You are on page 1of 17

INSTALLATION OF FIRE SPRINKLER SYSTEM EXCLUDING VALVE SYSTEM

Female Sick Room


BILL OF QUANTITIES

ITEM ITEM DESCRIPTION Unit Qty


Total Rate (LKR) AMOUNT (LKR)

-
E MASONRY WORKS -
E.1 Rubble work -
E.1.1 150mm walls
150mm (6") thick solid cement block work in bonded 1:5
m2 200 2,217.00 443,400.00
cement and sand mortar in walls.

G Concreet work

3/4 Concreting 100x100/150x100mm stiffner column (with


G.1 m 70 1,900.00 133,000.00
form work and reinforcement)

3/4 Concreting 100x100/150x100mm stiffner Beam (with


G.2 m 150 1,900.00 285,000.00
form work and reinforcement)

H FLOOR /WALL /CEILING FINISHES

H.1 WALL FINISHES


H.1.1 Internal Plastering

Plaster walls edges to be comprising with galvanised steel


plaster corner bead (Height to match the plaster thickness)
as per the detail drawing and specification

16mm thick 1:5 cement and sand plaster finished semi


m2 350 584.00 204,400.00
rough.
H.2 PAINTING WORK
Internal Painting
Prepare surface and apply external quality paint finish or
approved equivalent colour to architect approval. Paint to
carry 05 years warranty.
painting work m2 600 650.00 390,000.00

WATER PROOfING WORK

Laying of 1000 gauge damp proof polythene membrane


under floors and where excavated surfaces are in contact,
with minimum 150 mm end and side laps, measured net to
the followings.

Water proofing in toilet areas floors & walls up to 0.6m


height with "Baralastic" or equalent approved type
waterproofing compound. All as per the manufacture's
specification & to the Engineer's approval.

Providing sloping screed to base slab with maintaining of


slope, 1:200 towards collecting pit. (75mm maximum thick in
Gr.20 Concrete)

Page 1
INSTALLATION OF FIRE SPRINKLER SYSTEM EXCLUDING VALVE SYSTEM
Female Sick Room
BILL OF QUANTITIES

ITEM ITEM DESCRIPTION Unit Qty


Total Rate (LKR) AMOUNT (LKR)

H.3 Tile Work


H.3.1 Floor Tiling
Supply and laying 600x600mm thick non slipped ceramic
floor tiles laid including 3" thick 1:3 cement sand bedding
and pointing with water proofing tile grout to match the
color of tiles laid in wash room areas as per the detailes
and specifications.
In wash room areas m2 120 4,190.00 502,800.00
H.3.2 Wall Tilling
Supply and laying 300x600mm size, ceramic Polished wall
tiles up to 1800 mm from finish floor level, including tile
adhesive and grout on wash rooms (Excluding the area at
wash basin area) as per the detail drawings and
specification.
Bathroom Wall area m2 120 3,979.00 477,480.00
-

H.3.3 Skirting finishes


100mm high porcelain tile skirting to match the floor tiles
along the block area at labourer areas and top of the
m 70 561.00 39,270.00
skirting comprising with polished stainless steel edge trim
as per the detail drawing and specifications.

H.3.4 Mosaque Tile


Laying mosaque tile for wash rooms walls (100mm strips)
m 70 561.00 39,270.00

H.4 Sanitary installation


Supply and installaition and completion of water clost in
white vitreous china.100mm dia 'S' or 'P' trap siphonic
system, hinged acrulic soft closing seat and lid complete with
H.4.1 duel flush 6/4.5 liter capacity cistern with chromium plated nos 3 24,000.00 72,000.00
flexible hose in toilet. Rate including for secessary fixture,
Angel valves , flexible conectors to water supply line and
sewear lines

Page 2
INSTALLATION OF FIRE SPRINKLER SYSTEM EXCLUDING VALVE SYSTEM
Female Sick Room
BILL OF QUANTITIES

ITEM ITEM DESCRIPTION Unit Qty


Total Rate (LKR) AMOUNT (LKR)

-
Supply and installation of Vanity basing including 40mm dia
plastic bottel trap, 20mm dia 01 nr. Chromium plated piller
tap of approved quality, 40mm dia. Waste plug (push button
H.4.2 type), Chromium plated flexible hose, semi concealed nos 4 20,000.00 80,000.00
brackets with all other accessories and special connection to
complete work in order in sick room. Rate to include for
fixtures.
-
Supply and installation of urinal with water supply system
H.4.3 and other nacessary accessories. nos 2 18,000.00 36,000.00

Supply and installation of chromium plated bidet shower


H.4.4 head with arm. Rate to include for all fixtuers and concealed nos 3 8,000.00 24,000.00
valve.
-
Supply and installation of Soap dish with brackets. Rate shall
H.4.5 nos 3 3,300.00 9,900.00
include all fixtuers.
-
Supply and fixing of 150x150mm moulded uPVC floor trap
H.4.6 gully with 25mm trap and stainless steel cover plate. Rate nos 7 3,000.00 21,000.00
shall include for all fixtures.

-
I Doors And Windows -
Providing and fixing glazing in aluminium door, window,
ventilator shutters and partitions etc. with EPDM rubber
/neoprene gasket etc. complete as per the architectural -
drawings and the directions of engineer-in-charge with
necessory attachement

-
1000x2100 mm oveall size aluminium framed aluminium
I.1 nos 3 20,000.00 60,000.00
door (D1 type)
-
1000x2100 mm oveall size aluminium framed aluminium
I.2 nos 1 20,000.00 20,000.00
door (D2 type)
-
750x2100 mm oveall size aluminium framed aluminium door
I.3 nos 2 18,000.00 36,000.00
(D3 type)
-

Page 3
INSTALLATION OF FIRE SPRINKLER SYSTEM EXCLUDING VALVE SYSTEM
Female Sick Room
BILL OF QUANTITIES

ITEM ITEM DESCRIPTION Unit Qty


Total Rate (LKR) AMOUNT (LKR)

900x600 mm oveall size aluminium framed aluminium door


I.4 nos 5 12,000.00 60,000.00
(FL type)
-
J Electrical Work -
Wiring of light/fan/exsource fan points, from the respective
consumer unit using 2x1.5mm2 Cu/PVC/PVC + 2.5mm2
Cu/PVC(E) cable drawn through securely fixed concealed nos 25 4,500.00 112,500.00
PVC conduit with 10A flush switch as shown in layout
drawings.
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
-
3,046,020.00

Prepared By Checked By

Approved By

Page 4
Installtion of GI Pipes

Item
Description Unit QTY Rate Amount
No
Installtion of 150 mm GI Pipe
Considering 52 m length
1 DN150 ERW Heavy Duty GI Pipe Nos 52.00 7,840.00 407,680.00
Add - Wastage 5% 20,384.00
2 150 x 50 mm Dia. GI Reduser Nos 14.00 5,500.00 77,000.00
3 Bar Cutter Wheel Nos 2.00 950.00 1,900.00
4 Type 10 Welding Rod Kg 5.00 800.00 4,000.00
5 Grinding Wheels Nos 1.00 900.00 900.00
6 Brackets for Hanging the Pipe Nos 14.00 2,750.00 38,500.00
7 Paint and Other Accessories Item 3,500.00
Total Material Cost (A) 553,864.00
Cost for 1 m 10,651.23

Material Cost
8 Fabricating and Hanging 150 mm GI Pipe m 52.00 2,450.00 127,400.00
9 Fabrication and fixing of Brackets Nos 14.00 1,500.00 21,000.00
Add - Tools and Scaffolding 10% 14,840.00
Total Labour Cost (B) 163,240.00
Cost for 1 m 3,139.23

Plant Cost
10 Welding Plant Nos 3.00 800.00 2,400.00
11 Bar Cutter Machine Nos 2.00 500.00 1,000.00
12 Grinder Machine Nos 2.00 350.00 700.00
Total Plant Cost ( C ) 4,100.00
Cost for 1 m 78.85

Total Cost (A+B+C) 721,204.00


Cost for 1 m 13,869.31
12,451.00

Installtion of 100 mm GI Pipe


Considering 24 m length
1 DN100 ERW Heavy Duty GI Pipe m 24.00 5,460.00 131,040.00
Add - Wastage 5% 6,552.00
2 150 x 100 mm GI Reduser Nos 1.00 5,500.00 5,500.00
3 100 x 50 mm GI Reduser Nos 6.00 4,300.00 25,800.00
4 Bar Cutter Wheel Nos 1.00 950.00 950.00
5 Type 10 Welding Rod Kg 3.00 800.00 2,400.00
6 Grinding Wheels Nos 1.00 900.00 900.00
7 Brackets for Hanging the Pipe Nos 6.00 2,750.00 16,500.00
8 Paint and Other Accessories Item 2,500.00
Total Material Cost (A) 192,142.00
Cost for 1 m 8,005.92
Material Cost
9 Fabricating and Hanging 100 mm GI Pipe m 24.00 1,950.00 46,800.00
10 Fabrication and fixing of Brackets Nos 6.00 1,500.00 9,000.00
Add - Tools and Scaffolding 10% 5,580.00
Total Labour Cost (B) 61,380.00
Cost for 1 m 2,557.50

Plant Cost
11 Welding Plant Nos 2.00 800.00 1,600.00
12 Bar Cutter Machine Nos 1.00 500.00 500.00
13 Grinder Machine Nos 1.00 350.00 350.00
Total Plant Cost ( C ) 2,450.00
Cost for 1 m 102.08

Total Cost (A+B+C) 255,972.00


Cost for 1 m 10,665.50

Installtion of 65 mm GI Pipe
Considering 16 m length
1 DN 65 ERW Heavy Duty GI Pipe m 16.00 3,382.40 54,118.40
Add - Wastage 5% 2,705.92
2 65 x 50 mm GI Reduser (Tread Type) Nos 2.00 2,100.00 4,200.00
3 Bar Cutter Wheel 50% Nos 1.00 950.00 475.00
4 Type 10 Welding Rod Kg 0.50 800.00 400.00
5 Grinding Wheels 50% Nos 1.00 900.00 450.00
6 Brackets for Hanging the Pipe Nos 3.00 1,500.00 4,500.00
7 Paint and Other Accessories Item 1,000.00
Total Material Cost (A) 67,849.32
Cost for 1 m 4,240.58

Material Cost
8 Fabricating and Hanging 65 mm GI Pipe m 16.00 1,200.00 19,200.00
9 Fabrication and fixing of Brackets Nos 3.00 800.00 2,400.00
Add - Tools and Scaffolding 10% 2,160.00
Total Labour Cost (B) 23,760.00
Cost for 1 m 1,485.00

Plant Cost
10 Welding Plant Nos 0.50 800.00 400.00
11 Bar Cutter Machine Nos 0.50 500.00 250.00
12 Grinder Machine Nos 1.00 350.00 350.00
13 Tread Cutter Machine with Oil Nos 1.00 900.00 900.00
Total Plant Cost ( C ) 1,900.00
Cost for 1 m 118.75

Total Cost (A+B+C) 93,509.32


Cost for 1 m 5,844.33

Installtion of 50 mm GI Pipe
Considering 12 m length
1 DN 50 ERW Heavy Duty GI Pipe m 12.00 2,268.00 27,216.00
Add - Wastage 5% 1,360.80
2 50 x 40 mm GI Reduser (Tread Type) Nos 1.00 1,700.00 1,700.00
3 Bar Cutter Wheel Nos 1.00 950.00 950.00
4 Brackets for Hanging the Pipe Nos 3.00 1,500.00 4,500.00
5 Paint and Other Accessories Item 800.00
Total Material Cost (A) 36,526.80
Cost for 1 m 3,043.90
Material Cost
6 Fabricating and Hanging 50 mm GI Pipe m 12.00 950.00 11,400.00
7 Fabrication and fixing of Brackets Nos 3.00 800.00 2,400.00
Add - Tools and Scaffolding 10% 1,380.00
Total Labour Cost (B) 15,180.00
Cost for 1 m 1,265.00

Plant Cost
8 Bar Cutter Machine Nos 1.00 500.00 500.00
9 Grinder Machine Nos 0.50 350.00 175.00
10 Tread Cutter Machine with Oil Nos 1.00 900.00 900.00
Total Plant Cost ( C ) 1,575.00
Cost for 1 m 131.25

Total Cost (A+B+C) 53,281.80


Cost for 1 m 4,440.15

Installtion of 40 mm GI Pipe
Considering 6 m length
1 DN 40 ERW Heavy Duty GI Pipe m 6.00 1,960.00 11,760.00
Add - Wastage 5% 588.00
2 Bar Cutter Wheel 50% Nos 1.00 950.00 475.00
3 Brackets for Hanging the Pipe Nos 1.00 1,500.00 1,500.00
4 Paint and Other Accessories Item 500.00
Total Material Cost (A) 14,823.00
Cost for 1 m 2,470.50

Material Cost
5 Fabricating and Hanging 40 mm GI Pipe m 6.00 650.00 3,900.00
6 Fabrication and fixing of Brackets Nos 1.00 800.00 800.00
Add - Tools and Scaffolding 10% 470.00
Total Labour Cost (B) 5,170.00
Cost for 1 m 861.67

Plant Cost
7 Bar Cutter Machine Nos 1.00 500.00 500.00
8 Tread Cutter Machine with Oil Nos 1.00 900.00 900.00
Total Plant Cost ( C ) 1,400.00
Cost for 1 m 233.33

Total Cost (A+B+C) 21,393.00


Cost for 1 m 3,565.50

Installtion of 20 mm GI Pipe
Considering 07 Nos of Sprinkles Points
1 DN 20 ERW Heavy Duty GI Pipe m 7.00 1,204.00 8,428.00
Add - Wastage 5% 421.40
2 50 x 20 mm Reduser Tee Nos 3.00 1,150.00 3,450.00
3 40 x 20 mm Reduser Tee Nos 2.00 980.00 1,960.00
4 Bar Cutter Wheel Nos 1.00 950.00 950.00
5 Paint and Other Accessories Item 200.00
Total Material Cost (A) 15,409.40
Cost for 1 m (1 Nos) 2,201.34

Material Cost
6 Fabricating and Hanging 20 mm GI Pipe m 7.00 160.00 1,120.00
Add - Tools and Scaffolding 10% 112.00
Total Labour Cost (B) 1,232.00
Cost for 1 m 176.00

Plant Cost
7 Bar Cutter Machine Nos 1.00 500.00 500.00
8 Tread Cutter Machine with Oil Nos 1.00 900.00 900.00
Total Plant Cost ( C ) 1,400.00
Cost for 1 m 200.00

Total Cost (A+B+C) 18,041.40


Cost for 1 m 2,577.34
Remarks

28 Points

Nilona Rates

33600

06 Points
2 points
PROPOSED DESTINY TOWERS AT COLOMBO 02. SCHEDULE 01.
DESTINY 02. BILL OF QUANTITIES.
AIR CONDITIONING SYSTEM.

Rate Amount
Ref Description Qty Unit
LKR LKR

AIR CONDITIONING SYSTEM

Page 15 of 17
PROPOSED DESTINY TOWERS AT COLOMBO 02. SCHEDULE 01.
DESTINY 02. BILL OF QUANTITIES.
AIR CONDITIONING SYSTEM.

Rate Amount
Ref Description Qty Unit
LKR LKR

A.10 Any other works not covered by the above items but are
indicated in the specification / technical schedule and
necessary to complete the works as a whole (if not
stated herein, it shall deem to be included or absorbed in
the various breakdown items above):- 1 Item -

1)

Page 16 of 17
PROPOSED DESTINY TOWERS AT COLOMBO 02. SCHEDULE 01.
DESTINY 02. BILL OF QUANTITIES.
AIR CONDITIONING SYSTEM.

Rate Amount
Ref Description Qty Unit
LKR LKR

2)

3)

4)

AC SYSTEM TOTAL AMOUNT CARRIED TO ELECTRICAL SUMMARY. -

Page 17 of 17

You might also like