CADANGAN PEMBINAAN DAN PENYIAPAN HOSPITAL PENGAJAR DAN PUSAT KESIHATAN PRIMA (PKP) UNIVERSITI MALAYSIA SARAWAK (UNIMAS)

KOTA SAMARAHAN, SARAWAK (REKA DAN BINA) UNTUK TUJUAN KEMENTERIAN PENDIDIKAN MALAYSIA (BAHAGIAN PENGAJIAN TINGGI)
Medium Voltage System Schedule Rev 1
Year 2022 2023
No.
Month September October November December January Febuary March April May June July August September October

Week 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 53 54 55 56 58 59 60 61

1 Submission of Wayleave approval to RELEVANT Authorities

2 Submission of Stage 2 Document via Consultant to SEB/SESCO for release of SESCO connection Charges

3 11KV SWITCHGEAR PANELS (Existing 33/11KV Unimas Substation)


a. Preparation & Submission of Shop Drawing to SESCO and approval from SESCO
b. Fabrication
c. Factory Acceptance Test (FAT) PH
d. Shipment to Kuching
e. Discharge from port & deliver to site
f. Site installation
4 11KV SWITCHGEAR PANELS (Proposed 11KV Unimas Hospital Substation)
a. Preparation & Submission of Shop Drawing to SESCO and approval from SESCO
b. Fabrication
c. Factory Acceptance Test (FAT) PH
d. Shipment to Kuching
e. Discharge from port & deliver to site
f. Site installation
5 CONTROL RELAY PANEL (Existing 33/11KV Unimas Substation)
a. Preparation & Submission of Shop Drawing to SESCO and approval from SESCO
b. Fabrication
c. Factory Acceptance Test (FAT) PH
d. Shipment to Kuching
e. Discharge from port & deliver to site
f. Site installation
6 CONTROL RELAY PANEL (Proposed 11KV Unimas Hospital Substation)
a. Preparation & Submission of Shop Drawing to SESCO and approval from SESCO
b. Fabrication
c. Factory Acceptance Test (FAT) PH
d. Shipment to Kuching
e. Discharge from port & deliver to site
f. Site installation
7 110VDC BATTERY & CHARGER
a. Preparation & Submission of Shop Drawing to SESCO and approval from SESCO
b. Fabrication
c. Factory Acceptance Test (FAT) PH
d. Shipment to Kuching
e. Discharge from port & deliver to site
f. Site installation
8 Interface Cubicle
a. Preparation & Submission of Shop Drawing to SESCO and approval from SESCO
b. Fabrication
c. Factory Acceptance Test (FAT) PH
d. Shipment to Kuching
e. Discharge from port & deliver to site
f. Site installation
9 1500KVA 11/0.433kV OIL TYPE TRANSFORMERS
a. Preparation & Submission of Shop Drawing to SESCO and approval from SESCO
b. Fabrication
c. Factory Acceptance Test (FAT) PH
d. Shipment to Kuching
e. Discharge from port & deliver to site
f. Site installation
10 11KV 300MM² 3/CORE XLPE/SCW/MDPE/MDPE AL CABLE
a. Preparation, Submission & Approval of Shopdrawing
b. Fabrication
c. Factory Acceptance Test (FAT)
d. Shipment to Kuching
e. Discharge from port & deliver to site
f. Installation of 2 Ways 160mm Dia + 2 Ways 63mm Dia PN10 HDPE Pipe HDD for Existing Road Crossing
g. Laying of 2 Ways 160mm Dia + 2 Ways 63mm Dia PN10 HDPE Pipe for Drain Crossing
h. Trenching & Laying
i. Laying of 3C 11KV 185MM² 3/CORE XLPE/SCW/MDPE/MDPE AL CABLE from 11KV VCB to 6 units 1.5MVA
11/.433KV Transformer
11 LV 500mm² 1/CORE XLPE/AWA/PVC CU Cable & Control Cable
a. Preparation, Submission & Approval of Shopdrawing
b. Fabrication
c. Factory Acceptance Test (FAT)
d. Shipment to Kuching
e. Laying
12 16 Core OPUG Fibre Optic Cable
a. Preparation, Submission & Approval of Shopdrawing
b. Fabrication
c. Factory Acceptance Test (FAT)
d. Shipment to Kuching
e. Discharge from port & deliver to site
f. Laying PH
13 11KV & LV Cable Jointing & termination
a. 11KV Termination at 11KV VCB Switchgear
b. 11KV Heat Shrinkable Termination at Transformer
c. 11KV Straight Thru Joint
d. LV Cable Termination at Transformer & MSB
e. Fibre Optic Cable Termination

14 Testing & Commissioning (with SESCO)

15 SESCO substation inspection

16 Installation of SESCO Meter

Target Energisation by Early


17 Substation Energisation Date
October 2023