You are on page 1of 3

WBHO Checkers programme excl Alu Barlow Park- Part 3 Section of Works

Activities: Entire program


2023 2024
Current
Jan February March April May June July August September October November December January
Activity description Durn Start Finish 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19

B240 - Checkers Critical works tracker 176 20 Jan 23 22 Sep 23


- Predesessors
B750 - As it stands bar Concrete 26 31 Mar 23 05 May 23 B750 As it stands bar Concrete
B830 - External Yard and Facade 45 08 May 23 07 Jul 23
B840 - Yard Surface bed 13 08 May 23 24 May 23
B850 - Access 0 08 May 23 B850 Access
B860 - Install services(1x stormwater pipe) 3 08 May 23 10 May 23 B860 Install services(1x stormwater pipe)
B870 - G5 to final cut 2 11 May 23 12 May 23 B870 G5 to final cut
- Box outs for bollards and falls - Local (wash down)
B880 - Shutter to edges 1 15 May 23 15 May 23 B880 Shutter to edges
B910 - Rebar (around cols only) 1 15 May 23 15 May 23 B910 Rebar (around cols only)
B900 - Cast concrete to fall 1 16 May 23 16 May 23 B900 Cast concrete to fall
B890 - Sawcut 1 17 May 23 17 May 23 B890 Sawcut
B920 - Inspect 0 18 May 23 B920 Inspect
B970 - Curing 5 18 May 23 24 May 23 B970 Curing

B930 - Yard - trades 37 18 May 23 07 Jul 23


B950 - Setout walls 1 18 May 23 18 May 23 B950 Setout walls
B940 - Brick up facebrick walls 12 25 May 23 09 Jun 23 B940 Brick up facebrick walls
B960 - Cast wash down 4 25 May 23 30 May 23 B960 Cast wash down
B980 - Install bollards 5 12 Jun 23 16 Jun 23 B980 Install bollards
B990 - Install gates 8 19 Jun 23 28 Jun 23 B990 Install gates
C000 - Yard MEP Second and Final Soffit level 6 29 Jun 23 06 Jul 23 C000 Yard MEP Second and Final Soffit level
C010 - Snag yard 1 07 Jul 23 07 Jul 23 C010 Snag yard

C020 - External facade +- 6m height 30 08 May 23 16 Jun 23


C030 - Access 0 08 May 23 C030 Access
C040 - Brick up 46 000 bricks 27 08 May 23 13 Jun 23 C040 Brick up 46 000 bricks
C050 - Snag facade and joint seal 3 14 Jun 23 16 Jun 23 C050 Snag facade and joint seal

B250 - Mechanical, Electrical and Plumbing (MEP) 41 03 Apr 23 29 May 23


By Area
A100 - Soffit Services 41 03 Apr 23 29 May 23
A010 - BOH (Galvanised) 30 03 Apr 23 12 May 23
A110 - Access from soffit 0 03 Apr 23 A110 Access from soffit
A120 - Havc 1st 10 03 Apr 23 14 Apr 23 A120 Havc 1st
A130 - Plumbing 1st 8 17 Apr 23 26 Apr 23 A130 Plumbing 1st
A140 - Electrical 1st 8 27 Apr 23 08 May 23 A140 Electrical 1st
A150 - Fire 1st (dand fire only) 3 09 May 23 11 May 23 A150 Fire 1st (dand fire only)
A160 - Inspect 1 12 May 23 12 May 23 A160 Inspect

A020 - Office (Painted services) 28 04 Apr 23 11 May 23


A040 - Access from soffit 0 04 Apr 23 A040 Access from soffit
A050 - Havc 1st 10 04 Apr 23 17 Apr 23 A050 Havc 1st
A060 - Plumbing 1st 7 18 Apr 23 26 Apr 23 A060 Plumbing 1st
A070 - Electrical 1st 7 27 Apr 23 05 May 23 A070 Electrical 1st
A080 - Fire 1st (dand fire only) 3 08 May 23 10 May 23 A080 Fire 1st (dand fire only)
A090 - Inspect for paint 1 11 May 23 11 May 23 A090 Inspect for paint

A170 - Ablutions (Painted services) 16 03 Apr 23 24 Apr 23


A180 - Access from soffit 0 03 Apr 23 A180 Access from soffit
A190 - Havc 1st 4 03 Apr 23 06 Apr 23 A190 Havc 1st
A200 - Plumbing 1st 5 07 Apr 23 13 Apr 23 A200 Plumbing 1st
A210 - Electrical 1st 5 14 Apr 23 20 Apr 23 A210 Electrical 1st
A220 - Fire 1st (hand fire only) 1 21 Apr 23 21 Apr 23 A220 Fire 1st (hand fire only)
A230 - Inspect for paint 1 24 Apr 23 24 Apr 23 A230 Inspect for paint

A240 - Main trading and managers office 34 05 Apr 23 22 May 23


A250 - Access from soffit 0 05 Apr 23 A250 Access from soffit
A260 - Havc 1st 12 05 Apr 23 20 Apr 23 A260 Havc 1st
A270 - Plumbing 1st 10 21 Apr 23 04 May 23 A270 Plumbing 1st
A280 - Electrical 1st 8 05 May 23 16 May 23 A280 Electrical 1st
A290 - Fire 1st (dand fire only) 3 17 May 23 19 May 23 A290 Fire 1st (dand fire only)
A300 - Inspect for paint 1 22 May 23 22 May 23 A300 Inspect for paint

A770 - Paint / Spray soffit services 23 27 Apr 23 29 May 23


A780 - Access 70% of service installed 0 27 Apr 23 A780 Access 70% of service installed
A790 - Prep for paint & Cover facebricks 2 27 Apr 23 28 Apr 23 A790 Prep for paint & Cover facebricks
A800 - Spray Services 15 01 May 23 19 May 23 A800 Spray Services
A810 - Prime and Paint all soffit exc BOH 15 08 May 23 26 May 23 A810 Prime and Paint all soffit exc BOH
A820 - Inspect 1 29 May 23 29 May 23 A820 Inspect

A310 - Internal areas (Ablution/ Office/ Main / 176 20 Jan 23 22 Sep 23


BOH)
A440 - Trades- Ablutions 74 03 Apr 23 13 Jul 23
A320 - Abluitions 41 03 Apr 23 29 May 23
A340 - Access 0 03 Apr 23 A340 Access

Printed 17:46:58 15 May 2023 Page 1 of 3


Candy 2.01f13.2 (2 6 0) R
WBHO Checkers programme excl Alu Barlow Park- Part 3 Section of Works
Activities: Entire program
2023 2024
Current
Jan February March April May June July August September October November December January
Activity description Durn Start Finish 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19

A330 - Stock brick to height 10 03 Apr 23 14 Apr 23 A330 Stock brick to height
A350 - Wall services(Ducting and Plumbing 6 17 Apr 23 24 Apr 23 A350 Wall services(Ducting and Plumbing penetratrations to final finish requirement )
penetratrations to final finish requirement )
A360 - Wall services electrical (Inc DB tray) 5 25 Apr 23 01 May 23 A360 Wall services electrical (Inc DB tray)
A370 - Inspect for plaster 1 02 May 23 02 May 23 A370 Inspect for plaster
A380 - Plaster walls (2 coat above tiles) 6 03 May 23 10 May 23 A380 Plaster walls (2 coat above tiles)
A390 - Prime walls where required 2 11 May 23 12 May 23 A390 Prime walls where required
A400 - Install shaddow lines 2 15 May 23 16 May 23 A400 Install shaddow lines
A410 - Ceiling grids 4 17 May 23 22 May 23 A410 Ceiling grids
A420 - Electrical second fix 2 23 May 23 24 May 23 A420 Electrical second fix
A430 - Ducting second fix soffit 2 25 May 23 26 May 23 A430 Ducting second fix soffit
A450 - Inspect 1 29 May 23 29 May 23 A450 Inspect

A030 - Finishing 33 30 May 23 13 Jul 23


A470 - Access 0 30 May 23 A470 Access
A480 - Ceilings - board and skimm 3 30 May 23 01 Jun 23 A480 Ceilings - board and skimm
A490 - Paint final 3 02 Jun 23 06 Jun 23 A490 Paint final
A500 - MEP Final fixes 5 07 Jun 23 13 Jun 23 A500 MEP Final fixes
A510 - Doors and Ironmongary 4 14 Jun 23 19 Jun 23 A510 Doors and Ironmongary
A520 - Tiling & Cnr Protectors 12 20 Jun 23 05 Jul 23 A520 Tiling & Cnr Protectors
A530 - Joinery and Vanity 5 06 Jul 23 12 Jul 23 A530 Joinery and Vanity
A460 - Inspect 1 13 Jul 23 13 Jul 23 A460 Inspect

A540 - Trades- Office 78 05 Apr 23 21 Jul 23


A830 - Steel support & bulkehead 21 09 May 23 06 Jun 23
A900 - Access from Brickwork 0 09 May 23 A900 Access from Brickwork
A890 - Install bulkhead steel 6 09 May 23 16 May 23 A890 Install bulkhead steel
A880 - Ceiling Grid to bulkhead 5 17 May 23 23 May 23 A880 Ceiling Grid to bulkhead
A870 - Board and Skim 3 24 May 23 26 May 23 A870 Board and Skim
A860 - Prime bulkead 2 29 May 23 30 May 23 A860 Prime bulkead
A840 - Snag bulkhead 2 31 May 23 01 Jun 23 A840 Snag bulkhead
A850 - Install bottom track 2 02 Jun 23 05 Jun 23 A850 Install bottom track
A910 - Inspect 1 06 Jun 23 06 Jun 23 A910 Inspect

A550 - Office 55 05 Apr 23 20 Jun 23


A560 - Access 0 05 Apr 23 A560 Access
A570 - Stock brick to height 10 05 Apr 23 18 Apr 23 A570 Stock brick to height
A580 - Wall services(Ducting and Plumbing 8 19 Apr 23 28 Apr 23 A580 Wall services(Ducting and Plumbing penetratrations to final finish requirement )
penetratrations to final finish requirement )
A590 - Wall services electrical (Inc DB tray) 5 01 May 23 05 May 23 A590 Wall services electrical (Inc DB tray)
B740 - Cashroom Slab / Lintols and 90mm concrete 5 08 May 23 12 May 23 B740 Cashroom Slab / Lintols and 90mm concrete
A600 - Inspect for plaster 1 08 May 23 08 May 23 A600 Inspect for plaster
A610 - Plaster walls (2 coat above tiles) 15 09 May 23 29 May 23 A610 Plaster walls (2 coat above tiles)
A620 - Prime walls where required 5 30 May 23 05 Jun 23 A620 Prime walls where required
A630 - Install shaddow lines 2 06 Jun 23 07 Jun 23 A630 Install shaddow lines
A640 - Ceiling grids 4 08 Jun 23 13 Jun 23 A640 Ceiling grids
A650 - Electrical second fix 2 14 Jun 23 15 Jun 23 A650 Electrical second fix
A660 - Ducting second fix soffit 2 16 Jun 23 19 Jun 23 A660 Ducting second fix soffit
A670 - Inspect 1 20 Jun 23 20 Jun 23 A670 Inspect

A680 - Finishing 33 07 Jun 23 21 Jul 23


A690 - Access 0 07 Jun 23 A690 Access
A700 - Ceilings - board and skimm 3 07 Jun 23 09 Jun 23 A700 Ceilings - board and skimm
A710 - Paint final 3 12 Jun 23 14 Jun 23 A710 Paint final
A720 - MEP Final fixes 5 15 Jun 23 21 Jun 23 A720 MEP Final fixes
B680 - Install safe door and finish plaster 3 22 Jun 23 26 Jun 23 B680 Install safe door and finish plaster
A730 - Doors and Ironmongary 4 22 Jun 23 27 Jun 23 A730 Doors and Ironmongary
A740 - Tiling & Cnr Protectors 12 28 Jun 23 13 Jul 23 A740 Tiling & Cnr Protectors
A750 - Joinery and Vanity 5 14 Jul 23 20 Jul 23 A750 Joinery and Vanity
A760 - Inspect 1 21 Jul 23 21 Jul 23 A760 Inspect

A920 - Trades- Main Trading and Managers 124 04 Apr 23 22 Sep 23


A930 - Steel support & bulkehead 21 23 May 23 20 Jun 23
A940 - Access from Brickwork 0 23 May 23 A940 Access from Brickwork
A950 - Install bulkhead steel 6 23 May 23 30 May 23 A950 Install bulkhead steel
A960 - Ceiling Grid to bulkhead 5 31 May 23 06 Jun 23 A960 Ceiling Grid to bulkhead
A970 - Board and Skim 3 07 Jun 23 09 Jun 23 A970 Board and Skim
A980 - Prime bulkead 2 12 Jun 23 13 Jun 23 A980 Prime bulkead
A990 - Snag bulkhead 2 14 Jun 23 15 Jun 23 A990 Snag bulkhead
B000 - Install bottom track 2 16 Jun 23 19 Jun 23 B000 Install bottom track
B010 - Inspect 1 20 Jun 23 20 Jun 23 B010 Inspect

B020 - Main trading 74 04 Apr 23 14 Jul 23


B030 - Access 0 04 Apr 23 B030 Access
B040 - Stock brick to height 18 04 Apr 23 27 Apr 23 B040 Stock brick to height
B050 - Wall services(Ducting and Plumbing 6 28 Apr 23 05 May 23 B050 Wall services(Ducting and Plumbing penetratrations to final finish requirement )
penetratrations to final finish requirement )
B060 - Wall services electrical (Inc DB tray) 10 08 May 23 19 May 23 B060 Wall services electrical (Inc DB tray)

Printed 17:46:58 15 May 2023 Page 2 of 3


Candy 2.01f13.2 (2 6 0) R
WBHO Checkers programme excl Alu Barlow Park- Part 3 Section of Works
Activities: Entire program
2023 2024
Current
Jan February March April May June July August September October November December January
Activity description Durn Start Finish 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24 1 8 15 22 29 5 12 19

B070 - Inspect for plaster 1 22 May 23 22 May 23 B070 Inspect for plaster
B080 - Plaster walls (2 coat above tiles) 12 23 May 23 07 Jun 23 B080 Plaster walls (2 coat above tiles)
B090 - Prime walls where required 6 08 Jun 23 15 Jun 23 B090 Prime walls where required
B100 - Install shaddow lines 2 16 Jun 23 19 Jun 23 B100 Install shaddow lines
B110 - Ceiling grids 8 20 Jun 23 29 Jun 23 B110 Ceiling grids
B120 - Electrical second fix 15 23 Jun 23 13 Jul 23 B120 Electrical second fix
B130 - Ducting second fix soffit 10 26 Jun 23 07 Jul 23 B130 Ducting second fix soffit
B140 - Inspect 1 14 Jul 23 14 Jul 23 B140 Inspect

B150 - Finishing 50 17 Jul 23 22 Sep 23


B160 - Access 0 17 Jul 23 B160 Access
B170 - Ceilings - board and skimm 10 17 Jul 23 28 Jul 23 B170 Ceilings - board and skimm
B180 - Paint final 8 31 Jul 23 09 Aug 23 B180 Paint final
B190 - MEP Final fixes 5 31 Jul 23 04 Aug 23 B190 MEP Final fixes
B200 - Doors and Ironmongary 5 08 Aug 23 14 Aug 23 B200 Doors and Ironmongary
B210 - Tiling & Cnr Protectors 12 15 Aug 23 30 Aug 23 B210 Tiling & Cnr Protectors
B220 - Joinery and Vanity 6 28 Aug 23 04 Sep 23 B220 Joinery and Vanity
B270 - Self level grout 10 05 Sep 23 18 Sep 23 B270 Self level grout
B280 - Sand down self leveling 3 19 Sep 23 21 Sep 23 B280 Sand down self leveling
B230 - Inspect 1 22 Sep 23 22 Sep 23 B230 Inspect

B340 - Trades- Back of House (BOH) 105 06 Apr 23 30 Aug 23


B350 - Steel support & bulkehead 21 02 May 23 30 May 23
B360 - Access from Brickwork 0 02 May 23 B360 Access from Brickwork
B370 - Install bulkhead steel 6 02 May 23 09 May 23 B370 Install bulkhead steel
B380 - Ceiling Grid to bulkhead 5 10 May 23 16 May 23 B380 Ceiling Grid to bulkhead
B390 - Board and Skim 3 17 May 23 19 May 23 B390 Board and Skim
B400 - Prime bulkead 2 22 May 23 23 May 23 B400 Prime bulkead
B410 - Snag bulkhead 2 24 May 23 25 May 23 B410 Snag bulkhead
B420 - Install bottom track 2 26 May 23 29 May 23 B420 Install bottom track
B430 - Inspect 1 30 May 23 30 May 23 B430 Inspect

B690 - Cold Rooms / Freezer 35 25 May 23 12 Jul 23


- Access
B700 - Measure and order 12 25 May 23 09 Jun 23 B700 Measure and order
B710 - Install cold rooms 15 12 Jun 23 30 Jun 23 B710 Install cold rooms
B720 - Snag and inspect- With WSP 2 03 Jul 23 04 Jul 23 B720 Snag and inspect- With WSP
B730 - Cast coldroom infill and floors (by hand) 6 05 Jul 23 12 Jul 23 B730 Cast coldroom infill and floors (by hand)

B440 - Walls 71 06 Apr 23 13 Jul 23


B450 - Access 0 06 Apr 23 B450 Access
B460 - Stock brick to height 18 06 Apr 23 01 May 23 B460 Stock brick to height
B470 - Wall services(Ducting and Plumbing 6 02 May 23 09 May 23 B470 Wall services(Ducting and Plumbing penetratrations to final finish requirement )
penetratrations to final finish requirement )
B480 - Wall services electrical (Inc DB tray) 10 10 May 23 23 May 23 B480 Wall services electrical (Inc DB tray)
B490 - Inspect for plaster 1 24 May 23 24 May 23 B490 Inspect for plaster
B500 - Plaster walls (2 coat above tiles) 5 25 May 23 31 May 23 B500 Plaster walls (2 coat above tiles)
B510 - Prime walls where required 3 01 Jun 23 05 Jun 23 B510 Prime walls where required
B520 - Install shaddow lines 2 06 Jun 23 07 Jun 23 B520 Install shaddow lines
B530 - Ceiling grids 5 08 Jun 23 14 Jun 23 B530 Ceiling grids
B540 - Electrical second fix 7 15 Jun 23 23 Jun 23 B540 Electrical second fix
B550 - Ducting second fix soffit 8 03 Jul 23 12 Jul 23 B550 Ducting second fix soffit
B560 - Inspect 1 13 Jul 23 13 Jul 23 B560 Inspect

B570 - Finishing 34 14 Jul 23 30 Aug 23


B580 - Access 0 14 Jul 23 B580 Access
B590 - Ceilings - board and skimm 7 14 Jul 23 24 Jul 23 B590 Ceilings - board and skimm
B600 - Paint final 5 25 Jul 23 31 Jul 23 B600 Paint final
B610 - MEP Final fixes 5 25 Jul 23 31 Jul 23 B610 MEP Final fixes
B620 - Doors and Ironmongary * Apex doors to go in 6 01 Aug 23 08 Aug 23 B620 Doors and Ironmongary * Apex doors to go in last
last
B630 - Tiling & Cnr Protectors 6 09 Aug 23 16 Aug 23 B630 Tiling & Cnr Protectors
B640 - Joinery and Vanity 6 17 Aug 23 24 Aug 23 B640 Joinery and Vanity
B650 - Patch Floor 2 25 Aug 23 28 Aug 23 B650 Patch Floor
B660 - Sand down 1 29 Aug 23 29 Aug 23 B660 Sand down
B670 - Inspect 1 30 Aug 23 30 Aug 23 B670 Inspect

B780 - Completion 33 20 Jan 23 07 Mar 23


B790 - Clean / Acid Wash 5 20 Jan 23 26 Jan 23 Clean / Acid Wash
B810 - Handover certs 1 27 Jan 23 27 Jan 23 B810 Handover certs
B800 - Snag 2 30 Jan 23 31 Jan 23 B800 Snag
B820 - Desnag and Inspect 5 01 Feb 23 07 Feb 23 B820 Desnag and Inspect
B260 - Post BO items- Per BO requirements 33 20 Jan 23 07 Mar 23
B290 - Cover trench (Bondek and Concrete cart 6 20 Jan 23 27 Jan 23 Cover trench (Bondek and Concrete cart concrete by weelbarrow and protect floor)
concrete by weelbarrow and protect floor)
B300 - Final self leveling 5 30 Jan 23 03 Feb 23 B300 Final self leveling
B310 - Sand self level 2 06 Feb 23 07 Feb 23 B310 Sand self level
B320 - Vinyl to Main trading 15 08 Feb 23 28 Feb 23 B320 Vinyl to Main trading
B330 - Final Snag 5 01 Mar 23 07 Mar 23 B330 Final Snag
Printed 17:46:58 15 May 2023 Page 3 of 3