Professional Documents
Culture Documents
12.05.2023 Actionable Points On TBM Commissioning and Excavation
12.05.2023 Actionable Points On TBM Commissioning and Excavation
2023
TBM-1 (SHAKTI) Progress Beyond RTB Chainage 48180
A1 Shield Chainage 48916.65 Total excavtion by TBM-1 (in RM) 737.80
Face Chainage 48917.80 in terms of Rings 434.00 Inverts installed 422.00
TBM-2 (SHIV) Progress Beyond RTB Chainage 878
A2 Shield Chainage 1269.55 Total excavtion by TBM-2 (in RM) 392.70
Face Chainage 1270.70 in terms of Rings 231.00 Inverts installed 219.00
Page 1 of 2
#Actionable points on TBM Commissioning and Excavation Dated: 12.05.2023
Casting of Ring segments/Invert segment (Availability of parts for initial start-up of casting activities)
S.No. Item Scope Available Remarks
In % Date
Availability of Mould Sets 12 12 100%
1 Available 100% i.e. 12 sets recived
INVERT 12 12 100%
Total Required Total rings casted Total rings installed in tunnel Stock Available
Gasket for 2170 ring along with 8.46 ton
D 2 Supply of gaskets enough for 2170
12,224 Rings 1884 665 adhesive is available at site.
rings
Segment rings casted FTW FTM Cumulative Available 1884 Ring casted & 1419 Invert Casted.
3 Factory-1 48 68 1419
Tentative target- 2080 rings by May 2023
Factory-2 30 41 465 1884
(305 Rings for May 2023)
Invert 71 101 1419
G Availability of TBM consumable as per OEM List. Target Date = Dec-22 (Available for initial drive), remaining will be delivered at site as per consumption.
Page 2 of 2