You are on page 1of 1

Construction of Sukh Chayn Residence at F-

10 Markaz Islamabad

Dates for OFM of Civil Works at SCV End


Sr No Civil Materials (OFM) Dates Remarks
Kerb Stone & Concrete Paver Sizes (External Almost One month will consume for the
1 18/06/2023 delievery on site from SCV.
Development)

Almost 03 weeks will be consumed by SCV


2 Tile for ablution area - Basement 02 09/06/2023 for its color shade selection and
procurement.

3 Granite of Entrance area 13/06/2023 SCV

4 Granite for upstands - Void area (both towers) 18/06/2023 SCV

5 Granite for Sky light coping 18/06/2023 SCV

You might also like