Attachment 2 -

Consolidated Asset Schedule - WSWS Development

ID WBS Task Name Duration Start Finish 2014 2015


Oct o Dec Jan e Mar Apr a Jun Jul Aug e Oct o Dec Jan e
0 0 Consolidated Asset Schedule - WSWS Development 411.25 days Nov 7 '13 Nov 7 '14

1 1 RP13 - Proposed Schedule 399 days Nov 7 '13 Oct 27 '14

8 1.7 Proposal received from Braemar Casbarian 0 days Feb 17 '14 Feb 17 '14 Feb 17 '14

9 1.8 Merit Award to Braemar Casbarian 281 days Feb 20 '14 Oct 27 '14

13 1.8.4 Contract Award 0 days Mar 23 '14 Mar 23 '14 Mar 23 '14

29 1.8.20 RP13 structure available 0 days Oct 27 '14 Oct 27 '14 Oct 27 '14

30 2 Mobile Offshore Processing Unit (MOPU) - Proposed Schedule 403 days Nov 7 '13 Oct 31 '14

36 2.6 Option 1 - pursue Merit Contract 292 days Feb 13 '14 Oct 31 '14

38 2.6.2 Board Approval received 0 days Feb 14 '14 Feb 14 '14 Feb 14 '14

57 2.6.21 Facility In-Service (Option 1) 0 days Oct 31 '14 Oct 31 '14 Oct 31 '14

58 3 SWS Submarine Pipelines - 19 Priority pipelines - Proposed Schedule 301 days Feb 13 '14 Nov 7 '14

59 3.1 Option 1 - pursue Merit Contract 301 days Feb 13 '14 Nov 7 '14

68 3.1.9 2 inch to 6 inch Reel-lay (14 pipelines) 257 days Mar 24 '14 Nov 7 '14

73 3.1.9.5 2 inch to 6 inch Reel-Lay pipelines in service 0 days Nov 7 '14 Nov 7 '14 Nov 7 '14

74 3.2 Option 2 - Selective Tender to previously responsive Bidders 301 days Feb 13 '14 Nov 7 '14

87 3.2.13 8 inch to 12 inch Conventional Lay (5 pipelines) 215 days Apr 30 '14 Nov 7 '14

93 3.2.13.6 Pipelines in service 0 days Nov 7 '14 Nov 7 '14 Nov 7 '14