduits/tray in accordance to specification.

6 Routing clear of hot surface.

7 Check expantion fitting and flexible connections.

8 Check bending radius

9 Conduit sloped properly toward drain fitting

10 Seals, drains, breathers installed wherever specified.

11 Check all conduits are in plumb level.

12 Check protective bushing installed, where applicable.

13 Verify electrical continuity is maintained.

14 Check general workmanship.

15 Touch up paint done as required.

16 Ensure the conduit wall penetration is sufficient


Remarks :

Prepared by, Checked / Approved by, Reviewed / Witnessed by,


SUBCONTRACTOR CONTRACTOR COMPANY
Name

Signature

Date
: 1 of 1
:

Rev :

REMARKS
Reviewed / Witnessed by,
COMPANY
AIR SEPARATION UNIT (ASU) ITR-4000-206
PROJECT
Contract No. :

INSPECTION INSTALLATION OF LIGHTING AND SMALL POWER DISTRIBUTION BOARD and TEST RECORD

Project No. Client : Date Page


Main Contractor : PT. Amman Mineral Industry Doc. No.
Sub-Contractor : JGC Indonesia
:

Tag No: System No: Sub-System No:


Tag Desc: System Desc: Sub-System Desc:
Area : Building Name / Room No :
Brand: Model No: Serial No:
Rating: Voltage: No. of Circuits:
No: Checks Description Result
YES
1 Verify equipment is appropriate to area classification requirements of the
location as per project specification.
2 Verify panel installation correct as per the drawing.

3 Verify name plate details against drawing/data sheet.

4 Door seals intact.

5 Verify IP rating is maintained.

6 Equipment undamaged.

7 Incoming isolator/fuse switch rating correct.

8 Incoming isolator/fuse switch manual operation satisfactory.

9 All outgoing isolators/fused circuits of correct rating and manual operation


satisfactory.
10 Verify clearances of bus bars are maintained.

11 Equipment earthing done.

12 Ensure all connections are tight and identified.

13 Visually check for correct phase sequence from left to right, top to bottom and front to rear.

14 Circuit identification schedule complete.

15 Verify all labels and tags are correct.

16 Lamp rating, type, colour and position are correct.

17 Unused cable entries are blanked off with correct type of plugs.

18 No unauthorised modifications on electrical enclosures.

19 General condition of enclosure is satisfactory.

20 Enclosure glass parts and glass to metal sealing gasket and/or compounds are satisfactory.
TEST RECORD

: of 2
:
:

No:
Desc:

Result Remarks
NO N/A
AIR SEPARATION UNIT (ASU) ITR-4000-206
PROJECT
Contract No. :

INSPECTION INSTALLATION OF LIGHTING AND SMALL POWER DISTRIBUTION BOARD and TEST RECORD

Project No. : Date :


Client : PT. Amman Mineral Industry Page :
Main Contractor : JGC Indonesia Doc. No. :

Sub-Contractor :
Tag No: System No: Sub-System No:
Tag Desc: System Desc: Sub-System Desc:
Area : Building Name / Room No :
Brand: Model No: Serial No:
Rating: Voltage: No. of Circuits:
Insulation Resistance Test (Test Voltage: VDC for 1min.)

Test Result
Configuration
R-YBNE Y-RBNE B-RYNE N-RYBE
YES NO

Result (MΩ)

Test Equipment Manufacture Model Serial No. Cal Due Da


Type

Ambient Temperature: °C

Remarks:

Prepared by, Checked / Approved by, Reviewed / Witnes


SUBCONTRACTOR CONTRACTOR COMPANY
Name

Signature

Date
RECORD

of 2

Result
REMARKS
N/A

Cal Due Date

Reviewed / Witnessed by,


COMPANY
AIR SEPARATION UNIT (ASU) ITR-4000-207
PROJECT
Contract No. :

FUNCTION & PHASE SEQUENCE TEST RECORD


Project No. : Date
Client : PT. Amman Mineral Industry Page
Main Contractor : JGC Indonesia Doc. No.
Sub-Contractor : Rev.
Tag No: System No: Sub-System No:
Tag Desc: System Desc: Sub-System Desc:
Area : Building Name / Room No :
Brand: Model No: Serial No:
Rating: Voltage: No. of Circuits:
Circuit Description Voltage Protection Type Phase Sequence Result
No: CW CCW YES NO

Test Equipment Type Manufacture Model Serial No: Cal Due Dat

Ambient Temperature: °C Humidity: %


Remarks:

Prepared by, Checked / Approved by, Reviewed / Witnes


SUBCONTRACTOR CONTRACTOR COMPANY
Name
Signature

Date
:
: 1 of 1
:
:
No:
Desc:

ts:
Result
Remarks
N/A

Cal Due Date:

Reviewed / Witnessed by,


COMPANY
ITR-4000-208

AIR SEPARATION UNIT (ASU) PROJECT Contract No. :

INSTALLATION OF SOCKET OUTLETS

Project No. : Date Page


Client : PT. Amman Mineral Industry Main Contractor Doc. No.
: JGC Indonesia Rev.
Sub-Contractor :

Tag No: Type: System No: Sub-System No:


Equipment Title: Area: Building Name / Room No:
Manufacture: Model No: Serial No:
Rating: Voltage: No. of outlets/Circuits:
No Check Description Result
YES
1 Outlets and junction boxes undamaged.
2 Check IP rating of outlets and junction box enclosures suitable for the area.
3 All outlets and junction boxes earthed correctly.
4 Mounting of outlets satisfactory and location as per the drawing and accessible.
5 Correct connections at each outlet.
6 Visually verify polarity at each outlet.
7 No. of outlets / circuits is correct.
8 Cable terminations satisfactory and identified correctly.
9 Cable correct size and type/Cable glands correct and properly glanded (where applicable).
10 Identification Tags provided.
11 Switch on unit can only be closed with plug inserted.
12 Plug cannot be removed when switch is closed.
13 Verify rating of each outlet is correct.
14 Unused cable entries are blanked off with correct type of plugs.
15 No unauthorised modifications on electrical enclosures.
16 General condition of enclosure is satisfactory.
17 Enclosure flange faces are clean and undamaged and gaskets, if any, any are satisfactory.
18 Flange gap dimensions are within maximal values permitted.
19 Insulation Resistance Test (Test Voltage: VDC for 1min.)
IR Test: (Full Circuit) in Convenience Phase-N Phase-E N-E
MΩ Outlets
Welding Outlets L1-L2 L1-L3 L2-L3 L1-N L2-N L3-N L1-E

Test Equipment Type Manufacture Model Serial No.

Ambient Temperature: °C Humidity: %


Remarks:

Prepared by, Checked / Approved by, Reviewed / Witne


SUBCONTRACTOR CONTRACTOR COMPAN
Name

Signature
Date
00-208
t No. :

Date Page : 1 of 1
Doc. No. :
Rev. :
:

Sub-System No:
Building Name / Room No:
Serial No:
No. of outlets/Circuits:
Result REMARKS
NO N/A

N-E

L2-E L3-E N-E

Cal Due Date

Reviewed / Witnessed by,


COMPANY
ITR-4000-210
Contract No.
AIR SEPARATION UNIT (ASU) PROJECT

INSPECTION LIGHTING INSTALLATION INSIDE BUILDING


Project No. Client : Date Page
Main Contractor : PT. Amman Mineral Industry Doc. No.
Sub-Contractor : JGC Indonesia
:

Tag No : System No: Sub-System No:


IP Rating: System Desc: Sub-System Desc:
Circuit No: Lighting Type: Area :
Lighting Layout Drawing No: Building Name / Room No :
No. Checks Description Result
YES
1 Check Installation of Lighting switch as per approved drawing
2 Check Installation of Lighting as per approved drawing
3 All fittings solidly and correctly mounted and not obstructed by other services.
4 All equipment undamaged and clean
5 All labeling are correct.
6 Ensure Lamp rating, type and position are correct.
7 No undue accumulation of dust and dirt.

Notes :

Prepared by, Checked / Approved by, Reviewed / W


SUBCONTRACTOR CONTRACTOR COMP
Name
Signature

Date
TR-4000-210
:

ILDING
: 1 of 1
:
:

System No:
System Desc:
:
ding Name / Room No :
Result REMARKS
YES NO N/A

Reviewed / Witnessed by,


COMPANY
AIR SEPARATION UNIT (ASU) ITR-4000-211
PROJECT Contract No.

INSPECTION RECEPTACLE INSTALLATION


Project No. Client : Date Page
Main Contractor : PT. Amman Mineral Industry Doc. No.
Sub-Contractor : JGC Indonesia
:

Tag No : System No: Sub-System No:


IP Rating: System Desc: Sub-System Desc:
Circuit No: Lighting Type: Area :
Lighting Layout Drawing No: Building Name / Room No :
No. Checks Description Result
YES
1 Check Location, elevation and orientation of receptacle as per layout drawing.
2 Ensure type of installed receptacle is corect as per specification
3 Check Circuit Installed and Identified according to approved drawings and specifications.
4 All equipment undamaged, clean and all spare entries blanked of with correctly certified plugs.
5 All labeling are correct.
6 Earth connection and earth continuity in accordance with specification.
7 Check Earth connection and earth continuity are installed properly
8 Unused cable entries are blanked off with correct type of plugs.
9 No undue accumulation of dust and dirt.
10 Where applicable, sealing is satisfactory.

Notes :

Prepared by, Checked / Approved by, Reviewed / W


SUBCONTRACTOR CONTRACTOR COMP
Name
Signature

Date
TR-4000-211
:

: 1 of 1
:
:

System No:
System Desc:
:
ding Name / Room No :
Result REMARKS
YES NO N/A

Reviewed / Witnessed by,


COMPANY
AIR SEPARATION UNIT (ASU) PROJECT ITR-4000-212

Contract No. :

LIGHTING AND RECEPTACLE VOLTAGE CIRCUIT TEST RECORD

Project No. Client : Date Page :


Main Contractor : PT. Amman Mineral Industry Doc. No. :
Sub-Contractor : JGC Indonesia : 1
:

LP Tag No: System No: Sub-System No:


LP Tag Desc: System Desc: Sub-System Desc:
Area: Building Name :
Panel Schedule No: Rev:
Layout Drawing No: Rev:
NO Room No / Name BRANCH CIRCUIT RESULT REMARKS
CIRCUIT NO. VOLTAGE

Test Equipment Type Manufacture Model Serial No. Cal Due D

Remarks:

Prepared by, Checked / Approved by, Reviewed / Wit


SUBCONTRACTOR CONTRACTOR COMPA

Name
Signature

Date
of 1

em No:
em Desc:

REMARKS

Cal Due Date

Reviewed / Witnessed by,


COMPANY
AIR SEPARATION UNIT (ASU) PROJECT ITR-4000-213

Contract No. :

ILLUMINATION LEVEL MEASUREMENT TEST RECORD

Project No. Client : Date Page Doc. :


Main Contractor : PT. Amman Mineral Industry No. :
Sub-Contractor :
: JGC Indonesia
:

LP Tag No: System No: Sub-System No:


LP Tag Desc: System Desc: Sub-System Desc:
Area: Building Name / Room No:
Layout Drawing No: Rev:
NO. ROOM NAME / NO HEIGHT FROM ILLUMINATION STANDARD JUDG
MEASUREMENT POSITION GROUND LEVEL ( Lux ) ILLUMINATION (Lux) (Accepted

Test Equipment Type Manufacture Model Serial No. Cal Du

Remarks:

Prepared by, Checked / Approved by, Reviewed / W


SUBCONTRACTOR CONTRACTOR COM
Name
Signature
Date
1 of 1

Sub-System No:
Sub-System Desc:

JUDGEMENT
(Accepted/ Rejected)

Cal Due Date

Reviewed / Witnessed by,


COMPANY
AIR SEPARATION UNIT (ASU) ITR-4000-214
PROJECT
Contract No. :

INSPECTION OF SYSTEM EARTHING INSTALLATION and TEST RECORD


Project No. Client : Date Page :
Main Contractor : PT. Amman Mineral Industry Doc. No. :
Sub-Contractor : JGC Indonesia :
:

Tag No: System No: Sub-System No:


Tag Desc.: System Desc.: Sub-System Desc.:
Area: Location:
Drawing No: Rev:
Electrical Lightning Protection Instrument Earth
No: Check Description Result
YES
1 Cable size, type and route as specified in the layout drawings.
2 Depth of underground cable is acceptable.
3 Verify that adequate clearance is maintained between earth cable and other services
(especially for underground cables).
4 Cad weld connections/joints are checked for proper bonding.
5 Connections/joints are insulated properly (where applicable)
6 Check crimping of earthing clamps for proper bonding.
7 Above ground cables are fixed properly to the structure.
8 Clean earth bar assembly, insulators and connections fitted properly.
9 Check proper routing and dressing of the cables.
10 Tags provided as per the drawing (where applicable)
11 Earth electrodes are located as per layout drawing.
12 Earth electrodes are connected properly to the main grid.
13 Earth network disconnected for testing purpose.
14 Continuity between the connection point and adjacent Bar/Grid.
15 Verify cables are reconnected & tightened after test
16 Inspection pit provided and identified.
17 Earth bar located as per layout drawing.
18 Earth bar installation as per installation detail drawing.
19 Earth bar assembly and connections are fitted correctly.
20 All bondings to equipment are in accordance with installation detail drawing.
21 All wire lugs are properly crimped and bolted.
22 All non current carrying metal parts are bonded to earthing system.
23 Earthing Continuity Test Record
Tag Number Cable Continuity Resistance to Earth Grid
From To
nd TEST RECORD
of 2

em No:
em Desc.:

nt Earth
Result REMARKS
NO N/A
AIR SEPARATION UNIT (ASU) ITR-4000-214
PROJECT
C ntract No. :
o

INSPECTION OF SYSTEM EARTHING INSTALLATION and TEST RECORD


Project No. Client : Date :
Main Contractor : PT. Amman Mineral Industry Page :
Sub-Contractor : JGC Indonesia Doc. No. :
:

Tag No: System No: Sub-System No:


Tag Desc.: System Desc.: Sub-System Desc.:
Area: Location:
Drawing No: Rev:
Electrical Lightning Protection Instrument Earth
No: Check Description Result
YES
24 Earthing Resistance Test Record
Result of resistance measured
( Network )
Rod No.
R1 R2 R3 Avarage Value

Test Equipment Type Manufacture Model Serial No.

Remarks:
- All ground shall have a resistance to earth not exceeding 5 ohm in network connection.

Prepared by, Checked / Approved by, Reviewed / Witnes


SUBCONTRACTOR CONTRACTOR COMPANY
Name

Signature

Date
nd TEST RECORD
of 2

em No:
em Desc.:

nt Earth
Result REMARKS
NO N/A

erial No. Cal Due Date

Reviewed / Witnessed by,


COMPANY
ITR-4000-215
AIR SEPARATION UNIT (ASU) Contract No. :
PROJECT

INSPECTION OF LIGHTNING PROTECTION SYSTEM INSTALLATION AND TEST RECORD


Project No. Client : Date Page : 1 of
Main Contractor : PT. Amman Mineral Industry Doc. No. :
Sub-Contractor : JGC Indonesia :
:

Tag No: System No: Sub-System No:


Tag Desc.: System Desc.: Sub-System Desc.:
Area: Location:
Drawing No: Rev:
No: Check Description Result REMARKS
YES NO N/A
1 Earth electrodes are located as per layout drawing.
2 Earth electrodes are connected to the main grid.
3 All earth electrodes shown on the above mentioned layout drawing.
4 Inspection pits installed properly.
5 Connections are in accordance to the drawings.
6 Lightning air terminal location and installation is in accordance with drawing.
7 Earth tape and down conductors are installed as per the installation details.
8 Test clamps are fitted properly and disconnect facilities are functional.
9 All bonding to the metallic structures are in accordance with installation details and
layout drawings.
10 Earthing Continuity Test Record
Tag Number Cable Continuity Resistance to Earth Grid
From To

11 Earthing Resistance Test Record


Result of resistance measured
( Network )
Rod No.
R1 R2 R3
Value

Test Equipment Type Manufacture Model Serial No. Cal Due Date
Remarks:
- All ground shall have a resistance to earth not exceeding 5 ohm in network connection.

Prepared by, Checked / Approved by, Reviewed / Witnessed by,


SUBCONTRACTOR CONTRACTOR COMPANY
Name

Signature

Date
D
1

REMARKS

Cal Due Date


/ Witnessed by,
OMPANY
AIR SEPARATION UNIT (ASU) PROJECT

SUBJECT : PUNCH LIST REPORT

Project Title : AIR SEPARATION UNIT (ASU) PROJECT

Client : PT. Amman Mineral Industry

Area / Location Ref. Drawing No : Punch List No


: Unit / Facility

Item Punch List Category


No. Punch List Description A/B/C/D

Note Category Description : : Signifies that the Punch list item, defect, or omission must be repaired or completed before issuance of SYSTEM CO
ABC : Signifies that the Punch list item, defect,or omission may be completed after Construction Completion during Pre-Co
D CERTIFICATE.
: Signifies that the Punch list item, defect, or omission can be repaired and/or completed after System HANDOVER, b
and COMPANY.
: Recognized as an item that is desirable to Operations, but is outside the project work scope agreement, is not opera
"D" items will not prevent HANDOVER, TURNOVER, or ACCEPTANCE.

SUBCONTRACTOR CONTRACTOR
Prepared As Punch List
Print Name

Signature

Date
Report No :

Doc. No :
PROJECT
Contract No:

Project No:

System / Sub- :
System
Area :
Reference Dwg :
Punch List No :
Unit / Facility :

Punch List Category Target Date Date Accepted


Approved Cleared S/C JGC AMIN Remarks
JGC AMIN

before issuance of SYSTEM CONSTRUCTION COMPLETION CERTIFICATE.


ction Completion during Pre-Commissioning. All Category "B" items must be corrected before issuance of a System HANDOVER

ed after System HANDOVER, but must be done before TURNOVER. Deviations must be agreed to in writing between CONTRACTOR

scope agreement, is not operationally critical to the facility, process, or people, and will be rectified at COMPANY expense. Category

CONTRACTOR COMPANY
Punch List Completed As Punch List Completed

74 / 103
AIR SEPARATION UNIT (ASU) PROJECT Inspection and Test Plan for Building COMPANY No.
0201

HVAC Work CONTRACTOR No. : S-A000-1670-20

Contract No

Contractor : JGC Indonesia Location : Bojonegoro, East Java, Indonesia


Work Scope : Building

A : Approval R : Review S/C : SUBCONTRACTOR


W : Witness SW : Spot Witness P : Provide JGC : JGC Indonesia
H : Hold Point M : Monitor AMIN : PT. Amman Mineral Industry
V : Verification

Inspection Level
Activity No. Activity Description Reference Documents Acceptance Criteria Verify Doc.
S/C

MATERIAL RECEIVING INSPECTION

Approved Specification, Packing


List / Material Certificate
Approved Specification, Packing List
1.1 Material Receiving Inspection ITR-GEN-001 M
/ Material Certificate

Ducting Installation

Type, Size, Location, Elevation, Support of Ducting

2.1 Approved Design Drawing As per Approved Design Drawing ITR-4000-501 M

Tightness of Connection and Joints, Penetration Condition


As Approved Procedure &
2.2 Approved Procedure & Design Drawing ITR-4000-501 M
Design Drawing,

Check Installation of Accessories (Dampers, Grilles, Diffusers, Flexible Duct, Hanger)


As Approved Procedure &
2.3 Approved Procedure & Design Drawing ITR-4000-501 M
Design Drawing,

Check Insulation
As per Design Drawing, and
2.4 Approved Design Drawing, Specification ITR-4000-508 M
Specification

As per Data Sheet, Specification,


and Approved Procedure
Data Sheet, Specification, Instruction
2.5 Check Installation and Function Test of Damper ITR-4000-502 M
Manual, Approved Procedure

Data Sheet, Specification, Approved As per Data Sheet, Specification,


Procedure and Approved Procedure
2.6 Duct Leak Test ITR-4000-503 M

HVAC Equipment Installation

Installation of Split Type Room Air Conditioner

3.1

a Check Location, Elevation/Leveling, Alignment, Support, and Maintenance Access. As Approved Design Drawing,
Approved Standard Installation.
Approved Design Drawing, Approved
ITR-4000-504 M
Standard Installation.

b. Check the cable termination is correct


Approved Design Drawing, Approved As per Approved Design
Manufacture Drawing and Standard Drawing, Approved Manufacture
Installation. Drawing and Standard ITR-4000-504 M
Installation.

c Ensure tagging already installed is correct & proper

Approved Drawing As per Approved Drawing ITR-4000-504 M

d Insulation Resistance Measurement


Refer to ITP Elevtrical
Work For Building
Approved Specification As Approved Specification M

3.2 Installation of Fan

a Check Location, Elevation/Leveling, Alignment, Support, and Maintenance Access. As Approved Design Drawing,
Approved Standard Installation.
Approved Design Drawing, Approved
ITR-4000-505 M
Standard Installation.
b. Check the cable termination is correct
Approved Design Drawing, Approved As per Approved Design
Manufacture Drawing and Standard Drawing, Approved Manufacture
Installation. Drawing and Standard ITR-4000-505 M
Installation.

c Ensure tagging already installed is correct & proper

Approved Drawing As per Approved Drawing ITR-4000-505 M


COMPANY No. : ACCS-40-411-AS01-S-PLN-
0201

CONTRACTOR No. : S-A000-1670-201

Contract No :

Rev.2A

Inspection Level
REMARKS
JGC AMIN

W,R R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW , R

W,R SW , R
W,R SW , R

W,R SW , R
AIR SEPARATION UNIT (ASU) PROJECT Inspection and Test Plan for Building COMPANY No.
0201

HVAC Work CONTRACTOR No. : S-A000-1670-20

Contract No

Contractor : JGC Indonesia Location : Bojonegoro, East Java, Indonesia


Work Scope : Building

A : Approval R : Review S/C : SUBCONTRACTOR


W : Witness SW : Spot Witness P : Provide JGC : JGC Indonesia
H V : Hold Point M : Monitor AMIN : PT. Amman Mineral Industry
: Verification

Inspection Level
Activity No. Activity Description Reference Documents Acceptance Criteria Verify Doc.
S/C

Refrigerant & Drain Piping installation

4.1 Type, Size, Location, Elevation, Support of Piping Approved Design Drawing As per Approved Design Drawing ITR-4000-506 M

As Per Specification, and


4.2 Piping Pressure Test Specification and Approved Procedure ITR-4000-507 M
Approved Procedure

As per Approved Design


4.3 Insulation Check Approved Design Drawing, Specification ITR-4000-508 M
Drawing, and Specification

Design Drawing, Data Sheet, Specification, As per Design Drawing, Data


5 Final Inspection release ITR-4000-509 M
Approved Procedure Sheet, Specification
COMPANY No. : ACCS-40-411-AS01-S-PLN-
0201

CONTRACTOR No. : S-A000-1670-201

Contract No :

Rev.2A

Inspection Level
REMARKS
JGC AMIN

W , R SW , R

R R

W,R SW,R

W , R SW
ITR LIST
No Description

1 Material Receiving Inspection Report

2 HVAC Ducting System Installation

3 Damper Installation and Test

4 Duct Leak Test

5 Split Type Room Air Conditioner Installation

6 Fan Installation

7 Piping Installation Check

8 Pressure Test Record

9 Piping Insulation Inspection report

10 Final Inspection
ITR

ITR-GEN-001

ITR-4000-501

ITR-4000-502

ITR-4000-503

ITR-4000-504

ITR-4000-505

ITR-4000-506

ITR-4000-507

ITR-4000-508

ITR-4000-509
AIR SEPARATION UNIT (ASU)
PROJECT

REQUEST FOR INSPECTION (RFI) RFI. No
Issue Date :
:
Attn : Mr……. Rev No :
Project Construction Manager Mech. Static Mech. Rotating
Project Title : AIR SEPARATION UNIT (ASU) PROJECT Remarks
Gentlemen,
We would like to have your presence for inspection according to the following schedules.
Civil Telecommunication Instrument
Piping Electrical Pipeline
Date and time Place / Area Inspection Item

Comments :

Prepared by Checked / Approved by Reviewed/Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name
Signature
Date
AIR SEPARATION UNIT (ASU) PROJECT

SUBJECT : MATERIAL RECEIVING INSPECTION REPORT


Project AIR SEPARATION UNIT (ASU) PROJECT
Client PT. Amman Mineral Industry
Location                                                                        Reff.Dwg.                                                                       
Material/Equipment Identification
a. Material /Equipment Name :
b. Equipment Tag Number :
c. Purchase Order Number :
d. Supplier / Manufacture Name :
e. Material Approval Request (MAR No) :
f. Datasheet No :
g. Batch no (if any) :
h. Packing List :
i. Inspection Release Certificate :

NO DESCRIPTION QTY CONFORMANCE TO SPECT.


YES

Prepared By: Checked / Approved By:


SUBCONTRACTOR CONTRACTOR
Print Name
Signature

Date
ITR-GEN-001

Doc.No.:

Contract No :

Project No : Rev.2A

                  

NFORMANCE TO SPECT. REMARKS


NO

Checked / Approved By: Reviewed / Witnessed by


CONTRACTOR COMPANY

79 / 103
AIR SEPARATION UNIT (ASU) ITR-4000-501
PROJECT Doc.No : Contract No:

Subject : HVAC Ducting System Installation Project No :


Rev.2A
Project : AIR SEPARATION UNIT (ASU) PROJECT
Date :
Client : PT. Amman Mineral Industry RFI No :
General
a. Area/Building Name :                                                                                                                      
b. System / Sub-System :                                                                                                                      
c. Part/ Location :                                                                                                                      
d. Reference Drawing/Specification :                                                                                                                      
e. Equipment Tag Number :                                                                                                                      
f. Manufacturer Name :                                                                                                                      
g. Model Number :                                                                                                                      
h. Serial Number :                                                                                                                      

No Activities ACC REJ N/A Remarks


1 Tag identification is correctly as per inspection drawing
2 Check the Type and Size of Ducting is correct
3 Check ductwork and all associated equipment undamaged, clean and in good
condition
4 Flexible connection correctly fitted and do not take up offsets
5 Isolation materials included between supports and ducts correctly installed.

6 Ensure Hanger and Support already installed in properly & in correct position

7 Bird screens fitted to inlets and all bolting secured.


8 Check all connection: Tightness, joint gaskets fitted correctly and stress free

9 All Duct are internally Clean


10 Access to inspection/test place is clean and tidy before and after test.
11 Check Earthing / Bonding already done properly

Ducting Accessories Installation Record


Size & Joint Result
No Tag No Item Thickness Ducting Type Room Elevation
Bolting Gasket Sealed Acc Rej

Ducting Support Installation Record


Hanger Result
No Ducting Size Room
Spacing Trapeze Acc Rej

Remarks :
Prepared by Checked/Approved by Reviewed/Witnessed by
SUBCONTRACTOR CONTRACTOR COMPANY
Print Name
Signature

Date
ITR-4000-502
Doc.No : Contract No:

AIR SEPARATION UNIT (ASU)


PROJECT

Subject : Damper Installation and Test Rev.2A

Project AIR SEPARATION UNIT (ASU) PROJECT


Date :
Client PT. Amman Mineral Industry RFI No :

General
a. Area/Building Name
b. System / Sub-System
c. Part/ Location
d. Reference Drawing/Specification
e. Equipment Tag Number
f. Manufacturer Name
g. Model Number
h. Serial Number

No Activities ACC REJ N/A

1 Nameplate / Tag no. plate fitted. Details are correct to specification and drawings.

2 Check damper installation correct to design specification and drawings.

3 Check damper and all associated equipment undamaged, clean and in good condition.

4 Visually inspect damper for completeness.

5 Check damper internals are clean and free of debris

6 Access space available for inspection, maintenance and equipment removal.

7 Ensure equipment guards in place and securely fixed.

8 Damper blades move freely.

9 Blades close properly, adjustment level operates satisfactory.

10 Blade position external indication fitted and correct

11 Blade position locking quadrant satisfactory.

Remarks :

Prepared by Checked/Approved by Reviewed/Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
Rev.2A

REMARKS
ITR-4000-503
Doc.No : Contract No:

AIR SEPARATION UNIT (ASU) PROJECT

Subject : Duct Leak Test Rev.2A

Project : AIR SEPARATION UNIT (ASU) PROJECT Date :


Client :  PT. Amman Mineral Industr                            RFI No :                                                                                          

General
a. Area / Building Name :                                                                                                                                                   
b. System / Sub-System :                                                                                                                                                   
c. Part/ Location :                                                                                                                                                   
d. Reference Drawing / Specification :                                                                                                                                                   
e. Air System :                                                                                                                                                   
f. Leakage Class :                                                                                                                                                   
g. Fan CFM :                                                                                                                                                   
h. Specified Test Pressure :                                                                                                                                                   
i. Duct Construction Pressure :                                                                                                                                                   

DESIGN DATA FIELD DATA RECORD RESULT

Subject / Type of Allowable CFM (Test Duration Diameter Pressure


Duct Leakage Section)
Surface Area Date Actual CFM ACC REJ
Orifice Tube Duct Across
Orifice

Remarks :

Prepared by Checked/Approved by Reviewed/Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
Rev.2A

RESULT

REMARKS
N/A
AIR SEPARATION UNIT (ASU) ITR-4000-504
PROJECT Doc.No : Contract No:

Subject : Split Type Room Air Conditioner Installation Rev.2A


Project : AIR SEPARATION UNIT (ASU) PROJECT
Date :
Client : PT. Amman Mineral Industry RFI No :
General
a. Area/Building Name
b. System / Sub-System
c. Part/ Location
d. Reference Drawing/Specification
e. Equipment Tag Number
f. Manufacturer Name
g. Model Number
h. Serial Number

No Activities ACC REJ N/A


1 Check Location, Leveling and Elevation is correct as per drawing
2 Ensure the Indoor Unit & Outdoor Unit is installed in proper support and
Fixed
3 Ensure the tagging already installed
4 Check tubing connection of tubing is proper
5 Check the tubing installed is correct type and size
6 Ensure no leakage at all connections
7 Ensure all electrical connection is secured tightly on its proper post
8 Ensure the drain hose is installed properly
9 Check Cleanliness
Remarks

Prepared by Checked/Approved by Reviewed/Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
Rev.2A

Remarks
AIR SEPARATION UNIT (ASU) ITR-4000-505
PROJECT Doc.No : Contract No:

Subject : Fan Installation Rev.2A


Project : AIR SEPARATION UNIT (ASU) PROJECT
Date :
Client : PT. Amman Mineral Industry RFI No :
General
a. Area/Building Name
b. System / Sub-System
c. Part/ Location
d. Reference Drawing/Specification
e. Equipment Tag Number
f. Manufacturer Name
g. Model Number
h. Serial Number

No Activities ACC REJ N/A


1 Name plate / Tag Identification is Correct to Specification and Drawing
2 Check Location, Leveling and Elevation is correct as per drawing
3 Ensure the fan & motor is installed correctly and all accessories

4 Check unit and all associated equipment undamaged, clean and in good condition

5 Anti Vibration Mounts Installed Correctly


6 Access Space Available for Maintenance and Equipment Removal
7 Flexible connection between duct and unit tight and secured
Verify that the unit’s protective terminal(s) are properly connected to a suitable grounding
8 point. Ensure that all unit internal ground connections are
tight.
Remarks

Prepared by Checked/Approved by Reviewed/Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
Rev.2A

Remarks
AIR SEPARATION UNIT (ASU) PROJECT
Form.No : ITR-4000-506 Report

Rev : 2A Project No : Contract No : Date

CLIENT : PT. Amman Mineral Industry Pages No. :

Subject : PIPING INSTALLATION CHECK

SYSTEM / Sub-SYSTEM No : Area :

Ref. Drawing No. : Equipment No. :

CHECKED ACCEPTED
NO. ITEMS / DESCRIPTION
YES N/A S/C CONT COMPANY

1 Correct pipe support , location / type / size /material

2 Penetration on Wall / Roof / Floor

3 Soldering / Brazing of Joint

4 Surface Condition

5 Type of Insulation

6 Insulation Installation

RESULT: ACCEPTED REJECTED

Prepared / Inspected by, Checked / Approved by, Reviewed / Witnessed by

SUBCONTRACTOR CONTRACTOR COMPANY

NAME

SIGNATURE

DATE
No :

Pages No. :

ED
REMARKS
COMPANY

Reviewed / Witnessed by

COMPANY
AIR SEPARATION UNIT (ASU) PROJECT
Form.No : ITR-4000-507

Rev : 2A Project No : Contract No :

CLIENT : PT. Amman Mineral Industry

Subject : PRESSURE TEST RECORD

SYSTEM / Sub-SYSTEM No : Area


:
Ref. Drawing No. : Equipment No. :

PRESSURE TEST
Test Pressure (psi) Duration (minutes)
Circuit Description / Number Test Fluid
Rated Actual Rated Actual

REMARKS

Prepared / Inspected by, Checked / Approved by, Reviewed / Witnessed by

SUBCONTRACTOR CONTRACTOR COMPANY

Name
Signature

Date
Report No :

Date :

ation (minutes)
Test Result
Actual

Reviewed / Witnessed by

COMPANY
AIR SEPARATION UNIT (ASU) PROJECT

Subject : PIPING INSULATION INSPECTION REPORT


Project : AIR SEPARATION UNIT (ASU) PROJECT Date
:
Client : PT. Amman Mineral Industry RFI No :

Surface Insulation
Cleaning material
No Line No Insulation Spec

Result: Accepted
Calibration Details : Rejected

Prepared by
SUBCONTRACTOR
Print Name

Signature

Date
ITR-4000-508
Report No Contract No:

UNIT (ASU) PROJECT

Rev.2A

:
RFI No :

Insulation Thickness / No. of


layers
Vapor Barrier Metal Jacketing Remarks

Checked/Approved by Reviewed/Witnessed by
CONTRACTOR COMPANY

87 / 103
AIR SEPARATION UNIT (ASU) ITR-4000-509
PROJECT Doc.No :
Contract No:

Subject : Final Inspection Project No :

Project : AIR SEPARATION UNIT (ASU) PROJECT


Date :
Client : PT. Amman Mineral Industry RFI No
:
General
a. Area/Building Name
b. System / Sub-System
c. Part/ Location
d. Reference Drawing/Specification
We certify the scope of work defined in the above mentioned ITP is completed and is verified in accordance with
attached list of ITR’s.
All acceptance criteria described in the above mentioned ITP are met.

STATUS
No Activities
Complete Not Complete
1 Ducting Installation

2 Installation of Split Type Room Air Conditioner

3 Installation of Fan

4 Refrigerant & Drain Piping installation

Prepared by Checked/Approved by Reviewed / Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
Rev.2A

TUS
Remarks
N/A

88 / 103
AIR SEPARATION UNIT (ASU) PROJECT

SUBJECT : PUNCH LIST REPORT

Project Title : AIR SEPARATION UNIT (ASU) PROJECT

Client : PT. Amman Mineral Industry

Area / Location Ref. Drawing No : Punch List No Unit /


: Facility

Item Punch List Description Punch List Category


No. A/B/C/D Approved
JGC AMIN

Note Category Description : : Signifies that the Punch list item, defect, or omission must be repaired or completed before issuance of SYSTEM CONSTRUCTION COMPLETION CE
ABC : Signifies that the Punch list item, defect,or omission may be completed after Construction Completion during Pre-Commissioning. All Category "B" item
D CERTIFICATE.
: Signifies that the Punch list item, defect, or omission can be repaired and/or completed after System HANDOVER, but must be done before TURNOVE
COMPANY.
: Recognized as an item that is desirable to Operations, but is outside the project work scope agreement, is not operationally critical to the facility, proces
items will not prevent HANDOVER, TURNOVER, or ACCEPTANCE.

SUBCONTRACTOR CONTRACTOR
Prepared As Punch List Completed
Print Name

Signature

Date
Report No :

Doc. No :

Contract No:

Project No: Rev. 2A

System / Sub- :
System
Area :
Reference Dwg :
:
:

Target Date Accepted Remarks


Date Cleared S/C JGC AMIN

EM CONSTRUCTION COMPLETION CERTIFICATE.


Pre-Commissioning. All Category "B" items must be corrected before issuance of a System HANDOVER

VER, but must be done before TURNOVER. Deviations must be agreed to in writing between CONTRACTOR and

operationally critical to the facility, process, or people, and will be rectified at COMPANY expense. Category "D"

RACTOR COMPANY
Completed As Punch List Completed
AIR SEPARATION UNIT (ASU) INSPECTION AND TEST PLAN FOR B
PROJECT FIRE ALARM

Contractor : JGC Indonesia Location : Sumbawa, West Nusa Tenggara, Indonesia

Work Scope : Building

A : Approval
R : Review S/C : SUBCONTRACTOR
W : Witness
SW : Spot Witness JGC : JGC Indonesia
H : Hold Point
P : Provide AMIN : PT. Amman Mineral Industry
V : Verification
M : Monitor/Surveillance

Reference Document
Activity No. Activity Description

INSTALLATION FOR ELECTRICAL CABLES (INSIDE BUILDING)


1

PREPARATION

Data Sheet, Factory test report, Material certificate,


1.1 Material receiving inspection Packing List, IRC

Insulation Resistance /Continuity tests and Inspection of cables before Cable drum schedule/cable schedule, Manufacturer ’s
1.2 installation (on drum ) at warehouse, prior to release to site for instructions
installation

INSTALLATION & TESTING

Inspection of above ground cable

1.3 Check Conduit Installation Approved Procedure & Design Drawing

1.4 Check Cable glanding Approved Procedure & Design Drawing

1.5 Check Cable Termination Approved Procedure & Design Drawing

Insulation Resistance and Continuity test after glanding and termination


1.6 Approved Procedure & Design Drawing

1.7 Check Cable Identification/markers Approved Procedure & Design Drawing

INSTALLATION FOR FIRE ALARM CONTROL PANEL


2

PREPARATION

Data Sheet, Factory test report, Material certificate,


2.1 Material receiving inspection Packing List, IRC

INSTALLATION & TESTING

2.2 Installation Check Installation details, Layout drawing

2.3 Check Mounting & Alignment Installation details, Layout drawing

2.4 Earthing Connection Check Installation details, Layout drawing


2.5 Check cable connection and tagging correct Installation details, Layout drawing

Installation details, Approved Procedure, Layout drawing


2.6 Testing
ION AND TEST PLAN FOR BUILDING COMPANY No

ARM CONTRACTOR No

CONTRACT No

West Nusa Tenggara, Indonesia Rev.2A

al Industry

Acceptance Criteria Verify Doc. Inspection Level


REMARKS
S/C JGC AMIN

Comply to Data Sheet, Factory test report, Material


certificate, Packing List, IRC ITR-GEN-001 M W, R R

Complied with approve drawings and Installation Detail Refer to ITP Building
Electrical M W R

Refer to ITP Building


As Approved Procedure & Design Drawing, Electrical M W, R SW

Refer to ITP Building


As Approved Procedure & Design Drawing, Electrical M W, R SW

Refer to ITP Building


As Approved Procedure & Design Drawing, Electrical M W, R SW

Refer to ITP Building


As Approved Procedure & Design Drawing, Electrical M W, R SW

Refer to ITP Building


As Approved Procedure & Design Drawing, Electrical M W, R SW

Comply to Data Sheet, Factory test report, Material


certificate, Packing List, IRC ITR-GEN-001 M W, R R

Complies with approved drawings, installation details


ITR-4000-301 M W, R SW

Complies with approved drawings, installation details


ITR-4000-301 M W, R SW

Complies with approved drawings, installation details


ITR-4000-301 M W, R SW
Complies with approved drawings, installation details
ITR-4000-301 M W, R SW

Complies with approved drawings, installation details Commissioning Report


M W, R SW Commissioning Stage
AIR SEPARATION UNIT (ASU) INSPECTION AND TEST PLAN FOR B
PROJECT FIRE ALARM

Contractor : JGC Indonesia Location : Sumbawa, West Nusa Tenggara, Indonesia

Work Scope : Building

A : Approval
R : Review S/C : SUBCONTRACTOR
W : Witness
SW : Spot Witness JGC : JGC Indonesia
H : Hold Point
P : Provide AMIN : PT. Amman Mineral Industry
V : Verification
M : Monitor/Surveillance

Reference Document
Activity No. Activity Description

INSTALLATION FOR HEAT & SMOKE DETECTORS


3

PREPARATION

Data Sheet, Factory test report, Material certificate,


3.1 Material receiving inspection Packing List, IRC

INSTALLATION & TESTING

3.2 Installation Check Installation details, Layout drawing

Installation details, Approved Procedure, Layout drawing


3.3 Testing

4 INSTALLATION FOR MANUAL ALARM CALL POINT

PREPARATION

Data Sheet, Factory test report, Material certificate,


4.1 Material receiving inspection Packing List, IRC

INSTALLATION & TESTING

4.2 Installation Check Installation details, Layout drawing

Testing Installation details, Approved Procedure, Layout drawing

INSTALLATION FOR ALARM BELL


5

PREPARATION

Data Sheet, Factory test report, Material certificate,


5.1 Material receiving inspection Packing List, IRC

INSTALLATION & TESTING

5.2 Installation Check Installation details, Layout drawing


Installation details, Approved Procedure, Layout drawing
Testing

INSTALLATION FOR ALARM HORN STROBE AND BEACON


6

PREPARATION

Data Sheet, Factory test report, Material certificate,


6.1 Material receiving inspection Packing List, IRC

INSTALLATION & TESTING

6.2 Installation Check Installation details, Layout drawing

6.3 Testing Installation details, Approved Procedure, Layout drawing


ION AND TEST PLAN FOR BUILDING COMPANY No

ARM CONTRACTOR No

CONTRACT No

West Nusa Tenggara, Indonesia Rev.2A

al Industry

Acceptance Criteria Verify Doc. Inspection Level


REMARKS
S/C JGC AMIN

Comply to Data Sheet, Factory test report, Material


certificate, Packing List, IRC ITR-GEN-001 M W, R R

Complies with approved drawings, installation details


ITR-4000-302 M W, R SW

Complies with approved drawings, installation details Commissioning Report


M W,R SW Commissioning Stage

Comply to Data Sheet, Factory test report, Material


certificate, Packing List, IRC ITR-GEN-001 M W,R R

Complies with approved drawings, installation details


ITR-4000-303 M W, R SW

Complies with approved drawings, installation details Commissioning Report M W,R SW Commissioning Stage

92 / 103

Comply to Data Sheet, Factory test report, Material


certificate, Packing List, IRC ITR-GEN-001 M W, R R

Complies with approved drawings, installation details


ITR-4000-304 M W, R SW
Complies with approved drawings, installation details Commissioning Report
M W,R SW Commissioning Stage

Comply to Data Sheet, Factory test report, Material


certificate, Packing List, IRC ITR-GEN-001 M W, R R

Complies with approved drawings, installation details


ITR-4000-305 M W, R SW

Complies with approved drawings, installation details Commissioning Report M W,R SW Commissioning Stage

93 / 103
ITR LIST

No ITR Description

1 MATERIAL RECEIVING INSPECTION REPORT

2 INSTALLATION CHECK FOR FIRE ALARM CONTROL PANEL

3 INSTALLATION CHECK SHEET FOR DETECTORS

4 INSTALLATION CHECK SHEET FOR MANUAL CALL POINT

5 INSTALLATION CHECK SHEET FOR ALARM BELL

6 INSTALLATION CHECK SHEET FOR HORN AND BEACON


Verify Doc.

ITR-GEN-001

ITR-4000-301

ITR-4000-302

ITR-4000-303

ITR-4000-304

ITR-4000-305

94 / 103
AIR SEPARATION UNIT (ASU) PROJECT

SUBJECT : MATERIAL RECEIVING INSPECTION REPORT


Project AIR SEPARATION UNIT (ASU) PROJECT
Client PT. Amman Mineral Industry
Location                                                                         Reff.Dwg.                                                                        
Material/Equipment Identification
a. Material /Equipment Name :
b. Equipment Tag Number :
c. Purchase Order Number :
d. Suplier / Manufacture Name :
e. Material Approval Request (MAR No) :
f. Datasheet No :
g. Batch no (if any) :
h. Packing List :
i. Inspection Release Certificate :

NO DESCRIPTION QTY CONFORMANCE TO SPECT.


YES

Prepared By: Checked / Approved By:


SUBCONTRACTOR CONTRACTOR
Print Name
Signature

Date
ITR-GEN-001
Doc.No.:

Contract No :

Project No :

                  

FORMANCE TO SPECT. REMARKS


NO

Checked / Approved By: Reviewed / Witnessed by


CONTRACTOR COMPANY

95 / 103
ITR-4000-301
Doc.No : Contract No:

AIR SEPARATION UNIT (ASU)


PROJECT

Subject : INSTALLATION CHECK FOR FIRE ALARM CONTROL PANEL Project No : Rev.2A

Project AIR SEPARATION UNIT (ASU) PROJECT Date :                                       


Client  PT. Amman Mineral Indus RFI No :
General
a. Area/Building Name
b. System / Sub-System
c. System Description
d. Part/ Location
e. Reference Drawing/Specification
f. Equipment Tag Number
g. Tag Description
h. IP Rating

No Activities Accept Reject N/A Remarks


1 Check that panel board identification tag is correct and in accordance with drawings

2 Check the panel installed as per drawing

3 Check the panel dimension and elevation are as per drawing

4 Check the circuits are served by correctly-sized breakers and/or fuses

5 Verify that Power Earthing (PE) are correctly installed and terminal points are tightened

6 Verify that Instrument Earthing (IE) are correctly installed and terminal points are tightened

7 Verify that grounded conductors (neutrals) are correctly installed and terminal points are
tightened
8 Confirm Cable Entry and glanding are glanded /sealed properly.

9 Check the cable size for all incoming and outgoing cables is as per drawing

10 Check the Cable Marking & Core Marking are as per the drawing

11 Check that panel board is securely mounted and all the base bolt is installed

12 Check the Terminal Block ID and Number is installed as per approved shop drawings

13 Check the terminal block and connection points are secured properly

14 Panel board is clean and free from dust and paint

15 Ensure the grounding already installed properly

16 Check the IP Rating panel is correct as required

17 Ensure all unused cable entry already plug off properly

18 Ensure the panel door can fully open without any interfere with others

19 Ensure the circuit schedule is correct

Remarks
Prepared by Checked/Approved by Reviewed/Witnessed by,
SUBCONTRACTOR CONTRACTOR COMPANY
Print Name
Signature

Date
ITR-4000-302
Doc.No : Contract No:

AIR SEPARATION UNIT (ASU)


PROJECT

Subject : INSTALLATION CHECK SHEET FOR DETECTORS Project No :

Project :AIR SEPARATION UNIT (ASU) PROJECT


Date RFI No :
Client : PT. Amman Mineral Indu :
General
a. Area/Building Name
b. System / Sub-System
c. System Description
d. Part/ Location
e. Reference Drawing/Specification
f. Equipment Tag Number
g. Tag Description
h. IP Rating

No Activities Accept Reject N/A


1 Check type of detector as per approved material & drawing

2 Check location of detector as per approved drawings

3 Ensure the elevation & orientation are correct as per approved drawing

4 Ensure the IP Rating is correct as per datasheet

5 Check tag number of detector as per approved drawings

6 Check the material is undamaged

7 Check that the cable is correctly plugged to respective port

8 Ensure the equipment is securely mounted or bracket properly

9 Confirm that all incoming power source cable are installed correctly and secure

10 All equipment are properly grounded

11 Ensure no modification has been done of the equipments


Remarks

Prepared by Checked/Approved by Reviewed/Witnessed by,


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
ITR-4000-303
Doc.No : Contract No:

AIR SEPARATION UNIT (ASU)


PROJECT

Subject : INSTALLATION CHECK SHEET FOR MANUAL CALL POINT Project No :

Project : AIR SEPARATION UNIT (ASU) PROJECT Date RFI No :


Client : PT. Amman Mineral Ind :
General
a. Area/Building Name
b. System / Sub-System
c. System Description
d. Part/ Location
e. Reference Drawing/Specification
f. Equipment Tag Number
g. Tag Description
h. IP Rating

No Activities Accept Reject N/A

1 Check type of Manual Call Point as per approved material & drawing

2 Check location of Manual Call Point as per approved drawings

3 Ensure the elevation & orientation are correct as per approved drawing

4 Ensure the IP Rating is correct as per datasheet

5 Check tag number of Manual Call Point as per approved drawings

6 Check the material is undamaged

7 Check that the cable is correctly plugged to respective port


8 Ensure the equipment is securely mounted or bracket properly

9 Confirm that all incoming power source cable are installed correctly and
secure
10 All equipment are properly grounded

11 Ensure no modification has been done of the equipments

Remarks

Prepared by Checked/Approved by Reviewed/Witnessed by,


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
No : Rev. 2A

N/A Remarks
Rev. 2A

Remarks
ITR-4000-304
Doc.No : Contract No:

AIR SEPARATION UNIT (ASU)


PROJECT

Subject : INSTALLATION CHECK SHEET FOR ALARM BELL Project No : Rev. 2A

Project AIR SEPARATION UNIT (ASU) PROJECT


Date RFI No :
Client PT. Amman Mineral Industr :
General
a. Area/Building Name
b. System / Sub-System
c. System Description
d. Part/ Location
e. Reference Drawing/Specification
f. Equipment Tag Number
g. Tag Description
h. IP Rating

No Activities Accept Reject N/A Remarks

1 Check type of Alarm Bell as per approved material & drawing

2 Check location of Alarm Bell as per approved drawings

3 Ensure the elevation & orientation are correct as per approved drawing

4 Ensure the IP Rating is correct as per datasheet

5 Check tag number of Alarm Bell as per approved drawings

6 Check the material is undamaged

7 Check that the cable is correctly plugged to respective port

8 Ensure the equipment is securely mounted or bracket properly

9 Confirm that all incoming power source cable are installed correctly and secure

10 All equipment are properly grounded

11 Ensure no modification has been done of the equipments

12 Check Enclosure glass part and glass to metal sealing gasket / compound are
satisfactory.
13 Check Enclosure flange faces are clean and undamaged.

14 Check flange gap dimensions are within maximal value permitted

15 Equipment is adequately protected against corrosion, weather, vibration and


other adverse factor
16 NO undue accumulation of dust and dirty
Remarks

Prepared by Checked/Approved by Reviewed/Witnessed by,


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
ITR-4000-305
Doc.No : Contract No:

AIR SEPARATION UNIT (ASU)


PROJECT

Subject : INSTALLATION CHECK SHEET FOR HORN AND BEACON Project No

Project : AIR SEPARATION UNIT (ASU) PROJECT


Date :
Client : PT. Amman Mineral Indus RFI No :
General
a. Area/Building Name
b. System / Sub-System
c. System Description
d. Part/ Location
e. Reference Drawing/Specification
f. Equipment Tag Number
g. Tag Description
h. IP Rating

No Activities Accept Reject

1 Check type of Horn & Beacon as per approved material & drawing

2 Check location of Horn & Beacon as per approved drawings

3 Ensure the elevation & orientation are correcct as per approved drawing

4 Ensure the IP Rating is correct as per datasheet

5 Check tag number of Horn & Beacon as per approved drawings

6 Check the material is undamaged

7 Check that the cable is correctly plugged to respective port

8 Ensure the equipment is securely mounted or bracket properly

9 Confirm that all incoming power source cable are installed correctly and secure

10 All equipment are properly grounded

11 Ensure no modification has been done of the equipments


Remarks

Prepared by Checked/Approved by Reviewed/Witnessed by


SUBCONTRACTOR CONTRACTOR COMPANY
Print Name

Signature

Date
: Rev. 2A

N/A Remarks
AIR SEPARATION UNIT (ASU) PROJECT

SUBJECT : PUNCH LIST REPORT

Project Title : AIR SEPARATION UNIT (ASU) PROJECT

Client : PT. Amman Mineral Industry

Area / Location Ref. Drawing No : Punch List No Unit / :


: Facility :

Item Punch List Category Target


No. Punch List Description A/B/C/D Approved Date
JGC AMIN

Note Category Description : : Signifies that the Punch list item, defect, or omission must be repaired or completed before issuance of SYSTEM CONSTRUCTION COMPLETION CER
ABCD : Signifies that the Punch list item, defect,or omission may be completed after Construction Completion during Pre-Commissioning. All Category "B" items
CERTIFICATE.
: Signifies that the Punch list item, defect, or omission can be repaired and/or completed after System HANDOVER, but must be done before TURNOVER
CONTRACTOR and COMPANY.
: Recognized as an item that is desirable to Operations, but is outside the project work scope agreement, is not operationally critical to the facility, process
Category "D" items will not prevent HANDOVER, TURNOVER, or ACCEPTANCE.

SUBCONTRACTOR CONTRACTOR
Prepared As Punch List Completed
Print Name

Signature

Date
Report No :

Doc. No :

Contract No:

Project No:

System / Sub- :
System
Area :
Reference Dwg :

Target Date Accepted


Date Cleared S/C JGC AMIN Remarks

ONSTRUCTION COMPLETION CERTIFICATE.


ommissioning. All Category "B" items must be corrected before issuance of a System HANDOVER

but must be done before TURNOVER. Deviations must be agreed to in writing between

ationally critical to the facility, process, or people, and will be rectified at COMPANY expense.

COMPANY
Completed As Punch List Completed

101 / 103
DRAWING & DOCUMENT
COMMENT RESOLUTION LOG
Title CRL of Site Inspection Test Plan For Building (Drg. No. ACCS-40-411- AS01-S-PLN-
0201)
Vendor Name JGC Indonesia

1A 28-Aug-2022 Commented AMIN

TCE MSR

Rev. Date Status DIS PR ME EL IC CV ST ENV

Reviewed by

Note: Commented/Approved conveyed herein neither relieves Vendor/Contractor of his contractual obligations and his
responsibilities for correctness of dimension materials of construction weights, quantities, design details, assembly fits
system/performance requirement and conformity of supplies with statutory laws as may be applicable, nor does it limit the
Purchaser’s rights under the contract.
OG
CCS-40-411- AS01-S-PLN-

SME

gations and his


assembly fits
able, nor does it limit the

102 / 103
DRAWING & DOCUMENT COMMENT
RESOLUTION LOG

900 KTPA AMIN Captive Copper Smelter Project


Rev. No. 1A
Date of submission 22-Aug-2022
Date of comment 28-Aug-2022
Sr No AMIN Observations/Comments

1 This document is approved with following comments.


a] Inspection level: We will decide the same at a later stage in
consultation with OWNER.

2 Acceptance criteria: Shall be as per Approved drawings/Relevant


Codes and Technical specifications

Page 1 of 1
WING & DOCUMENT COMMENT Drg/Doc No. ACCS-40-411-AS01-S-PLN-0201
OLUTION LOG
Title: Site Inspection Test Plan For Building

JGC Response Status Remarks

Noted.

In JGC understanding, approved


drawing has been design by
CONTRACTOR and approved by
COMPANY that also refer to
specification and relevant codes.
So in JGC understanding, approved
drawing can represent both of spec and
relevant codes that has been discuss
and agreed by AMIN & JGC so that
approved drawing is enough for
acceptance criteria.
ge 1 of 1 103 / 103