You are on page 1of 2

CONTINGENCY PLANNING FORMS

CP Form 1: Hazard Analysis

HAZARD PROBABILITY IMPACT AVERAGE RANK


PROBABILITY +
RATE REMARKS RATE REMARKS IMPACT
2
Flood 5 Flood 4 Flood caused 4.5 1
particularly huge
occurs when deterioration
there is a heavy to school
rain properties.

Tropical Cyclone 3 When there is 4 Tropical 3.5 2


tropical cyclone
cyclone in the brought heavy
area heavy rainfall and
flood occurs caused major
floods in the
area.

Fire 3 Installation of 3 High 3 3


classroom consumption of
wirings. electricity
Octopus during school
wirings days.

Example:
CP Form 1: Hazard Analysis

HAZARD PROBABILITY IMPACT AVERAGE RANK


PROBABILIT
RATE REMARKS RATE REMARKS Y + IMPACT
2
Tropical Cyclone 5 Tropical cyclone and other 4 Previous tropical cyclone 4.5 1
weather disturbances brought heavy rainfall with wind
frequently pass through the speed ranging from 185 kph to
area 215 kph. The tropical cyclone
caused major floods in the area.
Earthquake 4 Area is proximal to a fault line. 4 Last major earthquake resulted to 4 2
30 deaths and 500 injuries. The
area has been isolated for 24
hours.
Fire 3 Some houses in the area are 3 There are available fire engines 3 4
made of light materials prone with firefighters who can readily
to fire outbreaks. suppress fire outbreaks.
Landslide 3 Some areas are declared as 2 Structural interventions to 2.5 5
landslide prone. prevent landslides are in place.
Armed Conflict Situation 4 Based on intelligence reports, 3 Security measures are in place. 3.5 3
there is the presence of armed The Crisis Management
rebel groups in the area. Committee is organized.