You are on page 1of 1

P3 Central Command

Centre Implementation
Submittals Comments Sheet

DOCUMENT TYPE MATERIALS SUBMITTAL


TRASMITTAL ST-QC-TR-001
DOCUMENT NO. MS-2022-141-INT-003 REV C0
DISCIPLINE: INTERIOR
DESCRIPTION: RAISED ACCESS FLOOR
MANUFACTURER:
SUPPLIER/SUB CONTRACTOR:
A: Accepted - Work to Proceed C: Revise and Resubmit - Work Not Proceed
B: Accepted as Noted - Work to proceed Subject to Incorporating Comments D: Rejected - Not Required to Resubmit

QC’s Comments:

1. Provide required QCDD / fire related compliance.

2. Provide installation details of LED light on the raised floor.

Commented
By AV
Date 29th Jan 2023

Page 1 of 1