TITLE : JOB METHOD OF STATEMENT FOR INSTALLATION OF AWNING

DOC NO : OBZA-PT2-JMS001
TARGET DATE : JULY 24TH 2023

A) List of Manpower
B) Required Tools and Equipment
C) Mobilization
D) Job Steps
E) Attachment (s)
F) Job Safety Analysis

A) List of Manpower

No. PT2
Name Position OGSP Remarks
Inducyion
1 Muhammad Farid Yusuf Supervisor Yes Yes -
2 Mohd Khairil Skilled Worker Yes Yes -
3 Hisham Abdullah Skilled Worker Yes Yes -
4 Hanafi Skilled Worker Yes Yes -
5 Mahadir Skilled Worker Yes Yes -

B) Required Tools and Equipment

No. Tools Quantity Usage


1 Drilling Machine 1 Set Drill the hole
2 Power Cable c/w industrial socket 1 roll Connecting power supply
3 Spanner set 1 set Transfer debris

 Machinery

No. Equipment Info Usage

 Safety tools;

No. Tools Qty Usage


1 Barricade As required To barricade work site
2 Canvas As required Dust - Cover working area

 Personal Protective Equipment (PPE);

1. Full Body Harness.


2. Safety Helmet.
3. Safety Goggles.
4. Protective Gloves.
5. Safety Shoes.
7. Dust Mask.

C) Mobilization & Preparation

1. Site Visit (2 days before operation day)


 Supervisor with the team perform site visit to the working area to identify actual
requirement for the work.
 Identify supporting work to execute the work - scaffolding and power supply
 Identify the best method to start cleaning work.
 Identify obstruction and take proper action to eliminate obstruction
 Identify water source for cleaning work. Propose Obza bring own water tank for smooth
operation.

2. Preparation of work (2 days before operation day)


 Inspect all electrical equipment
 JSA and JMS approved
 Lay the canvas around working area

3. Mobilization work (1 day before operation day)


 Mobilize equipment, tools and material to the site
 Secure all item at safe place.
 Ensure working platform - scaffolding ready to use and with valid green tag
 Finalize the manpower – safety induction
 Finalize the documentation – Method of statement, permits and etc
 Final discussion with PT2’s PIC for the operation.
 Transfer all inspected tools, equipment and machinery to the job area.
D) Job Steps

 Marking work for anchor bolts location


 Drill the hole for anchor bolt
 Install the truss and tightening the anchor bolts
 Install purlin & cladding properly
 Tighten all bolts
 Housekeeping work

E) Attachment(s) – N/A

F) Job Safety Analysis – See Appendix A

Approved By: _________________________

Signature: _________________________

Name: _________________________

Designation: _________________________

Date: _________________________