You are on page 1of 2

#Actionable points on TBM Commissioning and Excavation Dated: 12.05.

2023
TBM-1 (SHAKTI) Progress Beyond RTB Chainage 48180
A1 Shield Chainage 48916.65 Total excavtion by TBM-1 (in RM) 737.80
Face Chainage 48917.80 in terms of Rings 434.00 Inverts installed 422.00
TBM-2 (SHIV) Progress Beyond RTB Chainage 878
A2 Shield Chainage 1269.55 Total excavtion by TBM-2 (in RM) 392.70
Face Chainage 1270.70 in terms of Rings 231.00 Inverts installed 219.00

Supply of Conveyor belts: Remarks


CB -1 Target: Nov-22 2 KM for Upline & 2 KM Downline is available for initial setup , remaining will be dispatched for site as per
CB -2 Target: Nov-22 consumption on a regular basis every 3 months.
Target Status Remarks

Conveyor for TBM-1 is functional since 24.04.2023 and for TBM-2 by


Structural units
B 1st to 12th Lot: Mar'23 - W3 May'23-Week-4 , installation in progress in NATM section. Stoppage
of TBM-2 is planned from 15-05-2023 tentatively for conveyor
installation in TBM section, till then for TBM-2, contractor has
reached site
planned alternative muck handling system with TBM main
13th to 15th Lot: Mar'23 - W4 conveyor extended with a chute to collect & transport muck through
Electrical Units tippers to the Dumping Yard. Temporary extension has been
16th & 17th Lot for TBM 2: May'23 - W1 completed and is being used at the moment.

Supply of MSV – 1,2,3,4 (separately)


S.No. Item Target in (Status in %/ Target Date)
MSV-1 MSV-2 MSV-3 MSV-4 Remarks
1 Procurement Completed Completed Completed Completed
2 Factory Assembly Completed Completed Completed Completed
C 3 FAT Completed Completed Completed Completed
4 Transport to Site Completed Completed Completed Completed
5 Assembly Completed Completed Completed Completed
MSV's - 1 to 4 comissioned and functional
6 Commissioning Completed Completed Completed Completed
at site.

Page 1 of 2
#Actionable points on TBM Commissioning and Excavation Dated: 12.05.2023

Casting of Ring segments/Invert segment (Availability of parts for initial start-up of casting activities)
S.No. Item Scope Available Remarks
In % Date
Availability of Mould Sets 12 12 100%
1 Available 100% i.e. 12 sets recived
INVERT 12 12 100%
Total Required Total rings casted Total rings installed in tunnel Stock Available
Gasket for 2170 ring along with 8.46 ton
D 2 Supply of gaskets enough for 2170
12,224 Rings 1884 665 adhesive is available at site.
rings

Segment rings casted FTW FTM Cumulative Available 1884 Ring casted & 1419 Invert Casted.
3 Factory-1 48 68 1419
Tentative target- 2080 rings by May 2023
Factory-2 30 41 465 1884
(305 Rings for May 2023)
Invert 71 101 1419

Availability of spares - Target


Remarks
S.No. % Date
E 1 As per desired list of items 100% Jan-23-W-4
These are through SLA with HK.
2 Disc Cutters (Total No. reqd:) TBM 1
1 set Received at Site
3 Disc Cutters (Total No. reqd:) TBM 2

Stacking of aggregates/raw materials vis-à-vis Total required


S.No. Material Required Available (Tons) Remarks
1 Aggregates 21920
2 Grout- 1 component (BENTONITE) 120.74
F
3 Grout- 2 component 89.165
4 Microfine cement 9.75
5 Collidal Silica 3.60
6 PU grout 1

G Availability of TBM consumable as per OEM List. Target Date = Dec-22 (Available for initial drive), remaining will be delivered at site as per consumption.