Project : PROPOSED RE-CONST. OF TWO STOREY COMM'L BLDG. W/ P & S SERVICE BLDG.

Location : Tiguma, Pagadian


Subject : PROPOSED BID SCHEDULE OF ACTIVITIES (REVISED)
Date : August 23, 2019

ITEM ACTIVITIES NO. OF TIMELINE VENUE INCHARGE


NOS. DAYS From To

1.0 Submission on Scope of PM Services (Final) 1 Aug. 16 '19 Head Office CB Felix
Head NJ Ayag &
2.0 Selection and Evaluation of PM Proposal for Bid 1 Aug. 16 '19 Head NJ Ayag &
Office CB Felix
3.0 Working Detailed Plans (For Final Revision) 2 Aug. 20 '19 Head Office CB Felix
Office CB Felix
4.0 Signing of Working Detailed Plans (Blue Prints) 2 Aug. 23 '19 Head Office CB Felix
5.0 Preparationn & Issuance of Invitation for Bids 1 Aug. 27 '19 JDAA Office JDAA
6.0 Pre-Bid Conference 1 Sept. 3 '19 (@ 10:00 am) Head NJ Ayag &
Office CB Felix
7.0 Issuance & Availability of Bid / Tender Documents 3 Sept. 3 '19 Sept. 6 '19 JDAA Office JDAA
8.0 Issuance of Site Inspection Form 1 Sept. 3 '19 Project Site Reg. Manager
9.0 Bid Preparation / Request for Clarification and 30 Sept. 4 '19 Oct. 3 '19 JDAA Office Bidders
Actual Site Inspection Project Site
10.0 Submission of Sealed Bid Documents 1 Oct. 4 '19 (@ 5: 00 PM) Head NJ Ayag &
11.0 Opening of Bid Documents 1 Oct. 7 '19 Office CB Felix
12.0 Evaluation of Bids 3 Oct. 8 '19 Oct. 11 '19 Tiguma PM
13.0 Post Qualification (For Winning Bidder) 1 Oct. 15 '19 Project Site PM
14.0 Notification of Negotiation 1 Oct. 16 '19 Head Office PM
15.0 Approval of Resolution / Issuance of NOA 1 Oct. 17 '19 Head NJ Ayag &
(Notice of Awards) Office CB Felix
16.0 Submission and Approval of ADB 4 Oct. 18 '19 Oct. 23 '19 Head CB Felix
(For PF, PM, OSM and Contract Cost) Office
17.0 Contract Signing and Preparation of Payment for DP 0.5 Oct. 24 '19 Head CB Felix
(For PM and Awarded Bidder) Office
ITEM ACTIVITIES NO. OF TIMELINE VENUE INCHARGE
NOS. DAYS From To

18.0 Issuance of NTP (Notice to Proceed) 0.5 Oct. 24 '19 Head Office CB Felix
19.0 Pre-const. Meeting 1 Oct. 26 '19 Project Site PM &
20.0 Implementation / Start of Construction Oct. 30 '19 Project Site Contractor
(Duration : Construction Works : 10 Months)
(Demolition Works : 1.5 Month)

Prepared by : Checked by : Confirmed by :

CESAR B. FELIX NORAJANE P. AYAG ARCH. JOSE D. ALVARADO


FEA Bldg. Coordinator FEA Administrator Principal Architect

Approved by :

GUILBERT R. OLBEZ
SVP - Admin