19.05.2023 Actionable Points On TBM Commissioning and Excavation
19.05.2023 Actionable Points On TBM Commissioning and Excavation
2023
TBM-1 (SHAKTI) Progress Beyond RTB Chainage 48180
A1 Shield Chainage 48981.25 Total excavtion by TBM-1 (in RM) 802.40
Face Chainage 48982.40 in terms of Rings 472 Inverts installed 460
TBM-2 (SHIV) Progress Beyond RTB Chainage 878
A2 Shield Chainage 1289.95 Total excavtion by TBM-2 (in RM) 413.10
Face Chainage 1291.10 in terms of Rings 243 Inverts installed 231
243
Supply of Conveyor belts: Remarks
CB -1 Target: Nov-22 2 KM for Upline & 2 KM Downline is available for initial setup , remaining will be dispatched for site as per
CB -2 Target: Nov-22 consumption on a regular basis every 3 months.
Target Status Remarks
Page 1 of 2
#Actionable points on TBM Commissioning and Excavation Dated: 19.05.2023
Casting of Ring segments/Invert segment (Availability of parts for initial start-up of casting activities)
S.No. Item Scope Available Remarks
In % Date
Availability of Mould Sets 12 12 100%
1 Available 100% i.e. 12 sets recived
INVERT 12 12 100%
Total Required Total rings casted Total rings installed in tunnel Stock Available
Gasket for 2119 ring along with 8.46 ton
D 2 Supply of gaskets enough for 2119
12,224 Rings 1966 715 adhesive is available at site.
rings
Segment rings casted FTW FTM Cumulative Available 1966 Ring casted & 1508 Invert Casted.
3 Factory-1 55 123 1474
Tentative target- 2080 rings by May 2023
Factory-2 27 68 492 1966
(305 Rings for May 2023)
Invert 89 190 1508
G Availability of TBM consumable as per OEM List. Target Date = Dec-22 (Available for initial drive), remaining will be delivered at site as per consumption.