Standard Barchart
Standard Barchart
A330 - Stock brick to height 10 03 Apr 23 14 Apr 23 A330 Stock brick to height
A350 - Wall services(Ducting and Plumbing 6 17 Apr 23 24 Apr 23 A350 Wall services(Ducting and Plumbing penetratrations to final finish requirement )
penetratrations to final finish requirement )
A360 - Wall services electrical (Inc DB tray) 5 25 Apr 23 01 May 23 A360 Wall services electrical (Inc DB tray)
A370 - Inspect for plaster 1 02 May 23 02 May 23 A370 Inspect for plaster
A380 - Plaster walls (2 coat above tiles) 6 03 May 23 10 May 23 A380 Plaster walls (2 coat above tiles)
A390 - Prime walls where required 2 11 May 23 12 May 23 A390 Prime walls where required
A400 - Install shaddow lines 2 15 May 23 16 May 23 A400 Install shaddow lines
A410 - Ceiling grids 4 17 May 23 22 May 23 A410 Ceiling grids
A420 - Electrical second fix 2 23 May 23 24 May 23 A420 Electrical second fix
A430 - Ducting second fix soffit 2 25 May 23 26 May 23 A430 Ducting second fix soffit
A450 - Inspect 1 29 May 23 29 May 23 A450 Inspect
B070 - Inspect for plaster 1 22 May 23 22 May 23 B070 Inspect for plaster
B080 - Plaster walls (2 coat above tiles) 12 23 May 23 07 Jun 23 B080 Plaster walls (2 coat above tiles)
B090 - Prime walls where required 6 08 Jun 23 15 Jun 23 B090 Prime walls where required
B100 - Install shaddow lines 2 16 Jun 23 19 Jun 23 B100 Install shaddow lines
B110 - Ceiling grids 8 20 Jun 23 29 Jun 23 B110 Ceiling grids
B120 - Electrical second fix 15 23 Jun 23 13 Jul 23 B120 Electrical second fix
B130 - Ducting second fix soffit 10 26 Jun 23 07 Jul 23 B130 Ducting second fix soffit
B140 - Inspect 1 14 Jul 23 14 Jul 23 B140 Inspect