BUDDY WBS AND RACI BY KEIRVIN CLOI RAMOS & PAUL DE SILVA

UREA-INFUSED BIOCHAR
FOR URBAN GARDENING
I RESEARCH REFINEMENT Total Cost: Php 100
Duration: Oct 1 to 7
II BIOCHAR
SETUPS
APP Duration: Oct 8 to 21
Total Cost: Php 300
1. Retrieve the capstone project from school archives with necessary permits. (1 1. Develop three application setups based on the revised
day | Php 50) research plan. (7 days | Php 150)
2. Look-up studies focused on urea-infused biochar studies in urban gardening. 2. Keep the soil in recycled plastic bottles. (3 days | Php 100)
(2 days | Php 10) 3. Store for use as pots in the execution stage. (4 days | Php 50)
3. Evaluate old research for relevant content and to align with goals. (2 days | Php
10)
4. Construct a revised research plan. (2 days | Php 30)

GOAL FINALIZATION
III URBAN GARDEN
EXPLORATION
Duration: Oct 15 to 28
Total Cost: Php 300
IV AND EXECUTION
Duration: Oct 22 to Dec 9
Total Cost: Php 500 1. Secure permission from the Barangay Council for urban garden
visits, explaining the intent. (3 days | Php 50)
1. Finalize urban gardening goals based on gathered data and develop a detailed 2. Visit locations prepared with recording materials. (4 days | Php 100)
gardening plan, focusing on manageable but vital plants. (2 weeks | Php 100) 3. Gather information: garden history, techniques, issues, and conduct
2. Share the plan with the Barangay council, outlining intent and seeking approval. interviews with a garden authority. (4 days | Php 100)
4. Assess acquired data, explore other gardens, compare, and
(1 week | Php 100) summarize for evaluation. (3 days | Php 50)
3. Plant seeds in biochar-soil pots in designated areas, ensuring proper care and
watering. (2 weeks | Php 200)
4. Communicate regularly with the garden handler for smooth project execution. (2
weeks | Php 100)
We opted for this design to illustrate the CHRONOLOGICAL ORDER of
activities. The single arrowhead arrows signify the linear progression
of tasks, while the double arrowhead arrows indicate that activities

V EVALUATION AND EXPANSION Duration: Dec 10 to 16 can occur concurrently at some point in time. Color coding enables
clear printing, and Roman numerals ensure readability. Additionally,
Total Cost: Php 100
minor steps are numbered using the modern numerical system.
1. Analyze the data collected during the project execution. (2 days | Php 25)
2. Compile the results, observations, and any other relevant data into a comprehensive report.
(2 days | Php 25)
Sources:
3. Share findings with stakeholders, such as the Barangay council, community members, or
https://www.wrike.com/project-management-guide/faq/what-is-
other interested parties through presentations, reports, or meetings. (3 days | Php 50) work-breakdown-structure-in-project-management/

WORK BREAKDOWN
STRUCTURE
1
BUDDY WBS AND RACI BY KEIRVIN CLOI RAMOS & PAUL DE SILVA

UREA-INFUSED BIOCHAR
FOR URBAN GARDENING
The colors used in the RACI chart
correspond to the categories
outlined in the Work Breakdown
Structure, encompassing both
primary and secondary tasks. The
colors we used is the same as
chronological order of color in the
rainbow for easy memorization.
We integrated the RACI chart with
the Communication Plan-Cost
because effective communication
is essential at every stage and
sub-stage of the project, involving
all stakeholders.

We have opted for a simple


summary of our communication
plan for an organized and concise
presentation of the progress of
activities. The Communication
Cost-Plan table is presented side-
by-side the RACI Chart for a clear
distinction of the assigned tasks
among relevant individuals. The
table contains all the necessary
details related to the relay of
information amongst involved
individuals. A simple presentation
containing the medium of
communication, frequency, cost,
and responsible individual is in
significance of providing clarity yet
efficiency to the execution of the
tasks.

Sources:
https://project-
management.com/understandin
g-responsibility-assignment-
matrix-raci-matrix/
https://www.interactsoftware.co
m/blog/how-to-use-a-
communication-matrix-in-your-
internal-comms-plan/

RACI CHART
COMMUNICATION PLAN-COST