PROGRAM OF WORKS

Project Name: 3 Storey Parking Building


Location: Barangay San Roque (ciudad)

Activities Task Name Duration Days Start Date End Date

1-2 Site Setting 1 1/1/2024 1/1/2024


2-3 Layout 2 1/2/2024 1/4/2024
2-4 Delivery of Materials 1 1/1/2024 1/1/2024
4-5 Perimeter Fencing 2 1/2/2024 1/4/2024
4-6 Construction of Temp. Facilities 2 1/2/2024 1/4/2024
3-5 Excavation of Footings 7 1/5/2024 1/12/2024
5-7 Gravel Bedding 2 1/25/2024 1/27/2024
6-7 Fabrication of Rebars (for columns, footings and septic) 10 1/4/2024 1/14/2024
7-8 Installation of Forms (for columns and footing) 5 1/18/2024 1/23/2024
8-9 Installation of Rebars (for columns and footing) 8 1/25/2024 2/2/2024
9-10 Concrete Pouring for Footing 1 2/6/2024 2/7/2024
10-11 Installation of Forms (for columns and 1st lift) 4 2/7/2024 2/11/2024
10-12 Excavation for Tie Beams and Septic 10 2/7/2024 2/17/2024
12-13 Installation of Rebars (for tie beams and septic) 8 2/21/2024 2/29/2024
11-14 Stripping of Forms (for colum, 1st lift and septic) 1 2/13/2024 2/14/2024
14-15 Concrete Pouring for (for tie beams, septic and column 1st lift) 4 2/14/2024 2/18/2024
13-15 Delivery of Materials 1 2/6/2024 2/7/2024
10-15 Backfiling 5 3/5/2024 3/10/2024
15-16 Installation of Rebars (for 1st column to 2nd flr) 8 3/12/2024 3/20/2024
16-19 Installation of Forms (for 1st column to 2nd flr) 6 3/22/2024 3/28/2024
19-20 Concrete Pouring (1st column to 2nd flr and septic covering) 1 3/30/2024 3/31/2024
15-17 Fabrication of Rebars (for 2nd flr slab, beams and stairs) 15 3/12/2024 3/27/2024
15-18 Installation of Forms (for 2nd flr slab, beams and stairs) 8 3/12/2024 3/20/2024
18-21 Installation of Rebars (for 2nd flr slab, beams and stairs) 13 3/22/2024 4/4/2024
17-22 Installation of black out for Plumbing at 2nd flr 2 4/2/2024 4/4/2024
21-22 Installation of black out for Electrical at 2nd flr 2 4/10/2024 4/12/2024
20-22 Installation of black out for Mechanical at 2nd flr 2 4/2/2024 4/4/2024
22-23 Concrete Pouring for 2nd flr slab, beams and stairs 1 4/12/2024 4/13/2024
23-24 Stripping of forms (at 2nd floor slab) 4 4/13/2024 4/17/2024
23-25 Fabrication of Rebars 2nd flr-3rd flr columns 12 4/13/2024 4/25/2024
25-26 Installation of Rebars (2nd-3rd flr) 10 5/1/2024 5/11/2024
24-26 Installation of Forms (2nd-3rd flr) 5 4/19/2024 4/24/2024
26-27 Concrete Pouring (2nd flr column) 1 5/15/2024 5/16/2024
26-28 Installation CHB #6 and #4 exterior and interior walls 1st flr 14 4/26/2024 5/10/2024
28-30 Plastering of CHB partitions and exterior walls 12 5/16/2024 5/28/2024
27-29 Stripping of Forms (2nd flr column) 3 5/16/2024 5/19/2024
28-29 Preparation and Clearing for Slab on Grade (SOG) 2 5/26/2024 5/28/2024
29-31 Installation of Rebars for Slab on Grade (SOG) 4 6/1/2024 6/5/2024
29-32 Delivery of Materials 1 5/17/2024 5/18/2024
31-32 Concrete Pouring (SOG) 1 6/7/2024 6/8/2024
31-33 Fabrication of Rebars (for beams, slabs, and stairs at 3rd flr) 15 6/8/2024 6/23/2024
32-34 Installation of Forms (for beams, slabs, and stair ar 3rd flr) 13 5/18/2024 5/31/2024
33-35 Installation of Rebars (for beams, slabs, and stair ar 3rd flr) 13 6/8/2024 6/21/2024
34-36 Installation of Blackout for Plumbing at 3rd flr 2 6/29/2024 7/1/2024
35-37 Installation of Blackout for Electrical at 3rd flr 2 7/3/2024 7/5/2024
36-37 Installation of Blackout for Mechanical at 3rd flr 2 6/27/2024 6/29/2024
37-38 Concrete Pouring (for beams, slab and stairs ar 3rd floor) 1 7/5/2024 7/6/2024
38-39 Stripping of Forms (for beams, slab and stairs ar 3rd floor) 4 7/6/2024 7/10/2024
38-40 Fabrication of Rebars (for beams, slab and stairs ar 3rd floor) 8 7/6/2024 7/14/2024
40-41 Installation of Rebars (for 3rd flr columns) 6 7/18/2024 7/24/2024
39-42 Piling of CHB #6 and #4 for exterior and interior walls at 2nd fl 14 7/12/2024 7/26/2024
41-42 Plastering of walls at 2nd flr 6 7/26/2024 8/1/2024
42-43 Concrete Pouring (for columns at 3rd floor) 1 8/3/2024 8/4/2024
43-44 Installation of Forms (for roof beams) 5 8/6/2024 8/11/2024
43-45 Piling of CHB #6 and #4 for exterior and interior walls at 3rd flr 6 8/6/2024 8/12/2024
45-46 Plastering of walls at 3rd flr 5 8/14/2024 8/19/2024
44-46 Installation of Rebars at roof beam 6 8/13/2024 8/19/2024
46-47 Fabrication of steel truss and fire exit 6 8/21/2024 8/27/2024
46-48 Concrete Pouring at Roof Beam 1 8/21/2024 8/22/2024
46-49 Installation of Steel Truss and Fire Exit 4 8/29/2024 9/2/2024
47-50 Installation of Fire Protection and Fixtures 5 9/4/2024 9/9/2024
48-51 Installation of Canopy Cladding 2 8/22/2024 8/24/2024
49-51 Installation of Roofs 2 9/4/2024 9/6/2024
50-52 Installation of Electrical Fixtures 3 9/11/2024 9/14/2024
51-53 Installation of Plumbing Fixtures 3 9/6/2024 9/9/2024
52-53 Tile Works 4 9/14/2024 9/18/2024
53-54 Paint Works 16 9/20/2024 10/6/2024
54-55 Installation of doors and window 2 10/12/2024 10/14/2024
55-56 Clearing and Furnishing 2 10/16/2024 10/18/2024