PEMBANGUNAN PLTA KERINCI MERANGIN H

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Up Stream


Hari/Tanggal : Senin, 16 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 14:30 23:00 8:30 Grouting 24 m³ STA 5090.787
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1
2 Asst Formen 1 2 Genset 250 Kva 1
3 Operator 1 3 Compressor 750 CFM 2
4 Miner 9 4 Blower 110 1
5 Operator/ Driver 2 5 Shotcrete Aliva 2
6 SPV 1 6 Wheel Loader 1
7 Pelaksana /Surveyor 1 7 Sanchin 2
8 8 Jack Hammer 4
9 9 Breaker SH210 (07) 1
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
Issue
-
-

Prepared by

Satria Ronaldo
UNAN PLTA KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

AILY REPORT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
aan Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

Material Type Jumlah Satuan

1 Sigunit L-72 AF pcs


2 Semen pcs
3 Pasir Liter
4 Crushing Brush Sak
5 Oxygen M3
6 Apart Pcs
7 Mata Gerinda Tbg
8 Ring Baut 32 Bh
9 Sekop Pcs

Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HID

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Up Stream


Hari/Tanggal : Selasa, 17 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Jam)
1 8:30 19:00 10:30 Perbaikan Runtuhan
Jumlah (Jam) 0:00
Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
Issue
-

Prepared by

Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 05:00 WIB


Shift Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs

Approved by
PEMBANGUNAN PLTA KERINCI MERANG

TUNNEL WORK AD

DAILY REPORT

Lokasi : Adit 3 - Up Stream


Hari/Tanggal : Rabu, 18 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 7:00 11:00 4:00 Perbaikan Runtuhan
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1
2 Asst Formen 1 2 Genset 250 Kva 1
3 Operator 1 3 Compressor 750 CFM 2
4 Miner 9 4 Blower 110 1
5 Operator/ Driver 2 5 Shotcrete Aliva 2
6 SPV 1 6 Wheel Loader 1
7 Pelaksana /Surveyor 1 7 Sanchin 2
8 8 Jack Hammer 4
9 9 Breaker SH210 (07) 1
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
Issue
-

Prepared by
Satria Ronaldo
GUNAN PLTA KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

Y REPORT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
rjaan Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

Material Type Jumlah Satuan

1 Sigunit L-72 AF pcs


2 Semen pcs
3 Pasir Liter
4 Crushing Brush Sak
5 Oxygen M3
6 Apart Pcs
7 Mata Gerinda Tbg
8 Ring Baut 32 Bh
9 Sekop Pcs

Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Up Stream


Hari/Tanggal : Kamis, 19 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 8:00 12:30 4:30 Perbaikan Runtuhan
2 18:30 21:00 2:30 Safety Shotcrete 7 m³
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
Issue
-
-

Prepared by
Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs

Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Up Stream


Hari/Tanggal : Jum'at, 20 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
Issue
-

Prepared by
Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs

Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Up Stream


Hari/Tanggal : Sabtu, 21 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 14:00 0:00 10:00 Perbaikan Runtuhan
2 1:00 4:00 3:00 Safety Shotcrete 5 m³
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
Issue
-
-

Prepared by
Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs

Approved by
PEMBANGUNAN PLTA KERINCI MERANGIN HIDRO K

TUNNEL WORK ADIT 3

DAILY REPORT

Lokasi : Adit 3 - Up Stream


Hari/Tanggal : Minggu, 22 Agustus 2021

Jam Kerja Waktu


No Uraian Pekerjaan
Mulai Selesai (Menit)
1 13:30 18:30 5:00 Perbaikan Runtuhan
Jumlah (Jam) 0:00
Jumlah Jumlah
Man Power Main Equipment Material
(org) (Unit)
1 Formen 1 1 Genset 100 Kva 1 1
2 Asst Formen 1 2 Genset 250 Kva 1 2
3 Operator 1 3 Compressor 750 CFM 2 3
4 Miner 9 4 Blower 110 1 4
5 Operator/ Driver 2 5 Shotcrete Aliva 2 5
6 SPV 1 6 Wheel Loader 1 6
7 Pelaksana /Surveyor 1 7 Sanchin 2 7
8 8 Jack Hammer 4 8
9 9 Breaker SH210 (07) 1 9
10 10 Excavator 210 (10) 1
11 11 Excavator PC130 (25) 1
12 12 Dump Truck / Dux 6
13 13 Leg Drill 30
14 -
15
Jumlah 16 53
Catatan
-
-
-
Issue
-
-

Prepared by
Satria Ronaldo
A KERINCI MERANGIN HIDRO KAP. 350 MW

TUNNEL WORK ADIT 3

RT

Jam : 07:00 - 07:00 WIB


Shift : Day & Night

STA
Ket.
AWAL AKHIR +EXCAVASI (m) TOTAL (m)

Material Type Jumlah Satuan

Sigunit L-72 AF pcs


Semen pcs
Pasir Liter
Crushing Brush Sak
Oxygen M3
Apart Pcs
Mata Gerinda Tbg
Ring Baut 32 Bh
Sekop Pcs

Approved by