Professional Documents
Culture Documents
Contract No : 7600000196
TABLE OF CONTENTS:
1.0 SCOPE ……………………………………………………………………………………….…………………………………… 03
1.0 SCOPE
This method statement covers all required activities for concrete works part of the scope of work.
Methodology statement includes formworks, reinforcement, anchor bolts and embedment installation,
concrete pouring, curing activities and waterproof coating.
Structures covered in this methodology include all concrete foundation of structures, equipment pads,
slabs and paving specifically for the following:
1. Compressor shelter structure foundation and grade slab
2. Compressor equipment pad with sleeper foundations
3. Cooler fin fans structure foundation
4. Knock-out drum Equipment foundations
5. Dehydration system equipment pad with sleeper foundations
6. Dehydration system shelter structure foundations
7. Pipe rack equipment foundations
8. Pipe support and sleeper foundations
9. Oil cooler structure foundation
10. Lube oil system pad
11. Ladder foundations
12. Paving slab
13. Transformer equipment and shelter foundation
14. Corridor area pipe support
2.0 PURPOSE
The methods and sequence of activities contained in this document shall serve as guidance and
reference to ensure proper execution of all related activities are in accordance with contract requirement,
safety & quality assurance. This method statement shall detail the work and concerns that is to be given
attention in each area or work as to the following:
2.1 Survey for location, layout and marking for required sizes and orientation of foundations
2.2 Pre-pour job steps and check-ups for both on-site and pre-cast concrete foundations
2.3 Waterproofing of concrete foundations
2.4 Identify and conduct Inspection points and testing of concrete samples
2.5 Concrete pouring by mobile telescopic boom pump
2.6 Implementation of safety measures, PPE’s and compliance to HSE procedural requirements
2.7 Identification and preparation of required manpower, equipment and materials for all of the above
Doc No : KAK-ANA-CFS-CMS-0002
METHOD STATEMENT Rev No : A02
FOR Date : 28-July-2018
CONCRETE WORKS Page No : 4 of 10
3.0 REFERENCES
Obtain all necessary site clearance for construction, MOCs, site takeover permits, etc.
Ensure availability of approved and required site procedural requirements
Ensure that project requirements and scope are fully communicated to sub-contractor
Make available the required IFC drawings prior to start of activity and that any revisions to
approved drawings are promptly communicated to sub-contractor
Shall oversee overall site management to ensure that responsibilities are well covered and
performed by the project organization
Shall ensure availability of sub-contractor’s personnel, equipment and service provider’s access
to site to avoid work interruptions due to this
7.1.1 After excavation and earthwork preparations are made available, deliver required materials
on work area.
7.1.2 Substrate soil or plain concrete shall be clean of deleterious materials.
7.1.3 When concrete structure is casted on soil, soil compaction test verifications shall be checked
by field density test to be conducted by third party inspector.
7.1.4 Concrete constructed above ground shall be prepared by providing a safe working platform
(i.e. scaffolding)
7.1.5 Bottom level of concrete to be constructed shall be in accordance to IFC drawings.
7.1.6 Layout and dimensions of concrete shall be verified by survey.
7.2 FORMWORK, REBARS AND EMBEDMENT INSTALLATION FOR BOTH PRE-CAST AND ON-SITE POURS
Two methods of pouring will be adapted for concrete pouring activities. For all pre-cast
concrete, direct pouring by chute from mixer trucks will be implemented. Concrete pours on
site will be performed either by direct chute pouring or by using concrete pump with
telescopic boom.
7.3.1 Chute pouring shall be performed where structure to be poured can be easily accessed by
mixer trucks. In this way, concrete will flow through the chute and disposed on prepared
formwork. It shall be ensured that the chute edge will not be 1.0m higher than the point
where concrete will be disposed to avoid segregation of aggregates with the concrete due to
impact if chute is at very high position.
7.3.2 Pump pours shall be used for most of the structures poured on-site. When using telescopic
boom driven concrete, operator shall be wary of all overhead obstructions which may be
disturbed by the boom. It shall also be checked that the concrete is not released above 1.0m
higher than its of point of disposal to avoid aggregate segregation. The person directing the
pour at the end of the telescopic hose should ensure the height of concrete fall and no
person is directly in front where concrete is being released. After pouring, on one location,
operator shall ensure that hose is emptied or in vacuum before transferring the boom into
other spot or location so as to avoid any damage caused when concrete will spill out of the
hoses while it is on the air and moving to another location.
7.4.8 During pouring of concrete, workers should not be directly in physical contact with the
cement mixture. The workers working on the disposal point of concrete shall wear a face
shield.
7.4.9 Pump operation shall be with full caution to avoid hitting any other structures or equipment
on the site. Pump hoses shall be secured firmly by the worker to avoid letting the pump hose
freely jerking and hitting workers or equipments adjacent to the site.
7.4.10 Immediately upon concrete pouring completion, verify all embedment are in-place and did
not move from location. Any adjustments required may be performed while the concrete is
still in liquid state.
7.4.11 Upon consolidation, wet hessian cloth will be installed over new concrete to avoid rapid
evaporation.
7.4.12 Excess concrete on the site shall be cleaned off before drying.
7.5.1 Perform inspection with client QA/QC prior to concrete pouring to verify all installations are
correct in accordance to drawings and specifications.
7.5.2 Once all inspections are performed and satisfactory to the requirements, prepare the site for
concrete pouring.
7.5.3 Cold joints between concrete pouring shall be applied with concrete bonding agent to
increase bond between hardened concrete and fresh concrete.
7.5.4 Discontinuous concrete especially on expansion or control joints shall be provided with filler
or expansion boards prior to concrete pouring. A total of 7 concrete sample cylinders shall
be taken from concrete batch. 6 cylinders shall be laboratory cured and 1 sample will be field
cured. 3 cylinders will be crushed at 7-days maturity period and the rest of samples shall be
crushed at 28 days maturity period. Concrete samples should not display compressive
strength not less than design strength.
7.6.7 Waterproof coating shall cover all surface exposed to earth extending to surfaces 300mm
above grade level.
1.1 All workers shall provide with PPE (Personal Protective Equipment) and shall be worn every time they
entering the site. Safety Supervisor shall ensure all the workers wear all the safety equipment
provided.
1.2 Safety Supervisor shall ensure that the activity carried out in a safe manner.
1.3 All workers shall fully support and actively participate in all safety related activities and comply with all
practicable safety measures.
1.4 All workers shall be advised to report any accident or injury to supervisor and proper treatment to be
obtained.
1.5 The safety supervisor shall ensure that workers understand the safety regulations and explain in detail
in particular hazards, where the workers are working and the precaution to be taken their safety.
1.6 All workers shall ensure that all tools and equipment machinery are in good condition to avoid any oil
leakage that could harm to environment.
1.7 Domestic and construction waste from construction area must be collected into centralized garbage
bin and disposed at the designated area.
1.8 Movement of concrete mixers and pumps on the site shall be made in safe manner such that no
accident will be incurred. Flagman shall be available at all times to guide movement of heavy and
mobile equipments.
1.9 All mobile and engine operated equipments shall be inspected by Safety officer on the site. These
equipments should not display any signs of oil or fuel leaks to avoid cases of fire and spillage on the
site.
1.10 The working area where mobile equipments will work shall be barricaded to avoid access of persons
not involved with the site activity.