Professional Documents
Culture Documents
Document Number
Project Identifier Area/Unit No. Group Code No. Document Type Sequence No.
P4045ZOR 93 28 10 703
Change Log
Document Holds
Section Description
TABLE OF CONTENTS
1. GENERAL .....................................................................................................................................6
3. PREPARATORY WORK..............................................................................................................12
3.1 Setting out .........................................................................................................................12
3.2 Blinding concrete or building paper ....................................................................................12
3.2.1 Blinding concrete ...........................................................................................................12
3.2.2 Building paper ...............................................................................................................13
3.2.3 Concrete elements placed on steel structures ...............................................................13
5. MATERIALS ................................................................................................................................16
5.1 Cement ..............................................................................................................................17
5.1.1 Cement Type .................................................................................................................17
5.1.2 Test certificate ...............................................................................................................17
5.1.3 Transport and Storage ...................................................................................................17
5.2 Blast-Furnace Slag ............................................................................................................18
5.3 Silica Fume........................................................................................................................18
5.4 Aggregates ........................................................................................................................19
5.5 Reinforcing steel ................................................................................................................20
5.6 Water .................................................................................................................................20
5.7 Concrete Mixes..................................................................................................................21
5.8 Exposure conditions ..........................................................................................................22
6. FORMWORK ..............................................................................................................................24
6.1 General .............................................................................................................................24
6.2 Removal ............................................................................................................................24
1. GENERAL
This specification covers the technical requirements of concrete materials, placing & curing, grouting and
reinforcement work for the concrete work which will be applied for the onshore and offshore concrete
works of KNPC Al Zour Project – 045 in Kuwait.
The requirements for the concrete works shall be in accordance with Specification for the Marine Facilities
Civil Works – Part I P4001 NRP.93.10.28.001 Rev. F (P4049N-0000-BA30-DCN-0410_R4), Shell DEP
34.19.20.31-Gen(V.32) and Project Variation to Shell DEP 34.19.20.31. PV to DEP 34.19.20.31.
The project variation (Shell DEP 34.19.20.31. PV to DEP 34.19.20.31) has been prepared to define the
project-specific amendments that include additions, deletions, exceptions, and revisions to the relevant
DEP.
All works shall be performed in accordance with the latest version of project specifications, PVs, DEPs,
and international standards and codes over precedence.
In this Specification, reference is made to DEP specifications and standard drawings. For project use,
these referenced DEPs (specifications and drawings) shall be used in conjunction with its project
variations, as applicable.
ASTM C173 : Standard Test Method for Air Content of Freshly Mixed
Concrete by the Volumetric Method
3. PREPARATORY WORK
All work shall be set out accurately from datum and benchmarks. During execution the correct position,
level and alignment of all parts of the work shall be ensured at all times.
Setting out shall meet the requirements of BS 8110-1:1997 Clause 6.2.8, with the following additions:
Permitted
Item Distance
tolerance
A layer of blinding concrete of 50 mm minimum thickness shall be placed under foundations. The blinding
layer shall be laid immediately after excavation, draining and compacting of the bed area, in order to avoid
disturbance of soil by rain or ground water.
A case of precast footings for the foundation block of wave wall and the retaining wall at the shore
connection to U85 trestle is placed on soil to mobilize the full shear strength of the underlying soil without
the blinding concrete.
All below grade concrete foundations located onshore and linked reclaimed land, shall be protected by 3
coats of bitumen (Min. DFT 1500 microns) under polyethylene sheet liner (Min. Thk. 0.25mm) conforming
to ASTM D2103. The liner shall extend a minimum of 150 mm beyond all concrete foundation edges.
In foundations, the underside of concrete, where bitumen and polyethylene sheet cannot be used, shall
also be protected against chemical attack. The blinding concrete shall be treated with Vandex or similar
approved, prior to placing the concrete. Furthermore, the rebar distribution shall be such that serviceability
flexural cracking to the underside of the foundation is limited to 0.1mm.
To avoid damage to the steel and concrete when prefabricated concrete elements are placed directly on
steel structures, a load bearing layer shall be placed between those elements. The layer material shall be
neoprene, nylon, rubber or equivalent. When applicable the material shall be chemical resistant.
Where required, constructional and/or movement joints shall be provided in concrete structures and
indicated on drawing. Construction joints are described further in (8.6.2).
The minimum concrete cover in pile caps shall be 100mm. For other parts, the minimum cover on the
outer reinforcement shall be as follows:
Minimum
Description
Cover
1. Cast-in-place concrete (non pre-stressed)
Exposed to earth with bitumen & polyethylene protection 75 mm
Exposed to weather 50 mm
Not exposed to weather, water, or not in contact with the ground slabs, 40 mm
walls, beams, girders, columns
In contact with or above water, for all application 75 mm
Minimum
Description
Cover
2. Pre-cast concrete (manufactured under plant conditions)
Exposed to earth with bitumen & polyethylene protection 75 mm
Exposed to weather
- Wall panels 40 mm
- Other members 50 mm
Not exposed to weather, water, or not in contact with the ground
- slabs, walls, joints 30 mm
- beams, girders, columns 40 mm
In contact with or above water, for all application 75 mm
Minimum
Description
Cover
3. Pre-stressed concrete members
Exposed to earth 75 mm
Exposed to weather
- Horizontal surfaces 75 mm
- Non-horizontal surfaces 50 mm
Not exposed to weather, water, or not in contact with the ground 40 mm
In contact with or above water, for all application 75 mm
For all marine concrete other than pile caps, it is required that a minimum cover of 75mm should be
applied.
It is required that the concrete mix design should be performed with the concrete cover of minimum
75mm to ensure the design life of 50 year for U99 structures and 60 year for U98 breakwaters.
The minimum distance between individual bars shall be not less than:
250 mm - for main bars in slabs where bending moments are maximum
- for bars perpendicular to main bars in slabs
- for distribution bars in slabs
- for bars in walls
- for mild steel stirrups in beams
Crack width control shall satisfy the requirements of BS EN 1992-2, For Marine Structures; the Exposure
rating for Pre-stressed and Reinforced concrete shall not be less than Class XS. (refer to Design basis
for sea island, P4045ZOR-93-20-28-701_Rev.B)
Minimum Crack
Exposure Class Exposure Conditions
Width
XC2, XC3, XC4 Corrosion induced by carbonation
Corrosion induced by chlorides other than
XD1, XD2, XD3 0.3 mm
from sea water
Corrosion induced by chlorides from sea
XS1, XS2, XS3
water
For pre-stressed concrete the crack width shall be < 0.1 mm.
In foundations, the underside of concrete foundations, where bitumen and polyethylene cannot be used,
shall also be protected against chemical attack. The blinding concrete shall be treated with Vandex or
similar approved, prior to placing the concrete. Furthermore, the rebar and rebar distribution shall be such
that serviceability flexural cracking to the underside of the foundation is limited to 0.1mm.
Foundations for small pumps, staircases, etc. may be placed on reinforced concrete slabs or yard paving,
provided that they are properly connected to the slabs or paving and that cable trench locations are fixed.
If required, slabs or paving shall be strengthened locally.
In addition to all other requirements for the design of structures, special precautions shall be taken
regarding the liquid tightness of liquid-retaining structures, see EN 1992-3. All liquid retaining structures
shall be water tested under atmospheric pressure conditions, unless otherwise stated.
Design :
A detailed design and vibration analysis shall be performed in accordance with DEP
34.00.01.30-Gen.
Isolation of foundations:
Foundations subject to vibration shall be properly isolated from adjacent structures. Combined
foundations hall also meet the requirements of DEP 34.00.01.30-Gen.
Foundations and structures subject to temperature effects shall be designed for any temperature
difference that may occur in parts of structural members and/or the whole structure.
For loading due to thermal effects, see DEP 34.00.01.30-Gen.
All holes in table tops which have equipment underneath shall be closed after installation of piping,
equipment, etc. to prevent escalation of a fire which may occur under the table top because of
draught through such holes.
All edges of table top slabs shall have a curb of minimum 100 mm height to prevent liquid and
rainwater from being drained over the edge, except at locations of entrance such as staircases
and connections to other platforms. The table top slabs shall be sloped to discharge drains or
gullies provided with down spouts.
5. MATERIALS
5.1 Cement
Cement and additions for mixing Concrete shall comply with indicated table in Appendix 4.
Type of cement: Blast furnace cement with a slag content of > 65%(Portland cement Type Ⅰ with
GGBS of >65%) or Portland cement type II (ASTM C-150).
The common cement shall be complied BS EN 197-1(CEM 1), as Portland cement content, and SATM
C150(Type Ⅰ).
Cement shall be obtained from a source approved by the Company and shall not be changed without
Company approval.
A Manufacturer's test certificate, indicating the particular batch number or fabrication date, etc. shall be
submitted by the Supplier before or during the delivery of the cement.
The cement shall be delivered to the site in ply bags or in bulk carriers. Bags transported by sea shall be
packed in plastic. The name and brand of the manufacturer, including batch number or fabrication date,
shall be plainly marked on the bags.
The cement shall be stored in such a way that the date of manufacturing is clearly visible so that it is used
in sequence by the date of manufacture, oldest first.
The maximum height of storage of the bags shall be 2 m with a ventilated space between the floor and
lowest bags. In tropical and subtropical areas the outside of the cement storage shall be painted white.
The bulk cement shall be stored in a silo. The silo shall comply with the following:
in all areas the temperature shall not exceed 40 °C and/or the silo shall be maintained frost-proof.
The cement shall be suitably protected during storage to avoid deterioration in quality.
Cement which has been in storage for more than 3 months from the date of manufacture shall be tested
to verify that its quality is still in accordance with the standards referred to in Appendix 3.
The presence of lumps will lead to rejection of the cement. Cement older than 6 months shall not be used.
Blast furnace slag shall be in accordance with ASTM C989 and shall be a replacement of Minimum 65
percent by weight of the total cement for the concrete structures in contact with or above sea water.
Additions other than silica fume or ground granulated blast-furnace slag (GGBS) shall not be permitted.
Silica fume shall be used as a cement replacement for below-grade concrete. Silica fume shall be in
accordance with ASTM C1240 and shall be a replacement of six (6) to eight (8) percent by weight of the
total cement. Silica fume is not required for above grade applications, except where concrete is in direct
contact with sea- water or any other corrosive environment detrimental to concrete, such as sea-water
intake basin, sea-water cooling tower, etc. Where concrete without silica fume is used for above grade
applications, columns with silica fume shall be extended up to the first construction joint above grade. Use
of silica fume is not permitted for precast wall panels and slabs on grade (building floor and paving). Also,
silica fume is not required for plain (unreinforced) concrete below grade (refer to P4049-0000-DD00-VAR-
0011_2, Reinforced concrete)
The silica fume shall originate from a single furnace and shall be fresh furnace stock not more than 3
months old at the time of dispatch from the manufacturer’s works. It shall be stored in purpose built silos
before densification and bagging. Delivery of silica fume to the concrete batching plant shall be in dry
powder form. The silica fume shall be shipped in sealed containers. The packaging shall not deteriorate
under ultra-violet exposure for a minimum of 3 months after delivery. The silica fume shall be supplied
and used in strict accordance with the manufacturer’s instructions.
Silica Fume shall be obtained from a Company approved supplier. Contractor shall provide the following
details to the Company:
Documentation confirming that the silica fume complies with ASTM C1240.
Certificates of Origin, Bills of Lading, ISO Certification relating to silica fume production.
Certificates of analysis, including batch numbers and container numbers relating to each analysis.
The certificates shall bear the corporate stamp and signature of the authorized person directly
responsible for the analysis at the origination factory.
Confirmation that the Company has the right of access to the supplier’s works to inspect and verify
all claims made by the supplier.
Confirmation that the supply shall be adequate to meet the anticipated peak requirement.
Supplier’s test certification shall be provided for each delivery of silica fume. Certificate shall confirm that
the silica fume complies with all requirements listed above, and shall be submitted by the contractor along
with the mix design approval.
Company shall have the right to call for tests on each delivery of silica fume, to confirm it meets the
requirements of this specification. In such cases, samples shall be provided for testing in sufficient time
to enable assessment without delaying the Contractor’s program.
5.4 Aggregates
Coarse and fine aggregates shall comply with EN 12620 or ASTM C 33.
The content of water-soluble chlorides (expressed as Cl) shall not exceed 0.02% by weight of fine
aggregates and 0.02% by weight of coarse aggregates.
The content of acid-soluble sulphates (expressed as calculated SO3 equivalent) shall not exceed 0.4 %
by wt of fine aggregates and 0.4 % by wt of coarse aggregates.
The aggregates shall be examined in accordance with ASTM C 295 to determine presence of alkali-
reactive constituents or other deleterious reactivity.
At all times, the aggregates shall be free of impurities and if not, the aggregates shall be washed
mechanically with water to remove clay, silt and fine dust.
In case of the reinforcement concrete, coarse aggregates shall be crushed stones of 20mm maximum
size. In case of mass concrete, coarse aggregate shall be crushed stones of 40mm maximum size.
Aggregates shall be tested as indicated in Appendix 3 and shall conform to the limitations in the following
tables:
Coarse Aggregates
Fine Aggregates
General reinforcement shall conform to ASTM A615/A615M Grade 60 (or BS 4449 Grade B500B and BS
EN 10080 for higher yield strength reinforcement).
Welded wire fabric shall conform to ASTM A185 for plain fabric and to ASTM A497 for deformed fabric or
BS 4483.
5.6 Water
The water used shall be in accordance with EN 1008 and with the following.
Only clean, fresh water free from harmful matter shall be used. It shall not contain chlorides in excess of
500 mg/kg nor sulphates in excess of 200 mg/kg.
The water shall not contain dissolved solids in excess of 2000 mg/kg.
Furthermore the water shall not contain sugars, phosphates and harmful impurities (for instance oil).
The pH of the water shall be between 5.5 and 8.0. . Tests shall be carried out in accordance with Appendix
3.
Test water for chlorides per ASTM D512, and for sulphates per ASTM D516.
The concrete mix design shall take into account the type of foundations, structures, elements etc. for
which it is intended.
Concrete shall be in accordance with DEP 34. 19.20.31 - Gen, except as modified and supplemented
below. The requirements of Sections 2.2 and Appendix 1 of the above referenced DEP are mandatory.
The atmosphere in which the structures are to be built is aggressive, continuously chloride laden and
humid. The requirements of the DEP 34. 19.20.31 - Gen concrete specification shall therefore be modified
to the following minimum requirements (Concrete Grade based on 28day Cylinder strength).
Maximum Minimum
28day cylinder Maximum
free water cement
Application strength Aggregate Remark
cement content
(Mpa) size
ratio Kg./m3
Marine
40 0.38 450 20mm
Concrete
Onshore
30 0.40 375 20mm
Concrete
Footing block
Plain concrete 40 0.38 450 20mm & Unreinforced
wave wall
Appendix. 5
Core-Loc 40 0.38 450 20mm Core-Loc Technical
specification
Red Oxide
UG Duct 20 0.45 340 10mm
(as per Section 5.9)
Lean
20 0.55 340 20mm
Concrete
To verify whether the mix design meets the specified quality requirements, trial mixes shall be produced
(unless otherwise specified) preferably on site. For each trial mix tests shall be performed as referred to
in Appendix 3.
Special attention shall be paid to possible bleeding after placing. Trial tests, including a bleeding test in
accordance with ASTM C 232, shall be performed especially for large/thick concrete elements (e.g.
horizontal slabs, columns).
Special admixtures may be considered if bleeding cannot be controlled sufficiently by means of a standard
mix design. In general a low slump in combination with proper grading and/or the use of an air entrainer
The required concrete mixes shall be designed in accordance with EN 1992 and EN 206-1, or approved
equivalent, with a designation of nominal maximum size of aggregate and workability.
Furthermore, the concrete mix shall be designed for durability taking full account of the environment to
which it will be subjected.
For all concrete, the maximum acid soluble chloride ion concentrations in hardened concrete at age 28 to
42 days contributed from all ingredients including water, aggregates, cement, and admixtures, shall not
exceed 0.15 percent by weight of cement as tested per ASTM C1152.
Water /cement ratios shall be measured based on the free water available for cement hydration with the
aggregates being in saturated surface dry (SSD) condition. Aggregate moisture content and water
absorption shall be continually measured to ensure accurate measurement of the amount of free water in
the mix.
The unit weight of fresh concrete shall not be less than 2350 kg/m3 and shall be tested as indicated in
Appendix 3 – Tests.
The air content of fresh concrete shall not exceed 2% as determined by ASTM C173 or ASTM C138. See
Appendix 3 – ‘Tests’ for testing schedule.
The slump of various concrete mixes shall be such that the concrete can be transported, placed into forms,
and compacted without segregation in accordance with Section 7 and Section 8. For concrete without a
superplasticizer admixture (plain concrete), the slump shall be 100 mm +/- 25mm at the point of delivery.
For concrete with superplasticizer (structural concrete), the slump shall be 50 mm to 100 mm before the
admixture is added and a maximum slump of 200 mm at the point of delivery after the admixture is added.
Additional Testing - The following additional test results shall be submitted for approval as part of the
concrete mix qualification (These tests are not required for plain concrete mix with a water cement ratio
of 0.45.):
Water absorption and volume of permeable voids in hardened concrete at age 28 to 42 days shall
not exceed three (3) and seven (7) percent respectively, as tested in accordance with ASTM C642.
The amount of water soluble ion penetrating into hardened concrete in a period of 90 days shall
not exceed 0.02 percent by weight of concrete when tested in accordance with AASHTO T-259.
The required concrete strengths the maximum water/cement ratio (WCR), additions, concrete strength
and maximum aggregate size for the application concrete structures as indicated table in the following
Appendix 4.
The environments to which concrete is exposed in service can be classified into six main exposure classes
according to EN 206-1: no corrosion or attack; corrosion induced by carbonation; corrosion induced by
chlorides other than from sea water; corrosion induced by chlorides from sea water; freeze/thaw attack
with or without de-icing agents; and chemical attack. These main exposure classes with their subdivisions
The classification criteria and subsequent requirements for concrete exposed to chemical attack (including
recommendations for mix design related to a particular exposure class or condition) are given in Appendix
1.
Concrete encasement for underground electrical ducts shall be colored red by adding 1 kg of red oxide
powder per 100 kg of cement. Maximum aggregate size for underground ducts shall be 10 mm.
5.10 Accessories
Joint sealant materials shall conform to ASTM D6690 for horizontal joints, or ASTM D2628 for both vertical
and horizontal joints.
6. FORMWORK
6.1 General
Design, calculation and execution of formwork shall take into account climatic conditions, the expected
heat of hydration and finishing of concrete surfaces.
All edges of exposed concrete members shall have a chamfer of approximately 25 mm or 50 mm.
Formwork shall be kept clean and free from binding wire, sand, water, etc. This shall be confirmed by
inspection before pouring.
Internal form ties shall be of such a nature that no permanent metallic part has less cover than the
reinforcement.
Snap-ties or through-bolts shall not be used below ground water table. The ties shall be constructed to
permit removal of the ends or end fasteners by unskilled workmen, without causing spalling at the faces
of the concrete. Form ties shall be designed to give, on removal of the ends or end fasteners, a recess
having a maximum dimension of 50mm and a depth equal to the concrete cover specified in section 4.2.2.
Holes left by withdrawal of tie-rods shall be filled solidly with Company approved non-shrink repair mortar,
which shall be flush with the surface.
Formwork joints should be sealed to ensure no grout loss. In particular, suitable measures should be
applied to ensure joint sealing between formwork and head of pile. The joint between permanent formwork
and side of pile at bottom of pile plug should be sealed.
6.2 Removal
The formwork of building shall be removed in accordance with DEP 34.19.20.31-Gen. The formwork of
Core-LOC shall apply with CLI standard specification.
A striking plan shall be produced, which anticipates climatic conditions, heat of hydration, strength
development, load conditions and relevant curing methods.
7. REINFORCEMENT WORK
Reinforcing steel shall be cut, bent and welded in accordance with EN 1992-1-1:2004 Clauses
3.2 to 3.4.
Load-bearing welded joint of reinforcing steel for transmission of the design load under operating
condition should be avoided.
Non load-bearing welded joint of reinforcing steel whose strength is not taken into account in the
design of the reinforced concrete structure shall be in accordance with ISO 17660-2 or equivalent
international standard. Reinforcing steel shall be weldable material in accordance with applicable
international standard, EN 10080 or equivalent. Welds of reinforcing steel shall only be welded by
qualified welders and each weld shall be visually inspected. Welding shall be included in the quality
plan.
7.2 Placing
Black annealed steel binding wire of approximately 1.5 mm thickness shall be used for fixing the
reinforcing material. The ends of the binding wire shall be tucked in to prevent corrosion spots in
the concrete.
7.3 Spacers
Concrete spacer blocks shall conform to the requirements of this specification. Non-concrete spacer
blocks shall only be permitted provided they do not adversely affect the strength and durability of the
concrete.
The measuring, mixing, production and transporting of concrete shall be in accordance with EN 1992 and
EN 206-1. Concrete shall not be hand-mixed or re-tempered.
The Contractor shall provide full details of the fully automated concrete mixing plant(s) and devices, and
shall produce trial mixes before the permanent placing of concrete is started, to prove that the specified
concrete grade can be obtained.
The temperature of the fresh concrete can be reduced by cooling the water (by adding ice) and by storing
the aggregate under shade.
The amount of water shall be in compliance with the approved mix design. No additional water shall be
added to the mix at any time.
Ready mixed concrete suppliers shall hold a current NRMCA (National Ready Mixed Concrete Association)
Certificate of Conformance for Concrete Production Facilities.
The producer of the concrete shall furnish to the purchaser a delivery ticket in accordance with ASTM C94
or BS EN 206-1, for each load of concrete.
The addition of water after concrete is first mixed shall not be allowed.
When powder silica fume is added to concrete (for silica fume requirements, see section 8.2.2), the mixing
time shall be 50 percent greater than that of concrete without silica fume. Extra time will not be required
if silica fume is used in an approved slurry form, but maximum water- cementitious material ratio shall not
exceed the values in section 5.7 above.
8.2.1 Admixtures
An admixture is defined as a product which is added in quantities generally not more than 5 % by mass
of the cement before or during mixing or during an additional mixing operation, causing the required
modifications to the normal properties.
Admixtures shall comply with EN 206-1 or EN 934-2, and shall comply with ASTM C 494 or EN 480.
All admixtures used to modify one or more characteristics of concrete shall be accompanied by a
certificate from an approved institute, stating:
a recommendation on the maximum allowable quantities (as a percentage of the mass of the
The Contractor shall be responsible for any defective concrete that may result from the use of such
admixtures. All information regarding the admixture(s), such as certificates, concrete mix trials, test results,
etc. shall be made available to the Company.
Type G admixture (superplasticizer with retarding action) meeting the requirements of ASTM C494 and
ASTM C1017 shall be utilized in all structural concrete mixes to improve workability. Superplasticizer
content shall be adjusted according to ambient condition to provide enough workability with no
segregation when concrete is properly compacted, but shall not exceed two (2) percent by weight of
cement. Mixing shall be in accordance with manufacturer’s instructions.
8.2.2 Additions
An addition is defined as a finely divided material that is added to the concrete in order to improve certain
properties or to achieve special properties. Examples of additions are:
GGBS in accordance with EN 15167 or ASTM C989 (pozzolanic material, used to reduce heat
caused by hydration in mass concrete);
silica fume (pozzolanic material used for high strength concrete) ASTM C1240;
a recommendation on the maximum allowable quantities (as a percentage of the mass of the
cement) to achieve the particular requirement,
The Contractor shall be responsible for any defective concrete that may result from the use of such
additions. All information regarding the addition(s), such as certificates, concrete mix trials, test results,
etc. shall be made available to the Company.
The application maritime concrete of addition silica fume to protect the chloride ingress as indicated refer
to Appendix 4.
Provisions for pouring concrete in extreme weather conditions shall be made with reference to the
following standards:
ACI 305R;
EN 13670 ; and
Painting white the mixing plant, trucks, water tank, and cement silo
The heat of hydration shall not cause a temperature differential between the interior of the concrete and
any outside face greater than 20 °C.
The temperature gradient in slabs and walls over 600 mm thick shall be verified by computer models
and trail mix test pieces. If the temperature gradient is more than 20 °C, adequate measures shall be
taken to reduce the heat of hydration (e.g. by cooling, by using insulated formwork, and/or by applying
low-heat cement, retarder, pozzolanic material, etc.).
For slabs and walls over 600 mm thick, the following items shall be required with regard to the assessment
of hydration heat:
The performance of trial mixes with special attention to the heat of hydration and workability:
-Full size (scale 1:1) test pieces shall be cast and tested representing the actual pouring conditions.
Samples of concrete for compression tests shall be taken each day concrete is poured for the project.
There shall be five (5) test cylinders per sample. For large, continuous pours, one sample shall be taken
for each 40 m3 or portion of each 40 m3 of concrete placed. For small pours, there shall be one (1) sample
as a minimum.
Four (4) test cylinders shall be cured under standard moisture and temperature conditions in accordance
with ASTM C31. The fifth test cylinder shall be cured in the field for a minimum period of 28 days under
conditions similar to that of the curing the main concrete, unless directed otherwise by Company. Two (2)
of the moisture cured samples shall be tested 7 days after the concrete is poured, and the remaining two
(2) shall be tested on the 28th day after the concrete is poured. The field-cured 5th sample shall be stored
and tested when directed by Company.
If the test results indicate non-compliance, the quantity of concrete represented by the results shall be
removed and replaced with concrete meeting the requirement of this specification at no additional
expense to Company. Additionally, an investigation shall be performed by Contractor to identify the cause
of non-compliance and specify corrective measures. The extent of the investigation, and contractor’s
proposed corrective measures, shall be subject to Company approval.
8.6.1 General
Liquid containing construction shall comply with this specification and ACI 350 or BS EN 1992-3.
Waterproof through-tie system shall be employed in the formwork of liquid retaining construction.
8.6.2 Joints
Joints shall be designed and constructed in accordance with ASTM D5893 and ASTM D6690. Details and
positioning of these joints, together with the materials to be used, shall be shown on the construction
drawings.
Waterstops for joints shall be installed at the locations shown on the construction drawings. See Section
9.2.6 below for requirements of waterstops.
8.6.3 Testing
In addition to testing required in Section 12.2.3, tests shall be conducted to determine the overall water
tightness of the structure and particularly the joints, in accordance with ACI 350/350R.
The structure under test shall be filled to the designed level with potable water, and shall remain for a 7
day period to allow for absorption of water. The exposed faces shall be inspected for leaks during this
period. Any defect shall be corrected, by an approved method. This could involve demolition and
rebuilding, or lining the structure in case of leaks at the joints.
9. CONCRETE PLACING
9.1 General
The placing of concrete shall be in accordance with the appropriate clauses of EN 1992 with the
following pre-concreting operations:
A concreting and inspection test plan including all actions to be dealt with relevant to the execution.
The initial testing of concreting by trial casting, documented before the start of execution.
If concrete is placed directly against rock or ground, the fresh concrete shall be protected against
intermixing and water suction (blinding concrete, building paper) according to (3.4.1 and 3.4.2).
Ground, rock, formwork or structural parts in contact with the section to be cast shall have a
temperature which does not result in freezing of the concrete before it has sufficient strength to
resist the effects of freezing (in general > 5 N/mm²).
If the ambient temperature is expected to be high (hot weather concreting) at the time of casting or
in the curing period, precautions shall be taken to protect the concrete against damaging effects
(e.g. drying out or excessive shrinkage)
If the ambient temperature is expected to be below 0 °C (cold weather concreting) at the time of
casting or in the curing period, precautions shall be taken to protect the concrete against damage
due to freezing.
9.2 Specific
For placing by pumping, the concrete mix shall be in accordance with the CEB-FIP
Model Code 1990, Appendix D.11.5. A back up plan (including facilities) shall be in place to ensure the
continuity of concrete placing in case the pump should fail.
The total time required for mixing, transportation and pouring of the concrete should in general not exceed
60 min when not agitated and 120 min when agitated. During this period the segregation of aggregates
shall be prevented and the workability shall be maintained. A mixing, transportation and pouring schedule
shall be produced.
Special precautions are required when concrete is placed in underwater structures. A concrete placing
plan shall be submitted by the construction Contractor, for approval by the Company, based on trials which
demonstrate that the required quality and consistency of the concrete mix can be achieved.
Construction joints shall comply with EN 1992-1-1:2004 Clause 12.9.2 and with BS 8110-1:1997 Clause
6.2.9 and kickers shall be cast monolithically with beams/slabs/foundations.
Where construction joints are intended, they are to be defined on the construction drawings. Proper boding
of the joint is required in order to transfer tensile or shear stresses, and to prevent any passage of liquids.
Therefore, the surface shall be roughened to increase the bond strength and to achieve aggregate
interlock. The aggregate in the top surface of the first pour is to be exposed uniformly by removal of
laitance without loosening of the particles of aggregate or damaging the concrete surface of the first pour.
This preparation can be best achieved by pressure washing with water at an appropriate time after casting.
At the time of casting the further concrete con the construction joint, the hardened concrete shall be
saturated BUT free of surface water. Construction joints shall be at right angles to the main reinforcing
bars in the member, unless otherwise shown on the construction drawings. Stop ends for vertical joints
shall be removed as soon as it is practical without damaging the concrete face.
Additional construction joints (required because of limitation of concreting or shuttering), shall be approved
by Company. If these concrete joint surfaces to receive new concrete are more than one (1) hour old, the
concrete joint surface shall be roughened as specified in this section and primed with an approved bonding
agent prior to placement of new concrete.
The expansion joints for slabs on grade shall be provided on centers up to a maximum of 20m. These
joints shall be constructed to pass completely through the concrete section
The contraction joints for slabs on grade shall be provided on centers up to a maximum of 48 times the
slab thickness, but shall not exceed 8m. These joints shall be formed by scoring of the concrete prior to
taking its initial set, or by saw cutting within 12hours after placing.
It shall be ensured that joints are properly constructed and sealed as it is extremely difficult to repair a
failed joint. The expansion and contraction joints shall be sealed in accordance with ASTM 5893 and
ASTM D6690.
A. Organisation
- Personnel
B. Requirements
- Construction schedule and sequence, complete with manpower, plant and equipment
- Re-compaction requirements
C. Quality Control
- Inserts
- Concrete placing
- Curing
- Joint preparations
- Defects
- Toolbox meetings
Care shall be taken to avoid segregation, particularly when placing concrete in tall walls and
columns etc. Concrete shall not be dropped into place from a height exceeding one (1) meter, nor
shall it be dropped through dense reinforcing steel which could cause segregation of the coarse
aggregate, or displacement of the reinforcement or formwork.
Pouring equipment tested and ready one day before concrete is placed.
Structural concrete shall not be cast against the earth (i.e., open excavation), as the concrete cannot
be coated afterwards
9.2.6 Waterstops
Where waterstops are called for on the construction drawings for joints, the waterstops shall be fabricated
from PVC. Waterstops shall be accurately cut, fitted, and fully integrally joined at joints and junctions, to
provide a continuous watertight diaphragm at all points. Jointing of waterstops shall be by welding in
accordance with manufacturer’s instructions. The lapping of waterstops at joints, and use of adhesives
for jointing purposes, shall not be permitted unless approved by Company. Care shall be taken at all times
to ensure that waterstops are not perforated or damaged in any way during concrete placement. Damaged
waterstops shall be replaced or repaired before embedment in concrete. Particular attention shall be given
to placement and vibration of the concrete to ensure well compacted concrete around the ribs of the
waterstops. At all joints the concrete shall be placed up to the center line of the waterstop.
9.3.1 Finishing
Top surfaces of concrete in walls, beams, buttresses and floors shall be finished to the proper level and,
if specified, to the required slopes according to BS 8110. No holes or rough patches shall remain. Surfaces
requiring subsequent plastering or tiling shall be rough-finished to provide a proper key for the finishing
layer.
9.3.2 Setting
After initial setting of the concrete, any disturbance thereon (e.g. from walking, wheeling-over or vibration
of the formwork) shall be prevented until the concrete has sufficiently hardened.
Reinforcement, anchor bolts etc. projecting from the concrete shall not be disturbed during hardening of
the concrete.
9.3.3 Repair
Touching up of concrete surfaces after the removal of formwork is not permitted until they have been
inspected and released in accordance with the quality procedures.
The repair method, including materials and the extent of the repair works to remedy the imperfections of
the concrete, shall be specified and approved for each repair case and comply with the design
requirements of the structure concerned.
In general, cementitious repair materials shall be used based on blast furnace slag cement. Repair
materials based on other cement types shall be documented and submitted by the Contractor for approval
by the Company.
For the finishing of cones the following method shall be used, provided that the volume and surface of the
concrete are suitable for repair:
Coating shall be a bitumen based waterproofing sealer, subject to Company’s approval. ‘The coating shall
be applied in three layers to a total dry film thickness of 1500 microns. Surface preparation and coating
application shall be in accordance with the manufacturer’s instructions.
Proper curing is essential for the durability of the concrete. Curing shall be carried out to avoid premature
drying of the concrete and to provide the cement paste in the concrete with sufficient water in order to
achieve a high degree of hydration.
Curing shall be carried out in accordance with EN 206, EN 1992-1-1. Additional information can be found
in the CEB-FIP Model Code 1990, Appendix D 12.
10.1 General
Concrete shall be moist cured. Curing shall commence immediately after the finishing operation or within
two (2) hours after concrete setting, and shall continue for a minimum of 10 days.
The use of curing compounds shall be permitted only after Company approval, except for surfaces
receiving subsequent finishes.
Regular, frequent inspection shall be made of concrete being cured, to establish whether or not curing is
being performed within specification.
The curing method for hot weather concreting shall be in accordance with ACI 305R. The increase of
curing period and of thermal protection is recommended.
Immediately after finishing, surface shall be covered with white polyethylene sheeting, which shall be in
contact with concrete surface, with the edges lapped or tied down to exclude air circulation. After the
concrete has stiffened, but no longer than 2 hours, the sheeting shall be removed and replaced with a
hessian, soaked with water. The sheeting shall be placed over the hessian immediately, to prevent
evaporation from the hessian. For the duration of the curing period prescribed, concrete surfaces covered
with hessian shall be visibly wet. To achieve this, the hessian shall be maintained in a permanently wet
condition using water. The water used for curing shall be of the quality specified in section 5.6, and shall
be the same temperature as the concrete being cured.
Vertical timber formwork shall be draped with wet hessian as soon as concrete is placed. As soon as
formwork is removed, all surfaces shall be draped with wet hessian; covered with white polyethylene
sheeting held firmly in place along all edges; and kept continuously wet for the duration of the curing
period. For the duration of the curing period prescribed, all concrete surfaces covered with hessian shall
be visibly wet. Care shall be taken to avoid drying winds, caused by a wind tunnel arrangement of the
coverings or formwork slackened from the concrete.
11. GROUTING
11.1 General
Grouting refers to all work to be carried out to properly fill the spaces between concrete surfaces and base
plates of equipment, steel structures or prefabricated concrete elements with mortar in order to achieve
adequate transfer of horizontal and vertical forces and to inject pre-stressed systems (tendons).
For all the grouting work, the finished concrete support surface shall be such that it does not accumulate
water.
All grout shall be non-shrink cementitious grout unless otherwise specified on the construction drawings
to be ‘Epoxy Grout”.
A grout is regarded as non-shrink if its volume is not less than the initial volume, after hardening for 28
days. During this period the test specimens shall have been completely protected against drying,
evaporating, carbonation and exposure to temperatures outside the range 23 °C +/-3 °C.
The type and brand of non-shrink grout shall, after approval, be indicated on the drawings and/or
specification for concrete work
Contractor shall supply the Manufacturer's data sheets and certificates. The grout shall be free of chlorides
and shall have a pouring consistency. A metal-oxidising or gypsum-forming non-shrink grout shall not be
used.
Non-shrink grout shall be applied under all major steel structures and stationary, rotating and reciprocating
equipment. The selection of the type of grout for rotating and reciprocating equipment shall be in
accordance with DEP 31.29.00.10-Gen.
Maximum creep (ASTM C1181): 5 x 10-6 mm/mm, tested at 20°C and 60°C with 2.8 MPa applied
vertical load
Compressive strength shall be tested per ASTM C579, Method B Modified (for 7 day strength)
The injection grout shall have at least the same properties (compressive strengths, tensile strengths, The
Contractor shall compile the type and composition (including test results and data sheets) of the injection
grout.
The ducts of the tendons shall be dried by air blowing. The air shall be free of oil and shall have a maximum
relative humidity of 65 %. The ducts of the tendons shall be filled with injection grout and checked for
proper, complete filling. See also BS 1881-205 in this respect.
The pockets at the anchorage of the pre-stressed tendons shall be filled with concrete of at least the same
properties as the structural concrete. A modified poured (repair) concrete or gunited concrete should be
used. Surface preparation, such as removal of the laitance and the use of an approved bonding agent,
shall be considered to ensure proper bonding.
11.3.1 General
Surface preparation of foundations for rotating/reciprocating equipment: For surface preparation refer to
DEP 31.29.00.10-Gen.
Special attention shall be paid to the extent of the grouting. As mentioned in DEP 31.29.00.10-Gen., the
foundation shall be sized so that grouting can be extended to 50 mm beyond the base/sole plate or the
shims. If the size of concrete foundation is greater than the base/sole plate, formwork shall be used to
match the 50 mm.
The surface of the foundation under the base plate of the object to be grouted shall be chipped and
brushed to remove the weak upper layer of the concrete, damaged concrete and any oil-soaked concrete
areas. Prior to grouting, loose concrete or dust shall be removed, preferably by compressed air.
Before grouting commences the concrete surfaces shall be soaked with clean water for 24 h, unless the
grout Manufacturer specifies otherwise (saturated surface dry quality).
All grout mortar shall be machine mixed to an even consistency. Under no circumstances shall hand
mixing be employed.
Adequate wedges and/or shim plates shall be used for levelling steel structures or stationary equipment,
Shims under steel structures and equipment such as columns, vessels, heat exchangers, etc. shall
be of a machined type and need not be removed. Machined type shims need the approval of the
equipment Vendor.
Wedges are restricted to minor steel structures, supports etc. and shall be removed.
11.3.2 Shims
The following shall apply for shims that will remain in place after grouting:
The shim shall be embedded in a mortar bed so that the top of the shim is level in all planes.
Shim plates shall be installed so that they will be fully embedded in and surrounded by the grout to
be installed later; the minimum cover to shim sides shall be 50 mm.
Load per shim pack shall not exceed 7 N/mm2 under the worst loading condition. In this case th
e grout shall be considered as a filling material only when calculating the aforementioned bearing
stress.
11.4 Application
The Contractor shall be solely responsible for the quality control of all the materials, installations,
workmanship, and items or installations supplied by any of the Contractor’s subcontractors or vendors.
Notwithstanding the Contractor’s responsibility for quality, the grout manufacturer shall provide a
technical representative who will be on-site to review the grouting set-up procedures and the
manufacturer’s instructions with the ones who will actually be doing the grouting. The technical
representative shall remain at the grouting site as long as required to ensure that the grout
manufacturer’s installation instructions are being followed.
12.1 General
The Contractor shall submit a quality plan which shall comply with the EN 1992 (Eurocode 2) and shall
be based on ISO 9000 quality system requirements and EN 206-1. The quality plan shall cover quality
assurance and control and shall be divided into detailed design and production/execution plan. The
quality plan shall be subject to audit by the Company.
Contractor shall always have a qualified, dedicated and full time Concrete Quality Control Engineer
(CQCE), to ensure that concrete is properly produced, placed, cured and protected in accordance with
this specification. The CQCE shall be at least a graduate civil engineer with a minimum of 10 years
experience in QA/QC, or alternatively, approved by Company, and shall be responsible for the
maintenance and submission of all specified records. The CQCE shall not report to his own site
Construction Management but to his own Head Office Management and Company designate(s). CQCE
shall be authorized to:
Postpone concreting operations until outstanding requirements are fulfilled.
Prevent the use of equipment which could cause improper construction relative to this specification
Report any non-compliance to Company within 24 hours, but prior to pouring of concrete, and
provide records as required by Company.
12.2.1 General
The Production/Execution Quality Plan shall cover all aspects related to production/execution
requirements, such as performance of tests, trial mixes, availability of certificates/data sheets,
reinforcement, sources of cement/aggregates/sand/water, workmanship, batch plant(s), storage,
transport, handling etc.
The quality plan shall cover all aspects related to local conditions, such as climatic conditions, back up
facilities, spare parts, transport possibilities, storage facilities, quarries, local Suppliers/Manufactures,
test facilities (field laboratory), etc. Trial concrete mixes shall be proven to perform under local
conditions and with the equipment to be used during execution.
An overview of the tests, related to the concrete works, is given in Appendix 3. The contractor shall
prepare an Inspection & Test Plan (ITP) identifying the tests, frequencies, rejection criteria and
responsibilities.
A reporting system of quality records shall be part of the quality plan. The reporting system shall record
all results obtained during testing, transporting, production, supplying, placing/pouring, finishing, curing,
striking, etc. Weather conditions shall also be recorded in the quality records.
After completion, rebound and/or ultrasonic measurements should be taken to control and verify the
concrete quality against the compliance tests and required concrete quality if there is any doubt about
the above records. The results should be recorded. Any deviation shall be reported, including the
measurements to be taken.
In specific cases, for example when cracks and voids are visible, Company shall have the right to ask
for samples of any hardened concrete to be taken and tested for compliance with this specification.
The cost of tests shall be paid by Contractor. Company shall have the right to ask for removal and
replacement of concrete in non-conformance. Such replacement of concrete shall be at no cost to
Company.
Whether the tests on cored samples pass or fail, Contractor shall repair/restore the cored holes by
material/procedure approved by Company, at Contractor’s expense.
Protection against chemicals, even very dilute solutions, shall be provided either by suitable chemical
resistant bricks or tiles or by a monolithic epoxy compound.
For details of chemical-resistant linings for concrete structures, DEP 30.48.60.12-Gen. shall apply.
The design of the anchoring length of the anchor bolts shall be checked for maximum pull-out force.
Anchor bolts, pipe sleeves, anchor rails, inserts, bolts, etc. shall be positioned accurately, and be firmly
attached to the formwork before the concrete is poured.
If slight adjustment in the position of anchor (holding-down) bolts is required, this shall be indicated on the
base plate drawing supplied with the loading information, and it shall also be clearly indicated on the detail
foundation drawing with the method(s) to be applied.
Installed anchor bolts, etc., shall be properly protected against damage and corrosion until the
equipment/structure is permanently installed. The minimum concrete cover shall be 75 mm.
Anchor bolts shall be hot-dipped galvanized, unless otherwise noted, in accordance with ASTM A153,
Class C.
DESIGN
1.1 CLASSIFICATION
In order to classify the severity of chemical attack to concrete, the exposure shall be classified in
accordance with Table 1.
The exposure classes follow in general the guidelines of the present national and international standards.
Reference should be made to EN 206-1, BS 8500 and CEB Design Guide "Durable Concrete Structures".
The relation between the exposure classes and the various aggressivity criteria is shown in Tables 2, 3
and 4 in the following sections.
The aggressivity to concrete, depending on the concentration of chemicals present in water, is shown in
Table 2, which gives the limiting values of deleterious substances in water of predominantly natural
composition for the assessment of the severity of chemical attack. The values stated result from tests on
groundwater as described in Appendix 2.
Degree of severity 1)
Criterion of exposure class XA1 XA2 XA3
pH value 6.5 to 5.5 5.5 to 4.5 4.5 to 4.0
CO2 mg/l aggressive 15 to 40 40 to 100 >100 up to saturation
Ammonium (NH +) in mg/l 15 to 30 30 to 60 60 to 100
4
Sulphate (SO4 2-) in mg/l 200 to 600 600 to 3000 3000 to 6000
1) The degree of severity is valid for stagnant or slowly moving water under moderate climatic conditions
(e.g. Central Europe). For other locations (e.g. Middle East), where more severe environmental
conditions prevail, Table 2 shall be used only as a guide. It is dependent upon the highest degree of
severity even if it is only reached by one of the five criteria listed in lines 1 to 5. Where two or more
aggressive characteristics lead to the same class, the environment shall be classified into the next
higher class, unless a special study for this specific case proves this is not necessary.
1.3 SOIL
Degree of severity 1)
Criterion of exposure classes XA1 XA2 XA3
Acidity ml/kg >200 Not encountered in practice
2000 to 3000 3000 to 12000 12000 to 24000
Sulphate (SO 2-) in mg per kg
4
1) The degree of severity is valid for soils which are saturated at frequent intervals. It can be reduced with
decreasing permeability of the soil. If the content of sulphur from sulphides exceeds 100 mg S2- per kg air-dry soil
(more than 0.01% S2-) or if dumps of industrial waste products are concerned, the deleteriousness should be
assessed by a soil consultant.
The chemical attack is expected to be more severe at higher temperatures and at higher pressures or if the
concrete is additionally exposed to mechanical abrasion due to fast flowing water or to alternating freezing and
thawing. The severity can be assumed to be lower if the water temperature is consistently low, or if the quantities
of water are small and the water is almost motionless, as for example in soils with a permeability factor
k < 10-5 m/s.
Depending on the aggressivity of ground water and soil, measures shall be taken to adequately protect
the concrete against deterioration.
The resistance of concrete to chemical attack largely depends on the cement content, type of cement and
impermeability of the hardened concrete.
To achieve an adequate level of impermeability, the water/cement ratio (W/C) shall be kept as low as
practicable and shall not exceed the values stated in Table 3. The concrete shall be carefully cured,
preferably by wet curing for 7 days.
In case of aggressive conditions it shall be proven on samples derived from trial mixes that the water
penetration, determined in accordance with EN 12390-8, is less than the values shown in Table 4.
In order to protect the reinforcement against chloride attack, the following measures shall be taken if
concrete is exposed to a concentration of Cl > 100 mg/l.
4) Crack width in accordance with EN 1992 (Eurocode 2). For pre-stressed concrete the crack
width shall be < 0.1 mm.
3. REPORTING
The Contractor shall seek the advice of a soil consultant in the case of extreme environmental
conditions (e.g. soils containing industrial wastes, heavy salt laden atmosphere, severe weathering
regions).
A comprehensive report shall be submitted to the Company. The report shall contain but not be limited
to the following information:
1) Test results of chemical analysis of ground water and soils in accordance
with DEP 34.11.00.10-Gen.
2) The concrete mix design and measures to be taken, based on the test results as mentioned
under 1).
1. INSPECTION
Various causes can lead to significant reduction in the designed life of a concrete structure or to
unacceptable structural safety due to material deterioration. In order to ensure that the integrity of
concrete structures is maintained, regular inspection of the state of the structures will provide the
required information to initiate measures for eventual repairs.
The implementation of inspection record systems which record the history of the various structures
will help to decide whether structures can be left untreated or be repaired. The inspection can
initially be carried out visually combined with the "rebound hammer".
If this inspection gives rise to doubt about strength or durability of a structure, the structure should
be further investigated. At this stage an expert should be consulted, especially to obtain advice on
a repair method.
The investigation may involve following test methods and their purposes.
1.1 TEST METHODS
NDT = non-destructive
testing DT =
destructive
NOTE testing
a) Conclusions can be drawn on the durability of the concrete depending on:
- porosity;
- maximum size of aggregates;
- porosity of aggregates;
- cement content;
NOTE b) To determine which part of the concrete has lost its pacifying ability, a solution of 1 g
phenolphthalein to 1 L ethanol shall be sprayed on the concrete; if the concrete colours
pink, the concrete still has its pacifying ability.
NOTE c) Dust samples shall be taken over depths 0 mm to 30 mm, 30 mm to 60 mm and 60 mm
to 100 mm. Dust samples should be taken from small cores. If dust samples are taken by
using a drill, special precautions shall be taken to collect dust from the intended depth
and to prevent contamination of the sample. If the chloride content is greater than 0.3 %
of the cement content, there is a potential danger of rebar corrosion. If the SO3 content
is greater than 4 % of the cement content, there is a potential danger of sulphate attack.
The cement content of a concrete sample shall be determined in the laboratory (typical
cement:concrete ratio is 1:6).
NOTE d) Tests on ground water:
1) pH value (ASTM D 1293)
2) Hardness (ASTM D 1126)
a) Total hardness
b) Carbonate hardness
c) Non-carbonate hardness
3) Concentration of aggressive carbon dioxide (DIN 4030, Heyer test)
4) Concentration of sulphates (ASTM D 516)
5) Concentration of chlorides (ASTM D 512)
6) Concentration of magnesium (ASTM D 511)
7) Concentration of sulphides (DIN 4030)
8) Concentration of ammonium (ASTM D 1426)
9) Potassium permanganate index (ISO 8467)
10) Ca content (ASTM D 511) Soil
samples:
1) pH value of soil (ISO 10390)
2) Sulphate content (BS 1377)
3) Sulphide content (BS 1377)
4) Chloride content (BS 1377)
For sampling and tests on ground water and soil, see DEP 34.11.00.10-Gen.
An incomplete separation into two or more parts limited to a certain depth or extending over the whole
depth of a section.
Cracks are classified by direction, width and depth and may be longitudinal, transverse, vertical,
diagonal and random. Three width ranges are suggested as follows:
fine : generally less than 0.1 mm;
TYPE OF DEFECT
Cracking Deterioration Surface deposits Textural defects
POSSIBLE CAUSES Cracks Pattern Disinteg- Pop- Scaling Spalling Dummy Exuda- Encrus- Stalac- Dusting Rebar Rust Sand Honey-
(deep) cracking ration outs tion tation tite corro- stains streak combing
surface sion
Chemical influences
Carbonation X X
Chloride attack X X
Acids attack (soft water) X X X
Alkali aggregate reaction X X X X X
Sulphate attack X X
Physical influences
Fire X X X X
Frost X X X X
Leaching of lime X X
Mechanical influences
Overloading X
Differential settlements X
Impacts, explosions X X
Execution
Not properly vibrated X X
Not properly cured X X
Too high w/c ratio X X X
Excessive withdrawal of
X X X X
mixing water
Engineering
Too little concrete cover X X X
Too small rebar distances X X
Insufficient reinforcement X
Obstruction or deformation X
2. REPAIR METHODS
2.1 DEFECTS AND REPAIR METHODS
The repair methods are specified in sections (2.2), (2.3) and (2.5) of this Appendix. The following
table gives an indication of the relation between defect and most suitable repair method by
referencing to the relevant sections.
- Cracks active - seal off with sheet or use joint sealer
- Scaling - (2.4)
- Exudation - (2.4)
- Encrustation - (2.4)
- Dusting - (2.4)
For special applications such as basement walls, holding basins etc. a specialist sho
uld be consulted.
APPENDIX 3. TESTS
Legend:
A For approval before work commences E.D. Each Delivery T.M. Twice per Month
D Daily E.P. Each Pouring W Weekly
D.P. During Pouring O.M. Once per Month
D.V. Daily Visual S.W.C. at Sudden Weather Change
All relevant tests shall be repeated in case of change of quarry/Manufacturer/Supplier. The above tests should be part of the quality plan.
NOTE
Cylinder
Compressive Slump
Strength Max. Minimum Max. Size
Binder Type
Water/ Binder of
Unit Application (See Note Remark
Cement Content Coarse
below) 7day 28day Before Adding After Adding
Ratio (kg/m3) Aggregate
(Mpa) (Mpa) SuperPlasticizer SuperPlasticizer
Loading Platform Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structures
Service Platform Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structures
Berthing Dolphin Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structures
Mooring Dolphin Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structures
Unit 93
Helideck Platform Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structure
Marine Structures
Roadway Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm
(Pre-stressed concrete)
Pile Bent Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structures
CP Foundation Ⅰ or Ⅱ 20 30 0.40 375 20mm 50 - 100mm Max. 200mm Onshore Structures (Below Grade)
Cylinder
Compressive Max. Minimum Max. Size Slump
Binder Type
Strength Water/ Binder of
Unit Application (See Note Remark
Cement Content Coarse
below) 7day 28day Before Adding After Adding
Ratio (kg/m3) Aggregate
(Mpa) (Mpa) SuperPlasticizer SuperPlasticizer
Approach Trestle &
Utilities Platform Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structures
Loading Platform
(Berth) Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structures
Sector Light Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structures
Unit 85 Mooring Dolphin Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structures
Transfer Tower
Foundation Ⅰ 20 30 0.40 375 20mm 50 - 100mm Max. 200mm Onshore Structure (Below grade)
Wavewall
(Reinforced Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structure
Concrete)
Wavewall
(Plain Concrete) Ⅰ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structure (Plain Concrete)
Wavewall Footing
Block (Plain Ⅲ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structure (Plain Concrete)
Unit 98 Concete)
Cap Concrete
(Offshore)
(Quay Wall) Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structure(Dir. Contact sea water)
CORE-LOC Ⅰ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Concrete (Plain Concrete)
Harbour Lift Station Ⅰ or Ⅱ 20 30 0.40 375 20mm 50 - 100mm Max. 200mm Onshore Structure (Below grade)
Sanitary Sewage
Manhole Ⅰ or Ⅱ 20 30 0.40 375 20mm 50 - 100mm Max. 200mm Onshore Structure (Below grade)
Cylinder
Compressive Max. Minimum Max. Size Slump
Binder Type
Strength Water/ Binder of
Unit Application (See Note Remark
Cement Content Coarse
below) 7day 28day Before Adding After Adding
Ratio (kg/m3) Aggregate
(Mpa) (Mpa) SuperPlasticizer SuperPlasticizer
COC Sump Ⅰ or Ⅱ 20 30 0.40 375 20mm 50 - 100mm Max. 200mm Onshore Structure (Below grade)
Foundation
(Piperack, Overbrdige, Ⅰ or Ⅱ 20 30 0.40 375 20mm 50 - 100mm Max. 200mm Onshore Structure (below grade)
Pipe Sleeper)
Foundation
(Piperack, Overbrdige, Ⅰ or Ⅱ 20 30 0.40 375 20mm 50 - 100mm Max. 200mm Onshore Structure (below grade)
Pipe Sleeper)
Duct Bank Onshore Structure (below grade)
(Coloured Concrete) Ⅰ or Ⅱ 14 20 0.45 340 10mm 50 - 100mm Max. 200mm
Red oxide to be added (ref. Section 5.9)
Unit 98
(Onshore) Building Lift Station Ⅰ or Ⅱ 20 30 0.40 375 20mm 50 - 100mm Max. 200mm Onshore Structure (below grade)
Sanitary Sewage
Manhole Ⅰ or Ⅱ 20 30 0.40 375 20mm 50 - 100mm Max. 200mm Onshore Structure (Below grade)
Harbour Master’s Ⅰ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Onshore Structure (below grade)
Control Tower &
Admin. / Navigation
Lighthous Ⅲ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Onshore Structure (above grade)
Unit 98
(Archi.)
Ⅰ 20 30 0.40 375 20mm 50 - 100mm Max. 200mm Onshore Structure (below grade)
Other Building
Structure
Ⅲ 20 30 0.40 375 20mm 50 - 100mm Max. 200mm Onshore Structure (above grade)
Cylinder
Compressive Max. Minimum Max. Size Slump
Binder Type
Strength Water/ Binder of
Unit Application (See Note Remark
Cement Content Coarse
below) 7day 28day Before Adding After Adding
Ratio (kg/m3) Aggregate
(Mpa) (Mpa) SuperPlasticizer SuperPlasticizer
Wavewall
(Reinforced Concrete) Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structure
Wavewall
(Plain Concrete) Ⅰ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structure (Plain Concrete)
Wavewall Footing
Unit 99
Block (PlainConcrete) Ⅲ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structure (Plain Concrete)
Cap Concrete
(Revetment) Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structure
CORE-LOC Ⅰ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Concrete (Plain Concrete)
Onshore Pavement Ⅲ 20 30 0.40 375 20mm 50 - 100mm Max. 200mm Slab on grade
Unit 79
Offshore Pavement Ⅲ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Slab on grade
CSW : Catch Basin,
Swale, Manhole and Ⅰ or Ⅱ 20 30 0.40 375 20mm 50 - 100mm Max. 200mm Onshore Structure (below grade)
Ditch
Air release valve
Chamber Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Below Grade
Diffuser Dome Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structure(Dir. Contact sea water)
Unit 88 Manhole ring Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structure(Dir. Contact sea water)
Mass concrete Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm For Marker post(dir. Contact sea water)
Concrete collar Ⅰ or Ⅱ 28 40 0.38 450 20mm 50 - 100mm Max. 200mm Marine Structure(Dir. Contact sea water)
Ⅲ
COM
MON
Lean concrete 14 20 0.55 340 20mm 50 - 100mm Max. 200mm